| MONTHLY PHYSICAL AND FINANCIAL PROGRESS REPORT FOR THE MONTH ENDING JUNE 2009 | |||||||||||||||||||||||
| Sl.No | Name of Schemes | Length Km / M | Name of Contractor | Plan | Funding Agency | (Head) | SANCTIONED AMOUNT | Date of Commen- cement | Stipulated Date of Completion | Phy Prog-ress in % | Financial Progress | Balance | TOTAL SA-BAL | Remarks | |||||||||
| S. share | C.share | Total | Expenditure till date | ||||||||||||||||||||
| S.Share | C.Share | Total | S.Share | C.Share | Total | ||||||||||||||||||
| D | DISTRICT : WEST | ||||||||||||||||||||||
| CENTRAL SPONSORED SCHEMES | |||||||||||||||||||||||
| 1 | Restoration of damages, Slip clearence, Drainage &surface improvement works of Geythang-Karmatar road, Singshore diversion road and Utterey-Sopakha road in West Sikkim. | Kaluk | 2 Km | P.K.Subba | BADP | - | 0.00 | 300.00 | 300.00 | 1-Nov-08 | 31-Oct-09 | 45% | 0.00 | 0.00 | 0.00 | 0.00 | 300.00 | 300.00 | 300.00 | Work in progress | Kaluk | ||
| 2 | Construction of link road from Legship-Gyalsing road km 13th to Bhanu Sailik Km 1st-2nd. | Geyzing | 2Km | Karna Nanda Subedi | - | CRF | Link Road | 5.61 | 229.53 | 235.14 | 8-Mar-08 | 9-Dec-09 | 60% | 5.61 | 75.48 | 81.09 | 0.00 | 154.05 | 154.05 | 154.05 | Work in progress | Geyzing | |
| 3 | Surface improvement and strengthening and premix carpetting of Rimbi Yoksum road Km 1st to 21.70. | Geyzing | 21.70 Km | Mr. K. N. Bhutia | Tenth Plan | EI | Remv. | 96.11 | 219.37 | 315.48 | 7-Feb-04 | 6-Aug-05 | 89% | 54.51 | 219.37 | 273.88 | 41.60 | 0.00 | 41.60 | 41.60 | Work in progress | Geyzing | |
| 4 | Construction of road from Salangdang to Ramnam River connecting Lodhama (West Bengal) in West Sikkim. (Part -I) | D.P Deokota | ISC | New Road | 0.00 | 869.00 | 869.00 | - | - | 0% | 0.00 | 0.00 | 0.00 | 0.00 | 869.00 | 869.00 | 869.00 | Work to be started | Soreng | ||||
| 5 | Construction of road from Salangdang to Ramnam River connecting Lodhama (West Bengal) in West Sikkim in steel bridges excluding steel parts (Part -II) | D.P Deokota | ISC | New Road | 0.00 | 569.00 | 569.00 | - | - | 0% | 0.00 | 0.00 | 0.00 | 0.00 | 569.00 | 569.00 | 569.00 | Work to be started | Soreng | ||||
| 6 | App. Road to Rincheypong Gompa / Shreda from Rinchepong Dak Bunglow Road (Km 1st ch 17th ) | Kaluk | 1.1Km | Mr. D. Lachi Bhutia | Tenth Plan | MP LADS | - | 0.00 | 15.00 | 15.00 | 16-Feb-06 | 15-Feb-08 | 89% | 0.00 | 9.90 | 9.90 | 0.00 | 5.10 | 5.10 | 5.10 | Work in progress | Kaluk | |
| 7 | Upgradation of existing Soreng Kaluk Road from Km 1st - 5th (Part - I) | Kaluk | 5 Km | Subash Tamang | NABARD | Remv. | 0.00 | 0.00 | 0.00 | - | - | 0% | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | Work to be started | Soreng | ||
| 8 | Upgradation of existing Soreng Kaluk Road from Km 6th - 16th (Part -II) | Kaluk | 10 Km | S.B. Gurung | NABARD | Remv. | 0.00 | 893.00 | 893.00 | - | - | 0% | 0.00 | 0.00 | 0.00 | 0.00 | 893.00 | 893.00 | 893.00 | Work to be started | Soreng | ||
