MONTHLY PHYSICAL AND FINANCIAL  PROGRESS REPORT FOR THE MONTH ENDING SEPTEMBER 2009
   
Sl.No Name of Schemes   Length Km / M Name of Contractor Plan Funding Agency (Head) SANCTIONED  AMOUNT Date of Commen- cement Stipulated Date of Completion Phy Prog-ress               in % Financial Progress Balance  TOTAL SA-BAL Remarks
  S. share C.share Total Expenditure till date  
  S.Share C.Share Total S.Share C.Share Total  
D DISTRICT : WEST
  CENTRAL  SPONSORED  SCHEMES                                        
1 Restoration of damages, Slip clearence, Drainage &surface improvement works of Geythang-Karmatar road, Singshore diversion road and Utterey-Sopakha road in West Sikkim. Kaluk 2 Km P.K.Subba   BADP - 0.00 300.00 300.00 1-Nov-08 31-Oct-09 45% 0.00 0.00 0.00 0.00 300.00 300.00 300.00 Work in progress Kaluk
2 Construction of link road from Legship-Gyalsing road km 13th to Bhanu Sailik Km 1st-2nd. Geyzing 2Km Karna Nanda Subedi - CRF Link Road 5.61 229.53 235.14 8-Mar-08 9-Dec-09 60% 5.61 75.48 81.09 0.00 154.05 154.05 154.05 Work in progress Geyzing
3 Surface improvement and strengthening and premix carpetting of Rimbi Yoksum road Km 1st to 21.70. Geyzing 21.70 Km Mr. K. N. Bhutia Tenth Plan EI Remv. 96.11 219.37 315.48 7-Feb-04 6-Aug-05 89% 54.51 219.37 273.88 41.60 0.00 41.60 41.60 Work in progress Geyzing
4 Construction of road from Salangdang to Ramnam River connecting Lodhama (West Bengal) in West Sikkim. (Part -I)     D.P Deokota   ISC New Road 0.00 869.00 869.00 April, 09 Oct, 11 0% 0.00 0.00 0.00 0.00 869.00 869.00 869.00 Work to be started Soreng
5 Construction of road from Salangdang to Ramnam River connecting Lodhama (West Bengal) in West Sikkim in steel bridges excluding steel parts (Part -II)     D.P Deokota   ISC New Road 0.00 569.00 569.00 April, 09 Oct, 11 0% 0.00 0.00 0.00 0.00 569.00 569.00 569.00 Work to be started Soreng
6 App. Road to Rincheypong Gompa / Shreda from Rinchepong Dak Bunglow Road (Km 1st ch 17th ) Kaluk 1.1Km Mr. D. Lachi Bhutia Tenth Plan MP LADS                                                                                                                                                                                                                                                                      - 0.00 15.00 15.00 16-Feb-06 15-Feb-08 89% 0.00 9.90 9.90 0.00 5.10 5.10 5.10 Work in progress Kaluk
7 Upgradation of existing Soreng Kaluk Road from Km 1st - 5th (Part - I) Kaluk 5 Km Subash Tamang   NABARD Remv. 0.00 0.00 0.00 Feb, 09 Aug, 10 0% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Work just started Soreng
8 Upgradation of existing Soreng Kaluk Road from Km 6th - 16th (Part -II) Kaluk 10 Km S.B. Gurung   NABARD Remv. 0.00 893.00 893.00 March,09 March,11 7% 0.00 0.00 0.00 0.00 893.00 893.00 893.00 Work in progress Soreng
9 Upgradation of existing Chankung Gelling Road from Km 1st - 3rd(Part - I) Kaluk 3 Km Mahindra Lakhotia   NABARD   0.00 0.00 0.00 March,09 March,11 20% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Work in progress Soreng
