MONTHLY PHYSICAL AND FINANCIAL  PROGRESS REPORT FOR THE MONTH ENDING MARCH 2009
   
Sl.No Name of Schemes   Length Km / M Name of Contractor Plan Funding Agency (Head) SANCTIONED  AMOUNT Date of Commen- cement Stipulated Date of Completion Phy Prog-ress               in % Financial Progress Balance  TOTAL SA-BAL Remarks
  S. share C.share Total Expenditure till date  
  S.Share C.Share Total S.Share C.Share Total  
A DISTRICT:  NORTH          
  CENTRAL  SPONSORED  SCHEMES                      
1 Construction of app. Road to Thomchi Gumpa.   0.15 Km Mr. Tashi Lachungpa   BADP BADP 0.00 15.69 15.69 6-Feb-07 5-May-07 100% 0.00 9.97 9.97 0.00 5.72 5.72 5.72 Work completed
2 Construction of new road from Gumpa Golai to Chanzing, Lachen.   0.48 Km Mr Nangden Lachungpa   BADP BADP 0.00 38.10 38.10 - - - 0.00 0.00 0.00 0.00 38.10 38.10 38.10  
3 Upgradation / Strengthening and Carpeting of approach road to Latoong Village.   1Km Mr Nangden Lachungpa   BADP BADP 0.00 42.79 42.79 - - 70% 0.00 19.40 19.40 0.00 23.39 23.39 23.39 Work in progress
4 Construction of Guest House / Inspection Bunglow at Yakthang, Lachen (Thangu).   N/A -   BADP BADP 0.00 138.00 138.00 - - - 0.00 0.00 0.00 0.00 138.00 138.00 138.00 -
5 Extension of Bakcha -Labi road Km 3rd & 4th. State share of BADP land compansation.   2Km Mr. Ugen Nedup Bhutia   BADP BADP 0.00 50.00 50.00 - - 100% 0.00 49.91 49.91 0.00 0.09 0.09 0.09 Work completed
6 Upgradation & Surface strengthening of Ranka-Sichey road Km 1st to 3rd   3Km Mr. Rajesh Agarwal Tenth Plan CRF Removal 30.78 88.26 119.04 17-Mar-05 31-May-06 100% 0.00 72.10 72.10 30.78 16.16 46.94 46.94 Work completed
7 Upgradation of Phodong -Labrang Gumpa   2.25 Km Mr. K.N. Bhutia Tenth Plan CRF CRF 0.00 158.96 158.96 3-Nov-05 2-Oct-06 100% 0.00 151.37 151.37 0.00 7.59 7.59 7.59 Work completed
8 Construction of 18 mtrs span Steel Bridge over Rakshey Khola along Penlong - Tintek road at Km 13th, CH: 1   18m - Tenth Plan CRF CRF 0.00 90.99 90.99 18-Oct-06 - 90% 0.00 60.97 60.97 0.00 30.02 30.02 30.02 Work in progress
9 Widening of upgradation, carpetting, protective of drainage works on approach road to Zimchung Busty from DAC road, Mangan   2.45 Km Department. Tenth Plan MP (LAPS)  - 0.00 25.00 25.00 - - 100% 0.00 0.00 0.00 0.00 25.00 25.00 25.00 Work completed
10 Upgradation Ranka - Luing-Gangtok-Burthuk-Road Km 14th to 21st   7 Km Mr. Shyam Rai Tenth Plan NLCPR  Exp. 221.54 420.00 641.54 11-Jan-05 19-Jul-07 68% 0.00 408.00 408.00 221.54 12.00 233.54 233.54 Work in progress
11 Construction 0f 90m span steel bridge over Takcham Chu along C.R.B.A Road, Km 21st    90m Mrs. Meera Rai Tenth Plan NEC Exp. 0.00 476.74 476.74 9-Jan-06 8-Oct-06 90% 0.00 324.00 324.00 0.00 152.74 152.74 152.74 Work in progress
12 Upgradation / carpeting & extension i/c providing drainage and protective works of Marchak - Tumlabong road, Km 1st to 13th in East Sikkim   13Km M/s Ladakhi Const. Pvt. Ltd. Tenth Plan NEC Exp. 0.00 1,023.00 1,023.00 9-Nov-06 18-May-08 65% 0.00 339.05 339.05 0.00 683.95 683.95 683.95 Work in progress
13 Construction of steel bridge over Teesta river at Gour at Dzongu (LC from SP 6.84)   122m Mr. Samdup Lepcha Tenth Plan NEC NEC 6.84 488.57 495.41 21-Jan-06 22-Jan-07 94% 6.62 404.99 411.61 0.22 83.58 83.80 83.80 Work in progress
14 Strengthening / drainage carpetting of SBS road to Tingbong high school    7km Mr. G.N. Agarwal Tenth Plan NEC NEC / TSP 401.38 401.38 802.76 29-Apr-05 30-Apr-06 100% 401.38 367.19 768.57 0.00 34.19 34.19 34.19 Work completed
15 Construction of Steel Bridge on Approach road to Khedum Village in North Sikkim.   50m Mr. Penzong Lachungpa Tenth Plan NEC NEC 0.00 281.51 281.51 24-Feb-06 23-Jan-07 94% 0.00 198.75 198.75 0.00 82.76 82.76 82.76 Work in progress
16 Upgradation of Marchak Tumlabong Road (NEC ) State Share for LC   13Km Compensatiion   NEC Removal 100.00 1,023.00 1,123.00 - - 37% 37.00 522.75 559.75 63.00 500.25 563.25 563.25 Work in progress
17 Construction of road from lower Lingdum  to Adampool, Km 3rd & 4th   2Km Mr. Ajay Rai Tenth Plan NABARD  Exp. 29.64 73.43 103.07 16-Nov-06 15-May-07 100% 18.59 73.43 92.02 11.05 0.00 11.05 11.05 Work completed
18 Carpetting of app. Road to Crematorium ground at Jalipool.   0.28 Km Mr. Praveen Agarwal Tenth Plan NABARD  Exp. 11.14 20.66 31.80 31-Jan-06 15-Jun-06 100% 9.35 17.00 26.35 1.79 3.66 5.45 5.45 Work completed
19 Construction of Link Road from Takchi Phatak to Upper Luing, Km 1st   1Km Mr. Tsweang Rinzing Bhutia Tenth Plan NABARD New Road 0.00 289.930 289.930 18-Aug-05 17-Aug-06 90% 0.00 138.17 138.17 0.00 151.76 151.76 151.76 Work in progress
20 Construction of Link Road from Takchi Phatak to Upper Luing, Km 2 nd   1Km Dewjang Bhutia Tenth Plan NABARD New Road 18-Aug-05 17-Aug-06 85% 0.00 Work in progress
21 Construction of Link Road from Takchi Phatak to Upper Luing, Km 3rd   1Km Tempo Gyatso Bhutia Tenth Plan NABARD New Road 23-Sep-05 22-Sep-06 85% 0.00 Work in progress
22 Construction of Link Road from Takchi Phatak to Upper Luing, Km 4th   1Km Yangchen Dolma Bhutia Tenth Plan NABARD New Road 23-Sep-05 22-Sep-06 0% 0.00  
23 Construction of Link Road from Takchi Phatak to Upper Luing, Km 5th   1Km Yangchen Dolma Bhutia   NABARD New Road 23-Sep-05 22-Sep-06 0% 0.00  
24 Extension of 3rd Km road from 3rd mile turning (Tintek Dikchu road) to Rakshey via Kedangthang Km 4th to 6th   2Km Devi Dhakal Tenth Plan NABARD - 56.17 224.460 280.630 15-May-08 15-May-09 80% 0.00 174.73 174.73 56.17 49.73 105.90 105.90 Work in progress
25 Extension of link road fromGRS road Km 12th CH 5 to Tatopani at Rumtek   1Km M. Karki Tenth Plan NABARD - 0.00 40.190 40.190 15-May-08 15-May-09 20% 0.00 0.18 0.18 0.00 40.01 40.01 40.01 Work in progress
26 Construction of Link Road from Zimchung to Nampathang KM 1st to 3rd    3Km Mr. Zingmee Ongda, Mr. Dawa.Lepcha, Mr. Choppel Tshering Tenth Plan RSVY  RSVY  18.75 112.11 130.86 10-Nov-05 10-Nov-06 100% 16.32 112.11 128.43 2.43 0.00 2.43 2.43 Work completed
27 Construction of Link Road from 3rd Mile Turning of Tintek Dikchu road to Rakshey via Kedhangthang. Km 1st to 3rd.   3Km Punya Prasad Dhakhal Tenth Plan RSVY  New Road 22.00 121.79 143.79 25-Oct-05 31-Jan-07 100% 0.00 120.76 120.76 22.00 1.03 23.03 23.03 Work completed
