RSVY SCHEMES |
||||||
| Sl | Name of Scheme | Approved Cost | Fund Received | Expenditure March-08 | Balance Fund to recieve from GOI | Physical Progress |
| 0 | 1 | 2 | 4 | 5 | 6 | |
| 1 | Construction of link road from Bay to Pentong km 1st to 4th | 150.00 | 150.00 | 73.95 | 0.00 | 50% |
| 2 | Upgradation /Carpetting works of Chaten Khimten village road. | 38.00 | 38.00 | 38.00 | 100% | |
| 3 | Construction of link road from Zimchung-Nampathang km 1st to 3rd | 100.10 | 100.10 | 92.43 | 100% | |
| 4 | Extension of approach road to Dokey Chisopani primary school km 3rd ( ch 1st to 27th) | 25.00 | 25.00 | 21.82 | 100% | |
| 5 | Link road from Amba to Taza school km 1st to 2 nd | 60.00 | 60.00 | 54.46 | 100% | |
| 6 | Construction of link road from 3rd mile Turning (Tintek -Dikchu road ) to Rakshey via Kedangthang km 1st to km 3rd | 128.44 | 128.44 | 97.90 | 85% | |
| 7 | Link road to Ung Raam falls via Namplang and Rabong village km 1st to 6th | 180.00 | 180.00 | 138.25 | 85% | |
| 8 | Link road to Gagyong village 3 km | 87.00 | 87.00 | 70.37 | 100% | |
| 9 | Construction of truckable road from Borong -Phamtam road to upper Borong via Gurung Gumpa km 1st to 2nd. | 64.00 | 64.00 | 51.49 | 100% | |
| 10 | Extension of truckable road to lower Borong km 3rd to 4th. | 70.32 | 70.32 | 57.86 | 100% | |
| 11 | Extension of Bhaisalgaon-Salghari road to Farashey km 1st to 3rd | 100.00 | 100.00 | 92.96 | 100% | |
| 12 | Link road from Kaluk to lower Sribadam via Samdong km1st to 5th | 150.00 | 150.00 | 116.95 | 95% | |
| 13 | Construction of 65 mtr span steel bridge over Rangit river between Mangnam Phamtam. | 148.93 | 148.93 | 148.91 | 60% | |
| TOTAL | 1301.79 | 1301.79 | 1055.35 | 0.00 | ||