10 Upgradation of existing Chankung Gelling Road from Km 4th-7th(Part -II) Kaluk 4 Km Sanjay Chandak   NABARD   0.00 0.00 0.00 March,09 March,11 15% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Work in progress Soreng
11 Carpetting drainage & protective works of approach road from hee pool to Hee Yangthang Sr. Sec School in West Sikkim. Kaluk 4 Km Kundan Limboo   NABARD   11.35 56.77 68.12 17-Mar-09 16-Sep-10 0% 0.00 0.00 0.00 11.35 56.77 68.12 68.12 Agreement under process. Soreng
12 Strengthening, widening premix carpetting works along Pelling Chumbung Road Km 1st - 4th. Kaluk 4 Km P.C. Lama   NABARD Exp. 51.13 194.87 246.00 - - 25% 0.00 11.35 11.35 51.13 183.52 234.65 234.65 Work in progress Geyzing
13 Construction of link road from Alpinne Cheese factory  at kaluk Dentam Road km 19th ch 8th - Lidung Village under Dentam Consituency in West-Sikkim (Km 2nd Ch 3) Kaluk 4 Km Sabitri Thapa   NABARD   0.00 56.76 56.76 6-Feb-09 6-Dec-09 10% 0.00 0.00 0.00 0.00 56.76 56.76 56.76 Work in progress Geyzing
14 Construction of strengthening draianage & carpetting of Khanisherbong road Km 1st -11th. Soreng 11Km Mr. B. L. Gurung Eleventh Plan NEC - 0.00 486.36 486.36 3-Mar-07 9-Sep-08 50% 0.00 144.11 144.11 0.00 342.25 342.25 342.25 Work in progress Soreng
15 Strengthening draianage & carpetting of Sombaria Hilley road Km 1st- 26th Soreng 26Km Mr. Kamal Kr. Rai Tenth Plan NEC - 0.00 845.68 845.68 1-Nov-06 10-Oct-08 85% 0.00 317.22 317.22 0.00 528.46 528.46 528.46 Work in progress Soreng
16 Strengthening and carpetting, protection and drainage of Bermiock Legship road Km. 1st to 9th Kaluk 9Km Mr. Atul Dhanotia  Tenth Plan NEC - 0.00 449.46 449.46 16-Feb-06 15-Feb-08 89% 0.00 278.44 278.44 0.00 171.02 171.02 171.02 Work pending due to  non avaibility of bitumen Kaluk
17 Extension of road from Chakung to Khansirbong SPWD road to Majwa village via chota Samdong 3km length along with 2 nos RCC bridge in West Sikkim. Kaluk 9Km Mr. Atul Dhanotia  Tenth Plan NEC - 0.00 449.46 449.46 16-Feb-06 15-Feb-08 89% 0.00 278.44 278.44 0.00 171.02 171.02 171.02 Work pending due to  non avaibility of bitumen Kaluk
18 Construction of road from Sreebadam to Magalbaria 18.30Km in West-Sikkim. Geyzing 18.30 Km Bikash Tamang   NLCPR - 0.00 279.00 279.00 - - 5% 0.00 0.00 0.00 0.00 279.00 279.00 279.00 Work in progress Soreng
19 Repalacement of Rathong Suspension bridge by steel bridge on Rimbi-Yoksum road. Geyzing 60m Mrs. S. Dolma Bhutia Tenth Plan NLCPR - 0.00 327.57 327.57 2-Jun-05 31-Aug-06 97% 0.00 262.01 262.01 0.00 65.56 65.56   Work in progress Geyzing
20 Repalacement of Rimbi Suspension bridge by steel bridge on Pelling - Rimbi road. Geyzing 45m Mr. Keshav Pradhan Tenth Plan NLCPR - 2-Jun-05 31-Aug-06 90% Work in progress Geyzing
21 Construction of premix carpetting /imp. Dentam Uttrey road Km 1st to 10th  Kaluk 10Km Mr. C.B. Subba Tenth Plan NLCPR - 0.00 342.46 342.46 3-Mar-05 31-Aug-06 97% 0.00 282.49 282.49 0.00 59.97 59.97 59.97 Work in progress Kaluk
