| MONTHLY PHYSICAL AND FINANCIAL PROGRESS REPORT FOR THE MONTH ENDING MARCH
2009 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| Sl.No |
Name
of Schemes |
|
Length Km / M |
Name of
Contractor |
Plan |
Funding Agency |
(Head) |
SANCTIONED AMOUNT |
Date of Commen- cement |
Stipulated Date of
Completion |
Phy Prog-ress in % |
Financial
Progress |
Balance |
TOTAL SA-BAL |
Remarks |
|
|
| |
S. share |
C.share |
Total |
Expenditure
till date |
|
|
|
| |
S.Share |
C.Share |
Total |
S.Share |
C.Share |
Total |
|
|
|
| A |
DISTRICT: NORTH |
|
|
|
|
|
|
|
|
|
|
|
|
| |
CENTRAL SPONSORED
SCHEMES |
|
|
|
|
|
|
|
|
|
|
|
|
|
| 1 |
Construction
of app. Road to Thomchi Gumpa. |
|
0.15
Km |
Mr.
Tashi Lachungpa |
|
BADP |
BADP |
0.00 |
15.69 |
15.69 |
6-Feb-07 |
5-May-07 |
100% |
0.00 |
9.97 |
9.97 |
0.00 |
5.72 |
5.72 |
5.72 |
Work
completed |
|
|
| 2 |
Construction
of new road from Gumpa Golai to Chanzing, Lachen. |
|
0.48
Km |
Mr
Nangden Lachungpa |
|
BADP |
BADP |
0.00 |
38.10 |
38.10 |
- |
- |
- |
0.00 |
0.00 |
0.00 |
0.00 |
38.10 |
38.10 |
38.10 |
|
|
|
| 3 |
Upgradation
/ Strengthening and Carpeting of approach road to Latoong Village. |
|
1Km |
Mr
Nangden Lachungpa |
|
BADP |
BADP |
0.00 |
42.79 |
42.79 |
- |
- |
70% |
0.00 |
19.40 |
19.40 |
0.00 |
23.39 |
23.39 |
23.39 |
Work
in progress |
|
|
| 4 |
Construction
of Guest House / Inspection Bunglow at Yakthang, Lachen (Thangu). |
|
N/A |
- |
|
BADP |
BADP |
0.00 |
138.00 |
138.00 |
- |
- |
- |
0.00 |
0.00 |
0.00 |
0.00 |
138.00 |
138.00 |
138.00 |
- |
|
|
| 5 |
Extension
of Bakcha -Labi road Km 3rd & 4th. State share of BADP land compansation. |
|
2Km |
Mr.
Ugen Nedup Bhutia |
|
BADP |
BADP |
0.00 |
50.00 |
50.00 |
- |
- |
100% |
0.00 |
49.91 |
49.91 |
0.00 |
0.09 |
0.09 |
0.09 |
Work
completed |
|
|
| 6 |
Upgradation
& Surface strengthening of Ranka-Sichey road Km 1st to 3rd |
|
3Km |
Mr.
Rajesh Agarwal |
Tenth
Plan |
CRF |
Removal |
30.78 |
88.26 |
119.04 |
17-Mar-05 |
31-May-06 |
100% |
0.00 |
72.10 |
72.10 |
30.78 |
16.16 |
46.94 |
46.94 |
Work
completed |
|
|
| 7 |
Upgradation
of Phodong -Labrang Gumpa |
|
2.25
Km |
Mr.
K.N. Bhutia |
Tenth
Plan |
CRF |
CRF |
0.00 |
158.96 |
158.96 |
3-Nov-05 |
2-Oct-06 |
100% |
0.00 |
151.37 |
151.37 |
0.00 |
7.59 |
7.59 |
7.59 |
Work
completed |
|
|
| 8 |
Construction
of 18 mtrs span Steel Bridge over Rakshey Khola along Penlong - Tintek road
at Km 13th, CH: 1 |
|
18m |
- |
Tenth
Plan |
CRF |
CRF |
0.00 |
90.99 |
90.99 |
18-Oct-06 |
- |
90% |
0.00 |
60.97 |
60.97 |
0.00 |
30.02 |
30.02 |
30.02 |
Work
in progress |
|
|
| 9 |
Widening
of upgradation, carpetting, protective of drainage works on approach road to
Zimchung Busty from DAC road, Mangan |
|
2.45
Km |
Department. |
Tenth
Plan |
MP
(LAPS) |
- |
0.00 |
25.00 |
25.00 |
- |
- |
100% |
0.00 |
0.00 |
0.00 |
0.00 |
25.00 |
25.00 |
25.00 |
Work
completed |
|
|
| 10 |
Upgradation
Ranka - Luing-Gangtok-Burthuk-Road Km 14th to 21st |
|
7
Km |
Mr.
Shyam Rai |
Tenth
Plan |
NLCPR |
Exp. |
221.54 |
420.00 |
641.54 |
11-Jan-05 |
19-Jul-07 |
68% |
0.00 |
408.00 |
408.00 |
221.54 |
12.00 |
233.54 |
233.54 |
Work
in progress |
|
|
| 11 |
Construction
0f 90m span steel bridge over Takcham Chu along C.R.B.A Road, Km 21st |
|
90m |
Mrs.
Meera Rai |
Tenth
Plan |
NEC |
Exp. |
0.00 |
476.74 |
476.74 |
9-Jan-06 |
8-Oct-06 |
90% |
0.00 |
324.00 |
324.00 |
0.00 |
152.74 |
152.74 |
152.74 |
Work
in progress |
|
|
| 12 |
Upgradation
/ carpeting & extension i/c providing drainage and protective works of
Marchak - Tumlabong road, Km 1st to 13th in East Sikkim |
|
13Km |
M/s
Ladakhi Const. Pvt. Ltd. |
Tenth
Plan |
NEC |
Exp. |
0.00 |
1,023.00 |
1,023.00 |
9-Nov-06 |
18-May-08 |
65% |
0.00 |
339.05 |
339.05 |
0.00 |
683.95 |
683.95 |
683.95 |
Work
in progress |
|
|
| 13 |
Construction
of steel bridge over Teesta river at Gour at Dzongu (LC from SP 6.84) |
|
122m |
Mr.
Samdup Lepcha |
Tenth
Plan |
NEC |
NEC |
6.84 |
488.57 |
495.41 |
21-Jan-06 |
22-Jan-07 |
94% |
6.62 |
404.99 |
411.61 |
0.22 |
83.58 |
83.80 |
83.80 |
Work
in progress |
|
|
| 14 |
Strengthening
/ drainage carpetting of SBS road to Tingbong high school |
|
7km |
Mr.
G.N. Agarwal |
Tenth
Plan |
NEC |
NEC
/ TSP |
401.38 |
401.38 |
802.76 |
29-Apr-05 |
30-Apr-06 |
100% |
401.38 |
367.19 |
768.57 |
0.00 |
34.19 |
34.19 |
34.19 |
Work
completed |
|
|
| 15 |
Construction
of Steel Bridge on Approach road to Khedum Village in North Sikkim. |
|
50m |
Mr.
Penzong Lachungpa |
Tenth
Plan |
NEC |
NEC |
0.00 |
281.51 |
281.51 |
24-Feb-06 |
23-Jan-07 |
94% |
0.00 |
198.75 |
198.75 |
0.00 |
82.76 |
82.76 |
82.76 |
Work
in progress |
|
|
| 16 |
Upgradation
of Marchak Tumlabong Road (NEC ) State Share for LC |
|
13Km |
Compensatiion |
|
NEC |
Removal |
100.00 |
1,023.00 |
1,123.00 |
- |
- |
37% |
37.00 |
522.75 |
559.75 |
63.00 |
500.25 |
563.25 |
563.25 |
Work
in progress |
|
|
| 17 |
Construction
of road from lower Lingdum to
Adampool, Km 3rd & 4th |
|
2Km |
Mr.
Ajay Rai |
Tenth
Plan |
NABARD |
Exp. |
29.64 |
73.43 |
103.07 |
16-Nov-06 |
15-May-07 |
100% |
18.59 |
73.43 |
92.02 |
11.05 |
0.00 |
11.05 |
11.05 |
Work
completed |
|
|
| 18 |
Carpetting
of app. Road to Crematorium ground at Jalipool. |
|
0.28
Km |
Mr.
Praveen Agarwal |
Tenth
Plan |
NABARD |
Exp. |
11.14 |
20.66 |
31.80 |
31-Jan-06 |
15-Jun-06 |
100% |
9.35 |
17.00 |
26.35 |
1.79 |
3.66 |
5.45 |
5.45 |
Work
completed |
|
|
| 19 |
Construction
of Link Road from Takchi Phatak to Upper Luing, Km 1st |
|
1Km |
Mr.
Tsweang Rinzing Bhutia |
Tenth
Plan |
NABARD |
New
Road |
0.00 |
289.930 |
289.930 |
18-Aug-05 |
17-Aug-06 |
90% |
0.00 |
138.17 |
138.17 |
0.00 |
151.76 |
151.76 |
151.76 |
Work
in progress |
|
|
| 20 |
Construction
of Link Road from Takchi Phatak to Upper Luing, Km 2 nd |
|
1Km |
Dewjang
Bhutia |
Tenth
Plan |
NABARD |
New
Road |
18-Aug-05 |
17-Aug-06 |
85% |
0.00 |
Work
in progress |
|
|
| 21 |
Construction
of Link Road from Takchi Phatak to Upper Luing, Km 3rd |
|
1Km |
Tempo
Gyatso Bhutia |
Tenth
Plan |
NABARD |
New
Road |
23-Sep-05 |
22-Sep-06 |
85% |
0.00 |
Work
in progress |
|
|
| 22 |
Construction
of Link Road from Takchi Phatak to Upper Luing, Km 4th |
|
1Km |
Yangchen
Dolma Bhutia |
Tenth
Plan |
NABARD |
New
Road |
23-Sep-05 |
22-Sep-06 |
0% |
0.00 |
|
|
|
| 23 |
Construction
of Link Road from Takchi Phatak to Upper Luing, Km 5th |
|
1Km |
Yangchen
Dolma Bhutia |
|
NABARD |
New
Road |
23-Sep-05 |
22-Sep-06 |
0% |
0.00 |
|
|
|
| 24 |
Extension
of 3rd Km road from 3rd mile turning (Tintek Dikchu road) to Rakshey via
Kedangthang Km 4th to 6th |
|
2Km |
Devi Dhakal |
Tenth Plan |
NABARD |
- |
56.17 |
224.460 |
280.630 |
15-May-08 |
15-May-09 |
80% |
0.00 |
174.73 |
174.73 |
56.17 |
49.73 |
105.90 |
105.90 |
Work
in progress |
|
|
| 25 |
Extension
of link road fromGRS road Km 12th CH 5 to Tatopani at Rumtek |
|
1Km |
M. Karki |
Tenth Plan |
NABARD |
- |
0.00 |
40.190 |
40.190 |
15-May-08 |
15-May-09 |
20% |
0.00 |
0.18 |
0.18 |
0.00 |
40.01 |
40.01 |
40.01 |
Work
in progress |
|
|
| 26 |
Construction
of Link Road from Zimchung to Nampathang KM 1st to 3rd |
|
3Km |
Mr.
Zingmee Ongda, Mr. Dawa.Lepcha, Mr. Choppel Tshering |
Tenth
Plan |
RSVY |
RSVY |
18.75 |
112.11 |
130.86 |
10-Nov-05 |
10-Nov-06 |
100% |
16.32 |
112.11 |
128.43 |
2.43 |
0.00 |
2.43 |
2.43 |
Work
completed |
|
|
| 27 |
Construction
of Link Road from 3rd Mile Turning of Tintek Dikchu road to Rakshey via
Kedhangthang. Km 1st to 3rd. |
|
3Km |
Punya
Prasad Dhakhal |
Tenth
Plan |
RSVY |
New
Road |
22.00 |
121.79 |
143.79 |
25-Oct-05 |
31-Jan-07 |
100% |
0.00 |
120.76 |
120.76 |
22.00 |
1.03 |
23.03 |
23.03 |
Work
completed |
|
|
| 28 |
Construvction
of Link Road from Bay to Pentong in North Sikkim. |
|
3.9
Km |
Mr.