| 9 | Upgradation of existing Chankung Gelling Road from Km 1st - 3rd(Part - I) | Kaluk | 3 Km | Mahindra Lakhotia | NABARD | 0.00 | 0.00 | 0.00 | - | - | 0% | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | Work to be started | Soreng | |||
| 10 | Upgradation of existing Chankung Gelling Road from Km 4th-7th(Part -II) | Kaluk | 4 Km | Sanjay Chandak | NABARD | 0.00 | 0.00 | 0.00 | - | - | 0% | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | Work to be started | Soreng | |||
| 11 | Strengthening, widening premix carpetting works along Pelling Chumbung Road Km 1st - 4th. | Kaluk | 4 Km | P.C. lama | NABARD | Exp. | 51.13 | 194.87 | 246.00 | - | - | 10% | 0.00 | 11.35 | 11.35 | 51.13 | 183.52 | 234.65 | 234.65 | Work in progress | Geyzing | ||
| 12 | Construction of link road from Alpinne Cheese factory at kaluk Dentam Road km 19th ch 8th - Lidung Village under Dentam Consituency in West-Sikkim (Km 2nd Ch 3) | Kaluk | 4 Km | Sabitri Thapa | NABARD | 0.00 | 56.76 | 56.76 | 6-Feb-09 | 6-Dec-09 | 5% | 0.00 | 0.00 | 0.00 | 0.00 | 56.76 | 56.76 | 56.76 | Work in progress | Geyzing | |||
| 13 | Construction of strengthening draianage & carpetting of Khanisherbong road Km 1st -11th. | Soreng | 11Km | Mr. B. L. Gurung | Eleventh Plan | NEC | - | 0.00 | 486.36 | 486.36 | 3-Mar-07 | 9-Sep-08 | 50% | 0.00 | 144.11 | 144.11 | 0.00 | 342.25 | 342.25 | 342.25 | Work in progress | Soreng | |
| 14 | Strengthening draianage & carpetting of Sombaria Hilley road Km 1st- 26th | Soreng | 26Km | Mr. Kamal Kr. Rai | Tenth Plan | NEC | - | 0.00 | 845.68 | 845.68 | 1-Nov-06 | 10-Oct-08 | 72% | 0.00 | 317.22 | 317.22 | 0.00 | 528.46 | 528.46 | 528.46 | Work in progress | Soreng | |
| 15 | Strengthening and carpetting, protection and drainage of Bermiock Legship road Km. 1st to 9th | Kaluk | 9Km | Mr. Atul Dhanotia | Tenth Plan | NEC | - | 0.00 | 449.46 | 449.46 | 16-Feb-06 | 15-Feb-08 | 89% | 0.00 | 278.44 | 278.44 | 0.00 | 171.02 | 171.02 | 171.02 | Work in progress | Kaluk | |
| 16 | Construction of road from Sreebadam to Magalbaria 18.30Km in West-Sikkim. | Geyzing | 18.30 Km | Norden Bhutia | NLCPR | - | 0.00 | 736.00 | 736.00 | - | - | 0% | 0.00 | 0.00 | 0.00 | 0.00 | 736.00 | 736.00 | 736.00 | Work to be started | Soreng | ||
| 17 | Repalacement of Rathong Suspension bridge by steel bridge on Rimbi-Yoksum road. | Geyzing | 60m | Mrs. S. Dolma Bhutia | Tenth Plan | NLCPR | - | 0.00 | 327.57 | 327.57 | 2-Jun-05 | 31-Aug-06 | 97% | 0.00 | 262.01 | 262.01 | 0.00 | 65.56 | 65.56 | Work in progress | Geyzing | ||
| 18 | Repalacement of Rimbi Suspension bridge by steel bridge on Pelling - Rimbi road. | Geyzing | 45m | Mr. Keshav Pradhan | Tenth Plan | NLCPR | - | 2-Jun-05 | 31-Aug-06 | 90% | Work in progress | Geyzing | |||||||||||