22 Surface imp/ carpetting i/c drainage works on Pelling Dentam road Km 1st to 9th  Kaluk 9Km Mr. Anjani Kr. Agarwal Tenth Plan NLCPR - 0.00 606.54 606.54 3-Mar-05 31-Aug-06 97% 0.00 544.62 544.62 0.00 61.92 61.92 61.92 Work pending due to  non avaibility of bitumen Kaluk
23 Surface imp/ carpetting i/c drainage works on Pelling Dentam road Km 10th to 17th. Kaluk 7Km Mr. Mahabir Pd. Agarwal Tenth Plan NLCPR - 104.82 301.97 406.79 3-Mar-05 31-Aug-06 93% 70.49 301.97 372.46 34.33 0.00 34.33 34.33 Kaluk
24 Surface imp/ carpetting i/c drainage works on Pelling Dentam road Km  18th to 20th Kaluk 2Km CB Subba Tenth Plan NLCPR - 0.00 91.30 91.30 3-Mar-05 31-Aug-06 100% 0.00 85.80 85.80 0.00 5.50 5.50 5.50 Work completed Kaluk
25 Replacement of B.B. Lal Suspension Bridge on Pelling Dentam road along Gyalshing Soreng Road.  Kaluk 68m Mr. Mahabir Pd. Agarwal Tenth Plan NLCPR - 0.00 200.30 200.30 3-Mar-05 31-Aug-06 97% 0.00 75.07 75.07 0.00 125.23 125.23 125.23 Work in progress Kaluk
26 Construction of prestressed bridge over Rangit River on Legship-Tashiding road. Geyzing   Mahabir Pd. Agarwal Eleventh Plan NLCPR Remv. 273.03 1638.18 1,911.21 9-Mar-09 8-Mar-11 5% 0.00 273.03 273.03 273.03 1,365.15 1,638.18 1,638.18 Work in progress Geyzing
27 Construction of 65m Span Steel Bridge over Rangit river in between Mengnem & Phamtam Geyzing 65m Mr. U. P. Bhutia (Kazi) Tenth Plan RSVY Repl. 123.85 148.93 272.78 23-Nov-05 22-May-07 60% 29.13 136.56 165.69 94.72 12.37 107.09 107.09 Work in progress Geyzing
  STATE PLAN                                        
28 Slope stablization, slip aressting & benching works, permanent restoration, catch water drain works at Gundrukey on Legship-Tashiding road. Daramdin   Sandeep Kr. Sharma Eleventh Plan ACA ACA 115.00 0.00 115.00 13-Feb-09 12-Feb-10 60% 1.88 0.00 1.88 113.12 0.00 113.12 113.12 Work in progress Geyzing
29 Slope stablization, slip aressting & benching works, permanent restoration, catch water drain works at Nauley Bhir on Gyalshing Pelling road and protgection of Class IV  Govt. Qtr near mechanical turning on Gyalshing-Pelling road. Geyzing   Deepak Kr. Pradhan Eleventh Plan ACA ACA 200.00 0.00 200.00 12-Feb-09 12-Feb-10 0% 0.00 0.00 0.00 200.00 0.00 200.00 200.00 Work not yet started Geyzing
30 Slope stablization, restoration of road at Ringyang and Mandu on Tashiding-Kongree Labdong road. Geyzing   Bikash Subedi Eleventh Plan ACA ACA 350.00 0.00 350.00 - - 0% 0.00 0.00 0.00 350.00 0.00 350.00 350.00 Work not yet started Geyzing
31 Slope stablization & benching works, GEO grid netting permanent restoration, catch water drain works at Rimbi-Kchepadi road Daramdin   Tara Sharma Eleventh Plan ACA ACA 184.96 0.00 184.96 20-Apr-09 19-Feb-10 80% 0.00 0.00 0.00 184.96 0.00 184.96 184.96 Already started & to be completed sooner. Geyzing