28 Construvction of Link Road from Bay to Pentong in North Sikkim.   3.9 Km Mr. Bernald Lepcha Tenth Plan RSVY  New Road 37.45 150.00 187.45 22-Sep-05 31-Dec-08 65% 0.00 128.03 128.03 37.45 21.97 59.42 59.42 Work in progress
29 Construction of Heli Port at Lachung   N/A Mr. Nidup Lachungpa Ninth Plan Tourism Other Expenditure 38.89 0.00 38.89 3-Apr-00 2-Jan-01 75% 0.00 28.43 28.43 38.89 -28.43 10.46 10.46 Work in progress
  WORKS  SANCTIONED  UNDER  STATE  PLAN                              
30 Construction of Rest House at Samdong in East Sikkim.   N/A Mr. Nitup Lepcha Tenth Plan Addl.Facilities Addl.Facilities 78.70 0.00 78.70 20-May-03 19-Apr-04 100% 75.32 0.00 75.32 3.38 0.00 3.38 3.38 Work completed
31 Premix carpetting,on Penlong - Tintek road Km 12th - 20th    8Km Mr. Suresh Mundra Tenth Plan State Plan Exp. 158.79 0.00 158.79 28-Nov-02 31-Mar-06 100% 99.54 0.00 99.54 59.25 0.00 59.25 59.25 Work completed
32 Const. of GOR Santok road Km. 1st    1Km Mr.Pentok Lepcha Tenth Plan State Plan Exp. 29.76 0.00 29.76 - - 100% 21.61 0.00 21.61 8.15 0.00 8.15 8.15 Work completed
33 Construction of link road to Aho - Manghim Km 1st - 3rd (L.C = 42.02)   3 Km Mr. B.K. Upreti / BR Subba / Beena Subba Tenth Plan State Plan Link Road 97.05 0.00 97.05 2-Dec-04 15-Jan-07 63% 36.37 0.00 36.37 60.68 0.00 60.68 60.68 Work in progress
34 Surface renewal / restoration works on approach road to Mission Khoti.   2Km 13ch Mr. Ugen palzor   State Plan Removal 32.79 0.00 32.79 28-Feb-04 27-Aug-04 100% 32.60 0.00 32.60 0.19 0.00 0.19 0.19 Work completed
35 Premix carpetting p/w approach road to Hee-Gyathang School.   0.7 Km Department. Tenth Plan State Plan Removal 23.01 0.00 23.01  -  - 100% 19.99 0.00 19.99 3.02 0.00 3.02 3.02 Work completed
36 Premix carpeting on GRBA road KM 1st -10th (Phase I ) Revised   10Km Mr. A.N. Upreti Tenth Plan State Plan Removal 215.65 0.00 215.65 13-Jan-03 12-Jul-04 96% 207.01 0.00 207.01 8.64 0.00 8.64 8.64 Work in progress
37 Premix carpetting, improvement of GRBA road Km 18th to 21st and Assam Pakyong Road Km 1st to 6th.   9Km Mr. Amrit Rai Tenth Plan State Plan Removal 254.76 0.00 254.76 25-Aug-04 31-Mar-06 100% 184.20 0.00 184.20 70.56 0.00 70.56 70.56 Work completed
38 Uplifting & Surface & Drainage works, improvement along approach road to Sichey school.   0.21 km Mr. Rohit Pradhan Tenth Plan State Plan Removal 3.77 0.00 3.77 27-Feb-06 29-Dec-06 100% 3.03 0.00 3.03 0.74 0.00 0.74 0.74 Work completed
39 Upgradation and Imp of Rumtek Ranka road Km 18th   1Km Department. Ninth Plan State Plan Removal 1.36 0.00 1.36 - - 0% 0.00 0.00 0.00 1.36 0.00 1.36 1.36  
40 Construction of 15 mtrs span RCCl Bridge over Khedum Chu   15m Gyatso Bhutia   State Plan Removal 20.72 0.00 20.72 12-Nov-98 11-Mar-99 100% 19.36 0.00 19.36 1.36 0.00 1.36 1.36 Work completed
41 Construction of 55m Supension Bridge over Khedumcu at Lachung   55m Needup Lacungpa Tenth Plan State Plan Removal 112.31 0.00 112.31 12-Nov-98 11-Jul-99 100% 100.09 0.00 100.09 12.22 0.00 12.22 12.22 Work Completed/ payment of land to be made
42 Upgradation,carpetting, protective and drainage of SBS road to Lingtam PHSE Km 1st to 5th.   5Km Mr. Samdup Lepcha Eleventh Plan State Plan Strengthning Road Infrastructure 385.54 0.00 385.54 - - 55% 42.22 0.00 42.22 343.32 0.00 343.32 343.32 Work in progress
43 Upgradation,carpetting, protective and drainage works of DSM road to Gour School Km 1st to 8th.   8Km Mr. Soden Gyamptso Bhutia Tenth Plan State Plan Strengthning Road Infrastructure 391.66 0.00 391.66 1-Jun-08 1-Jan-09 50% 57.78 0.00 57.78 333.88 0.00 333.88 333.88 Work in progress
44 Protective Drainage and Carpetting works on SBS Road Km 3 & 4    2Km Mr. Pintso Namgyal Ninth Plan State Plan TSP 27.19 0.00 27.19 27-Nov-01 26-Feb-02 100% 19.37 0.00 19.37 7.82 0.00 7.82 7.82 Work completed
45 Protective Drainage and Carpetting works on SBS Road Km 5 & 6    2Km Mr. Karma Lepcha Ninth Plan State Plan TSP 23.38 0.00 23.38 11-Jan-03 10-Oct-03 100% 16.77 0.00 16.77 6.61 0.00 6.61 6.61 Work completed
46 Protective Drainage and Carpetting works on SBS Road Km 7    1Km Mr. Ten Tsh. Lepcha Ninth Plan State Plan TSP 11.17 0.00 11.17 27-Nov-01 26-Nov-02 100% 7.17 0.00 7.17 4.00 0.00 4.00 4.00 Work completed
47 Protective Drainage and Carpetting works on SBS Road Km 8    1Km Mr. Dupden Lepcha Ninth Plan State Plan TSP 22.48 0.00 22.48 27-Nov-01 27-Nov-02 100% 19.28 0.00 19.28 3.20 0.00 3.20 3.20 Work completed
48 Protective Drainage and Carpetting works on SBS Road Km 9    1Km Mr. Pintso Lepcha   State Plan TSP 19.23 0.00 19.23 27-Nov-01 28-Nov-02 100% 18.21 0.00 18.21 1.02 0.00 1.02 1.02 Work completed
49 Construction of Guest House at Pentok, Mangan, North Sikkim.   N/A - Eleventh Plan State Plan TSP 187.08 0.00 187.08 2006 - - 0.00 0.00 0.00 187.08 0.00 187.08 187.08  
50 Widening protective work drainage & carpetting work on S.B.S Road Km 10th & 12th   2Km Mr. Lobzang Lepcha Tenth Plan State Plan TSP 34.51 0.00 34.51 15-Nov-03 14-Aug-04 73% 14.99 0.00 14.99 19.52 0.00 19.52 19.52 Work in progress
51 Widening protective work drainage & carpetting work on S.B.S Road Km 13th    1Km Mr. Sonam Dorjee Tenth Plan State Plan TSP 18.68 0.00 18.68 18-Nov-04 17-May-05 70% 0.73 0.00 0.73 17.95 0.00 17.95 17.95 Work in progress
52 Widening protective work drainage & carpetting work on S.B.S Road Km 14th & 15TH   2Km Mr. Topnam Lepcha   State Plan TSP 35.15 0.00 35.15 11-Jan-03 10-Oct-03 80% 10.24 0.00 10.24 24.91 0.00 24.91 24.91 Work in progress
53 Strengthening, protective / drainage carpetting works on approach road to Ringtham Gumpa Km1st to 3rd  Mangan.   3Km K.N. Lachenpa   State Plan TSP 276.00 0.00 276.00 14-Mar-08 18-Sep-09 55% 11.51 0.00 11.51 264.49 0.00 264.49 264.49 Work in progress
54 Construction approach road to medicine pond B-6   0.96 Km Tempo Lepcha   State Plan TSP 105.00 0.00 105.00 6-Mar-08 7-Mar-09 65% 62.73 0.00 62.73 42.27 0.00 42.27 42.27 Work in progress
55 Construction approach road to Shakothang at Sarchok village   0.67 Km Dawa Gaytmso Lachenpa Tenth Plan State Plan TSP 64.98 0.00 64.98 7-Apr-08 8-Apr-09 40% 3.27 0.00 3.27 61.71 0.00 61.71 61.71 Work in progress
56 Protective works, widening, drainage and carpeting on Bictchu road Km 1st to 3rd to Gai Gaon at Lachung   3Km Needup Lacungpa   State Plan TSP 298.00 0.00 298.00 21-Aug-08 2-Aug-10 50% 86.28 0.00 86.28 211.72 0.00 211.72 211.72 Work in progress