| 19 | Construction of premix carpetting /imp. Dentam Uttrey road Km 1st to 10th | Kaluk | 10Km | Mr. C.B. Subba | Tenth Plan | NLCPR | - | 0.00 | 342.46 | 342.46 | 3-Mar-05 | 31-Aug-06 | 97% | 0.00 | 282.49 | 282.49 | 0.00 | 59.97 | 59.97 | 59.97 | Work in progress | Kaluk | |
| 20 | Surface imp/ carpetting i/c drainage works on Pelling Dentam road Km 1st to 9th | Kaluk | 9Km | Mr. Anjani Kr. Agarwal | Tenth Plan | NLCPR | - | 0.00 | 606.54 | 606.54 | 3-Mar-05 | 31-Aug-06 | 97% | 0.00 | 544.62 | 544.62 | 0.00 | 61.92 | 61.92 | 61.92 | Work in progress | Kaluk | |
| 21 | Surface imp/ carpetting i/c drainage works on Pelling Dentam road Km 18th to 20th | Kaluk | 2Km | CB Subba | Tenth Plan | NLCPR | - | 0.00 | 91.30 | 91.30 | 3-Mar-05 | 31-Aug-06 | 100% | 0.00 | 85.80 | 85.80 | 0.00 | 5.50 | 5.50 | 5.50 | Work completed | Kaluk | |
| 22 | Surface imp/ carpetting i/c drainage works on Pelling Dentam road Km 10th to 17th. | Kaluk | 7Km | Mr. Mahabir Pd. Agarwal | Tenth Plan | NLCPR | - | 104.82 | 301.97 | 406.79 | 3-Mar-05 | 31-Aug-06 | 93% | 70.49 | 301.97 | 372.46 | 34.33 | 0.00 | 34.33 | 34.33 | Work in progress | Kaluk | |
| 23 | Replacement of B.B. Lal Suspension Bridge on Pelling Dentam road along Gyalshing Soreng Road. | Kaluk | 68m | Mr. Mahabir Pd. Agarwal | Tenth Plan | NLCPR | - | 0.00 | 200.30 | 200.30 | 3-Mar-05 | 31-Aug-06 | 97% | 0.00 | 75.07 | 75.07 | 0.00 | 125.23 | 125.23 | 125.23 | Work in progress | Kaluk | |
| 24 | Construction of prestressed bridge over Rangit River on Legship-Tashiding road. | Geyzing | Mahabir Pd. Agarwal | Eleventh Plan | NLCPR | Remv. | 273.03 | 1638.18 | 1,911.21 | 9-Mar-09 | 8-Mar-11 | 0% | 0.00 | 273.03 | 273.03 | 273.03 | 1,365.15 | 1,638.18 | 1,638.18 | Work not yet started | Geyzing | ||
| 25 | Construction of 65m Span Steel Bridge over Rangit river in between Mengnem & Phamtam | Geyzing | 65m | Mr. U. P. Bhutia (Kazi) | Tenth Plan | RSVY | Repl. | 123.85 | 148.93 | 272.78 | 23-Nov-05 | 22-May-07 | 60% | 29.13 | 136.56 | 165.69 | 94.72 | 12.37 | 107.09 | 107.09 | Work in progress | Geyzing | |
| STATE PLAN | |||||||||||||||||||||||
| 26 | Slope stablization, slip aressting & benching works, permanent restoration, catch water drain works at Gundrukey on Legship-Tashiding road. | Daramdin | Sandeep Kr. Sharma | Eleventh Plan | ACA | ACA | 115.00 | 0.00 | 115.00 | 13-Feb-09 | 12-Feb-10 | 15% | 1.88 | 0.00 | 1.88 | 113.12 | 0.00 | 113.12 | 113.12 | Work in progress | Geyzing | ||
| 27 | Slope stablization, slip aressting & benching works, permanent restoration, catch water drain works at Nauley Bhir on Gyalshing Pelling road and protgection of Class IV Govt. Qtr near mechanical turning on Gyalshing-Pelling road. | Geyzing | Deepak Kr. Pradhan | Eleventh Plan | ACA | ACA | 200.00 | 0.00 | 200.00 | 12-Feb-09 | 12-Feb-10 | 0% | 0.00 | 0.00 | 0.00 | 200.00 | 0.00 | 200.00 | 200.00 | Work not yet started | Geyzing | ||
