DETAILS OF STATE PLAN SCHEMES INDICATING SPILLOVER BALANCES AS ON 01.04.2007( FINANCIAL YEAR  2007-08)
NORTH DISTRICT ( MANGAN SUB-DIVISION & SUB- DIVISION- IV)
A.    MAJOR HEAD :- 5054-04-04.337-60-47-60.47.71 - Removal (Plan)         ( RUPEES IN LAKHS)       
Sl. NAME OF WORK Name of Contractor Date of Due date of Year of Sanction Sanctioned Cost Total Expenditure Spillover Physical  
Commencement Completion 2007-08 Progress Remarks
A B C D E F G H I J K
                     
1 Widening, Protective work, drainage & Carpetting work on SBS road km 10th  ( 10% above)                  
                   
  (Lobzang Lepcha) 15.11.03 31-5-06 2003 17.11 6.36 10.75 73% Work under progress 
2 Widening, Protective work, drainage & Carpetting work on SBS road km 12th  ( 10% above)                  
                   
  (Lobzang Lepcha) 15.11.03 31-5-06 2003 17.40 8.63 8.77 72% Work under progress 
3 Widening, Protective work, drainage & Carpetting work on SBS road km 13th  ( 10% above)                  
                   
  (Sonam Dorjee Lepcha) 18.11.04 31-5-06 2003 18.86 0.73 18.13 69% Work under progress 
4 Widening, Protective work, drainage & Carpetting work on SBS road km 14th  ( 10% above)                  
                   
  (Topnan Lepcha) 11.01.03 31-5-06 2003 19.76 10.24 9.52 67% Work under progress 
5 Widening, Protective work, drainage & Carpetting work on SBS road km 15th  ( 10% above)                  
                   
  (Topnam Lepcha) 11.01.03 31-5-06 2003 15.35 0.00 15.35 70% Work under progress 
6 Restoration work/ Surface renewal on approach road to Mission Kothi, Mangan                  
  Ugen Palzor Kazi 11.01.03 31-5-06 2003 32.79 29.73 3.06 100% Work A/ c  to be Closed 
7 Premix Carpeting PW drainage on approach road to Hee Gyathang School Deptt     2005 23.01 4.94 18.07 100% Work A/ c  to be Closed 
  (a) Removal Mangan Sub Division   Sub Total      144.28 60.63 83.65    
  SUB - Div IV                  
8 Premixed carpetting on GRS Road km 1st - 4th (13% below)                  
(Phurba Bhutia) 30-05-03 completed 2003 64.41 47.51 16.90 100% Work A/ c  to be Closed 
9 Premix Carpetting on Penlong Tintek Road km 1st to 9th                  
Mohan Bajaj 13.01.03 completed 2003 160.01 130.93 29.08 100% Work A/ c  to be Closed 
10 Premix carpetting on GRBA road Km 1st to 10th. [Phase I] REVISED Shri A.N. Upprety 13/01/03 12/7/2004 2003 215.65 188.16 27.49 100% Work A/ c  to be Closed 
11 Premix carpetting on GRBA road Km 18-21,Assam Pakyong 1st-6th.                        [Phase II] REVISED Shri Amrit Rai 01/01/03 30/06/04 2003.00 254.76 172.00 82.76 95% Work under progress 
12 Carpetting to app.road to Sichey School. Rohit Pradhan 27.02.06 26.5.06 2005 3.77 0.00 3.77 100% Work A/ c  to be Closed 
13 Upgradation Ranka Sichey km 1st to 3rd (Above portion of CRF).Revised                   
Rajesh Agrawal 17.3.05 31.5.06 2004 30.79 0.00 30.79 100% Work A/ c  to be Closed 
14 Upgradayion improvement of Rumtek-Ranka road km. 18th. Departmental     2005 1.36 0.00 1.36 100% Work A/ c  to be Closed 
15 Upgradation of Mrachok- Tumblabong Raod  (NEC) Land Comp  M/s ladaki Cost. Pvt Ltd     2006 100.00 0.00 100.00 0% Compensation to be paid 
        Sub- Total   830.75 538.60 292.15    
      A. TOTAL REMOVAL NORTH DISTT      975.03 599.23 375.80 -  
B.   REPLACEMENT NORTH                    
MAJOR HEAD :- 5054-04-04.337-60-47-60.47.72 - Replacement (Plan)                    
(a)  Mangan Sub Division                    
1 Const of 15 M RCC Bridge over Khedum Chu Gyatso Bhutia 12.11.98 11.03.99 1998-99 20.72 19.36 1.36 100% A/c Closed
  TOTAL  B.  REPLACEMENT  NORTH 20.72 19.36 1.36    
C. MAJOR HEAD :- 5054-04-04.337-60-47-60.47.73 - Expansion (Plan)          
  A. Mangan Sub- Div                  
1 Premix Carpetting, Imp. & widening of D-S-M road km 4th to 7th (10% above)                  
  (Ragubir Agrawal) 15.01.03 completed 2003 136.57 106.83 29.74 100% Final bill to be Paid 
2 Premix Carpetting, Imp. & widening of D-S-M road km 8th to 11th (10%above)                  
  (Gajanand Agrawal) 15.01.04 completed 2003 118.41 93.63 24.78 100% Final bill to be paid 
3 Premix Carpetting, Imp. & widening of D-S-M road km 12 to 16 (10% above)                  
  (Singi Lepcha) 15.01.04 31.5.06 2003 124.05 54.90 69.15 75% Work under progress 
4 Premix Carpetting, Imp. & widening of D-S-M road km 17th  (10% above)                  
  (Chewang Norbu) 11.01.03 completed 2003 19.41 9.93 9.48 100% Final bill to be paid 
5 Premix Carpetting, Imp. & widening of D-S-M road km 18th  (10% above)                  
  (Dawa Tsh. Lepcha) 11.01.03 31.5.06 2003 19.56 10.91 8.65 74% Work under progress 
6 Premix Carpetting, Imp. & widening of D-S-M road km 19th (10% above)                  
  (Ongden Lepcha) 11.01.03 31.5.06 2003 20.44 7.44 13.00 73% Work under progress 
7 Premix Carpetting, Imp. & widening of D-S-M road km 20th (10% above)                  
  (Mingma Tsh. Lepcha) 11.01.03 31.5.06 2003 20.04 12.50 7.54 74% Work under progress 
8 Premix Carpetting, Imp. & widening of D-S-M road km 21st (10% above)                  
  (Lazang Lepcha) 11.01.03 31.5.06 2003 23.38 13.55 9.83 75% Work under progress 
9 Premix Carpetting, Imp. & widening of D-S-M road km 22nd (10% above)                  
  (Tashi Tsh. Lepcha) 11.01.03 31.5.06 2003 14.55 11.41 3.14 100% Work a/c closed 
10 Const. of Gour Santok road km 1st & 2nd 10% Above  Pentook Lepcha & C.Lepcha  old IX th Plan    1996 29.76 21.61 8.15 100% Bill not received 
11 Stregenthening & drainage Carpeting of SBS Road to Tingvong High Scgool (NEC) Above % Share  Gajanand Agrawal 29.04.05 30.4.06 2005 46.37 0.00 46.37 NEC Final bill to be Paid 
    Sub Total        572.54 342.71 229.83    
B. SUB-DIVISION :-  No. IV                  
12 Premix Carpetting on Penlong Tintek Road km 12th to 20th Suresh Mundra 28.11.02 31.5.06 2000 158.79 105.05 53.74 92% work under progress 
13 Upgradation of Gangtok-Burtuk-Ranka Road [S.Share of NLCPR] Shyam Rai 11.01.06 31.3.06 2004 221.54 0.00 221.54 45%  NLCPR 
14 Premix Carpetting on Pangthang Lingdok Road km 6th - 12th Karma Bhutia 15.01.03 31.3.05 2003 129.90 115.34 14.56 100% Final Bill to be Paid 
15 Const. of link road from lower Lingdum to Adampool Km 3rd & 4th, Phase-II( NABARD) Ajay Rai 16.11.05 15.05.07 2005 29.64 0.00 29.64 58% NABARD
16 Premix Carpetting & Protective work to approch road to cremation ground at Ranipool(NABARD-state share) Praveen Kumar Agrawal 31.01.06 31.3.06 2005 11.14 0.00 11.14 60% NABARD
    Expansion (Plan)   Sub Total    551.01 220.39 330.62    
    C.  TOTAL EXPANSION NORTH DISTT        1123.55 563.10 560.45    
                     