57 Premix Carpetting imp & widening of D.S.M road km 12th to 16th    4Km Mr. Singhik Lepcha Tenth Plan State Plan TSP 124.05 0.00 124.05 15-Jan-03 14-Jul-04 80% 54.90 0.00 54.90 69.15 0.00 69.15 69.15 Bill prepared till work done, Road Handed to BRO
58 Premix Carpetting imp & widening of D.S.M road km 17th    1Km Mr. Chewang Norbu Tenth Plan State Plan TSP 19.41 0.00 19.41 11-Jan-03 10-Oct-03 100% 9.93 0.00 9.93 9.48 0.00 9.48 9.48 Work completed
59 Premix Carpetting imp & widening of D.S.M road km 18th    1Km Mr. Dawa Tshering  Tenth Plan State Plan TSP 19.56 0.00 19.56 11-Jan-03 10-Oct-03 85% 10.91 0.00 10.91 8.65 0.00 8.65 8.65 Bill prepared till work done, Road Handed to BRO
60 Premix Carpetting imp & widening of D.S.M road km 19th    1Km Mr. Ongden lepcha Tenth Plan State Plan TSP 20.44 0.00 20.44 11-Jan-03 10-Oct-03 73% 7.44 0.00 7.44 13.00 0.00 13.00 13.00
61 Premix Carpetting imp & widening of D.S.M road km 20th    1Km Mr. Mingma Tshering Tenth Plan State Plan TSP 20.04 0.00 20.04 11-Jan-03 10-Oct-03 74% 12.50 0.00 12.50 7.54 0.00 7.54 7.54
62 Premix Carpetting imp & widening of D.S.M road km 21st     1Km Mr. Lobzang Lepcha   State Plan TSP 23.38 0.00 23.38 11-Jan-03 10-Oct-03 75% 13.55 0.00 13.55 9.83 0.00 9.83 9.83
B DISTRICT :EAST      
  CENTRAL  SPONSORED  SCHEMES                                
1 Const. of link road from Arubotey to Subaneydara km 1st-3rd. Pakyong 3Km Om Bhd. Gurung Ninth Plan BADP - 0.00 29.97 29.97 30-Nov-00 16-Mar-01 68% 0.00 22.98 22.98 0.00 6.99 6.99 6.99 Work abondoned
2 Const. of link road from sisney to North Regu km 1st -4th. Pakyong 4Km T.S. Lama Tenth Plan BADP - 0.00 30.31 30.31 21-Nov-00 5-Mar-01 95% 0.00 24.54 24.54 0.00 5.77 5.77 5.77 Work abondoned
3 Construction of 60 m span steel bridge at Bongliung over Rongli Chu in East Sikkim   60m Gazendra Rai Eleventh Plan CSS   0.00 74.07 74.07 29-Mar-08 29-Sep-09 20% 0.00 0.00 0.00 0.00 74.07 74.07 74.07 Work in progress
4 Const. of 12 m span R.C.C. Bridge on Sangkhola Zingla Martam Road at Km 11th ch-3rd.   12m Anita Gurung Eleventh Plan CRF  - 0.00 38.63 38.63 1-Apr-07 31-Mar-08 50% 0.00 10.23 10.23 0.00 28.40 28.40 28.40 Work in progress
5 Const. of 12 m span R.C.c. Bridge on Sangkhola Zingla Martam Road at Km 12th ch-4th..   12m T.B. Pradhan Eleventh Plan CRF  - 0.00 45.12 45.12 1-Apr-07 31-Mar-08 70% 0.00 27.70 27.70 0.00 17.42 17.42 17.42 Work in progress
6 Surface improvement and widening of Sang Sirwani Road Km 1st & App Road from Mech Sub Div Office at Dochum   1Km Kishor Pradhan Eleventh Plan CRF  - 0.00 155.00 155.00 10-Oct-07 9-Sep-08 90% 0.00 71.18 71.18 0.00 83.82 83.82 83.82 Work in progress
7 Surface improvement and widening of Sang Sirwani Road Km 2nd & App Road to Mech Workshop Dochum   1Km K.R. Sharma Eleventh Plan CRF  - 0.00 38.49 38.49 10-Oct-07 9-Sep-08 100% 0.00 12.61 12.61 0.00 25.88 25.88 25.88 Work completed
8 Upgradation of Link Road from NH-31A to Dokey Chisopani Km 1st    1Km Kishor Pradhan Eleventh Plan CRF  - 0.00 152.58 0.00 29-Feb-08 28-Feb-09 35% 0.00 29.41 0.00 0.00 123.17 0.00 0.00 Work in progress
9 Upgradation of Link Road from NH-31A to Dokey Chisopani Km 2nd  Singtam 1Km Gopal Sharma Eleventh Plan CRF  - 29-Feb-08 28-Feb-09 30% 0.00 Work in progress
10 Upgradation of Link Road from NH-31A to Dokey Chisopani Km 3rd Singtam 1Km Suren Gurung Ninth Plan CRF  - 29-Feb-08 28-Feb-09 45% 0.00 Work in progress
11 Construction of link road from pakyong  Nop gaon to barpipal Dara, Km 1st-3rd in East-Sikkim Pakyong 3Km Hemandri Adhikari Eleventh Plan CRF CSS 0.00 102.29 102.29 5-Aug-08 5-Mar-10 50% 0.00 0.00 0.00 0.00 102.29 102.29 102.29 Work in progress
12 Upgradationand premix carpeting along Duga Pachaykhani road KM 1st-14th. Singtam 14Km B.K.Agarwal Tenth Plan EI Remv. 407.61 433.77 841.38 21-Feb-05 5-Mar-08 100% 24.00 433.77 457.77 383.61 0.00 383.61 383.61 Work completed
13 Construction of Road from Rathong (NH-31A) to Kimchithang Km 1st to 15th (EI)   15Km KK Agarwal Tenth Plan EI New Road 765.00 701.89 1,466.89 2007 - 30% 0.00 209.91 209.91 765.00 491.98 1,256.98 1,256.98 Work in progress
14 Improvement of  Sang Dipudara Road (EI)   14Km - Tenth Plan EI - 0.00 347.74 347.74 2007 - 90% 0.00 0.00 0.00 0.00 347.74 347.74 347.74 Work in progress
15 Improvement of  Pakyong - Karthok - Naya busty - Raigoan  Road (EI)   7Km - Eleventh Plan EI - 0.00 398.42 398.42 2007 - 45% 0.00 160.00 160.00 0.00 238.42 238.42 238.42 Work in progress
16 Widening, upgradation of pavement & drainage system along  Rangpo Duga Pendam road km 1st - 15th    15Km M/s Apex Project & Investment                 P. Ltd. Eleventh Plan ISC  - 0.00 950.00 950.00 15-Jun-08 16-Dec-08 65% 0.00 303.67 303.67 0.00 646.33 646.33 646.33 Work in progress
17 Improvement of Rhenock - Simanakhola Road Km 1st to 3rd. (ISC)   3Km Mr. Kuber Raj Rai Tenth Plan ISC  - 0.00 250.00 250.00 26-Mar-08 - 30% 0.00 49.43 49.43 0.00 200.57 200.57 200.57 Work in progress
18 Strengthening/drainage and P/Wprks for the road from Lal Turning to Bashilakha Road Km 1st to 3rd Pakyong 3Km G.M Gurung   NABARD Exp. 33.19 125.21 158.40 30/09/07 31/03/08 100% 0.00 124.82 124.82 33.19 0.39 33.58 33.58 Work completed
19 Const. of link road from King Stone to Simana Khola Km 1st to 2nd.   2Km Departmental Eleventh Plan NABARD Exp. 8.60 34.41 43.01 - - 100% 0.00 31.68 31.68 8.60 2.73 11.33 11.33 Work completed
20 Construction of Link Road from Sakyong to Beyong km 1st to 2nd (State Share of NABARD)   2Km KRSharma & TB Pradhan Eleventh Plan NABARD Exp. 0.00 79.51 79.51 12-Mar-08 11-Mar-09 80% 0.00 23.59 23.59 0.00 55.92 55.92 55.92 Work in progress
21 Strengthening,drainage and Carpeting and construction of 30m span steel bridge along Assam-Pakyong road km 7th - 15th. Pakyong 30m S.K. Agarwal Tenth Plan NEC  - 0.00 750.76 750.76 6-Nov-06 5-May-08 80% 0.00 465.96 465.96 0.00 284.80 284.80 284.80 Work in progress
22 Construction of major retaining structures on approach road to Raj Bhawan,VIP Complex and TNA Public School Complex   N/A   Tenth Plan NEC  - 0.00 110.58 110.58 30-May-05 29-May-06 100% 0.00 99.67 99.67 0.00 10.91 10.91 10.91 Work completed
23 Replacement of Sumin Wooden Suspension Bridge on Sang Khola Sumin Road   40m   Eleventh Plan NEC  - 0.00 285.40 285.40 8-Apr-04 - - 0.00 233.00 233.00 0.00 52.40 52.40 52.40 -