Bernald Lepcha |
Tenth
Plan |
RSVY |
New
Road |
37.45 |
150.00 |
187.45 |
22-Sep-05 |
31-Dec-08 |
65% |
0.00 |
128.03 |
128.03 |
37.45 |
21.97 |
59.42 |
59.42 |
Work
in progress |
|
|
| 29 |
Construction
of Heli Port at Lachung |
|
N/A |
Mr.
Nidup Lachungpa |
Ninth
Plan |
Tourism |
Other
Expenditure |
38.89 |
0.00 |
38.89 |
3-Apr-00 |
2-Jan-01 |
75% |
0.00 |
28.43 |
28.43 |
38.89 |
-28.43 |
10.46 |
10.46 |
Work
in progress |
|
|
| |
WORKS
SANCTIONED UNDER STATE
PLAN |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 30 |
Construction
of Rest House at Samdong in East Sikkim. |
|
N/A |
Mr.
Nitup Lepcha |
Tenth
Plan |
Addl.Facilities |
Addl.Facilities |
78.70 |
0.00 |
78.70 |
20-May-03 |
19-Apr-04 |
100% |
75.32 |
0.00 |
75.32 |
3.38 |
0.00 |
3.38 |
3.38 |
Work
completed |
|
|
| 31 |
Premix
carpetting,on Penlong - Tintek road Km 12th - 20th |
|
8Km |
Mr.
Suresh Mundra |
Tenth
Plan |
State
Plan |
Exp. |
158.79 |
0.00 |
158.79 |
28-Nov-02 |
31-Mar-06 |
100% |
99.54 |
0.00 |
99.54 |
59.25 |
0.00 |
59.25 |
59.25 |
Work
completed |
|
|
| 32 |
Const.
of GOR Santok road Km. 1st |
|
1Km |
Mr.Pentok
Lepcha |
Tenth
Plan |
State
Plan |
Exp. |
29.76 |
0.00 |
29.76 |
- |
- |
100% |
21.61 |
0.00 |
21.61 |
8.15 |
0.00 |
8.15 |
8.15 |
Work
completed |
|
|
| 33 |
Construction
of link road to Aho - Manghim Km 1st - 3rd (L.C = 42.02) |
|
3
Km |
Mr.
B.K. Upreti / BR Subba / Beena Subba |
Tenth
Plan |
State
Plan |
Link
Road |
97.05 |
0.00 |
97.05 |
2-Dec-04 |
15-Jan-07 |
63% |
36.37 |
0.00 |
36.37 |
60.68 |
0.00 |
60.68 |
60.68 |
Work
in progress |
|
|
| 34 |
Surface
renewal / restoration works on approach road to Mission Khoti. |
|
2Km
13ch |
Mr.
Ugen palzor |
|
State
Plan |
Removal |
32.79 |
0.00 |
32.79 |
28-Feb-04 |
27-Aug-04 |
100% |
32.60 |
0.00 |
32.60 |
0.19 |
0.00 |
0.19 |
0.19 |
Work
completed |
|
|
| 35 |
Premix
carpetting p/w approach road to Hee-Gyathang School. |
|
0.7
Km |
Department. |
Tenth
Plan |
State
Plan |
Removal |
23.01 |
0.00 |
23.01 |
- |
- |
100% |
19.99 |
0.00 |
19.99 |
3.02 |
0.00 |
3.02 |
3.02 |
Work
completed |
|
|
| 36 |
Premix
carpeting on GRBA road KM 1st -10th (Phase I ) Revised |
|
10Km |
Mr.
A.N. Upreti |
Tenth
Plan |
State
Plan |
Removal |
215.65 |
0.00 |
215.65 |
13-Jan-03 |
12-Jul-04 |
96% |
207.01 |
0.00 |
207.01 |
8.64 |
0.00 |
8.64 |
8.64 |
Work
in progress |
|
|
| 37 |
Premix
carpetting, improvement of GRBA road Km 18th to 21st and Assam Pakyong Road
Km 1st to 6th. |
|
9Km |
Mr.
Amrit Rai |
Tenth
Plan |
State
Plan |
Removal |
254.76 |
0.00 |
254.76 |
25-Aug-04 |
31-Mar-06 |
100% |
184.20 |
0.00 |
184.20 |
70.56 |
0.00 |
70.56 |
70.56 |
Work
completed |
|
|
| 38 |
Uplifting
& Surface & Drainage works, improvement along approach road to Sichey
school. |
|
0.21
km |
Mr.
Rohit Pradhan |
Tenth
Plan |
State
Plan |
Removal |
3.77 |
0.00 |
3.77 |
27-Feb-06 |
29-Dec-06 |
100% |
3.03 |
0.00 |
3.03 |
0.74 |
0.00 |
0.74 |
0.74 |
Work
completed |
|
|
| 39 |
Upgradation
and Imp of Rumtek Ranka road Km 18th |
|
1Km |
Department. |
Ninth
Plan |
State
Plan |
Removal |
1.36 |
0.00 |
1.36 |
- |
- |
0% |
0.00 |
0.00 |
0.00 |
1.36 |
0.00 |
1.36 |
1.36 |
|
|
|
| 40 |
Construction
of 15 mtrs span RCCl Bridge over Khedum Chu |
|
15m |
Gyatso
Bhutia |
|
State
Plan |
Removal |
20.72 |
0.00 |
20.72 |
12-Nov-98 |
11-Mar-99 |
100% |
19.36 |
0.00 |
19.36 |
1.36 |
0.00 |
1.36 |
1.36 |
Work
completed |
|
|
| 41 |
Construction
of 55m Supension Bridge over Khedumcu at Lachung |
|
55m |
Needup
Lacungpa |
Tenth
Plan |
State
Plan |
Removal |
112.31 |
0.00 |
112.31 |
12-Nov-98 |
11-Jul-99 |
100% |
100.09 |
0.00 |
100.09 |
12.22 |
0.00 |
12.22 |
12.22 |
Work
Completed/ payment of land to be made |
|
|
| 42 |
Upgradation,carpetting,
protective and drainage of SBS road to Lingtam PHSE Km 1st to 5th. |
|
5Km |
Mr.
Samdup Lepcha |
Eleventh
Plan |
State
Plan |
Strengthning
Road Infrastructure |
385.54 |
0.00 |
385.54 |
- |
- |
55% |
42.22 |
0.00 |
42.22 |
343.32 |
0.00 |
343.32 |
343.32 |
Work
in progress |
|
|
| 43 |
Upgradation,carpetting,
protective and drainage works of DSM road to Gour School Km 1st to 8th. |
|
8Km |
Mr.
Soden Gyamptso Bhutia |
Tenth
Plan |
State
Plan |
Strengthning
Road Infrastructure |
391.66 |
0.00 |
391.66 |
1-Jun-08 |
1-Jan-09 |
50% |
57.78 |
0.00 |
57.78 |
333.88 |
0.00 |
333.88 |
333.88 |
Work
in progress |
|
|
| 44 |
Protective
Drainage and Carpetting works on SBS Road Km 3 & 4 |
|
2Km |
Mr.
Pintso Namgyal |
Ninth
Plan |
State
Plan |
TSP |
27.19 |
0.00 |
27.19 |
27-Nov-01 |
26-Feb-02 |
100% |
19.37 |
0.00 |
19.37 |
7.82 |
0.00 |
7.82 |
7.82 |
Work
completed |
|
|
| 45 |
Protective
Drainage and Carpetting works on SBS Road Km 5 & 6 |
|
2Km |
Mr.
Karma Lepcha |
Ninth
Plan |
State
Plan |
TSP |
23.38 |
0.00 |
23.38 |
11-Jan-03 |
10-Oct-03 |
100% |
16.77 |
0.00 |
16.77 |
6.61 |
0.00 |
6.61 |
6.61 |
Work
completed |
|
|
| 46 |
Protective
Drainage and Carpetting works on SBS Road Km 7 |
|
1Km |
Mr.
Ten Tsh. Lepcha |
Ninth
Plan |
State
Plan |
TSP |
11.17 |
0.00 |
11.17 |
27-Nov-01 |
26-Nov-02 |
100% |
7.17 |
0.00 |
7.17 |
4.00 |
0.00 |
4.00 |
4.00 |
Work
completed |
|
|
| 47 |
Protective
Drainage and Carpetting works on SBS Road Km 8 |
|
1Km |
Mr.
Dupden Lepcha |
Ninth
Plan |
State
Plan |
TSP |
22.48 |
0.00 |
22.48 |
27-Nov-01 |
27-Nov-02 |
100% |
19.28 |
0.00 |
19.28 |
3.20 |
0.00 |
3.20 |
3.20 |
Work
completed |
|
|
| 48 |
Protective
Drainage and Carpetting works on SBS Road Km 9 |
|
1Km |
Mr.
Pintso Lepcha |
|
State
Plan |
TSP |
19.23 |
0.00 |
19.23 |
27-Nov-01 |
28-Nov-02 |
100% |
18.21 |
0.00 |
18.21 |
1.02 |
0.00 |
1.02 |
1.02 |
Work
completed |
|
|
| 49 |
Construction
of Guest House at Pentok, Mangan, North Sikkim. |
|
N/A |
- |
Eleventh
Plan |
State
Plan |
TSP |
187.08 |
0.00 |
187.08 |
2006 |
- |
- |
0.00 |
0.00 |
0.00 |
187.08 |
0.00 |
187.08 |
187.08 |
|
|
|
| 50 |
Widening
protective work drainage & carpetting work on S.B.S Road Km 10th &
12th |
|
2Km |
Mr.
Lobzang Lepcha |
Tenth
Plan |
State
Plan |
TSP |
34.51 |
0.00 |
34.51 |
15-Nov-03 |
14-Aug-04 |
73% |
14.99 |
0.00 |
14.99 |
19.52 |
0.00 |
19.52 |
19.52 |
Work
in progress |
|
|
| 51 |
Widening
protective work drainage & carpetting work on S.B.S Road Km 13th |
|
1Km |
Mr.
Sonam Dorjee |
Tenth
Plan |
State
Plan |
TSP |
18.68 |
0.00 |
18.68 |
18-Nov-04 |
17-May-05 |
70% |
0.73 |
0.00 |
0.73 |
17.95 |
0.00 |
17.95 |
17.95 |
Work
in progress |
|
|
| 52 |
Widening
protective work drainage & carpetting work on S.B.S Road Km 14th &
15TH |
|
2Km |
Mr.
Topnam Lepcha |
|
State
Plan |
TSP |
35.15 |
0.00 |
35.15 |
11-Jan-03 |
10-Oct-03 |
80% |
10.24 |
0.00 |
10.24 |
24.91 |
0.00 |
24.91 |
24.91 |
Work
in progress |
|
|
| 53 |
Strengthening,
protective / drainage carpetting works on approach road to Ringtham Gumpa
Km1st to 3rd Mangan. |
|
3Km |
K.N.
Lachenpa |
|
State
Plan |
TSP |
276.00 |
0.00 |
276.00 |
14-Mar-08 |
18-Sep-09 |
55% |
11.51 |
0.00 |
11.51 |
264.49 |
0.00 |
264.49 |
264.49 |
Work
in progress |
|
|
| 54 |
Construction
approach road to medicine pond B-6 |
|
0.96
Km |
Tempo
Lepcha |
|
State
Plan |
TSP |
105.00 |
0.00 |
105.00 |
6-Mar-08 |
7-Mar-09 |
65% |
62.73 |
0.00 |
62.73 |
42.27 |
0.00 |
42.27 |
42.27 |
Work
in progress |
|
|
| 55 |
Construction
approach road to Shakothang at Sarchok village |
|
0.67
Km |
Dawa
Gaytmso Lachenpa |
Tenth
Plan |
State
Plan |
TSP |
64.98 |
0.00 |
64.98 |
7-Apr-08 |
8-Apr-09 |
40% |
3.27 |
0.00 |
3.27 |
61.71 |
0.00 |
61.71 |
61.71 |
Work
in progress |
|
|
| 56 |
Protective
works, widening, drainage and carpeting on Bictchu road Km 1st to 3rd to Gai
Gaon at Lachung |
|
3Km |
Needup
Lacungpa |
|
State
Plan |
TSP |
298.00 |
0.00 |
298.00 |
21-Aug-08 |
2-Aug-10 |
50% |
86.28 |
0.00 |
86.28 |
211.72 |
0.00 |
211.72 |
211.72 |
Work
in progress |
|
|
| 57 |
Premix
Carpetting imp & widening of D.S.M road km 12th to 16th |
|
4Km |
Mr.