| 28 | Slope stablization, restoration of road at Ringyang and Mandu on Tashiding-Kongree Labdong road. | Geyzing | Bikash Subedi | Eleventh Plan | ACA | ACA | 350.00 | 0.00 | 350.00 | - | - | 0% | 0.00 | 0.00 | 0.00 | 350.00 | 0.00 | 350.00 | 350.00 | Work not yet started | Geyzing | ||
| 29 | Construction of motorable road from Relli Khola to Phamtam Km 14th - 17th. | Geyzing | 3Km | Mr. K.N.Bhutia | Tenth Plan | State Plan | New Road | 125.19 | 0.00 | 125.19 | 4-Mar-03 | 1-Mar-04 | 85% | 111.05 | 0.00 | 111.05 | 14.14 | 0.00 | 14.14 | 14.14 | Work in progress | Geyzing | |
| 30 | Construction of motorable road from Relli Khola to Phamtam Km 18th-21st. | Geyzing | 3Km | Mr. A.P. Pradhan | Tenth Plan | State Plan | New Road | 131.74 | 0.00 | 131.74 | 4-Mar-03 | 1-Mar-04 | 99% | 121.25 | 0.00 | 121.25 | 10.49 | 0.00 | 10.49 | 10.49 | Work in progress | Geyzing | |
| 31 | Construction of road from Upper Rumbuk to Tereybair in West Sikkim Km 3rd. | Soreng | 1Km | Mr. Phurdiki Sherpa | Tenth Plan | State Plan | New Road | 24.73 | 0.00 | 24.73 | 1-Jan-05 | 4-Apr-06 | 85% | 20.13 | 0.00 | 20.13 | 4.60 | 0.00 | 4.60 | 4.60 | Work in progress | Soreng | |
| 32 | Construction of road from Upper Rumbuk to Tereybair in West Sikkim Km 4th. | Soreng | 1Km | Mr. Lakpa Sherpa | Tenth Plan | State Plan | New Road | 22.36 | 0.00 | 22.36 | 1-Jan-05 | 4-Apr-06 | 70% | 19.56 | 0.00 | 19.56 | 2.80 | 0.00 | 2.80 | 2.80 | Soreng | ||
| 33 | Construction of road from Upper Rumbuk to Tereybair in West Sikkim Km 5th. | Soreng | 1Km | Mr. Lakpa Sherpa | Tenth Plan | State Plan | New Road | 24.45 | 0.00 | 24.45 | 1-Jan-05 | 4-Apr-06 | 85% | 20.05 | 0.00 | 20.05 | 4.40 | 0.00 | 4.40 | 4.40 | Work in progress | Soreng | |
| 34 | Construction of road from Upper Rumbuk to Tereybair in West Sikkim Km 6th. | Soreng | 1Km | Mr. Lakpa Sherpa | Tenth Plan | State Plan | New Road | 22.75 | 0.00 | 22.75 | 1-Jan-05 | 4-Apr-06 | 80% | 15.00 | 0.00 | 15.00 | 7.75 | 0.00 | 7.75 | 7.75 | Soreng | ||
| 35 | Construction of 1.60 Km approach road to 50m Span Steel BridgeOver Rangit river at Phamtam | Geyzing | 1.6 Km | Departmental | - | State Plan | New Road | 149.03 | 0.00 | 149.03 | 1-Jun-08 | 1-Mar-09 | 22% | 32.32 | 0.00 | 32.32 | 116.71 | 0.00 | 116.71 | 116.71 | Work in progress | Geyzing | |
| 36 | Construction of approach road to Phamtam road point to 50m Span Steel BridgeOver Rangit river. | Geyzing | 50m | Departmental | - | State Plan | New Road | 37.52 | 0.00 | 37.52 | 10-Jun-08 | 2-Mar-09 | 94% | 29.67 | 0.00 | 29.67 | 7.85 | 0.00 | 7.85 | 7.85 | Work in progress | Geyzing | |
| 37 | Construction of motorable road from Khanisirbong to kamling. 13th - 21st | Soreng | 1Km | Mr. N.T. Tamang | Tenth Plan | State Plan | Remv. | 105.56 | 0.00 | 105.56 | 1-Jan-05 | 11-Nov-06 | 10% | 23.50 | 0.00 | 23.50 | 82.06 | 0.00 | 82.06 | 82.06 | Work order cancelled | Soreng | |