24 Const. of Goshkhan Dara Bridge over River Teesta at Singtam, East Sikkim Singtam 120m M.P Agarwal Tenth Plan NLCPR  - 0.00 1,337.11 1,337.11 10-Jan-07 11-Jun-08 40% 0.00 468.00 468.00 0.00 869.11 869.11 869.11 Work in progress
25 Const. of diversion road Ranipool-Pakyong road km 1st-3rd. Pakyong 3Km B.K. Agarwal Tenth Plan NLCPR  Exp. 102.98 236.87 339.85 21-Feb-05 21-Nov-05 100% 64.60 170.78 235.38 38.38 66.09 104.47 104.47 Work completed
26 Extension of Link Road to Dokey Chisopani Pry School    ( State Share of RSVY Scheme)   0.81Km Nabin Rai Eleventh Plan RSVY New Road 1.72 25.00 26.72 17-Oct-05 27-Mar-06 100% 0.00 25.00 25.00 1.72 0.00 1.72 1.72 Work completed
  STATE PLAN                                        
27 Repairs of IETC SMITE Overhead crane station at 5th Mile Tadong   N/A Departmental Tenth Plan State Plan Addl.Facilities 1.35 0.00 1.35 20-Jul-06 - 5% 1.35 0.00 1.35 0.00 0.00 0.00 0.00 Work in progress
28 Fencing around SPWD Mech. Workshop Tadong   N/A Departmental Eleventh Plan State Plan Addl.Facilities 2.74 0.00 2.74 31-Aug-06 - 5% 2.73 0.00 2.73 0.01 0.00 0.01 0.01 Work in progress
29 Additonal facilities installation of portable magazine at Sirwani-Singtam   N/A Departmental Tenth Plan State Plan Addl.Facilities 10.00 0.00 10.00 22-Aug-07 - 5% 9.45 0.00 9.45 0.55 0.00 0.55 0.55 Work in progress
30 Premix carpetting/Imp. Of Rongli Rorathang road, Km 1st - 11th.( Revised)   11Km Kuber Raj Rai Tenth Plan State Plan Exp. 254.00 0.00 254.00 1-Jan-03 3-Apr-06 100% 215.36 0.00 215.36 38.64 0.00 38.64 38.64 Work completed
31 Upgradation/carpeting P/works and drainage along Pakyong-Karthok road km 1st-4th. Pakyong 4Km P. N. Kazi Tenth Plan State Plan Exp. 286.69 0.00 286.69 28-Mar-05 27-Jul-06 60% 95.08 0.00 95.08 191.61 0.00 191.61 191.61 Work in progress
32 Upgradation and premix carpeting of Kotlaytar Rai Gaon Road,km 1st & 2nd  Pakyong 2Km Miss Devi Dakhal Tenth Plan State Plan Exp. 146.88 0.00 146.88 28-Mar-05 27-Sep-06 80% 31.05 0.00 31.05 115.83 0.00 115.83 115.83 Work in progress
33 Upgradation and premix carpeting of Kotlaytar Rai Gaon Road,km 3rd Pakyong 1Km Mr. G.K. Pradhan Tenth Plan State Plan Exp. 22.70 0.00 22.70 1-Jul-05 31-Dec-07 90% 22.13 0.00 22.13 0.57 0.00 0.57 0.57 Work in progress
34 Upgradation and premix carpeting of Kotlaytar Rai Gaon Road,km 4th Pakyong 1Km XXX Tenth Plan State Plan Exp. 17.92 0.00 17.92 1-Jul-05 31-Dec-07 90% 17.60 0.00 17.60 0.32 0.00 0.32 0.32 Work in progress
35 Upgradation and premix carpeting of Kotlaytar Rai Gaon Road,km 5th Pakyong 1Km K.S.Rai Tenth Plan State Plan Exp. 27.01 0.00 27.01 1-Jul-05 31-Dec-07 90% 16.04 0.00 16.04 10.97 0.00 10.97 10.97 Work in progress
36 Upgradation and premix carpeting of Kotlaytar Rai Gaon Road,km 6th Pakyong 1Km Ishore Dakahal Tenth Plan State Plan Exp. 21.15 0.00 21.15 1-Jul-05 31-Dec-07 70% 17.79 0.00 17.79 3.36 0.00 3.36 3.36 Work in progress
37 Upgradation and premix carpeting of Kotlaytar Rai Gaon Road,km 7th Pakyong 1Km K.S.Rai Tenth Plan State Plan Exp. 22.10 0.00 22.10 1-Jul-05 31-Dec-07 55% 8.68 0.00 8.68 13.42 0.00 13.42 13.42 Work in progress
38 Upgradation and premix carpeting of Kotlaytar Rai Gaon Road,km 8th Pakyong 1Km Mr. M.K. Pradhan Tenth Plan State Plan Exp. 21.66 0.00 21.66 1-Jul-05 31-Dec-07 55% 17.06 0.00 17.06 4.60 0.00 4.60 4.60 Work in progress
39 Premix Carpetting and Surface improvement Chewribotay Pendam  Km 1st - 6th Singtam 6Km Basudev Pradhan Tenth Plan State Plan Exp. 117.78 0.00 117.78 29/05/2003 31/01/04 95% 83.84 0.00 83.84 33.94 0.00 33.94 33.94 Work in progress
40 Construction of Bye Pass Road below Mintokgang Station 0.30Km DB Chettri Tenth Plan State Plan Exp. 80.26 0.00 80.26 26-Feb-04 5-Aug-04 100% 71.46 0.00 71.46 8.80 0.00 8.80 8.80 Work completed
41 Premix carpetting & Surface Imp.of KLT 16th to 26th Km (Revised)   10Km P.D. Denzongpa Tenth Plan State Plan Exp. 260.57 0.00 260.57 2003 - 100% 252.36 0.00 252.36 8.21 0.00 8.21 8.21 Work completed
42 Premix carpetting & Surface Imp.of KLT 7th to 15th Km (Revised)   8Km L.N. Sarda Tenth Plan State Plan Exp. 232.83 0.00 232.83 2003 - 100% 214.16 0.00 214.16 18.67 0.00 18.67 18.67 Work completed
43 Ext. of Pakyong-Mamring Tareythang road km 1st   1Km Khush N.Adhikari Tenth Plan State Plan Exp. 28.91 0.00 28.91 1-Jul-05 31-Dec-07 90% 28.72 0.00 28.72 0.19 0.00 0.19 0.19 Work in progress
44 Ext. of Pakyong-Mamring Tareythang road km 2nd   1Km Johar Man Rai Tenth Plan State Plan Exp. 16.61 0.00 16.61 1-Jul-05 31-Dec-07 90% 16.37 0.00 16.37 0.24 0.00 0.24 0.24 Work in progress
45 Ext. of Pakyong-Mamring Tareythang road km 3rd   1Km G.K. Pradhan Tenth Plan State Plan Exp. 22.70 0.00 22.70 1-Jul-05 31-Dec-07 90% 12.94 0.00 12.94 9.76 0.00 9.76 9.76 Work in progress
46 Ext. of Pakyong-Mamring Tareythang road km 4th.   1Km Udai Mishara Tenth Plan State Plan Exp. 17.92 0.00 17.92 1-Jul-05 31-Dec-07 90% 12.02 0.00 12.02 5.90 0.00 5.90 5.90 Work in progress
47 Ext. of Pakyong-Mamring Tareythang road km 5th.   1Km K.S.Rai Tenth Plan State Plan Exp. 27.01 0.00 27.01 1-Jul-05 31-Dec-07 90% 16.05 0.00 16.05 10.96 0.00 10.96 10.96 Work in progress
48 Ext. of Pakyong-Mamring Tareythang road km 6th.   1Km Ishore Dakahal Tenth Plan State Plan Exp. 21.15 0.00 21.15 1-Jul-05 31-Dec-07 80% 18.71 0.00 18.71 2.44 0.00 2.44 2.44 Work in progress
49 Ext. of Pakyong-Mamring Tareythang road km 7th.   1Km K.S.Rai Tenth Plan State Plan Exp. 22.10 0.00 22.10 1-Jul-05 31-Dec-07 70% 8.68 0.00 8.68 13.42 0.00 13.42 13.42 Work in progress
50 Ext. of Pakyong-Mamring Tareythang road km.8th    1Km M. K. Pradhan Tenth Plan State Plan Exp. 21.66 0.00 21.66 1-Jul-05 31-Dec-07 70% 0.00 0.00 0.00 21.66 0.00 21.66 21.66 Work in progress
51 Ext. of Pakyong-Mamring Tareythang road km.9th    1Km Kamal Adhikari Tenth Plan State Plan Exp. 19.24 0.00 19.24 1-Jul-05 31-Dec-07 100% 8.00 0.00 8.00 11.24 0.00 11.24 11.24 Work completed
52 Ext. of Pakyong-Mamring Tareythang road km.10th    1Km Milan Dahal Tenth Plan State Plan Exp. 10.70 0.00 10.70 1-Jul-05 31-Dec-07 100% 0.00 0.00 0.00 10.70 0.00 10.70 10.70 Work completed
53 Construction of Arithang Road connecting Indira Bye-Pass Road  Station 0.6Km Departmental Tenth Plan   Exp. 57.47 0.00 57.47 2005 - 100% 55.75 0.00 55.75 1.72 0.00 1.72 1.72 Work completed
54 Const. of road from Zingla Martam KM 16th-18th (2.36km) i/c LC   2Km UP Kazi Tenth Plan State Plan TSP Exp. 77.96 0.00 77.96 3-Oct-05 3-Oct-06 100% 83.16 0.00 83.16 -5.20 0.00 -5.20 -5.20 Work completed