Singhik Lepcha |
Tenth
Plan |
State
Plan |
TSP |
124.05 |
0.00 |
124.05 |
15-Jan-03 |
14-Jul-04 |
80% |
54.90 |
0.00 |
54.90 |
69.15 |
0.00 |
69.15 |
69.15 |
Bill
prepared till work done, Road Handed to BRO |
|
|
| 58 |
Premix
Carpetting imp & widening of D.S.M road km 17th |
|
1Km |
Mr.
Chewang Norbu |
Tenth
Plan |
State
Plan |
TSP |
19.41 |
0.00 |
19.41 |
11-Jan-03 |
10-Oct-03 |
100% |
9.93 |
0.00 |
9.93 |
9.48 |
0.00 |
9.48 |
9.48 |
Work
completed |
|
|
| 59 |
Premix
Carpetting imp & widening of D.S.M road km 18th |
|
1Km |
Mr.
Dawa Tshering |
Tenth
Plan |
State
Plan |
TSP |
19.56 |
0.00 |
19.56 |
11-Jan-03 |
10-Oct-03 |
85% |
10.91 |
0.00 |
10.91 |
8.65 |
0.00 |
8.65 |
8.65 |
Bill prepared till work done, Road Handed to BRO |
|
|
| 60 |
Premix
Carpetting imp & widening of D.S.M road km 19th |
|
1Km |
Mr.
Ongden lepcha |
Tenth
Plan |
State
Plan |
TSP |
20.44 |
0.00 |
20.44 |
11-Jan-03 |
10-Oct-03 |
73% |
7.44 |
0.00 |
7.44 |
13.00 |
0.00 |
13.00 |
13.00 |
|
|
| 61 |
Premix
Carpetting imp & widening of D.S.M road km 20th |
|
1Km |
Mr.
Mingma Tshering |
Tenth
Plan |
State
Plan |
TSP |
20.04 |
0.00 |
20.04 |
11-Jan-03 |
10-Oct-03 |
74% |
12.50 |
0.00 |
12.50 |
7.54 |
0.00 |
7.54 |
7.54 |
|
|
| 62 |
Premix
Carpetting imp & widening of D.S.M road km 21st |
|
1Km |
Mr.
Lobzang Lepcha |
|
State
Plan |
TSP |
23.38 |
0.00 |
23.38 |
11-Jan-03 |
10-Oct-03 |
75% |
13.55 |
0.00 |
13.55 |
9.83 |
0.00 |
9.83 |
9.83 |
|
|
| B |
DISTRICT :EAST |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
CENTRAL
SPONSORED SCHEMES |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 1 |
Const.
of link road from Arubotey to Subaneydara km 1st-3rd. |
Pakyong |
3Km |
Om
Bhd. Gurung |
Ninth
Plan |
BADP |
- |
0.00 |
29.97 |
29.97 |
30-Nov-00 |
16-Mar-01 |
68% |
0.00 |
22.98 |
22.98 |
0.00 |
6.99 |
6.99 |
6.99 |
Work
abondoned |
|
|
| 2 |
Const.
of link road from sisney to North Regu km 1st -4th. |
Pakyong |
4Km |
T.S.
Lama |
Tenth
Plan |
BADP |
- |
0.00 |
30.31 |
30.31 |
21-Nov-00 |
5-Mar-01 |
95% |
0.00 |
24.54 |
24.54 |
0.00 |
5.77 |
5.77 |
5.77 |
Work
abondoned |
|
|
| 3 |
Construction
of 60 m span steel bridge at Bongliung over Rongli Chu in East Sikkim |
|
60m |
Gazendra
Rai |
Eleventh
Plan |
CSS |
|
0.00 |
74.07 |
74.07 |
29-Mar-08 |
29-Sep-09 |
20% |
0.00 |
0.00 |
0.00 |
0.00 |
74.07 |
74.07 |
74.07 |
Work
in progress |
|
|
| 4 |
Const.
of 12 m span R.C.C. Bridge on Sangkhola Zingla Martam Road at Km 11th ch-3rd. |
|
12m |
Anita
Gurung |
Eleventh
Plan |
CRF |
- |
0.00 |
38.63 |
38.63 |
1-Apr-07 |
31-Mar-08 |
50% |
0.00 |
10.23 |
10.23 |
0.00 |
28.40 |
28.40 |
28.40 |
Work
in progress |
|
|
| 5 |
Const.
of 12 m span R.C.c. Bridge on Sangkhola Zingla Martam Road at Km 12th
ch-4th.. |
|
12m |
T.B.
Pradhan |
Eleventh
Plan |
CRF |
- |
0.00 |
45.12 |
45.12 |
1-Apr-07 |
31-Mar-08 |
70% |
0.00 |
27.70 |
27.70 |
0.00 |
17.42 |
17.42 |
17.42 |
Work
in progress |
|
|
| 6 |
Surface
improvement and widening of Sang Sirwani Road Km 1st & App Road from Mech
Sub Div Office at Dochum |
|
1Km |
Kishor
Pradhan |
Eleventh
Plan |
CRF |
- |
0.00 |
155.00 |
155.00 |
10-Oct-07 |
9-Sep-08 |
90% |
0.00 |
71.18 |
71.18 |
0.00 |
83.82 |
83.82 |
83.82 |
Work
in progress |
|
|
| 7 |
Surface
improvement and widening of Sang Sirwani Road Km 2nd & App Road to Mech
Workshop Dochum |
|
1Km |
K.R.
Sharma |
Eleventh
Plan |
CRF |
- |
0.00 |
38.49 |
38.49 |
10-Oct-07 |
9-Sep-08 |
100% |
0.00 |
12.61 |
12.61 |
0.00 |
25.88 |
25.88 |
25.88 |
Work
completed |
|
|
| 8 |
Upgradation
of Link Road from NH-31A to Dokey Chisopani Km 1st |
|
1Km |
Kishor
Pradhan |
Eleventh
Plan |
CRF |
- |
0.00 |
152.58 |
0.00 |
29-Feb-08 |
28-Feb-09 |
35% |
0.00 |
29.41 |
0.00 |
0.00 |
123.17 |
0.00 |
0.00 |
Work
in progress |
|
|
| 9 |
Upgradation
of Link Road from NH-31A to Dokey Chisopani Km 2nd |
Singtam |
1Km |
Gopal
Sharma |
Eleventh
Plan |
CRF |
- |
29-Feb-08 |
28-Feb-09 |
30% |
0.00 |
Work
in progress |
|
|
| 10 |
Upgradation
of Link Road from NH-31A to Dokey Chisopani Km 3rd |
Singtam |
1Km |
Suren
Gurung |
Ninth
Plan |
CRF |
- |
29-Feb-08 |
28-Feb-09 |
45% |
0.00 |
Work
in progress |
|
|
| 11 |
Construction
of link road from pakyong Nop gaon to
barpipal Dara, Km 1st-3rd in East-Sikkim |
Pakyong |
3Km |
Hemandri
Adhikari |
Eleventh
Plan |
CRF |
CSS |
0.00 |
102.29 |
102.29 |
5-Aug-08 |
5-Mar-10 |
50% |
0.00 |
0.00 |
0.00 |
0.00 |
102.29 |
102.29 |
102.29 |
Work
in progress |
|
|
| 12 |
Upgradationand
premix carpeting along Duga Pachaykhani road KM 1st-14th. |
Singtam |
14Km |
B.K.Agarwal |
Tenth
Plan |
EI |
Remv. |
407.61 |
433.77 |
841.38 |
21-Feb-05 |
5-Mar-08 |
100% |
24.00 |
433.77 |
457.77 |
383.61 |
0.00 |
383.61 |
383.61 |
Work
completed |
|
|
| 13 |
Construction
of Road from Rathong (NH-31A) to Kimchithang Km 1st to 15th (EI) |
|
15Km |
KK
Agarwal |
Tenth
Plan |
EI |
New
Road |
765.00 |
701.89 |
1,466.89 |
2007 |
- |
30% |
0.00 |
209.91 |
209.91 |
765.00 |
491.98 |
1,256.98 |
1,256.98 |
Work
in progress |
|
|
| 14 |
Improvement
of Sang Dipudara Road (EI) |
|
14Km |
- |
Tenth
Plan |
EI |
- |
0.00 |
347.74 |
347.74 |
2007 |
- |
90% |
0.00 |
0.00 |
0.00 |
0.00 |
347.74 |
347.74 |
347.74 |
Work
in progress |
|
|
| 15 |
Improvement
of Pakyong - Karthok - Naya busty -
Raigoan Road (EI) |
|
7Km |
- |
Eleventh
Plan |
EI |
- |
0.00 |
398.42 |
398.42 |
2007 |
- |
45% |
0.00 |
160.00 |
160.00 |
0.00 |
238.42 |
238.42 |
238.42 |
Work
in progress |
|
|
| 16 |
Widening,
upgradation of pavement & drainage system along Rangpo Duga Pendam road km 1st - 15th |
|
15Km |
M/s
Apex Project & Investment
P. Ltd. |
Eleventh
Plan |
ISC |
- |
0.00 |
950.00 |
950.00 |
15-Jun-08 |
16-Dec-08 |
65% |
0.00 |
303.67 |
303.67 |
0.00 |
646.33 |
646.33 |
646.33 |
Work
in progress |
|
|
| 17 |
Improvement
of Rhenock - Simanakhola Road Km 1st to 3rd. (ISC) |
|
3Km |
Mr.
Kuber Raj Rai |
Tenth
Plan |
ISC |
- |
0.00 |
250.00 |
250.00 |
26-Mar-08 |
- |
30% |
0.00 |
49.43 |
49.43 |
0.00 |
200.57 |
200.57 |
200.57 |
Work
in progress |
|
|
| 18 |
Strengthening/drainage
and P/Wprks for the road from Lal Turning to Bashilakha Road Km 1st to 3rd |
Pakyong |
3Km |
G.M
Gurung |
|
NABARD |
Exp. |
33.19 |
125.21 |
158.40 |
30/09/07 |
31/03/08 |
100% |
0.00 |
124.82 |
124.82 |
33.19 |
0.39 |
33.58 |
33.58 |
Work
completed |
|
|
| 19 |
Const.
of link road from King Stone to Simana Khola Km 1st to 2nd. |
|
2Km |
Departmental |
Eleventh
Plan |
NABARD |
Exp. |
8.60 |
34.41 |
43.01 |
- |
- |
100% |
0.00 |
31.68 |
31.68 |
8.60 |
2.73 |
11.33 |
11.33 |
Work
completed |
|
|
| 20 |
Construction
of Link Road from Sakyong to Beyong km 1st to 2nd (State Share of NABARD) |
|
2Km |
KRSharma
& TB Pradhan |
Eleventh
Plan |
NABARD |
Exp. |
0.00 |
79.51 |
79.51 |
12-Mar-08 |
11-Mar-09 |
80% |
0.00 |
23.59 |
23.59 |
0.00 |
55.92 |
55.92 |
55.92 |
Work
in progress |
|
|
| 21 |
Strengthening,drainage
and Carpeting and construction of 30m span steel bridge along Assam-Pakyong
road km 7th - 15th. |
Pakyong |
30m |
S.K.
Agarwal |
Tenth
Plan |
NEC |
- |
0.00 |
750.76 |
750.76 |
6-Nov-06 |
5-May-08 |
80% |
0.00 |
465.96 |
465.96 |
0.00 |
284.80 |
284.80 |
284.80 |
Work
in progress |
|
|
| 22 |
Construction
of major retaining structures on approach road to Raj Bhawan,VIP Complex and
TNA Public School Complex |
|
N/A |
|
Tenth
Plan |
NEC |
- |
0.00 |
110.58 |
110.58 |
30-May-05 |
29-May-06 |
100% |
0.00 |
99.67 |
99.67 |
0.00 |
10.91 |
10.91 |
10.91 |
Work
completed |
|
|
| 23 |
Replacement
of Sumin Wooden Suspension Bridge on Sang Khola Sumin Road |
|
40m |
|
Eleventh
Plan |
NEC |
- |
0.00 |
285.40 |
285.40 |
8-Apr-04 |
- |
- |
0.00 |
233.00 |
233.00 |
0.00 |
52.40 |
52.40 |
52.40 |
- |
|
|
| 24 |
Const.
of Goshkhan Dara Bridge over River Teesta at Singtam, East Sikkim |
Singtam |
120m |
M.P
Agarwal |
Tenth
Plan |
NLCPR |
- |
0.00 |
1,337.11 |
1,337.11 |
10-Jan-07 |
11-Jun-08 |
40% |
0.00 |
468.00 |
468.00 |
0.00 |
869.11 |
869.11 |
869.11 |
Work
in progress |
|
|
| 25 |
Const.
of diversion road Ranipool-Pakyong road km 1st-3rd. |
Pakyong |
3Km |
B.K.
