| DETAILS OF STATE PLAN SCHEMES INDICATING SPILLOVER BALANCES AS ON 01.04.2007( FINANCIAL YEAR 2007-08) | ||||||||||
| NORTH DISTRICT ( MANGAN SUB-DIVISION & SUB- DIVISION- IV) | ||||||||||
| A. MAJOR HEAD :- 5054-04-04.337-60-47-60.47.71 - Removal (Plan) | ( RUPEES IN LAKHS) | |||||||||
| Sl. | NAME OF WORK | Name of Contractor | Date of | Due date of | Year of Sanction | Sanctioned Cost | Total Expenditure | Spillover | Physical | |
| Commencement | Completion | 2007-08 | Progress | Remarks | ||||||
| A | B | C | D | E | F | G | H | I | J | K |
| 1 | Widening, Protective work, drainage & Carpetting work on SBS road km 10th ( 10% above) | |||||||||
| (Lobzang Lepcha) | 15.11.03 | 31-5-06 | 2003 | 17.11 | 6.36 | 10.75 | 73% | Work under progress | ||
| 2 | Widening, Protective work, drainage & Carpetting work on SBS road km 12th ( 10% above) | |||||||||
| (Lobzang Lepcha) | 15.11.03 | 31-5-06 | 2003 | 17.40 | 8.63 | 8.77 | 72% | Work under progress | ||
| 3 | Widening, Protective work, drainage & Carpetting work on SBS road km 13th ( 10% above) | |||||||||
| (Sonam Dorjee Lepcha) | 18.11.04 | 31-5-06 | 2003 | 18.86 | 0.73 | 18.13 | 69% | Work under progress | ||
| 4 | Widening, Protective work, drainage & Carpetting work on SBS road km 14th ( 10% above) | |||||||||
| (Topnan Lepcha) | 11.01.03 | 31-5-06 | 2003 | 19.76 | 10.24 | 9.52 | 67% | Work under progress | ||
| 5 | Widening, Protective work, drainage & Carpetting work on SBS road km 15th ( 10% above) | |||||||||
| (Topnam Lepcha) | 11.01.03 | 31-5-06 | 2003 | 15.35 | 0.00 | 15.35 | 70% | Work under progress | ||
| 6 | Restoration work/ Surface renewal on approach road to Mission Kothi, Mangan | |||||||||
| Ugen Palzor Kazi | 11.01.03 | 31-5-06 | 2003 | 32.79 | 29.73 | 3.06 | 100% | Work A/ c to be Closed | ||
| 7 | Premix Carpeting PW drainage on approach road to Hee Gyathang School | Deptt | 2005 | 23.01 | 4.94 | 18.07 | 100% | Work A/ c to be Closed | ||
| (a) Removal Mangan Sub Division | Sub Total | 144.28 | 60.63 | 83.65 | ||||||
| SUB - Div IV | ||||||||||
| 8 | Premixed carpetting on GRS Road km 1st - 4th (13% below) | |||||||||
| (Phurba Bhutia) | 30-05-03 | completed | 2003 | 64.41 | 47.51 | 16.90 | 100% | Work A/ c to be Closed | ||
| 9 | Premix Carpetting on Penlong Tintek Road km 1st to 9th | |||||||||
| Mohan Bajaj | 13.01.03 | completed | 2003 | 160.01 | 130.93 | 29.08 | 100% | Work A/ c to be Closed | ||
| 10 | Premix carpetting on GRBA road Km 1st to 10th. [Phase I] REVISED | Shri A.N. Upprety | 13/01/03 | 12/7/2004 | 2003 | 215.65 | 188.16 | 27.49 | 100% | Work A/ c to be Closed |
| 11 | Premix carpetting on GRBA road Km 18-21,Assam Pakyong 1st-6th. [Phase II] REVISED | Shri Amrit Rai | 01/01/03 | 30/06/04 | 2003.00 | 254.76 | 172.00 | 82.76 | 95% | Work under progress |
| 12 | Carpetting to app.road to Sichey School. | Rohit Pradhan | 27.02.06 | 26.5.06 | 2005 | 3.77 | 0.00 | 3.77 | 100% | Work A/ c to be Closed |
| 13 | Upgradation Ranka Sichey km 1st to 3rd (Above portion of CRF).Revised | |||||||||
| Rajesh Agrawal | 17.3.05 | 31.5.06 | 2004 | 30.79 | 0.00 | 30.79 | 100% | Work A/ c to be Closed | ||