32 Slope stablization & slip aressting &  benching works, permanent restoration, catch water drain works 12 mile slide on Rimbi-Yoksum road Daramdin   D.K Pradhan Eleventh Plan ACA ACA 135.86 0.00 135.86 15-Jun-09 14-Mar-10 5% 0.00 0.00 0.00 135.86 0.00 135.86 135.86 Stacking of non stock material is under progress. Geyzing
33 Construction of motorable road from Relli Khola to Phamtam Km 14th - 17th. Geyzing 3Km Mr. K.N.Bhutia Tenth Plan State Plan New Road 125.19 0.00 125.19 4-Mar-03 1-Mar-04 85.5% 111.05 0.00 111.05 14.14 0.00 14.14 14.14 Work in progress Geyzing
34 Construction of motorable road from Relli Khola to Phamtam Km 18th-21st. Geyzing 3Km Mr. A.P. Pradhan Tenth Plan State Plan New Road 131.74 0.00 131.74 4-Mar-03 1-Mar-04 99% 121.25 0.00 121.25 10.49 0.00 10.49 10.49 Work in progress Geyzing
35 Construction of road from Upper Rumbuk to Tereybair in West Sikkim Km 3rd. Soreng 1Km Mr. Phurdiki Sherpa Tenth Plan State Plan New Road 24.73 0.00 24.73 1-Jan-05 4-Apr-06 85% 20.13 0.00 20.13 4.60 0.00 4.60 4.60 Work in progress Soreng
36 Construction of road from Upper Rumbuk to Tereybair in West Sikkim Km 4th. Soreng 1Km Mr. Lakpa Sherpa Tenth Plan State Plan New Road 22.36 0.00 22.36 1-Jan-05 4-Apr-06 70% 19.56 0.00 19.56 2.80 0.00 2.80 2.80 Soreng
37 Construction of road from Upper Rumbuk to Tereybair in West Sikkim Km 5th. Soreng 1Km Mr. Lakpa Sherpa Tenth Plan State Plan New Road 24.45 0.00 24.45 1-Jan-05 4-Apr-06 70% 20.05 0.00 20.05 4.40 0.00 4.40 4.40 Work in progress Soreng
38 Construction of road from Upper Rumbuk to Tereybair in West Sikkim Km 6th. Soreng 1Km Mr. Lakpa Sherpa Tenth Plan State Plan New Road 22.75 0.00 22.75 1-Jan-05 4-Apr-06 40% 15.00 0.00 15.00 7.75 0.00 7.75 7.75 Soreng
39 Construction of 1.60 Km approach road to 50m Span Steel BridgeOver Rangit river at Phamtam Geyzing 1.6 Km Departmental - State Plan New Road 149.03 0.00 149.03 01-Jun-08 01-Mar-09 28% 32.32 0.00 32.32 116.71 0.00 116.71 116.71 Work in progress Geyzing
40 Construction of approach road to  Phamtam road point to 50m Span Steel BridgeOver Rangit river. Geyzing 50m Departmental - State Plan New Road 37.52 0.00 37.52 10-Jun-08 02-Mar-09 98.5% 29.67 0.00 29.67 7.85 0.00 7.85 7.85 Work in progress Geyzing
41 Providing breast wall along approach road tolower Rumbuk School from Saili Gaon Km 1st Ch 21 Geyzing 50m Sukmit Lepcha - State Plan Remv. 6.15 0.00 6.15 Feb, 09 Aug,09 50.0% 4.36 0.00 4.36 1.79 0.00 1.79 1.79 Work in progress Geyzing
42 Construction of motorable road from Khanisirbong to kamling. 13th - 21st Soreng 1Km Mr. N.T. Tamang Tenth Plan State Plan Remv. 105.56 0.00 105.56 1-Jan-05 11-Nov-06 10% 23.50 0.00 23.50 82.06 0.00 82.06 82.06 Work order cancelled Soreng
43 Widening, surface improvement, premix carpetting of Sombaria Puretar Km 6th to 13th Soreng 7Km Mr. Amrit Subba, Prakash Subba, S.H. Sherpa, P.D. Sherpa  Tenth Plan State Plan Remv. 128.00 0.00 128.00 1-Jan-05 10-Oct-06 100% 124.92 0.00 124.92 3.08 0.00 3.08 3.08 Work completed Soreng
44 Technical Surveillance and rehabilitation of Singshore Suspensiopn Bridge along Dentam Uttarey Road  Kaluk N/A AS Bumper   State Plan Repl. 110.00 0.000 110.00 7-Jun-06 7-Nov-08 60% 67.70 0.00 67.70 42.30 0.00 42.30 42.30 Work in progress Kaluk