Agarwal |
Tenth
Plan |
NLCPR |
Exp. |
102.98 |
236.87 |
339.85 |
21-Feb-05 |
21-Nov-05 |
100% |
64.60 |
170.78 |
235.38 |
38.38 |
66.09 |
104.47 |
104.47 |
Work
completed |
|
|
| 26 |
Extension
of Link Road to Dokey Chisopani Pry School
( State Share of RSVY Scheme) |
|
0.81Km |
Nabin
Rai |
Eleventh
Plan |
RSVY |
New
Road |
1.72 |
25.00 |
26.72 |
17-Oct-05 |
27-Mar-06 |
100% |
0.00 |
25.00 |
25.00 |
1.72 |
0.00 |
1.72 |
1.72 |
Work
completed |
|
|
| |
STATE
PLAN |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 27 |
Repairs
of IETC SMITE Overhead crane station at 5th Mile Tadong |
|
N/A |
Departmental |
Tenth Plan |
State Plan |
Addl.Facilities |
1.35 |
0.00 |
1.35 |
20-Jul-06 |
- |
5% |
1.35 |
0.00 |
1.35 |
0.00 |
0.00 |
0.00 |
0.00 |
Work
in progress |
|
|
| 28 |
Fencing
around SPWD Mech. Workshop Tadong |
|
N/A |
Departmental |
Eleventh
Plan |
State
Plan |
Addl.Facilities |
2.74 |
0.00 |
2.74 |
31-Aug-06 |
- |
5% |
2.73 |
0.00 |
2.73 |
0.01 |
0.00 |
0.01 |
0.01 |
Work
in progress |
|
|
| 29 |
Additonal
facilities installation of portable magazine at Sirwani-Singtam |
|
N/A |
Departmental |
Tenth
Plan |
State
Plan |
Addl.Facilities |
10.00 |
0.00 |
10.00 |
22-Aug-07 |
- |
5% |
9.45 |
0.00 |
9.45 |
0.55 |
0.00 |
0.55 |
0.55 |
Work
in progress |
|
|
| 30 |
Premix
carpetting/Imp. Of Rongli Rorathang road, Km 1st - 11th.( Revised) |
|
11Km |
Kuber
Raj Rai |
Tenth
Plan |
State
Plan |
Exp. |
254.00 |
0.00 |
254.00 |
1-Jan-03 |
3-Apr-06 |
100% |
215.36 |
0.00 |
215.36 |
38.64 |
0.00 |
38.64 |
38.64 |
Work
completed |
|
|
| 31 |
Upgradation/carpeting
P/works and drainage along Pakyong-Karthok road km 1st-4th. |
Pakyong |
4Km |
P.
N. Kazi |
Tenth
Plan |
State
Plan |
Exp. |
286.69 |
0.00 |
286.69 |
28-Mar-05 |
27-Jul-06 |
60% |
95.08 |
0.00 |
95.08 |
191.61 |
0.00 |
191.61 |
191.61 |
Work
in progress |
|
|
| 32 |
Upgradation
and premix carpeting of Kotlaytar Rai Gaon Road,km 1st & 2nd |
Pakyong |
2Km |
Miss
Devi Dakhal |
Tenth
Plan |
State
Plan |
Exp. |
146.88 |
0.00 |
146.88 |
28-Mar-05 |
27-Sep-06 |
80% |
31.05 |
0.00 |
31.05 |
115.83 |
0.00 |
115.83 |
115.83 |
Work
in progress |
|
|
| 33 |
Upgradation
and premix carpeting of Kotlaytar Rai Gaon Road,km 3rd |
Pakyong |
1Km |
Mr.
G.K. Pradhan |
Tenth
Plan |
State
Plan |
Exp. |
22.70 |
0.00 |
22.70 |
1-Jul-05 |
31-Dec-07 |
90% |
22.13 |
0.00 |
22.13 |
0.57 |
0.00 |
0.57 |
0.57 |
Work
in progress |
|
|
| 34 |
Upgradation
and premix carpeting of Kotlaytar Rai Gaon Road,km 4th |
Pakyong |
1Km |
XXX |
Tenth
Plan |
State
Plan |
Exp. |
17.92 |
0.00 |
17.92 |
1-Jul-05 |
31-Dec-07 |
90% |
17.60 |
0.00 |
17.60 |
0.32 |
0.00 |
0.32 |
0.32 |
Work
in progress |
|
|
| 35 |
Upgradation
and premix carpeting of Kotlaytar Rai Gaon Road,km 5th |
Pakyong |
1Km |
K.S.Rai |
Tenth
Plan |
State
Plan |
Exp. |
27.01 |
0.00 |
27.01 |
1-Jul-05 |
31-Dec-07 |
90% |
16.04 |
0.00 |
16.04 |
10.97 |
0.00 |
10.97 |
10.97 |
Work
in progress |
|
|
| 36 |
Upgradation
and premix carpeting of Kotlaytar Rai Gaon Road,km 6th |
Pakyong |
1Km |
Ishore
Dakahal |
Tenth
Plan |
State
Plan |
Exp. |
21.15 |
0.00 |
21.15 |
1-Jul-05 |
31-Dec-07 |
70% |
17.79 |
0.00 |
17.79 |
3.36 |
0.00 |
3.36 |
3.36 |
Work
in progress |
|
|
| 37 |
Upgradation
and premix carpeting of Kotlaytar Rai Gaon Road,km 7th |
Pakyong |
1Km |
K.S.Rai |
Tenth
Plan |
State
Plan |
Exp. |
22.10 |
0.00 |
22.10 |
1-Jul-05 |
31-Dec-07 |
55% |
8.68 |
0.00 |
8.68 |
13.42 |
0.00 |
13.42 |
13.42 |
Work
in progress |
|
|
| 38 |
Upgradation
and premix carpeting of Kotlaytar Rai Gaon Road,km 8th |
Pakyong |
1Km |
Mr.
M.K. Pradhan |
Tenth
Plan |
State
Plan |
Exp. |
21.66 |
0.00 |
21.66 |
1-Jul-05 |
31-Dec-07 |
55% |
17.06 |
0.00 |
17.06 |
4.60 |
0.00 |
4.60 |
4.60 |
Work
in progress |
|
|
| 39 |
Premix
Carpetting and Surface improvement Chewribotay Pendam Km 1st - 6th |
Singtam |
6Km |
Basudev
Pradhan |
Tenth
Plan |
State
Plan |
Exp. |
117.78 |
0.00 |
117.78 |
29/05/2003 |
31/01/04 |
95% |
83.84 |
0.00 |
83.84 |
33.94 |
0.00 |
33.94 |
33.94 |
Work
in progress |
|
|
| 40 |
Construction
of Bye Pass Road below Mintokgang |
Station |
0.30Km |
DB
Chettri |
Tenth
Plan |
State
Plan |
Exp. |
80.26 |
0.00 |
80.26 |
26-Feb-04 |
5-Aug-04 |
100% |
71.46 |
0.00 |
71.46 |
8.80 |
0.00 |
8.80 |
8.80 |
Work
completed |
|
|
| 41 |
Premix
carpetting & Surface Imp.of KLT 16th to 26th Km (Revised) |
|
10Km |
P.D.
Denzongpa |
Tenth
Plan |
State
Plan |
Exp. |
260.57 |
0.00 |
260.57 |
2003 |
- |
100% |
252.36 |
0.00 |
252.36 |
8.21 |
0.00 |
8.21 |
8.21 |
Work
completed |
|
|
| 42 |
Premix
carpetting & Surface Imp.of KLT 7th to 15th Km (Revised) |
|
8Km |
L.N.
Sarda |
Tenth
Plan |
State
Plan |
Exp. |
232.83 |
0.00 |
232.83 |
2003 |
- |
100% |
214.16 |
0.00 |
214.16 |
18.67 |
0.00 |
18.67 |
18.67 |
Work
completed |
|
|
| 43 |
Ext.
of Pakyong-Mamring Tareythang road km 1st |
|
1Km |
Khush
N.Adhikari |
Tenth
Plan |
State
Plan |
Exp. |
28.91 |
0.00 |
28.91 |
1-Jul-05 |
31-Dec-07 |
90% |
28.72 |
0.00 |
28.72 |
0.19 |
0.00 |
0.19 |
0.19 |
Work
in progress |
|
|
| 44 |
Ext.
of Pakyong-Mamring Tareythang road km 2nd |
|
1Km |
Johar
Man Rai |
Tenth
Plan |
State
Plan |
Exp. |
16.61 |
0.00 |
16.61 |
1-Jul-05 |
31-Dec-07 |
90% |
16.37 |
0.00 |
16.37 |
0.24 |
0.00 |
0.24 |
0.24 |
Work
in progress |
|
|
| 45 |
Ext.
of Pakyong-Mamring Tareythang road km 3rd |
|
1Km |
G.K.
Pradhan |
Tenth
Plan |
State
Plan |
Exp. |
22.70 |
0.00 |
22.70 |
1-Jul-05 |
31-Dec-07 |
90% |
12.94 |
0.00 |
12.94 |
9.76 |
0.00 |
9.76 |
9.76 |
Work
in progress |
|
|
| 46 |
Ext.
of Pakyong-Mamring Tareythang road km 4th. |
|
1Km |
Udai
Mishara |
Tenth
Plan |
State
Plan |
Exp. |
17.92 |
0.00 |
17.92 |
1-Jul-05 |
31-Dec-07 |
90% |
12.02 |
0.00 |
12.02 |
5.90 |
0.00 |
5.90 |
5.90 |
Work
in progress |
|
|
| 47 |
Ext.
of Pakyong-Mamring Tareythang road km 5th. |
|
1Km |
K.S.Rai |
Tenth
Plan |
State
Plan |
Exp. |
27.01 |
0.00 |
27.01 |
1-Jul-05 |
31-Dec-07 |
90% |
16.05 |
0.00 |
16.05 |
10.96 |
0.00 |
10.96 |
10.96 |
Work
in progress |
|
|
| 48 |
Ext.
of Pakyong-Mamring Tareythang road km 6th. |
|
1Km |
Ishore
Dakahal |
Tenth
Plan |
State
Plan |
Exp. |
21.15 |
0.00 |
21.15 |
1-Jul-05 |
31-Dec-07 |
80% |
18.71 |
0.00 |
18.71 |
2.44 |
0.00 |
2.44 |
2.44 |
Work
in progress |
|
|
| 49 |
Ext.
of Pakyong-Mamring Tareythang road km 7th. |
|
1Km |
K.S.Rai |
Tenth
Plan |
State
Plan |
Exp. |
22.10 |
0.00 |
22.10 |
1-Jul-05 |
31-Dec-07 |
70% |
8.68 |
0.00 |
8.68 |
13.42 |
0.00 |
13.42 |
13.42 |
Work
in progress |
|
|
| 50 |
Ext.
of Pakyong-Mamring Tareythang road km.8th |
|
1Km |
M.