55 Const of 40 Mts span Bridge over Rongli Khola along  arubotey subaney dara Raod Ssno 2/E/exp/06-07   40m Ashok Ts. Bhutia Eleventh Plan   Exp. 16.50 0.00 16.50 2006 - 100% 14.24 0.00 14.24 2.26 0.00 2.26 2.26 Work completed
56 Immediate Restoration of Mamring Amba Road km 3rd   1Km Departmental Tenth Plan   Exp. 6.77 0.00 6.77 6-Nov-06 5-May-08 100% 6.68 0.00 6.68 0.09 0.00 0.09 0.09 Work completed
57 Construction of 20 chain road Bio Control Laboratory to Phewk Busty road  Station 0.60Km Mr. G.K.Rai Tenth Plan State Plan Link Road 25.03 0.00 25.03 28-Sep-05 27-Mar-05 100% 9.00 0.00 9.00 16.03 0.00 16.03 16.03 Work completed
58 Const. of link road from Basilakhs to Middle camp via Rodongtar km 6th to 8th RCC Bridge (LC = 19.47) Pakyong 2 Km Justin Rai / Jeewn Subba / Paul Rai  Tenth Plan State Plan New Road 75.99 0.00 75.99 5-Oct-05 9-Feb-05 100% 12.41 0.00 12.41 63.58 0.00 63.58 63.58 Work completed
59 Const. of 10m span RCC Culvert on Basilakha to middle camp km 8th.   10m Patrush Subba Tenth Plan State Plan New Road 12.32 0.00 12.32 5-Oct-05 9-Feb-05 75% 0.00 0.00 0.00 12.32 0.00 12.32 12.32 Work in progress
60 Const of Approach road to Sivalaya Mandir at pacheykhani Km 1st   1Km R.N. Baral   State Plan New Road 23.51 0.00 23.51 18-Jul-05 15-Jun-06 85% 12.87 0.00 12.87 10.64 0.00 10.64 10.64 Work in progress
61 Construction of Link Road from Amba to Taja School 1st and 2nd km   2Km Mon Narayan Dhakal Tenth Plan State Plan New Road 5.06 0.00 5.06 - - 75% 3.96 0.00 3.96 1.10 0.00 1.10 1.10 Work in progress
62 Const. of link road from Assam-Pakyong road to Kadamtam village km.1st. Pakyong 1Km M.B.Mangar Tenth Plan State Plan New Road 39.65 0.00 39.65 1-Jul-05 30-Jun-06 100% 39.51 0.00 39.51 0.14 0.00 0.14 0.14 Work completed
63 Const. of link road from Assam-Pakyong road to Kadamtam village km.2nd. Pakyong 1Km Elies Lepcha Tenth Plan State Plan New Road 41.40 0.00 41.40 1-Jul-05 30-Jun-06 100% 41.39 0.00 41.39 0.01 0.00 0.01 0.01 Work completed
64 Const. of link road from Assam-Pakyong road to Kadamtam village km.3rd & 4th. Pakyong 2Km D.P. Mangar Tenth Plan State Plan New Road 41.51 0.00 41.51 1-Jul-05 30-Jun-06 75% 29.71 0.00 29.71 11.80 0.00 11.80 11.80 Work in progress
65 Const. of link road from Assam-Pakyong road to Kadamtam village km.3rd & 4th.Contingency Rs.4.26 + Land Compansation Pakyong 2Km LC & Contg Tenth Plan State Plan New Road 87.70 0.00 87.70 - - 100% 34.27 0.00 34.27 53.43 0.00 53.43 53.43 Work completed
66 Construction of road from Chandmari village to Jawaharlall Nehru road  Station 0.38 Km K Wangchuk   State Plan New Road 30.63 0.00 30.63 31-May-05 30-Nov-05 100% 23.76 0.00 23.76 6.87 0.00 6.87 6.87 Work completed
67 Const. of Song-zingla Martam road km 9th.   1Km P.T. Lepcha Eleventh Plan State Plan New Road 12.45 0.00 12.45 5-Mar-03 20-Dec-03 80% 5.63 0.00 5.63 6.82 0.00 6.82 6.82 Work in progress
68 Const. of Sang-Zingla Martam road KM 10th.   1Km P.T. Rongong Eleventh Plan State Plan New Road 14.51 0.00 14.51 6-Mar-03 6-Dec-03 100% 12.45 0.00 12.45 2.06 0.00 2.06 2.06 Work completed
69 Const. of Song-Zingla Martam road km 11th    1Km Anita Gurung Eleventh Plan State Plan New Road 16.17 0.00 16.17 6-Mar-03 6-Dec-03 100% 12.28 0.00 12.28 3.89 0.00 3.89 3.89 Work completed
70 Const. of Song-Zingla Martam road km 12th.   1Km U. Lama Eleventh Plan State Plan New Road 17.74 0.00 17.74 6-Mar-03 6-Dec-03 100% 13.11 0.00 13.11 4.63 0.00 4.63 4.63 Work completed
71 Const.of Song-Zingla Martam road km 14th  Singtam 1Km Tenging Bhutia Eleventh Plan State Plan New Road 25.54 0.00 25.54 6-Mar-03 6-Dec-03 100% 19.63 0.00 19.63 5.91 0.00 5.91 5.91 Work completed
72 Const. of Song-Zingla Martam road km 15th. Singtam 1Km S.K.Chettri   State Plan New Road 26.75 0.00 26.75 6-Mar-03 6-Dec-03 95% 19.95 0.00 19.95 6.80 0.00 6.80 6.80 Work in progress
73 Carpeting and surface strengthening, improvement, including drainage works of roads in and around Gangtok. Station 9.41 Km PM Chamling Tenth Plan State Plan Remv. 361.89 0.00 361.89 6-Jun-04 5-Sep-05 100% 229.45 0.00 229.45 132.44 0.00 132.44 132.44 Work completed
74 Surface strengthening upgradation and carpeting of Pakyong-Karthok Naya Busty road km 5th -7th. Pakyong 2Km Adup Bhutia Tenth Plan State Plan Remv. 220.68 0.00 220.68 21/06/05 31-Aug-08 50% 57.04 0.00 57.04 163.64 0.00 163.64 163.64 Work in progress
75 P/L edging ,soling, metalling, premix carpeting and cross drain of link road from sichey to Indira Bye Pass via Shivalaya Mandir   Station 0.3Km Mrs Rupa Dhakal Tenth Plan State Plan Remv. 8.16 0.00 8.16 1/0/2002 2-Jul-05 80% 5.81 0.00 5.81 2.35 0.00 2.35 2.35 Work in progress
76 Surface stregenthening , upgradation and carpeting of Roads during the visit of His Holiness the Dalai Lama  Station N/A Departmental Tenth Plan State Plan Remv. 40.35 0.00 40.35 2005 - 100% 38.79 0.00 38.79 1.56 0.00 1.56 1.56 Work completed
77 Providing 75mm thick CC pitching over approach raod to Gairi Goan from NH 31A Near Hotel Tashi Targey) Ssno 2/E/Remv/06-07 Station 0.3 Km Departmental Tenth Plan State Plan Remv. 3.40 0.00 3.40 2006 - 0% 0.00 0.00 0.00 3.40 0.00 3.40 3.40  
78 Const of PW along TNSS to Dhupidara Ssno 6/E/Remov/0607 Station N/A   Tenth Plan State Plan Remv. 3.44 0.00 3.44 2006 - 100% 3.42 0.00 3.42 0.02 0.00 0.02 0.02 Work completed
79 Permanent restoration work of Chief Justic Banglow Road Ssno7/E/Remo/06-07 Station 0.38 Km Departmental Tenth Plan State Plan Remv. 11.21 0.00 11.21 2006 - 100% 10.31 0.00 10.31 0.90 0.00 0.90 0.90 Work completed
80 Immediate protective work to donak khola along tarethang Bering Road km      ch.22nd 23 ch Singtam 0.06 Km Departmental Tenth Plan State Plan Remv. 19.72 0.00 19.72 2006 - 100% 17.65 0.00 17.65 2.07 0.00 2.07 2.07 Work completed
81 Restoration work at km 8th Ch.4-5 (Namphey khola)along Assam-Pakyong road Pakyong 0.06 Km Departmental Tenth Plan State Plan Remv. 19.93 0.00 19.93 2006 - 100% 19.93 0.00 19.93 0.00 0.00 0.00 0.00 Work completed
82 Immediate traffic clerance of rest work on lingtam-Agamlok rod km 1st &2nd. Pakyong 2Km Departmental Tenth Plan State Plan Remv. 4.48 0.00 4.48 2006 - 100% 4.48 0.00 4.48 0.00 0.00 0.00 0.00 Work completed
83 Surface improvement at approach road to MLA Hostel and SLA premises Station 0.6Km Departmental   State Plan Remv. 12.83 0.00 12.83 2006 - 100% 4.00 0.00 4.00 8.83 0.00 8.83 8.83 Work completed