45 Construction of 25m span suspension bridge at Reshi Khola on Shribadam Deyathang road. Soreng 25m Mr. B.R. Sharma Tenth Plan State Plan Repl. 45.03 0.00 45.03 3-Mar-05 3-Mar-07 80% 27.11 0.00 27.11 17.92 0.00 17.92 17.92 Work in progress Soreng
46 Construction  of road from Rinnchenpong Magalbaria -Deorali to Upper & Lower Chuchen village via Mangbir in West Sikkim.     Khusendra Sharma   State Plan STIDF 0.00 0.00 0.00 - - 0% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Work started Kaluk
47 Construction  of road from Kalez khola Power House intake to Jhakridunga via Ferek Km 1st - 9th in West-Sikkim.      Kamal Singh Gurung   State Plan STIDF 0.00 0.00 0.00 - - 0% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Work started Kaluk
48 Construction  of 55.00m Steel Bridge over Rateypani Khola along Mangley Chuchen Road.     Bir Man Rai   State Plan STIDF 0.00 0.00 0.00 - - 0% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Documents  under process. Kaluk
49 Construction  of 30.00m Steel Bridge over Rateypani Khola along Mangley Chuchen Road.     Bir Man Rai   State Plan STIDF 0.00 0.00 0.00 - - 0% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Documents  under process. Kaluk
50 Construction  of 10.00m Steel Bridge over Rateypani Khola along Mangley Chuchen Road.     Bir Man Rai   State Plan STIDF 0.00 0.00 0.00 - - 0% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Documents  under process. Kaluk
51 Construction  of 57.00m Steel Bridge over Kalej Khola along Intake Jhakridunga road.     Man Kr. Gurung   State Plan STIDF 0.00 0.00 0.00 - - 0% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Documents  under process. Kaluk
52 Construction  of 25.00m Steel Bridge over Farek Khola along Intake Jhakridunga road.     Gayendra Pd. Basnett   State Plan STIDF 0.00 0.00 0.00 - - 0% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Documents  under process. Kaluk
53 Surface improvement and strengthening and premix carpetting of Ribdi Bhareng road Km1st to 4th in West Sikkim     Mr. Mohan Prasad Rai   State Plan TSP 423.00 0.00 423.00 June, 09 June, 11 0% 0.00 0.00 0.00 423.00 0.00 423.00 423.00 Work to be started Kaluk
54 Permanent restoration of roads near naya bazar Forest Check Post on NDP road km 2nd.     Prem Kr. Chandak   State Plan Major Works Plan 164.66 0.00 164.66 Feb, 09 Aug, 9 95% 161.10 0.00 161.10 3.56 0.00 3.56 3.56 Work in progress Kaluk
55 Permanent restoration of Bojeck Slide &b other drainage roads.     Departmental   State Plan Major Works Plan 180.00 0.00 180.00 Nov, 08 July, 09 0% 179.96 0.00 179.96 0.04 0.00 0.04 0.04 Work in progress Kaluk
56 Reconstruction of short span RCC bridge bover Jhandy Khola on Soreng Sombarey road.     Departmental   State Plan Major Works Plan 25.00 0.00 25.00 Jan, 09 July, 09 100% 24.99 0.00 24.99 0.01 0.00 0.01 0.01 Work completed Kaluk
                                             
 
 
 
 
 
 