K. Pradhan |
Tenth
Plan |
State
Plan |
Exp. |
21.66 |
0.00 |
21.66 |
1-Jul-05 |
31-Dec-07 |
70% |
0.00 |
0.00 |
0.00 |
21.66 |
0.00 |
21.66 |
21.66 |
Work
in progress |
|
|
| 51 |
Ext.
of Pakyong-Mamring Tareythang road km.9th |
|
1Km |
Kamal
Adhikari |
Tenth
Plan |
State
Plan |
Exp. |
19.24 |
0.00 |
19.24 |
1-Jul-05 |
31-Dec-07 |
100% |
8.00 |
0.00 |
8.00 |
11.24 |
0.00 |
11.24 |
11.24 |
Work
completed |
|
|
| 52 |
Ext.
of Pakyong-Mamring Tareythang road km.10th |
|
1Km |
Milan
Dahal |
Tenth
Plan |
State
Plan |
Exp. |
10.70 |
0.00 |
10.70 |
1-Jul-05 |
31-Dec-07 |
100% |
0.00 |
0.00 |
0.00 |
10.70 |
0.00 |
10.70 |
10.70 |
Work
completed |
|
|
| 53 |
Construction
of Arithang Road connecting Indira Bye-Pass Road |
Station |
0.6Km |
Departmental |
Tenth
Plan |
|
Exp. |
57.47 |
0.00 |
57.47 |
2005 |
- |
100% |
55.75 |
0.00 |
55.75 |
1.72 |
0.00 |
1.72 |
1.72 |
Work
completed |
|
|
| 54 |
Const.
of road from Zingla Martam KM 16th-18th (2.36km) i/c LC |
|
2Km |
UP
Kazi |
Tenth
Plan |
State
Plan TSP |
Exp. |
77.96 |
0.00 |
77.96 |
3-Oct-05 |
3-Oct-06 |
100% |
83.16 |
0.00 |
83.16 |
-5.20 |
0.00 |
-5.20 |
-5.20 |
Work
completed |
|
|
| 55 |
Const
of 40 Mts span Bridge over Rongli Khola along
arubotey subaney dara Raod Ssno 2/E/exp/06-07 |
|
40m |
Ashok
Ts. Bhutia |
Eleventh
Plan |
|
Exp. |
16.50 |
0.00 |
16.50 |
2006 |
- |
100% |
14.24 |
0.00 |
14.24 |
2.26 |
0.00 |
2.26 |
2.26 |
Work
completed |
|
|
| 56 |
Immediate
Restoration of Mamring Amba Road km 3rd |
|
1Km |
Departmental |
Tenth
Plan |
|
Exp. |
6.77 |
0.00 |
6.77 |
6-Nov-06 |
5-May-08 |
100% |
6.68 |
0.00 |
6.68 |
0.09 |
0.00 |
0.09 |
0.09 |
Work
completed |
|
|
| 57 |
Construction
of 20 chain road Bio Control Laboratory to Phewk Busty road |
Station |
0.60Km |
Mr.
G.K.Rai |
Tenth
Plan |
State
Plan |
Link
Road |
25.03 |
0.00 |
25.03 |
28-Sep-05 |
27-Mar-05 |
100% |
9.00 |
0.00 |
9.00 |
16.03 |
0.00 |
16.03 |
16.03 |
Work
completed |
|
|
| 58 |
Const.
of link road from Basilakhs to Middle camp via Rodongtar km 6th to 8th RCC
Bridge (LC = 19.47) |
Pakyong |
2
Km |
Justin
Rai / Jeewn Subba / Paul Rai |
Tenth
Plan |
State
Plan |
New
Road |
75.99 |
0.00 |
75.99 |
5-Oct-05 |
9-Feb-05 |
100% |
12.41 |
0.00 |
12.41 |
63.58 |
0.00 |
63.58 |
63.58 |
Work
completed |
|
|
| 59 |
Const.
of 10m span RCC Culvert on Basilakha to middle camp km 8th. |
|
10m |
Patrush
Subba |
Tenth
Plan |
State
Plan |
New
Road |
12.32 |
0.00 |
12.32 |
5-Oct-05 |
9-Feb-05 |
75% |
0.00 |
0.00 |
0.00 |
12.32 |
0.00 |
12.32 |
12.32 |
Work
in progress |
|
|
| 60 |
Const
of Approach road to Sivalaya Mandir at pacheykhani Km 1st |
|
1Km |
R.N. Baral |
|
State
Plan |
New
Road |
23.51 |
0.00 |
23.51 |
18-Jul-05 |
15-Jun-06 |
85% |
12.87 |
0.00 |
12.87 |
10.64 |
0.00 |
10.64 |
10.64 |
Work
in progress |
|
|
| 61 |
Construction
of Link Road from Amba to Taja School 1st and 2nd km |
|
2Km |
Mon Narayan Dhakal |
Tenth
Plan |
State
Plan |
New
Road |
5.06 |
0.00 |
5.06 |
- |
- |
75% |
3.96 |
0.00 |
3.96 |
1.10 |
0.00 |
1.10 |
1.10 |
Work
in progress |
|
|
| 62 |
Const.
of link road from Assam-Pakyong road to Kadamtam village km.1st. |
Pakyong |
1Km |
M.B.Mangar |
Tenth
Plan |
State
Plan |
New
Road |
39.65 |
0.00 |
39.65 |
1-Jul-05 |
30-Jun-06 |
100% |
39.51 |
0.00 |
39.51 |
0.14 |
0.00 |
0.14 |
0.14 |
Work
completed |
|
|
| 63 |
Const.
of link road from Assam-Pakyong road to Kadamtam village km.2nd. |
Pakyong |
1Km |
Elies
Lepcha |
Tenth
Plan |
State
Plan |
New
Road |
41.40 |
0.00 |
41.40 |
1-Jul-05 |
30-Jun-06 |
100% |
41.39 |
0.00 |
41.39 |
0.01 |
0.00 |
0.01 |
0.01 |
Work
completed |
|
|
| 64 |
Const.
of link road from Assam-Pakyong road to Kadamtam village km.3rd & 4th. |
Pakyong |
2Km |
D.P.
Mangar |
Tenth
Plan |
State
Plan |
New
Road |
41.51 |
0.00 |
41.51 |
1-Jul-05 |
30-Jun-06 |
75% |
29.71 |
0.00 |
29.71 |
11.80 |
0.00 |
11.80 |
11.80 |
Work
in progress |
|
|
| 65 |
Const.
of link road from Assam-Pakyong road to Kadamtam village km.3rd &
4th.Contingency Rs.4.26 + Land Compansation |
Pakyong |
2Km |
LC
& Contg |
Tenth
Plan |
State
Plan |
New
Road |
87.70 |
0.00 |
87.70 |
- |
- |
100% |
34.27 |
0.00 |
34.27 |
53.43 |
0.00 |
53.43 |
53.43 |
Work
completed |
|
|
| 66 |
Construction
of road from Chandmari village to Jawaharlall Nehru road |
Station |
0.38
Km |
K
Wangchuk |
|
State
Plan |
New
Road |
30.63 |
0.00 |
30.63 |
31-May-05 |
30-Nov-05 |
100% |
23.76 |
0.00 |
23.76 |
6.87 |
0.00 |
6.87 |
6.87 |
Work
completed |
|
|
| 67 |
Const.
of Song-zingla Martam road km 9th. |
|
1Km |
P.T.
Lepcha |
Eleventh
Plan |
State
Plan |
New
Road |
12.45 |
0.00 |
12.45 |
5-Mar-03 |
20-Dec-03 |
80% |
5.63 |
0.00 |
5.63 |
6.82 |
0.00 |
6.82 |
6.82 |
Work
in progress |
|
|
| 68 |
Const.
of Sang-Zingla Martam road KM 10th. |
|
1Km |
P.T.
Rongong |
Eleventh
Plan |
State
Plan |
New
Road |
14.51 |
0.00 |
14.51 |
6-Mar-03 |
6-Dec-03 |
100% |
12.45 |
0.00 |
12.45 |
2.06 |
0.00 |
2.06 |
2.06 |
Work
completed |
|
|
| 69 |
Const.
of Song-Zingla Martam road km 11th |
|
1Km |
Anita
Gurung |
Eleventh
Plan |
State
Plan |
New
Road |
16.17 |
0.00 |
16.17 |
6-Mar-03 |
6-Dec-03 |
100% |
12.28 |
0.00 |
12.28 |
3.89 |
0.00 |
3.89 |
3.89 |
Work
completed |
|
|
| 70 |
Const.
of Song-Zingla Martam road km 12th. |
|
1Km |
U.
Lama |
Eleventh
Plan |
State
Plan |
New
Road |
17.74 |
0.00 |
17.74 |
6-Mar-03 |
6-Dec-03 |
100% |
13.11 |
0.00 |
13.11 |
4.63 |
0.00 |
4.63 |
4.63 |
Work
completed |
|
|
| 71 |
Const.of
Song-Zingla Martam road km 14th |
Singtam |
1Km |
Tenging
Bhutia |
Eleventh
Plan |
State
Plan |
New
Road |
25.54 |
0.00 |
25.54 |
6-Mar-03 |
6-Dec-03 |
100% |
19.63 |
0.00 |
19.63 |
5.91 |
0.00 |
5.91 |
5.91 |
Work
completed |
|
|
| 72 |
Const.
of Song-Zingla Martam road km 15th. |
Singtam |
1Km |
S.K.Chettri |
|
State
Plan |
New
Road |
26.75 |
0.00 |
26.75 |
6-Mar-03 |
6-Dec-03 |
95% |
19.95 |
0.00 |
19.95 |
6.80 |
0.00 |
6.80 |
6.80 |
Work
in progress |
|
|
| 73 |
Carpeting
and surface strengthening, improvement, including drainage works of roads in
and around Gangtok. |
Station |
9.41
Km |
PM
Chamling |
Tenth
Plan |
State
Plan |
Remv. |
361.89 |
0.00 |
361.89 |
6-Jun-04 |
5-Sep-05 |
100% |
229.45 |
0.00 |
229.45 |
132.44 |
0.00 |
132.44 |
132.44 |
Work
completed |
|
|
| 74 |
Surface
strengthening upgradation and carpeting of Pakyong-Karthok Naya Busty road km
5th -7th. |
Pakyong |
2Km |
Adup
Bhutia |
Tenth
Plan |
State
Plan |
Remv. |
220.68 |
0.00 |
220.68 |
21/06/05 |
31-Aug-08 |
50% |
57.04 |
0.00 |
57.04 |
163.64 |
0.00 |
163.64 |
163.64 |
Work
in progress |
|
|
| 75 |
P/L
edging ,soling, metalling, premix carpeting and cross drain of link road from
sichey to Indira Bye Pass via Shivalaya Mandir |
Station |
0.3Km |
Mrs
Rupa Dhakal |
Tenth
Plan |
State
Plan |
Remv. |
8.16 |
0.00 |
8.16 |
1/0/2002 |
2-Jul-05 |
80% |
5.81 |
0.00 |
5.81 |
2.35 |
0.00 |
2.35 |
2.35 |
Work
in progress |
|
|
| 76 |
Surface
stregenthening , upgradation and carpeting of Roads during the visit of His
Holiness the Dalai Lama |
Station |
N/A |
Departmental |
Tenth
Plan |
State
Plan |
Remv. |
40.35 |
0.00 |
40.35 |
2005 |
- |
100% |
38.79 |
0.00 |
38.79 |
1.56 |
0.00 |
1.56 |
1.56 |
Work
completed |
|
|
| 77 |
Providing
75mm thick CC pitching over approach raod to Gairi Goan from NH 31A Near
Hotel Tashi Targey) Ssno 2/E/Remv/06-07 |
Station |
0.3
Km |
Departmental |
Tenth
Plan |
State
Plan |
Remv. |
3.40 |
0.00 |
3.40 |
2006 |
- |
0% |
0.00 |
0.00 |
0.00 |
3.40 |
0.00 |
3.40 |
3.40 |
|
|
|
| 78 |
Const
of PW along TNSS to Dhupidara Ssno 6/E/Remov/0607 |
Station |
N/A |
|
Tenth
Plan |
State
Plan |
Remv. |
3.44 |
0.00 |
3.44 |
2006 |
- |
100% |
3.42 |
0.00 |
3.42 |
0.02 |
0.00 |
0.02 |
0.02 |
Work
completed |
|
|
| 79 |
Permanent
restoration work of Chief Justic Banglow Road Ssno7/E/Remo/06-07 |
Station |
0.38
Km |
Departmental |
Tenth
Plan |
State
Plan |
Remv. |
11.21 |
0.00 |
11.21 |
2006 |
- |
100% |
10.31 |
0.00 |
10.31 |
0.90 |
0.00 |
0.90 |
0.90 |
Work
completed |
|
|
| 80 |
Immediate
protective work to donak khola along tarethang Bering Road km ch.22nd 23 ch |
Singtam |
0.06
Km |
Departmental |
Tenth
Plan |
State
Plan |
Remv. |
19.72 |
0.00 |
19.72 |
2006 |
- |
100% |
17.65 |
0.00 |
17.65 |
2.07 |
0.00 |
2.07 |
2.07 |
Work
completed |
|
|
| 81 |
Restoration
work at km 8th Ch.4-5 (Namphey khola)along Assam-Pakyong road |
Pakyong |
0.06
Km |
Departmental |
Tenth
Plan |
State
Plan |
Remv. |
19.93 |
0.00 |
19.93 |
2006 |
- |
100% |
19.93 |
0.00 |
19.93 |
0.00 |
0.00 |
0.00 |
0.00 |
Work
completed |
|
|
| 82 |
Immediate
traffic clerance of rest work on lingtam-Agamlok rod km 1st &2nd. |
Pakyong |
2Km |
Departmental |
Tenth
Plan |
State
Plan |
Remv. |
4.48 |
0.00 |
4.48 |
2006 |
- |
100% |
4.48 |
0.00 |
4.48 |
0.00 |
0.00 |
0.00 |
0.00 |
Work
completed |
|
|
| 83 |
Surface
improvement at approach road to MLA Hostel and SLA premises |
Station |
0.6Km |
Departmental |
|
State
Plan |
Remv. |
12.83 |
0.00 |
12.83 |
2006 |
- |
100% |
4.00 |
0.00 |
4.00 |
8.83 |
0.00 |
8.83 |
8.83 |
Work
completed |
|
|
| 84 |
Slip
clearance along KLT road km 2nd ch 25th & 27th |
Singtam |
N/A |
Departmental |
Eleventh
Plan |
State
Plan |
Remv. |
3.61 |
0.00 |
3.61 |
- |
- |
100% |
3.08 |
0.00 |
3.08 |
0.53 |
0.00 |
0.53 |
0.53 |
Work
completed |
|
|
| 85 |
Slope
stabilisation work km 2nd Ch:6to 8 along Pakyong-Machong Road |
Pakyong |
N/A |
Departmental |
Eleventh
Plan |
State
Plan |
Remv. |
4.68 |
0.00 |
4.68 |
2007 |
- |
100% |
0.00 |
0.00 |
0.00 |
4.68 |
0.00 |
4.68 |
4.68 |
Work
completed |
|
|
| 86 |
Providing
protective work at Paemragoan |
Pakyong |
N/A |
Departmental |
Tenth
Plan |
State
Plan |
Remv. |
2.24 |
0.00 |
2.24 |
2008 |
- |
100% |
0.00 |
0.00 |
0.00 |
2.24 |
0.00 |
2.24 |
2.24 |
Work
completed |
|
|
| C |
DISTRICT : SOUTH |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| A. |
CENTRAL SPONSORED
SCHEMES |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 1 |
Construction
of 25 m. Span Steel Bridge over Mayalu Jhora at Km 3rd on Melli -Nayabazar
road. |
Namchi |
25m |
Mr.