84 Slip clearance along KLT road km 2nd ch 25th & 27th  Singtam N/A Departmental Eleventh Plan State Plan Remv. 3.61 0.00 3.61 - - 100% 3.08 0.00 3.08 0.53 0.00 0.53 0.53 Work completed
85 Slope stabilisation work km 2nd Ch:6to 8 along Pakyong-Machong Road Pakyong N/A Departmental Eleventh Plan State Plan Remv. 4.68 0.00 4.68 2007 - 100% 0.00 0.00 0.00 4.68 0.00 4.68 4.68 Work completed
86 Providing protective work at Paemragoan  Pakyong N/A Departmental Tenth Plan State Plan Remv. 2.24 0.00 2.24 2008 - 100% 0.00 0.00 0.00 2.24 0.00 2.24 2.24 Work completed
C DISTRICT :  SOUTH      
A. CENTRAL  SPONSORED  SCHEMES                                        
1 Construction of 25 m. Span Steel Bridge over Mayalu Jhora at Km 3rd on Melli -Nayabazar road. Namchi 25m Mr. P. C. Mundra Tenth Plan CRF Repl. 3.28 58.97 62.25 12-Mar-04 30-Jun-06 100% 0.00 52.83 52.83 3.28 6.14 9.42 9.42 Work completed
2 Construction of 25 m. Span Steel Bridge over Rolu Khola at Km 9th on Melli -Nayabazar road.  Namchi 25m Mr. G.M. Gurung Eleventh Plan CRF Repl. 3.28 52.60 55.88 22-Jul-04 31-May-06 100% 0.00 48.63 48.63 3.28 3.97 7.25 7.25 Work completed
3 Construction of Gurassey Road from Bio-Diversity Park (Temi)     Passang Lepcha Tenth Plan EI New Road 0.00 1010.92 1,010.92 26-Mar-08 - - 0.00 127.26 127.26 0.00 883.66 883.66 883.66 -
4 Widening, Improvement, protective work, drainage and carpetting of Melli, Phong road, Km. 1st to 24th.   24Km Pawan Kr. AgarwaL Tenth Plan ISC Remv. 77.40 1298.61 1,376.01 - - 40% 33.11 235.00 268.11 44.29 1,063.61 1,107.90 1,107.90 Work in progress
5 Widening, surface improvement, p/w & drainage system along Phongla-Bermiock-Sirwani road Km  1st- 28th. Ravangla 28Km Sunil Kr. Agarwal Tenth Plan ISC Remv. 558.00 999.08 1,557.08 Feb-05 Mar-08 100% 30.32 866.00 896.32 527.68 133.08 660.76 660.76 Work completed
6 Upgradation & carpetting of Bhaisalgoan to Salghari road Km 1st to 2nd in South Sikkim.   2Km Mr. Hanuman Das Agarwal Tenth Plan NABARD Exp. 18.91 63.41 82.32 12-Feb-07 11-Jan-08 100% 0.00 63.41 63.41 18.91 0.00 18.91 18.91 Work completed
7 Construction of trukable road from Tiffin Dara to Lower Tinghrithang  School Km 1st to 7th   7Km - Tenth Plan NABARD New Road 28.26 254.370 282.63 6-Jun-06 12-Dec-07 84% 0.00 135.97 135.97 28.26 118.40 146.66 146.66 Work in progress
8 Surfce strengthening, carpetting, drainage and Protective Works along A/R to Buddha Statue (Sakymuni) Ravangla 2Km Pawan Kr. AgarwaL   NABARD CSS 0.00 360.910 360.91 - - 46% 0.00 125.00 125.00 0.00 235.91 235.91 235.91 Work in progress
9 Truakable road from 10th mile to Tingmoo villageKm 1st, 2nd and 7th Ravangla 3Km Mr. Nim S. Sherpa Tenth Plan NEC CSS 0.00 468.29 468.29 4-Apr-06 4-Apr-07 64% 0.00 104.15 104.15 0.00 364.14 364.14 364.14 Work in progress
10 Truakable road from 10th mile to Tingmoo villageKm 3rd and 6th Ravangla 2Km Mr. Sonam O. Bhutia Tenth Plan NEC CSS 4-Apr-06 4-Apr-07 51% 0.00 Work in progress
11 Truakable road from 10th mile to Tingmoo villageKm 4th and 5th Ravangla 2Km Mr. Lhendup D. Kaleon Tenth Plan NEC CSS 5-Apr-06 4-Apr-07 50% 0.00 Work in progress
12 Truakable road from 10th mile to Tingmoo villageKm 8th. Ravangla 1Km Mr. Bala R. Limboo Tenth Plan NEC CSS 9-Apr-06 4-Apr-07 61% 0.00 Work in progress
13 Strengthening / drainage carpetting of Ralang-Phamthang road Km 14th to 26th & Replacement of Two existing Bridges over Bermali & Chil Khola in South Sikkim. Ravangla 12Km & 65m x 2 nos Mr. N.T. Bhutia Tenth Plan NEC Remv. 100.00 1100.83 1,200.83 11-Nov-06 5-May-08 45% 0.00 213.00 213.00 100.00 887.83 987.83 987.83 Work in progress
14 Construction of 40m Span Bridge over Lower Ben Khola at Saino Tar along Pabong - Simchuthang - Yangang road, South Sikkim. Ravangla 40m Mr. Anjani Kr, Agarwal Tenth Plan NEC CSS 0.00 137.34 137.34 Sep-05 Jun-06 100% 0.00 107.65 107.65 0.00 29.69 29.69 29.69 Work completed
15 Construction of 60m span steel bridge over Kaw Khola on KS road. Ravangla 60m Mr. S.S. Dhakhal Tenth Plan NEC CSS 0.00 164.35 164.35 Nov-06 Nov-08 80% 0.00 75.00 75.00 0.00 89.35 89.35 89.35 Work in progress
16 Imp drainage, carpetting works Km 1st -14th and replacement of Rangla Khola bridge on Kimotey Sokpay roads. Ravangla 14Km Mr. Sunil Kr. Agarwal Tenth Plan NEC Remv. 0.00 680.00 680.00 Nov-06 Nov-08 72% 0.00 268.00 268.00 0.00 412.00 412.00 412.00 Work in progress
17 Replacement of 110m Span Suspension Bridge over Rabi Khola in Melli Phong road Km 9th in S/Sikkim.    110m Mr. Om Agarwal Tenth Plan NEC CSS 0.00 497.30 497.30 39125.00 12-Feb-08 45% 0.00 144.11 144.11 0.00 353.19 353.19 353.19 Work in progress
18 Construction of link road Turung School to Suminkhor Primary School.   4.75 Km Mr. Subaash Kharel Tenth Plan NEC New Road 22.79 358.66 381.45 39428.00 6-Jun-09 79% 0.00 169.05 169.05 22.79 189.61 212.40 212.40 Work in progress
19 Construction of 30m Span Steel Bridges Over Rinzi Khola at Kolagari along Namchi-Vok Road   30m Bhupal Chamling Tenth Plan NEC Repl. 28.34 157.50 185.84 12-Dec-07 6-Jun-09 100% 0.00 109.03 109.03 28.34 48.47 76.81 76.81 Work completed
20 Construction of Steel Bridge over Upper Ben Khola on G.L.V.C. road.   25m - Tenth Plan NEC CSS 0.00 90.83 90.83 14-Feb-06 - 100% 0.00 81.77 81.77 0.00 9.06 9.06 9.06 Work completed
21 Construction of Makha Suspension Bridge over Tista Khola at Tanak on Makha -Lingi -Yangang- Ravangla Road in South Sikkim.(NEC) Ravangla 100m R.N. Chamling Tenth Plan NEC CSS 0.00 495.25 495.25 25-Aug-06 - 10% 0.00 32.28 32.28 0.00 462.97 462.97 462.97 Work in progress
22 Improvement of Ralang - Phamtam Road    13Km - Eleventh Plan NEC CSS 0.00 1183.00 1,183.00 25-Aug-06 -   0.00 269.13 269.13 0.00 913.87 913.87 913.87 -
23 Surface strengthening drainage & P. Works on Namchi- Damthang Ravangla road- Km 1st -26th.   26Km - Tenth Plan NLCPR Remv. 461.61 1,207.00 1,668.61 1-Jan-05 1-Feb-07 99% 224.94 1,164.19 1,389.13 236.67 42.81 279.48 279.48 Work in progress
24 Replacement of existing Sikkip Suspension Bridge over Rangit River   82m Mr. Chandra Khaling Tenth Plan NLCPR Repl. 24.47 53.66 78.13 15-Dec-03 30-Mar-07 100% 11.78 53.65 65.43 12.69 0.01 12.70 12.70 Work completed