| 14 | Upgradayion improvement of Rumtek-Ranka road km. 18th. | Departmental | 2005 | 1.36 | 0.00 | 1.36 | 100% | Work A/ c to be Closed | ||
| 15 | Upgradation of Mrachok- Tumblabong Raod (NEC) Land Comp | M/s ladaki Cost. Pvt Ltd | 2006 | 100.00 | 0.00 | 100.00 | 0% | Compensation to be paid | ||
| Sub- Total | 830.75 | 538.60 | 292.15 | |||||||
| A. TOTAL REMOVAL NORTH DISTT | 975.03 | 599.23 | 375.80 | - | ||||||
| B. REPLACEMENT NORTH | ||||||||||
| MAJOR HEAD :- 5054-04-04.337-60-47-60.47.72 - Replacement (Plan) | ||||||||||
| (a) Mangan Sub Division | ||||||||||
| 1 | Const of 15 M RCC Bridge over Khedum Chu | Gyatso Bhutia | 12.11.98 | 11.03.99 | 1998-99 | 20.72 | 19.36 | 1.36 | 100% | A/c Closed |
| TOTAL B. REPLACEMENT NORTH | 20.72 | 19.36 | 1.36 | |||||||
| C. MAJOR HEAD :- 5054-04-04.337-60-47-60.47.73 - Expansion (Plan) | ||||||||||
| A. Mangan Sub- Div | ||||||||||
| 1 | Premix Carpetting, Imp. & widening of D-S-M road km 4th to 7th (10% above) | |||||||||
| (Ragubir Agrawal) | 15.01.03 | completed | 2003 | 136.57 | 106.83 | 29.74 | 100% | Final bill to be Paid | ||
| 2 | Premix Carpetting, Imp. & widening of D-S-M road km 8th to 11th (10%above) | |||||||||
| (Gajanand Agrawal) | 15.01.04 | completed | 2003 | 118.41 | 93.63 | 24.78 | 100% | Final bill to be paid | ||
| 3 | Premix Carpetting, Imp. & widening of D-S-M road km 12 to 16 (10% above) | |||||||||
| (Singi Lepcha) | 15.01.04 | 31.5.06 | 2003 | 124.05 | 54.90 | 69.15 | 75% | Work under progress | ||
| 4 | Premix Carpetting, Imp. & widening of D-S-M road km 17th (10% above) | |||||||||
| (Chewang Norbu) | 11.01.03 | completed | 2003 | 19.41 | 9.93 | 9.48 | 100% | Final bill to be paid | ||
| 5 | Premix Carpetting, Imp. & widening of D-S-M road km 18th (10% above) | |||||||||
| (Dawa Tsh. Lepcha) | 11.01.03 | 31.5.06 | 2003 | 19.56 | 10.91 | 8.65 | 74% | Work under progress | ||
| 6 | Premix Carpetting, Imp. & widening of D-S-M road km 19th (10% above) | |||||||||
| (Ongden Lepcha) | 11.01.03 | 31.5.06 | 2003 | 20.44 | 7.44 | 13.00 | 73% | Work under progress | ||
| 7 | Premix Carpetting, Imp. & widening of D-S-M road km 20th (10% above) | |||||||||
| (Mingma Tsh. Lepcha) | 11.01.03 | 31.5.06 | 2003 | 20.04 | 12.50 | 7.54 | 74% | Work under progress | ||
| 8 | Premix Carpetting, Imp. & widening of D-S-M road km 21st (10% above) | |||||||||
| (Lazang Lepcha) | 11.01.03 | 31.5.06 | 2003 | 23.38 | 13.55 | 9.83 | 75% | Work under progress | ||
| 9 | Premix Carpetting, Imp. & widening of D-S-M road km 22nd (10% above) | |||||||||
| (Tashi Tsh. Lepcha) | 11.01.03 | 31.5.06 | 2003 | 14.55 | 11.41 | 3.14 | 100% | Work a/c closed | ||
| 10 | Const. of Gour Santok road km 1st & 2nd 10% Above | Pentook Lepcha & C.Lepcha | old IX th Plan | 1996 | 29.76 | 21.61 | 8.15 | 100% | Bill not received | |
| 11 | Stregenthening & drainage Carpeting of SBS Road to Tingvong High Scgool (NEC) Above % Share | Gajanand Agrawal | 29.04.05 | 30.4.06 | 2005 | 46.37 | 0.00 | 46.37 | NEC | Final bill to be Paid |
| Sub Total | 572.54 | 342.71 | 229.83 | |||||||
| B. SUB-DIVISION :- No. IV | ||||||||||