P. C. Mundra |
Tenth
Plan |
CRF |
Repl. |
3.28 |
58.97 |
62.25 |
12-Mar-04 |
30-Jun-06 |
100% |
0.00 |
52.83 |
52.83 |
3.28 |
6.14 |
9.42 |
9.42 |
Work
completed |
|
|
| 2 |
Construction
of 25 m. Span Steel Bridge over Rolu Khola at Km 9th on Melli -Nayabazar
road. |
Namchi |
25m |
Mr.
G.M. Gurung |
Eleventh
Plan |
CRF |
Repl. |
3.28 |
52.60 |
55.88 |
22-Jul-04 |
31-May-06 |
100% |
0.00 |
48.63 |
48.63 |
3.28 |
3.97 |
7.25 |
7.25 |
Work
completed |
|
|
| 3 |
Construction
of Gurassey Road from Bio-Diversity Park (Temi) |
|
|
Passang
Lepcha |
Tenth
Plan |
EI |
New
Road |
0.00 |
1010.92 |
1,010.92 |
26-Mar-08 |
- |
- |
0.00 |
127.26 |
127.26 |
0.00 |
883.66 |
883.66 |
883.66 |
- |
|
|
| 4 |
Widening,
Improvement, protective work, drainage and carpetting of Melli, Phong road,
Km. 1st to 24th. |
|
24Km |
Pawan
Kr. AgarwaL |
Tenth
Plan |
ISC |
Remv. |
77.40 |
1298.61 |
1,376.01 |
- |
- |
40% |
33.11 |
235.00 |
268.11 |
44.29 |
1,063.61 |
1,107.90 |
1,107.90 |
Work
in progress |
|
|
| 5 |
Widening,
surface improvement, p/w & drainage system along Phongla-Bermiock-Sirwani
road Km 1st- 28th. |
Ravangla |
28Km |
Sunil
Kr. Agarwal |
Tenth
Plan |
ISC |
Remv. |
558.00 |
999.08 |
1,557.08 |
Feb-05 |
Mar-08 |
100% |
30.32 |
866.00 |
896.32 |
527.68 |
133.08 |
660.76 |
660.76 |
Work
completed |
|
|
| 6 |
Upgradation
& carpetting of Bhaisalgoan to Salghari road Km 1st to 2nd in South
Sikkim. |
|
2Km |
Mr.
Hanuman Das Agarwal |
Tenth
Plan |
NABARD |
Exp. |
18.91 |
63.41 |
82.32 |
12-Feb-07 |
11-Jan-08 |
100% |
0.00 |
63.41 |
63.41 |
18.91 |
0.00 |
18.91 |
18.91 |
Work
completed |
|
|
| 7 |
Construction
of trukable road from Tiffin Dara to Lower Tinghrithang School Km 1st to 7th |
|
7Km |
- |
Tenth
Plan |
NABARD |
New
Road |
28.26 |
254.370 |
282.63 |
6-Jun-06 |
12-Dec-07 |
84% |
0.00 |
135.97 |
135.97 |
28.26 |
118.40 |
146.66 |
146.66 |
Work
in progress |
|
|
| 8 |
Surfce
strengthening, carpetting, drainage and Protective Works along A/R to Buddha
Statue (Sakymuni) |
Ravangla |
2Km |
Pawan
Kr. AgarwaL |
|
NABARD |
CSS |
0.00 |
360.910 |
360.91 |
- |
- |
46% |
0.00 |
125.00 |
125.00 |
0.00 |
235.91 |
235.91 |
235.91 |
Work
in progress |
|
|
| 9 |
Truakable
road from 10th mile to Tingmoo villageKm 1st, 2nd and 7th |
Ravangla |
3Km |
Mr.
Nim S. Sherpa |
Tenth
Plan |
NEC |
CSS |
0.00 |
468.29 |
468.29 |
4-Apr-06 |
4-Apr-07 |
64% |
0.00 |
104.15 |
104.15 |
0.00 |
364.14 |
364.14 |
364.14 |
Work
in progress |
|
|
| 10 |
Truakable
road from 10th mile to Tingmoo villageKm 3rd and 6th |
Ravangla |
2Km |
Mr.
Sonam O. Bhutia |
Tenth
Plan |
NEC |
CSS |
4-Apr-06 |
4-Apr-07 |
51% |
0.00 |
Work
in progress |
|
|
| 11 |
Truakable
road from 10th mile to Tingmoo villageKm 4th and 5th |
Ravangla |
2Km |
Mr.
Lhendup D. Kaleon |
Tenth
Plan |
NEC |
CSS |
5-Apr-06 |
4-Apr-07 |
50% |
0.00 |
Work
in progress |
|
|
| 12 |
Truakable
road from 10th mile to Tingmoo villageKm 8th. |
Ravangla |
1Km |
Mr.
Bala R. Limboo |
Tenth
Plan |
NEC |
CSS |
9-Apr-06 |
4-Apr-07 |
61% |
0.00 |
Work
in progress |
|
|
| 13 |
Strengthening
/ drainage carpetting of Ralang-Phamthang road Km 14th to 26th &
Replacement of Two existing Bridges over Bermali & Chil Khola in South
Sikkim. |
Ravangla |
12Km
& 65m x 2 nos |
Mr.
N.T. Bhutia |
Tenth
Plan |
NEC |
Remv. |
100.00 |
1100.83 |
1,200.83 |
11-Nov-06 |
5-May-08 |
45% |
0.00 |
213.00 |
213.00 |
100.00 |
887.83 |
987.83 |
987.83 |
Work
in progress |
|
|
| 14 |
Construction
of 40m Span Bridge over Lower Ben Khola at Saino Tar along Pabong -
Simchuthang - Yangang road, South Sikkim. |
Ravangla |
40m |
Mr.
Anjani Kr, Agarwal |
Tenth
Plan |
NEC |
CSS |
0.00 |
137.34 |
137.34 |
Sep-05 |
Jun-06 |
100% |
0.00 |
107.65 |
107.65 |
0.00 |
29.69 |
29.69 |
29.69 |
Work
completed |
|
|
| 15 |
Construction
of 60m span steel bridge over Kaw Khola on KS road. |
Ravangla |
60m |
Mr.
S.S. Dhakhal |
Tenth
Plan |
NEC |
CSS |
0.00 |
164.35 |
164.35 |
Nov-06 |
Nov-08 |
80% |
0.00 |
75.00 |
75.00 |
0.00 |
89.35 |
89.35 |
89.35 |
Work
in progress |
|
|
| 16 |
Imp
drainage, carpetting works Km 1st -14th and replacement of Rangla Khola
bridge on Kimotey Sokpay roads. |
Ravangla |
14Km |
Mr.
Sunil Kr. Agarwal |
Tenth
Plan |
NEC |
Remv. |
0.00 |
680.00 |
680.00 |
Nov-06 |
Nov-08 |
72% |
0.00 |
268.00 |
268.00 |
0.00 |
412.00 |
412.00 |
412.00 |
Work
in progress |
|
|
| 17 |
Replacement
of 110m Span Suspension Bridge over Rabi Khola in Melli Phong road Km 9th in
S/Sikkim. |
|
110m |
Mr.
Om Agarwal |
Tenth
Plan |
NEC |
CSS |
0.00 |
497.30 |
497.30 |
39125.00 |
12-Feb-08 |
45% |
0.00 |
144.11 |
144.11 |
0.00 |
353.19 |
353.19 |
353.19 |
Work
in progress |
|
|
| 18 |
Construction
of link road Turung School to Suminkhor Primary School. |
|
4.75
Km |
Mr.
Subaash Kharel |
Tenth
Plan |
NEC |
New
Road |
22.79 |
358.66 |
381.45 |
39428.00 |
6-Jun-09 |
79% |
0.00 |
169.05 |
169.05 |
22.79 |
189.61 |
212.40 |
212.40 |
Work
in progress |
|
|
| 19 |
Construction
of 30m Span Steel Bridges Over Rinzi Khola at Kolagari along Namchi-Vok Road |
|
30m |
Bhupal
Chamling |
Tenth
Plan |
NEC |
Repl. |
28.34 |
157.50 |
185.84 |
12-Dec-07 |
6-Jun-09 |
100% |
0.00 |
109.03 |
109.03 |
28.34 |
48.47 |
76.81 |
76.81 |
Work
completed |
|
|
| 20 |
Construction
of Steel Bridge over Upper Ben Khola on G.L.V.C. road. |
|
25m |
- |
Tenth
Plan |
NEC |
CSS |
0.00 |
90.83 |
90.83 |
14-Feb-06 |
- |
100% |
0.00 |
81.77 |
81.77 |
0.00 |
9.06 |
9.06 |
9.06 |
Work
completed |
|
|
| 21 |
Construction
of Makha Suspension Bridge over Tista Khola at Tanak on Makha -Lingi
-Yangang- Ravangla Road in South Sikkim.(NEC) |
Ravangla |
100m |
R.N.
Chamling |
Tenth
Plan |
NEC |
CSS |
0.00 |
495.25 |
495.25 |
25-Aug-06 |
- |
10% |
0.00 |
32.28 |
32.28 |
0.00 |
462.97 |
462.97 |
462.97 |
Work
in progress |
|
|
| 22 |
Improvement
of Ralang - Phamtam Road |
|
13Km |
- |
Eleventh
Plan |
NEC |
CSS |
0.00 |
1183.00 |
1,183.00 |
25-Aug-06 |
- |
|
0.00 |
269.13 |
269.13 |
0.00 |
913.87 |
913.87 |
913.87 |
- |
|
|
| 23 |
Surface
strengthening drainage & P. Works on Namchi- Damthang Ravangla road- Km
1st -26th. |
|
26Km |
- |
Tenth
Plan |
NLCPR |
Remv. |
461.61 |
1,207.00 |
1,668.61 |
1-Jan-05 |
1-Feb-07 |
99% |
224.94 |
1,164.19 |
1,389.13 |
236.67 |
42.81 |
279.48 |
279.48 |
Work
in progress |
|
|
| 24 |
Replacement
of existing Sikkip Suspension Bridge over Rangit River |
|
82m |
Mr.