25 Upgradation, Surface strengthening, drainage & P/W on Ravangla Makha Road Km 10th,11th,12th and 13th.   4Km Smt. Sonam Doma Bhutia Tenth Plan NLCPR CSS 0.00 119.05 119.05 15-Jan-03 30-Nov-06 100% 0.00 116.17 116.17 0.00 2.88 2.88 2.88 Work completed
26 Upgradation, Surface strengthening, drainage & P/W on Ravangla Makha Road Km 18th to 21st   3Km Mr. S. B. Chamling Tenth Plan NLCPR CSS 0.00 109.18 109.18 15-Jan-03 30-Nov-06 100% 0.00 102.96 102.96 0.00 6.22 6.22 6.22 Work completed
27 Const. of motorable link road from upper Vok to Ung Raam (Water falls) via Namplang and rabong village in Omchu    6Km Mr. B. Tsh. Bhutia Tenth Plan RSVY  New Road 60.11 180.00 240.11 22-Aug-05 21-Aug-07 85% 54.40 180.00 234.40 5.71 0.00 5.71 5.71 Work in progress
28 Construction of truckable roasd from Borong-Phamtam road to Upper Borong via Gurug Gumpa Km 1st.   1Km Shri K. B. Gurung Tenth Plan RSVY CSS 0.00 64.00 64.00 2-Feb-06 12-Nov-06 100% 0.00 63.98 63.98 0.00 0.02 0.02 0.02 Work completed
29 Construction of truckable roasd from Borong-Phamtam road to Upper Borong via Gurug Gumpa Km 2nd.   1Km Shr. D. M. Gurung Tenth Plan RSVY CSS 2-Feb-06 13-Nov-06 100% 0.00 Work completed
30 Construction of link road to Gagyong village km 3   3Km -   RSVY CSS 0.00 87.00 87.00 - - 100% 0.00 77.71 77.71 0.00 9.29 9.29 9.29 Work completed
  STATE PLAN                                        
31 Construction of Link Road from Rangang to Yangang-Makha via Majuwa : Km 1st and 2nd Ravangla 2Km Mr. S. B. Chamling Tenth Plan State Plan Addl. Facilities 62.36 0.00 62.36 1-Jan-05 10-Oct-05 99% 53.95 0.00 53.95 8.41 0.00 8.41 8.41 Work in progress
32 Construction of Link Road from Rangang to Yangang-Makha via Majuwa : Km 3rd. Ravangla 1Km Mr. Nar Bhd. Gurung Tenth Plan State Plan Addl. Facilities 22.83 0.00 22.83 1-Jan-05 10-Oct-05 100% 16.17 0.00 16.17 6.66 0.00 6.66 6.66 Work completed
33 Construction of Kitchen for PWD Guest House at Temi, South Sikkim. Ravangla N/A Mr. Bindra Kumar Rai Tenth Plan State Plan Addl. Facilities 11.01 0.00 11.01 2-Feb-07 8-Aug-07 95% 0.00 0.00 0.00 11.01 0.00 11.01 11.01 Work in progress
34 Construction of Helipad at Pokhari dara in Upper Yangyang Ravangla N/A M/s Rinchen Ongmu Bhutia Eleventh Plan State Plan Helipad 90.640 0.00 90.64 1-Jul-08 1-Jan-10 97% 43.00 0.00 43.00 47.64 0.00 47.64 47.64 Work in progress
35 Construction of 18ch link road from Helipad to Central University at Yanyang. Ravangla 0.54Km Mrs. Sumitra Gurung Eleventh Plan State Plan Helipad 42.670 0.00 42.67 1-Sep-08 1-Dec-08 100% 0.00 0.00 0.00 42.67 0.00 42.67 42.67 Work completed
36 Surface strengthening & drainage on Yang-yang-Rangang road. Km 1st.-2nd   2Km Mr. S. B. Chamling Tenth Plan State Plan Exp. 39.32 0.00 39.32 16-Feb-03 11-Jan-06 99% 35.74 0.00 35.74 3.58 0.00 3.58 3.58 Work in progress
37 Carpetting, drainage & Protective Works onYangang- Rangang road form Bifurcation Point Km 1st and 2nd   2Km S.B.Chamling Tenth Plan State Plan Exp. 37.80 0.00 37.80 16-Feb-03 31-Mar-05 95% 0.00 0.00 0.00 37.80 0.00 37.80 37.80 Work in progress
38 Premix carpetting,drainage work and protective work on Melli Turuk Sadam Bhanjyang road Km 1st - 16th.   16Km Mr. Tej man Rai, Birbal Subba, & Rup Narayan Rai Tenth Plan State Plan Exp. 290.49 0.00 290.49 1-Jan-03 Aug- 31st 100% 248.50 0.00 248.50 41.99 0.00 41.99 41.99 Work completed
39 Construction of Bye Pass road from Agam Singh Path to Damthang road 3Km.   2.15 Km Shri Bhupal Chamling Tenth Plan State Plan Exp. 160.94 0.00 160.94 3-Mar-04 3-Mar-05 100% 123.88 0.00 123.88 37.06 0.00 37.06 37.06 Work completed
40 Surface Improvement of  Approach Road to Rock Garden from Debrong Golai-Namchi-Damthang road Km 1st & 2nd.   2Km Dikila Bhutia Tenth Plan State Plan Exp. 70.22 0.00 70.22 18-Mar-04 18-Mar-05 100% 67.05 0.00 67.05 3.17 0.00 3.17 3.17 Work completed
41 Premix carpetting  on Ravangla Zarrong road km 1st-11th. Ravangla 11Km Shreekishan Agarwal Tenth Plan State Plan Exp. 0.00 0.00 0.00 24-Jun-05 - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Transferred to TSP
42 Construction of link road Rangang road-Yang Yang Makha via Mazuwa Gaon, 3 kms       Rs. 9.49 (LC)]   3Km Santa Bdr. Chamling, Nar Bdr. Gurung Tenth Plan State Plan Exp. 88.30 0.00 88.30 6-Jun-05 6-Sep-06 100% 80.25 0.00 80.25 8.05 0.00 8.05 8.05 Work completed
43 Providing premix carpetting on Approach road & Yard to Palchen Choling Monastry [New Gumpa] at Ralang   0.25 Km Departmental Tenth Plan State Plan Exp. 14.65 0.00 14.65 18-Jun-05 18-Dec-05 100% 14.26 0.00 14.26 0.39 0.00 0.39 0.39 Work completed
44 Restoration work on Namchi-Phong km. 3rd ch. 30 South Sikkim.   N/A Departmental Tenth Plan State Plan Exp. 2.90 0.00 2.90 27-Jun-05 - 100% 0.00 0.00 0.00 2.90 0.00 2.90 2.90 Work completed
45 Immediate restoration work on Namchi-Rong-Sumbuk road km. 7th-13th.   6Km Departmental Tenth Plan State Plan Exp. 2.63 0.00 2.63 2005 - 100% 0.00 0.00 0.00 2.63 0.00 2.63 2.63 Work completed
46 Extension of Ravongla Biring road to Legship Tashiding road 5th kms in South Sikkim.   5Km   Tenth Plan State Plan Exp. 119.40 0.00 119.40 2005 - 100% 43.94 0.00 43.94 75.46 0.00 75.46 75.46 Work completed
47 Diversion of turning at Km 13 on Ravangla - Zarong Road in S-Sikkim Ravangla 1Km Smt. R K  Rai Tenth Plan State Plan Exp. 6.93 0.00 6.93 1-Apr-06 9-Sep-06 100% 4.03 0.00 4.03 2.90 0.00 2.90 2.90 Work completed
48 Carpeting & Protective Work on Rabong -Ralong Road Km 1st to 3rd   3Km Binod Gurung   State Plan Exp. 6.42 0.00 6.42 - - 100% 0.00 0.00 0.00 6.42 0.00 6.42 6.42 Work completed
49 Carpeting & Protective Work on Rabong -Ralong Road Km 4th to 6th   2Km N.T.Bhutia   State Plan Exp. 11.10 0.00 11.10 - - 100% 0.00 0.00 0.00 11.10 0.00 11.10 11.10 Work completed
50 Carpeting & Protective Work on Rabong -Ralong Road Km 7th to 10th   3Km Roshan Lall Agarwal   State Plan Exp. 8.18 0.00 8.18 - - 100% 0.00 0.00 0.00 8.18 0.00 8.18 8.18 Work completed
51 Carpeting & Protective Work on Rabong -Ralong Road Km 11th to 13th   2Km Tshering Gyatso Kaleon Tenth Plan State Plan Exp. 3.63 0.00 3.63 - - 100% 0.00 0.00 0.00 3.63 0.00 3.63 3.63 Work completed
52 New cutting of Sangmoo link road Km 4th     Mr. K. Bhutia Tenth Plan State Plan Exp. 6.97 0.00 6.97 1-Nov-97 - - 0.00 0.00 0.00 6.97 0.00 6.97 6.97 -
53 Extension of Truakable road from Ravangla Bining Road to Tashiding Km 14th. Ravangla 1Km Mr. Loden C. Bhutia Tenth Plan State Plan Exp. 22.02 0.00 22.02 June-05 12-Dec-06 95% 16.83 0.00 16.83 5.19 0.00 5.19 5.19 Work in progress
