| MONTHLY PHYSICAL AND FINANCIAL PROGRESS REPORT FOR THE MONTH ENDING JUNE 2009 | . | ||||||||||||||||||||||
| . | |||||||||||||||||||||||
| Sl.No | Name of Schemes | Length Km / M | Name of Contractor | Plan | Funding Agency | (Head) | SANCTIONED AMOUNT | Date of Commen- cement | Stipulated Date of Completion | Phy Prog-ress in % | Financial Progress | Balance | TOTAL SA-BAL | Remarks | |||||||||
| S. share | C.share | Total | Expenditure till date | ||||||||||||||||||||
| S.Share | C.Share | Total | S.Share | C.Share | Total | ||||||||||||||||||
| B | DISTRICT :EAST | ||||||||||||||||||||||
| CENTRAL SPONSORED SCHEMES | |||||||||||||||||||||||
| 1 | Const. of link road from Arubotey to Subaneydara km 1st-3rd. | Pakyong | 3Km | Om Bhd. Gurung | Ninth Plan | BADP | - | 0.00 | 29.97 | 29.97 | 30-Nov-00 | 16-Mar-01 | 68% | 0.00 | 22.98 | 22.98 | 0.00 | 6.99 | 6.99 | 6.99 | Work abondoned | Pakyong | |
| 2 | Const. of link road from sisney to North Regu km 1st -4th. | Pakyong | 4Km | T.S. Lama | Tenth Plan | BADP | - | 0.00 | 30.31 | 30.31 | 21-Nov-00 | 5-Mar-01 | 95% | 0.00 | 24.54 | 24.54 | 0.00 | 5.77 | 5.77 | 5.77 | Work abondoned | Pakyong | |
| 3 | Construction of 60 m span steel bridge at Bongliung over Rongli Chu in East Sikkim | 60m | Gazendra Rai | Eleventh Plan | CSS(BRGF) | - | 0.00 | 74.07 | 74.07 | 29-Mar-08 | 29-Sep-09 | 20% | 0.00 | 0.00 | 0.00 | 0.00 | 74.07 | 74.07 | 74.07 | Work in progress | Pakyong | ||
| 4 | Const. of 12 m span R.C.C. Bridge on Sangkhola Zingla Martam Road at Km 11th ch-3rd. | 12m | Anita Gurung | Eleventh Plan | CRF | - | 0.00 | 38.63 | 38.63 | 1-Apr-07 | 31-Mar-08 | 65% | 0.00 | 10.23 | 10.23 | 0.00 | 28.40 | 28.40 | 28.40 | Work in progress | |||
| 5 | Const. of 12 m span R.C.c. Bridge on Sangkhola Zingla Martam Road at Km 12th ch-4th.. | 12m | T.B. Pradhan | Eleventh Plan | CRF | - | 0.00 | 45.12 | 45.12 | 1-Apr-07 | 31-Mar-08 | 90% | 0.00 | 27.70 | 27.70 | 0.00 | 17.42 | 17.42 | 17.42 | Work in progress | |||
| 6 | Surface improvement and widening of Sang Sirwani Road Km 1st & App Road from Mech Sub Div Office at Dochum | 1Km | Kishor Pradhan | Eleventh Plan | CRF | - | 0.00 | 155.00 | 155.00 | 10-Oct-07 | 9-Sep-08 | 95% | 0.00 | 71.18 | 71.18 | 0.00 | 83.82 | 83.82 | 83.82 | Work in progress | |||
| 7 | Upgradation of Link Road from NH-31A to Dokey Chisopani Km 1st | 1Km | Kishor Pradhan | Eleventh Plan | CRF | - | 0.00 | 152.58 | 0.00 | 29-Feb-08 | 28-Feb-09 | 45% | 0.00 | 42.47 | 0.00 | 0.00 | 110.11 | 0.00 | 0.00 | Work in progress | |||
| 8 | Upgradation of Link Road from NH-31A to Dokey Chisopani Km 2nd | Singtam | 1Km | Gopal Sharma | Eleventh Plan | CRF | - | 29-Feb-08 | 28-Feb-09 | 30% | 0.00 | Work in progress | |||||||||||