Chandra Khaling |
Tenth
Plan |
NLCPR |
Repl. |
24.47 |
53.66 |
78.13 |
15-Dec-03 |
30-Mar-07 |
100% |
11.78 |
53.65 |
65.43 |
12.69 |
0.01 |
12.70 |
12.70 |
Work
completed |
|
|
| 25 |
Upgradation,
Surface strengthening, drainage & P/W on Ravangla Makha Road Km
10th,11th,12th and 13th. |
|
4Km |
Smt.
Sonam Doma Bhutia |
Tenth
Plan |
NLCPR |
CSS |
0.00 |
119.05 |
119.05 |
15-Jan-03 |
30-Nov-06 |
100% |
0.00 |
116.17 |
116.17 |
0.00 |
2.88 |
2.88 |
2.88 |
Work
completed |
|
|
| 26 |
Upgradation,
Surface strengthening, drainage & P/W on Ravangla Makha Road Km 18th to
21st |
|
3Km |
Mr.
S. B. Chamling |
Tenth
Plan |
NLCPR |
CSS |
0.00 |
109.18 |
109.18 |
15-Jan-03 |
30-Nov-06 |
100% |
0.00 |
102.96 |
102.96 |
0.00 |
6.22 |
6.22 |
6.22 |
Work
completed |
|
|
| 27 |
Const.
of motorable link road from upper Vok to Ung Raam (Water falls) via Namplang
and rabong village in Omchu |
|
6Km |
Mr.
B. Tsh. Bhutia |
Tenth
Plan |
RSVY |
New
Road |
60.11 |
180.00 |
240.11 |
22-Aug-05 |
21-Aug-07 |
85% |
54.40 |
180.00 |
234.40 |
5.71 |
0.00 |
5.71 |
5.71 |
Work
in progress |
|
|
| 28 |
Construction
of truckable roasd from Borong-Phamtam road to Upper Borong via Gurug Gumpa
Km 1st. |
|
1Km |
Shri
K. B. Gurung |
Tenth
Plan |
RSVY |
CSS |
0.00 |
64.00 |
64.00 |
2-Feb-06 |
12-Nov-06 |
100% |
0.00 |
63.98 |
63.98 |
0.00 |
0.02 |
0.02 |
0.02 |
Work
completed |
|
|
| 29 |
Construction
of truckable roasd from Borong-Phamtam road to Upper Borong via Gurug Gumpa
Km 2nd. |
|
1Km |
Shr.
D. M. Gurung |
Tenth
Plan |
RSVY |
CSS |
2-Feb-06 |
13-Nov-06 |
100% |
0.00 |
Work
completed |
|
|
| 30 |
Construction
of link road to Gagyong village km 3 |
|
3Km |
- |
|
RSVY |
CSS |
0.00 |
87.00 |
87.00 |
- |
- |
100% |
0.00 |
77.71 |
77.71 |
0.00 |
9.29 |
9.29 |
9.29 |
Work
completed |
|
|
| |
STATE
PLAN |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 31 |
Construction
of Link Road from Rangang to Yangang-Makha via Majuwa : Km 1st and 2nd |
Ravangla |
2Km |
Mr.
S. B. Chamling |
Tenth
Plan |
State
Plan |
Addl.
Facilities |
62.36 |
0.00 |
62.36 |
1-Jan-05 |
10-Oct-05 |
99% |
53.95 |
0.00 |
53.95 |
8.41 |
0.00 |
8.41 |
8.41 |
Work
in progress |
|
|
| 32 |
Construction
of Link Road from Rangang to Yangang-Makha via Majuwa : Km 3rd. |
Ravangla |
1Km |
Mr.
Nar Bhd. Gurung |
Tenth
Plan |
State
Plan |
Addl.
Facilities |
22.83 |
0.00 |
22.83 |
1-Jan-05 |
10-Oct-05 |
100% |
16.17 |
0.00 |
16.17 |
6.66 |
0.00 |
6.66 |
6.66 |
Work
completed |
|
|
| 33 |
Construction
of Kitchen for PWD Guest House at Temi, South Sikkim. |
Ravangla |
N/A |
Mr.
Bindra Kumar Rai |
Tenth
Plan |
State
Plan |
Addl.
Facilities |
11.01 |
0.00 |
11.01 |
2-Feb-07 |
8-Aug-07 |
95% |
0.00 |
0.00 |
0.00 |
11.01 |
0.00 |
11.01 |
11.01 |
Work
in progress |
|
|
| 34 |
Construction
of Helipad at Pokhari dara in Upper Yangyang |
Ravangla |
N/A |
M/s
Rinchen Ongmu Bhutia |
Eleventh
Plan |
State
Plan |
Helipad |
90.640 |
0.00 |
90.64 |
1-Jul-08 |
1-Jan-10 |
97% |
43.00 |
0.00 |
43.00 |
47.64 |
0.00 |
47.64 |
47.64 |
Work
in progress |
|
|
| 35 |
Construction
of 18ch link road from Helipad to Central University at Yanyang. |
Ravangla |
0.54Km |
Mrs.
Sumitra Gurung |
Eleventh
Plan |
State
Plan |
Helipad |
42.670 |
0.00 |
42.67 |
1-Sep-08 |
1-Dec-08 |
100% |
0.00 |
0.00 |
0.00 |
42.67 |
0.00 |
42.67 |
42.67 |
Work
completed |
|
|
| 36 |
Surface
strengthening & drainage on Yang-yang-Rangang road. Km 1st.-2nd |
|
2Km |
Mr.
S. B. Chamling |
Tenth
Plan |
State
Plan |
Exp. |
39.32 |
0.00 |
39.32 |
16-Feb-03 |
11-Jan-06 |
99% |
35.74 |
0.00 |
35.74 |
3.58 |
0.00 |
3.58 |
3.58 |
Work
in progress |
|
|
| 37 |
Carpetting,
drainage & Protective Works onYangang- Rangang road form Bifurcation
Point Km 1st and 2nd |
|
2Km |
S.B.Chamling |
Tenth
Plan |
State
Plan |
Exp. |
37.80 |
0.00 |
37.80 |
16-Feb-03 |
31-Mar-05 |
95% |
0.00 |
0.00 |
0.00 |
37.80 |
0.00 |
37.80 |
37.80 |
Work
in progress |
|
|
| 38 |
Premix
carpetting,drainage work and protective work on Melli Turuk Sadam Bhanjyang
road Km 1st - 16th. |
|
16Km |
Mr.
Tej man Rai, Birbal Subba, & Rup Narayan Rai |
Tenth
Plan |
State
Plan |
Exp. |
290.49 |
0.00 |
290.49 |
1-Jan-03 |
Aug-
31st |
100% |
248.50 |
0.00 |
248.50 |
41.99 |
0.00 |
41.99 |
41.99 |
Work
completed |
|
|
| 39 |
Construction
of Bye Pass road from Agam Singh Path to Damthang road 3Km. |
|
2.15
Km |
Shri
Bhupal Chamling |
Tenth
Plan |
State
Plan |
Exp. |
160.94 |
0.00 |
160.94 |
3-Mar-04 |
3-Mar-05 |
100% |
123.88 |
0.00 |
123.88 |
37.06 |
0.00 |
37.06 |
37.06 |
Work
completed |
|
|
| 40 |
Surface
Improvement of Approach Road to Rock
Garden from Debrong Golai-Namchi-Damthang road Km 1st & 2nd. |
|
2Km |
Dikila
Bhutia |
Tenth
Plan |
State
Plan |
Exp. |
70.22 |
0.00 |
70.22 |
18-Mar-04 |
18-Mar-05 |
100% |
67.05 |
0.00 |
67.05 |
3.17 |
0.00 |
3.17 |
3.17 |
Work
completed |
|
|
| 41 |
Premix
carpetting on Ravangla Zarrong road km
1st-11th. |
Ravangla |
11Km |
Shreekishan
Agarwal |
Tenth
Plan |
State
Plan |
Exp. |
0.00 |
0.00 |
0.00 |
24-Jun-05 |
- |
- |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
Transferred
to TSP |
|
|
| 42 |
Construction
of link road Rangang road-Yang Yang Makha via Mazuwa Gaon, 3 kms Rs. 9.49 (LC)] |
|
3Km |
Santa
Bdr. Chamling, Nar Bdr. Gurung |
Tenth
Plan |
State
Plan |
Exp. |
88.30 |
0.00 |
88.30 |
6-Jun-05 |
6-Sep-06 |
100% |
80.25 |
0.00 |
80.25 |
8.05 |
0.00 |
8.05 |
8.05 |
Work
completed |
|
|
| 43 |
Providing
premix carpetting on Approach road & Yard to Palchen Choling Monastry
[New Gumpa] at Ralang |
|
0.25
Km |
Departmental |
Tenth
Plan |
State
Plan |
Exp. |
14.65 |
0.00 |
14.65 |
18-Jun-05 |
18-Dec-05 |
100% |
14.26 |
0.00 |
14.26 |
0.39 |
0.00 |
0.39 |
0.39 |
Work
completed |
|
|
| 44 |
Restoration
work on Namchi-Phong km. 3rd ch. 30 South Sikkim. |
|
N/A |
Departmental |
Tenth
Plan |
State
Plan |
Exp. |
2.90 |
0.00 |
2.90 |
27-Jun-05 |
- |
100% |
0.00 |
0.00 |
0.00 |
2.90 |
0.00 |
2.90 |
2.90 |
Work
completed |
|
|
| 45 |
Immediate
restoration work on Namchi-Rong-Sumbuk road km. 7th-13th. |
|
6Km |
Departmental |
Tenth
Plan |
State
Plan |
Exp. |
2.63 |
0.00 |
2.63 |
2005 |
- |
100% |
0.00 |
0.00 |
0.00 |
2.63 |
0.00 |
2.63 |
2.63 |
Work
completed |
|
|
| 46 |
Extension
of Ravongla Biring road to Legship Tashiding road 5th kms in South Sikkim. |
|
5Km |
|
Tenth
Plan |
State
Plan |
Exp. |
119.40 |
0.00 |
119.40 |
2005 |
- |
100% |
43.94 |
0.00 |
43.94 |
75.46 |
0.00 |
75.46 |
75.46 |
Work
completed |
|
|
| 47 |
Diversion
of turning at Km 13 on Ravangla - Zarong Road in S-Sikkim |
Ravangla |
1Km |
Smt.
R K Rai |
Tenth
Plan |
State
Plan |
Exp. |
6.93 |
0.00 |
6.93 |
1-Apr-06 |
9-Sep-06 |
100% |
4.03 |
0.00 |
4.03 |
2.90 |
0.00 |
2.90 |
2.90 |
Work
completed |
|
|
| 48 |
Carpeting
& Protective Work on Rabong -Ralong Road Km 1st to 3rd |
|
3Km |
Binod
Gurung |
|
State
Plan |
Exp. |
6.42 |
0.00 |
6.42 |
- |
- |
100% |
0.00 |
0.00 |
0.00 |
6.42 |
0.00 |
6.42 |
6.42 |
Work
completed |
|
|
| 49 |
Carpeting
& Protective Work on Rabong -Ralong Road Km 4th to 6th |
|
2Km |
N.T.Bhutia |
|
State
Plan |
Exp. |
11.10 |
0.00 |
11.10 |
- |
- |
100% |
0.00 |
0.00 |
0.00 |
11.10 |
0.00 |
11.10 |
11.10 |
Work
completed |
|
|
| 50 |
Carpeting
& Protective Work on Rabong -Ralong Road Km 7th to 10th |
|
3Km |
Roshan
Lall Agarwal |
|
State
Plan |
Exp. |
8.18 |
0.00 |
8.18 |
- |
- |
100% |
0.00 |
0.00 |
0.00 |
8.18 |
0.00 |
8.18 |
8.18 |
Work
completed |
|
|
| 51 |
Carpeting
& Protective Work on Rabong -Ralong Road Km 11th to 13th |
|
2Km |
Tshering
Gyatso Kaleon |
Tenth
Plan |
State
Plan |
Exp. |
3.63 |
0.00 |
3.63 |
- |
- |
100% |
0.00 |
0.00 |
0.00 |
3.63 |
0.00 |
3.63 |
3.63 |
Work
completed |
|
|
| 52 |
New
cutting of Sangmoo link road Km 4th |
|
|
Mr.
K. Bhutia |
Tenth
Plan |
State
Plan |
Exp. |
6.97 |
0.00 |
6.97 |
1-Nov-97 |
- |
- |
0.00 |
0.00 |
0.00 |
6.97 |
0.00 |
6.97 |
6.97 |
- |
|
|
| 53 |
Extension
of Truakable road from Ravangla Bining Road to Tashiding Km 14th. |
Ravangla |
1Km |
Mr.