54 Extension of Truakable road from Ravangla Bining Road to Tashiding Km 15th. Ravangla 1Km Mr. Lha T. Bhutia Tenth Plan State Plan Exp. 20.89 0.00 20.89 June-05 13-Dec-06 100% 12.01 0.00 12.01 8.88 0.00 8.88 8.88 Work completed
55 Extension of Truakable road from Ravangla Bining Road to Tashiding Km 16th. Ravangla 1Km Mr. Loden C. Bhutia   State Plan Exp. 22.63 0.00 22.63 June-05 14-Dec-06 100% 9.90 0.00 9.90 12.73 0.00 12.73 12.73 Work completed
56 Extension of Truakable road from Ravangla Bining Road to Tashiding Km 17th. Ravangla 1Km Mr. Lha T. Bhutia Tenth Plan State Plan Exp. 19.87 0.00 19.87 June-05 15-Dec-06 100% 9.77 0.00 9.77 10.10 0.00 10.10 10.10 Work completed
57 Extension of Truakable road from Ravangla Bining Road to Tashiding Km 18th. Ravangla 1Km Mr. Lha T. Bhutia Tenth Plan State Plan Exp. 19.31 0.00 19.31 June-05 16-Dec-06 100% 5.60 0.00 5.60 13.71 0.00 13.71 13.71 Work completed
58 Construction of motorable road from Slap Village (Chettri Gaon) km 1st and 2nd Ravangla 2Km Mr. Lha T. Bhutia Tenth Plan State Plan Exp. 38.02 0.00 38.02 9-Sep-06 2-Feb-07 87% 21.40 0.00 21.40 16.62 0.00 16.62 16.62 Work in progress
59 Surface strengthening & drainage on Yang-yang-Rangang road. Km 1st & 2nd.  Ravangla 2 Km Mr. S. B. Chamling Tenth Plan State Plan Exp. 36.19 0.00 36.19 16-Feb-03 11-Jan-06 100% 21.03 0.00 21.03 15.16 0.00 15.16 15.16 Work completed
60 Diversion of turning at Km 14 th to 18th on Ravangla - Zarong Road in S-Sikkim   4Km Smt. Ratna Kum. Rai Tenth Plan State Plan Exp. 104.72 0.00 104.72 Jun-05 Mar-08 87% 54.11 0.00 54.11 50.61 0.00 50.61 50.61 Work in progress
61 Construction of link road from Kholaghari to Jaubari, Km 3rd 4th to 9th. (LC = Rs. 170.52 lakh)   11.5 Km Bhanu Rai & Lakpa Chuki Sherpa Tenth Plan State Plan Link Road 276.13 0.00 276.13 18-Mar-03 18-Dec-04 100% 172.04 0.00 172.04 104.09 0.00 104.09 104.09
Work completed
62 Construction of link road from Namchi-Kopchey road to Singithang Km 1st & 2nd. (LC = 20.76 lakh)   2Km Chandra Bir Rai & D.P.Rai Tenth Plan State Plan Link Road 64.36 0.00 64.36 15-Mar-04 15/12/2004 100% 41.78 0.00 41.78 22.58 0.00 22.58 22.58 Work completed
63 Construction of Truckable road from Rong Sadhu Gaon 2km. [Lungkhiya] (LC = 17.45 lakh)   2Km Suk Deo Rai Tenth Plan State Plan Link Road 53.59 0.00 53.59 15-Mar-04 15/12/2004 100% 52.29 0.00 52.29 1.30 0.00 1.30 1.30 Work completed
64 Construction of truckable road from Rong to Khani Gaon 2Km.    2Km -   State Plan Link Road 43.13 0.00 43.13 6-Jun-04 6-Jun-06 100% 20.18 0.00 20.18 22.95 0.00 22.95 22.95 Work completed
65 Compensation for Construction of Namchi-Nayabazar road to Harrabotey Km 1st to 2nd   N/A Compensation   State Plan Link Road 10.07 0.00 10.07 - -   3.39 0.00 3.39 6.68 0.00 6.68 6.68  
66 Construction of Kink road from Kateng Bokrang to Namthang South Sikkim.   8 Km Buddha Singh Tamang   State Plan Link Road 426.21 0.00 426.21 12-Dec-08 12-Dec-10 35% 0.00 0.00 0.00 426.21 0.00 426.21 426.21 Work in progress
67 Construction of Link road from Ben-Thalbari to Mangley km 1st-14th ( LC = Rs. 73.56 lakh) Ravangla 14Km Chumden Kaleon Tenth Plan State Plan New Road 313.80 0.00 313.80 8-Dec-03 27-Dec-04 100% 259.82 0.00 252.03 53.98 0.00 61.77 61.77 Work completed
68 Construction of truckable road from Ben to Namprik Km 1st. Ravangla 1Km Chumden Kaleon Tenth Plan State Plan New Road 20.85 0.00 20.85 2002 2003 100% 20.85 0.00 20.70 0.00 0.00 0.15 0.15 Work completed
69 Construction of truckable road from Lingi Paiyong Govt. Jr. high School Km 2nd (I/c 17.71 lac Comp.+2.62 Forest Comp) Ravangla 1Km S.S.Dhakal Tenth Plan State Plan New Road 57.78 0.00 57.78 2002 - 95% 27.21 0.00 27.21 30.57 0.00 30.57 30.57 Work in progress
70 Construction of truckable  roads from Kholaghari to Jawbari Km 10th & 11th (14th Chain)    2Km Departmental Tenth Plan State Plan New Road 44.09 0.00 44.09 2005 - 100% 25.54 0.00 25.54 18.55 0.00 18.55 18.55 Work completed
71 Construction of Truckable Road from Assangthang to Salghari   N/A Compensation Eleventh Plan State Plan New Road 54.87 0.00 54.87 2007 -   40.00 0.00 40.00 14.87 0.00 14.87 14.87  
72 Construction of truckable road from Kholaghari to Jaubari Km 10th & 11th (14 Chain).   2.1Km - Tenth Plan State Plan New Road 44.09 0.00 44.09 - - 90% 39.87 0.00 39.87 4.22 0.00 4.22 4.22 Work in progress
73 Construction of truckable road from Lingi Payong Govt. jr. high School Km 2nd .   1Km Mr. S. S. Dhakal   State Plan New Road 57.78 0.00 57.78 1-Mar-03 28-Feb-04 90% 27.21 0.00 27.21 30.57 0.00 30.57 30.57 Work in progress
74 Primix Carpeting Imp.of & Strengthening of Sirwani Pabong Tarku (SPT) km 11st to 18th    7Km Prem Kr.Agarwal   State Plan Remv. 101.300 0.00 101.30 13-Nov-02 12-Jun-04 100% 0.00 0.00 0.00 101.30 0.00 101.30 101.30 Work completed
75 Providing Box Drain and Protective work along Pabong Simchuthang Yangang Road Km 15th Ch 1st to 20th   0.6Km Sonam Gyamtso Tenth Plan State Plan Remv. 5.250 0.00 5.25 - - 100% 5.04 0.00 5.04 0.21 0.00 0.21 0.21 Work completed
76 Permanent Restoration Work along Kholaghari Jawbari Road Km 2nd & 3rd   2Km Bhanu Rai & Others Tenth Plan State Plan Remv. 30.980 0.00 30.98 28-Jun-05 - 100% 30.98 0.00 30.98 0.00 0.00 0.00 0.00 Work completed
77 Strengthening, Carpetting and Stabilization of approach Road to Melli - Bazar.(State Share of NABARD)   0.60 Km Departmental Tenth Plan State Plan Remv. 8.51 0.00 8.51 28-Jun-05 - 100% 0.00 0.00 0.00 8.51 0.00 8.51 8.51 Work completed
78 Permanent restoration nwork at Rock Garden from Debrung-Golai, Namchi Damthang road Km 1st & 2nd in S/Sikkim   2Km - Eleventh Plan State Plan Non-Plan 41.10 0.00 41.10 1-Jul-09 - 14% 0.00 0.00 0.00 41.10 0.00 41.10 41.10 Work in progress
D DISTRICT : WEST
  CENTRAL  SPONSORED  SCHEMES                                        
1 Restoration of damages, Slip clearence, Drainage &surface improvement works of Geythang-Karmatar road, Singshore diversion road and Utterey-Sopakha road in West Sikkim. Kaluk 2 Km P.K.Subba   BADP - 0.00 300.00 300.00 1-Nov-08 31-Oct-09 20% 0.00 0.00 0.00 0.00 300.00 300.00 300.00 Work in progress
2 Surface improvement and strengthening and premix carpetting of Rimbi Yoksum road Km 1st to 21.70. Geyzing 21.70 Km Mr. K. N. Bhutia Tenth Plan EI - 96.11 219.37 315.48