| 12 | Premix Carpetting on Penlong Tintek Road km 12th to 20th | Suresh Mundra | 28.11.02 | 31.5.06 | 2000 | 158.79 | 105.05 | 53.74 | 92% | work under progress |
| 13 | Upgradation of Gangtok-Burtuk-Ranka Road [S.Share of NLCPR] | Shyam Rai | 11.01.06 | 31.3.06 | 2004 | 221.54 | 0.00 | 221.54 | 45% | NLCPR |
| 14 | Premix Carpetting on Pangthang Lingdok Road km 6th - 12th | Karma Bhutia | 15.01.03 | 31.3.05 | 2003 | 129.90 | 115.34 | 14.56 | 100% | Final Bill to be Paid |
| 15 | Const. of link road from lower Lingdum to Adampool Km 3rd & 4th, Phase-II( NABARD) | Ajay Rai | 16.11.05 | 15.05.07 | 2005 | 29.64 | 0.00 | 29.64 | 58% | NABARD |
| 16 | Premix Carpetting & Protective work to approch road to cremation ground at Ranipool(NABARD-state share) | Praveen Kumar Agrawal | 31.01.06 | 31.3.06 | 2005 | 11.14 | 0.00 | 11.14 | 60% | NABARD |
| Expansion (Plan) | Sub Total | 551.01 | 220.39 | 330.62 | ||||||
| C. TOTAL EXPANSION NORTH DISTT | 1123.55 | 563.10 | 560.45 | |||||||
| D. MAJOR HEAD :-LINK ROAD (North district) | ||||||||||
| 1 | Const. of link road to Aho Manghim km 1st to 3rd. | Smt. Beena Subba B.R. Subba B. K . Upreti | 1.12.04 | 1.10.05 | 2003-04 | 62.65 | 11.37 | 51.28 | 70% | Work under progress |
| A. TOTAL LINK ROAD NORTH DISTT | 62.65 | 11.37 | 51.28 | - | ||||||
| SUB-DIVISION :- MANGAN | ||||||||||
| MAJOR HEAD :- E. ADDITIONAL FACILITIES | ||||||||||
| 1 | Construction of Rest House at Samdong in East Sikkim | |||||||||
| (Nithup Lepcha)/ | 20.05.03 | completed | 2004 | 78.70 | 75.32 | 3.38 | 100% | Final bill to be paid | ||
| TOTAL :- E. ADDITIONAL FACILITIES NORTH DISTRICT | 78.70 | 75.32 | 3.38 | - | ||||||
| 1 | Const. of Link road to Yumi Samdong km 1st & 2nd 37.41and LC 17.07 ( Forest) | |||||||||
| Tshering Do. Lachungpa | 21.6.04 | 21.12.05 | 2004 & 2005 | 54.48 | 31.57 | 22.91 | 20.00% | |||
| 2 | Upgradation, carpeting works of Chaten Khimten village road, North Sikkim | |||||||||
| 3 | Construction of link road from Bay to Pentong in North Sikkim. (state portion of RSVY works) | Bernard Lepcha | 2005 | 119.45 | 0.00 | 119.45 | 15% | F. clearance pending | ||
| 4 | Construction of link road from Zimchung to Nampatam in North Sikkim. (state portion of RSVY works) Land Compensation | 2005 | 82.00 | 0.00 | 82.00 | 100% | L/c Pending | |||
| 5 | Extension of Bagcha to labi Km 3rd & 4th ( share of Land Compensation for BADP Work) | 2005 | 42.00 | 0.00 | 42.00 | 100% | L/c Pending | |||
| 6 | Construction of Link road from Takchi phatak to upper luing km 1st to 5th | Tsh. R Bhutia- km 1st | ||||||||
| Dewjang Bhutia - km 2nd | 2005 | 258.25 | 0.00 | 258.25 | 0% | Work not yet started | ||||
| T.G Bhutia - 3rd | ||||||||||
| Y. Dolma Bhutia-4th | ||||||||||
| Y.Dolma Bhutia-5th | ||||||||||
| 7 | Construction of Link road from 3rd Mile turning of Tintek Dikchu to Raksay via Kedangthang ( State share of Land Compensation for RSVY Scheme) | - | - | - | 22.00 | 0.00 | 22.00 | - | L/c Pending | |
| TOTAL NEW ROADS | 578.18 | 31.57 | 546.61 | |||||||
| . TOTAL NORTH DISTT | 2838.83 | 1299.95 | 1538.88 | - | ||||||