D. MAJOR HEAD :-LINK ROAD  (North district)              
1 Const. of link road to Aho Manghim km 1st to 3rd. Smt. Beena Subba B.R. Subba B. K . Upreti  1.12.04 1.10.05 2003-04 62.65 11.37 51.28 70% Work under progress
    A. TOTAL LINK ROAD  NORTH DISTT        62.65 11.37 51.28  
SUB-DIVISION :-  MANGAN                  
MAJOR HEAD :- E.   ADDITIONAL FACILITIES                 
1 Construction of Rest House at Samdong in East Sikkim                  
  (Nithup Lepcha)/ 20.05.03 completed 2004 78.70 75.32 3.38 100% Final bill to be paid
  TOTAL  :- E.   ADDITIONAL FACILITIES NORTH DISTRICT       78.70 75.32 3.38 -  
1 Const. of Link road to Yumi Samdong km 1st & 2nd 37.41and LC 17.07 ( Forest)                  
  Tshering Do. Lachungpa 21.6.04 21.12.05 2004 & 2005 54.48 31.57 22.91 20.00%  
2 Upgradation, carpeting works of Chaten Khimten village road, North Sikkim                  
3 Construction of link road from Bay to Pentong in North Sikkim.  (state portion of RSVY works) Bernard Lepcha     2005 119.45 0.00 119.45 15%  F. clearance pending  
4 Construction of link road from Zimchung  to Nampatam  in North Sikkim.  (state portion of RSVY works) Land Compensation       2005 82.00 0.00 82.00 100% L/c Pending 
5 Extension of Bagcha to labi Km 3rd & 4th  ( share of Land Compensation for BADP Work)       2005 42.00 0.00 42.00 100% L/c Pending 
6 Construction of Link road from Takchi phatak to upper luing km 1st to 5th Tsh. R  Bhutia- km 1st                
  Dewjang Bhutia - km 2nd     2005 258.25 0.00 258.25 0% Work not yet started
    T.G Bhutia   -   3rd                
    Y. Dolma Bhutia-4th                
    Y.Dolma Bhutia-5th                
7 Construction of Link road from 3rd Mile turning of Tintek Dikchu to Raksay via Kedangthang ( State share of Land Compensation for RSVY Scheme)                  -                      -              -   22.00 0.00 22.00 - L/c Pending 
  TOTAL NEW ROADS          578.18 31.57 546.61    
. TOTAL   NORTH DISTT    2838.83 1299.95 1538.88 -