| 38 | Widening, surface improvement, premix carpetting of Sombaria Puretar Km 6th to 13th | Soreng | 7Km | Mr. Amrit Subba, Prakash Subba, S.H. Sherpa, P.D. Sherpa | Tenth Plan | State Plan | Remv. | 128.00 | 0.00 | 128.00 | 1-Jan-05 | 10-Oct-06 | 100% | 124.92 | 0.00 | 124.92 | 3.08 | 0.00 | 3.08 | 3.08 | Work completed | Soreng | |
| 39 | Technical Surveillance and rehabilitation of Singshore Suspensiopn Bridge along Dentam Uttarey Road | Kaluk | N/A | AS Bumper | State Plan | Repl. | 110.00 | 0.000 | 110.00 | 7-Jun-06 | 7-Nov-08 | 60% | 67.70 | 0.00 | 67.70 | 42.30 | 0.00 | 42.30 | 42.30 | Work in progress | Kaluk | ||
| 40 | Construction of 25m span suspension bridge at Reshi Khola on Shribadam Deyathang road. | Soreng | 25m | Mr. B.R. Sharma | Tenth Plan | State Plan | Repl. | 45.03 | 0.00 | 45.03 | 3-Mar-05 | 3-Mar-07 | 80% | 27.11 | 0.00 | 27.11 | 17.92 | 0.00 | 17.92 | 17.92 | Work in progress | Soreng | |
| 41 | Construction of road from Rinnchenpong Magalbaria -Deorali to Upper & Lower Chuchen village via Mangbir in West Sikkim. | Khusendra Sharma | State Plan | STIDF | 0.00 | 0.00 | 0.00 | - | - | 0% | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | Agreement to be drawn | Kaluk | ||||
| 42 | Construction of road from Kalez khola Power House intake to Jhakridunga via Ferek Km 1st - 9th in West-Sikkim. | Kamal Singh Gurung | State Plan | STIDF | 0.00 | 0.00 | 0.00 | - | - | 0% | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | Agreement to be drawn | Kaluk | ||||
| 43 | Construction of 55.00m Steel Bridge over Rateypani Khola along Mangley Chuchen Road. | Bir Man Rai | State Plan | STIDF | 0.00 | 0.00 | 0.00 | - | - | 0% | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | Agreement to be drawn | Kaluk | ||||
| 44 | Construction of 30.00m Steel Bridge over Rateypani Khola along Mangley Chuchen Road. | Bir Man Rai | State Plan | STIDF | 0.00 | 0.00 | 0.00 | - | - | 0% | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | Agreement to be drawn | Kaluk | ||||
| 45 | Construction of 10.00m Steel Bridge over Rateypani Khola along Mangley Chuchen Road. | Bir Man Rai | State Plan | STIDF | 0.00 | 0.00 | 0.00 | - | - | 0% | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | Agreement to be drawn | Kaluk | ||||
| 46 | Construction of 57.00m Steel Bridge over Kalej Khola along Intake Jhakridunga road. | Man Kr. Gurung | State Plan | STIDF | 0.00 | 0.00 | 0.00 | - | - | 0% | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | Agreement to be drawn | Kaluk | ||||
| 47 | Construction of 25.00m Steel Bridge over Farek Khola along Intake Jhakridunga road. | Gayendra Pd. Basnett | State Plan | STIDF | 0.00 | 0.00 | 0.00 | - | - | 0% | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | Agreement to be drawn | Kaluk | ||||