Loden C. Bhutia |
Tenth
Plan |
State
Plan |
Exp. |
22.02 |
0.00 |
22.02 |
June-05 |
12-Dec-06 |
95% |
16.83 |
0.00 |
16.83 |
5.19 |
0.00 |
5.19 |
5.19 |
Work
in progress |
|
|
| 54 |
Extension
of Truakable road from Ravangla Bining Road to Tashiding Km 15th. |
Ravangla |
1Km |
Mr.
Lha T. Bhutia |
Tenth
Plan |
State
Plan |
Exp. |
20.89 |
0.00 |
20.89 |
June-05 |
13-Dec-06 |
100% |
12.01 |
0.00 |
12.01 |
8.88 |
0.00 |
8.88 |
8.88 |
Work
completed |
|
|
| 55 |
Extension
of Truakable road from Ravangla Bining Road to Tashiding Km 16th. |
Ravangla |
1Km |
Mr.
Loden C. Bhutia |
|
State
Plan |
Exp. |
22.63 |
0.00 |
22.63 |
June-05 |
14-Dec-06 |
100% |
9.90 |
0.00 |
9.90 |
12.73 |
0.00 |
12.73 |
12.73 |
Work
completed |
|
|
| 56 |
Extension
of Truakable road from Ravangla Bining Road to Tashiding Km 17th. |
Ravangla |
1Km |
Mr.
Lha T. Bhutia |
Tenth
Plan |
State
Plan |
Exp. |
19.87 |
0.00 |
19.87 |
June-05 |
15-Dec-06 |
100% |
9.77 |
0.00 |
9.77 |
10.10 |
0.00 |
10.10 |
10.10 |
Work
completed |
|
|
| 57 |
Extension
of Truakable road from Ravangla Bining Road to Tashiding Km 18th. |
Ravangla |
1Km |
Mr.
Lha T. Bhutia |
Tenth
Plan |
State
Plan |
Exp. |
19.31 |
0.00 |
19.31 |
June-05 |
16-Dec-06 |
100% |
5.60 |
0.00 |
5.60 |
13.71 |
0.00 |
13.71 |
13.71 |
Work
completed |
|
|
| 58 |
Construction
of motorable road from Slap Village (Chettri Gaon) km 1st and 2nd |
Ravangla |
2Km |
Mr.
Lha T. Bhutia |
Tenth
Plan |
State
Plan |
Exp. |
38.02 |
0.00 |
38.02 |
9-Sep-06 |
2-Feb-07 |
87% |
21.40 |
0.00 |
21.40 |
16.62 |
0.00 |
16.62 |
16.62 |
Work
in progress |
|
|
| 59 |
Surface
strengthening & drainage on Yang-yang-Rangang road. Km 1st &
2nd. |
Ravangla |
2
Km |
Mr.
S. B. Chamling |
Tenth
Plan |
State
Plan |
Exp. |
36.19 |
0.00 |
36.19 |
16-Feb-03 |
11-Jan-06 |
100% |
21.03 |
0.00 |
21.03 |
15.16 |
0.00 |
15.16 |
15.16 |
Work
completed |
|
|
| 60 |
Diversion
of turning at Km 14 th to 18th on Ravangla - Zarong Road in S-Sikkim |
|
4Km |
Smt.
Ratna Kum. Rai |
Tenth
Plan |
State
Plan |
Exp. |
104.72 |
0.00 |
104.72 |
Jun-05 |
Mar-08 |
87% |
54.11 |
0.00 |
54.11 |
50.61 |
0.00 |
50.61 |
50.61 |
Work
in progress |
|
|
| 61 |
Construction
of link road from Kholaghari to Jaubari, Km 3rd 4th to 9th. (LC = Rs. 170.52
lakh) |
|
11.5
Km |
Bhanu
Rai & Lakpa Chuki Sherpa |
Tenth
Plan |
State
Plan |
Link
Road |
276.13 |
0.00 |
276.13 |
18-Mar-03 |
18-Dec-04 |
100% |
172.04 |
0.00 |
172.04 |
104.09 |
0.00 |
104.09 |
104.09 |
|
|
|
| 62 |
Construction
of link road from Namchi-Kopchey road to Singithang Km 1st & 2nd. (LC =
20.76 lakh) |
|
2Km |
Chandra
Bir Rai & D.P.Rai |
Tenth
Plan |
State
Plan |
Link
Road |
64.36 |
0.00 |
64.36 |
15-Mar-04 |
15/12/2004 |
100% |
41.78 |
0.00 |
41.78 |
22.58 |
0.00 |
22.58 |
22.58 |
Work
completed |
|
|
| 63 |
Construction
of Truckable road from Rong Sadhu Gaon 2km. [Lungkhiya] (LC = 17.45 lakh) |
|
2Km |
Suk
Deo Rai |
Tenth
Plan |
State
Plan |
Link
Road |
53.59 |
0.00 |
53.59 |
15-Mar-04 |
15/12/2004 |
100% |
52.29 |
0.00 |
52.29 |
1.30 |
0.00 |
1.30 |
1.30 |
Work
completed |
|
|
| 64 |
Construction
of truckable road from Rong to Khani Gaon 2Km. |
|
2Km |
- |
|
State
Plan |
Link
Road |
43.13 |
0.00 |
43.13 |
6-Jun-04 |
6-Jun-06 |
100% |
20.18 |
0.00 |
20.18 |
22.95 |
0.00 |
22.95 |
22.95 |
Work
completed |
|
|
| 65 |
Compensation
for Construction of Namchi-Nayabazar road to Harrabotey Km 1st to 2nd |
|
N/A |
Compensation |
|
State
Plan |
Link
Road |
10.07 |
0.00 |
10.07 |
- |
- |
|
3.39 |
0.00 |
3.39 |
6.68 |
0.00 |
6.68 |
6.68 |
|
|
|
| 66 |
Construction
of Kink road from Kateng Bokrang to Namthang South Sikkim. |
|
8
Km |
Buddha
Singh Tamang |
|
State
Plan |
Link
Road |
426.21 |
0.00 |
426.21 |
12-Dec-08 |
12-Dec-10 |
35% |
0.00 |
0.00 |
0.00 |
426.21 |
0.00 |
426.21 |
426.21 |
Work
in progress |
|
|
| 67 |
Construction
of Link road from Ben-Thalbari to Mangley km 1st-14th ( LC = Rs. 73.56 lakh) |
Ravangla |
14Km |
Chumden
Kaleon |
Tenth
Plan |
State
Plan |
New
Road |
313.80 |
0.00 |
313.80 |
8-Dec-03 |
27-Dec-04 |
100% |
259.82 |
0.00 |
252.03 |
53.98 |
0.00 |
61.77 |
61.77 |
Work
completed |
|
|
| 68 |
Construction
of truckable road from Ben to Namprik Km 1st. |
Ravangla |
1Km |
Chumden
Kaleon |
Tenth
Plan |
State
Plan |
New
Road |
20.85 |
0.00 |
20.85 |
2002 |
2003 |
100% |
20.85 |
0.00 |
20.70 |
0.00 |
0.00 |
0.15 |
0.15 |
Work
completed |
|
|
| 69 |
Construction
of truckable road from Lingi Paiyong Govt. Jr. high School Km 2nd (I/c 17.71
lac Comp.+2.62 Forest Comp) |
Ravangla |
1Km |
S.S.Dhakal |
Tenth
Plan |
State
Plan |
New
Road |
57.78 |
0.00 |
57.78 |
2002 |
- |
95% |
27.21 |
0.00 |
27.21 |
30.57 |
0.00 |
30.57 |
30.57 |
Work
in progress |
|
|
| 70 |
Construction
of truckable roads from Kholaghari to
Jawbari Km 10th & 11th (14th Chain) |
|
2Km |
Departmental |
Tenth
Plan |
State
Plan |
New
Road |
44.09 |
0.00 |
44.09 |
2005 |
- |
100% |
25.54 |
0.00 |
25.54 |
18.55 |
0.00 |
18.55 |
18.55 |
Work
completed |
|
|
| 71 |
Construction
of Truckable Road from Assangthang to Salghari |
|
N/A |
Compensation |
Eleventh
Plan |
State
Plan |
New
Road |
54.87 |
0.00 |
54.87 |
2007 |
- |
|
40.00 |
0.00 |
40.00 |
14.87 |
0.00 |
14.87 |
14.87 |
|
|
|
| 72 |
Construction
of truckable road from Kholaghari to Jaubari Km 10th & 11th (14 Chain). |
|
2.1Km |
- |
Tenth
Plan |
State
Plan |
New
Road |
44.09 |
0.00 |
44.09 |
- |
- |
90% |
39.87 |
0.00 |
39.87 |
4.22 |
0.00 |
4.22 |
4.22 |
Work
in progress |
|
|
| 73 |
Construction
of truckable road from Lingi Payong Govt. jr. high School Km 2nd . |
|
1Km |
Mr.
S. S. Dhakal |
|
State
Plan |
New
Road |
57.78 |
0.00 |
57.78 |
1-Mar-03 |
28-Feb-04 |
90% |
27.21 |
0.00 |
27.21 |
30.57 |
0.00 |
30.57 |
30.57 |
Work
in progress |
|
|
| 74 |
Primix
Carpeting Imp.of & Strengthening of Sirwani Pabong Tarku (SPT) km 11st to
18th |
|
7Km |
Prem
Kr.Agarwal |
|
State
Plan |
Remv. |
101.300 |
0.00 |
101.30 |
13-Nov-02 |
12-Jun-04 |
100% |
0.00 |
0.00 |
0.00 |
101.30 |
0.00 |
101.30 |
101.30 |
Work
completed |
|
|
| 75 |
Providing
Box Drain and Protective work along Pabong Simchuthang Yangang Road Km 15th
Ch 1st to 20th |
|
0.6Km |
Sonam
Gyamtso |
Tenth
Plan |
State
Plan |
Remv. |
5.250 |
0.00 |
5.25 |
- |
- |
100% |
5.04 |
0.00 |
5.04 |
0.21 |
0.00 |
0.21 |
0.21 |
Work
completed |
|
|
| 76 |
Permanent
Restoration Work along Kholaghari Jawbari Road Km 2nd & 3rd |
|
2Km |
Bhanu
Rai & Others |
Tenth
Plan |
State
Plan |
Remv. |
30.980 |
0.00 |
30.98 |
28-Jun-05 |
- |
100% |
30.98 |
0.00 |
30.98 |
0.00 |
0.00 |
0.00 |
0.00 |
Work
completed |
|
|
| 77 |
Strengthening,
Carpetting and Stabilization of approach Road to Melli - Bazar.(State Share
of NABARD) |
|
0.60
Km |
Departmental |
Tenth
Plan |
State
Plan |
Remv. |
8.51 |
0.00 |
8.51 |
28-Jun-05 |
- |
100% |
0.00 |
0.00 |
0.00 |
8.51 |
0.00 |
8.51 |
8.51 |
Work
completed |
|
|
| 78 |
Permanent
restoration nwork at Rock Garden from Debrung-Golai, Namchi Damthang road Km
1st & 2nd in S/Sikkim |
|
2Km |
- |
Eleventh
Plan |
State
Plan |
Non-Plan |
41.10 |
0.00 |
41.10 |
1-Jul-09 |
- |
14% |
0.00 |
0.00 |
0.00 |
41.10 |
0.00 |
41.10 |
41.10 |
Work
in progress |
|
|
| D |
DISTRICT : WEST |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
CENTRAL SPONSORED
SCHEMES |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 1 |
Restoration
of damages, Slip clearence, Drainage &surface improvement works of
Geythang-Karmatar road, Singshore diversion road and Utterey-Sopakha road in
West Sikkim. |
Kaluk |
2
Km |
P.K.Subba |
|
BADP |
- |
0.00 |
300.00 |
300.00 |
1-Nov-08 |
31-Oct-09 |
20% |
0.00 |
0.00 |
0.00 |
0.00 |
300.00 |
300.00 |
300.00 |
Work
in progress |
|
|
| 2 |
Surface
improvement and strengthening and premix carpetting of Rimbi Yoksum road Km
1st to 21.70. |
Geyzing |
21.70
Km |
Mr.
K. N. Bhutia |
Tenth
Plan |
EI |
- |
96.11 |
219.37 |
315.48 |
|