| 9 | Upgradation of Link Road from NH-31A to Dokey Chisopani Km 3rd | Singtam | 1Km | Suren Gurung | Ninth Plan | CRF | - | 29-Feb-08 | 28-Feb-09 | 50% | 0.00 | Work in progress | |||||||||||
| 10 | Construction of link road from pakyong Nop gaon to barpipal Dara, Km 1st-3rd in East-Sikkim | Pakyong | 3Km | Hemandri Adhikari | Eleventh Plan | CRF | CSS | 0.00 | 102.29 | 102.29 | 5-Aug-08 | 5-Mar-10 | 55% | 0.00 | 57.15 | 57.15 | 0.00 | 45.14 | 45.14 | 45.14 | Work in progress | Pakyong | |
| 11 | Surface strengthening upgradation and carpeting of Pakyong-Karthok Naya Busty road km 5th -7th. | Pakyong | 2Km | Adup Bhutia | Tenth Plan | EI | Remv. | 183.89 | 183.89 | 367.78 | 21/06/05 | 31-Aug-08 | 60% | 3.16 | 28.52 | 31.68 | 180.73 | 155.37 | 336.10 | 336.10 | Work in progress | Pakyong | |
| 12 | Upgradation/carpeting P/works and drainage along Pakyong-Karthok road km 1st-4th. | Pakyong | 4Km | P. N. Kazi | Tenth Plan | EI | Exp. | 143.35 | 143.35 | 286.70 | 28-Mar-05 | 27-Jul-06 | 65% | 38.43 | 47.54 | 85.97 | 104.92 | 95.81 | 200.73 | 200.73 | Work in progress | Pakyong | |
| 13 | Upgradation and premix carpeting of Kotlaytar Rai Gaon Road,km 1st & 2nd | Pakyong | 2Km | Miss Devi Dakhal | Tenth Plan | EI | Exp. | 73.14 | 73.14 | 146.28 | 27-Sep-05 | 27-Sep-06 | 95% | 41.52 | 0.00 | 41.52 | 31.62 | 73.14 | 104.76 | 104.76 | Work in progress | Pakyong | |
| 14 | Construction of Road from Rathong (NH-31A) to Kimchithang Km 1st to 15th (EI) | 15Km | KK Agarwal | Tenth Plan | EI | New Road | 874.19 | 701.89 | 1,576.08 | 21-Apr-08 | 20-Apr-10 | 35% | 0.63 | 212.00 | 212.63 | 873.56 | 489.89 | 1,363.45 | 1,363.45 | Work in progress | |||
| 15 | Improvement of Sang Dipudara Road (EI) | 14Km | Dalu Ram Sharma / Sanjay Kumar | Tenth Plan | EI | Remv. | 277.44 | 347.74 | 625.18 | 18-Nov-02 | 17-Aug-04 | 80% | 233.08 | 0.00 | 233.08 | 44.36 | 347.74 | 392.10 | 392.10 | Work in progress | |||
| 16 | Widening, upgradation of pavement & drainage system along Rangpo Duga Pendam road km 1st - 15th | 15Km | M/s Apex Project & Investment P. Ltd. | Eleventh Plan | ISC | - | 0.00 | 950.00 | 950.00 | 15-Jun-08 | 16-Dec-08 | 65% | 0.00 | 303.67 | 303.67 | 0.00 | 646.33 | 646.33 | 646.33 | Work in progress | |||
| 17 | Improvement of Rhenock - Simanakhola Road Km 1st to 3rd. (ISC) | 3Km | Mr. Kuber Raj Rai | Tenth Plan | ISC | - | 0.00 | 250.00 | 250.00 | 26-Mar-08 | 27-Mar-09 | 35% | 0.00 | 50.00 | 50.00 | 0.00 | 200.00 | 200.00 | 200.00 | Work in progress | Pakyong | ||
| 18 | Construction of Link Road from Sakyong to Beyong km 1st to 2nd (State Share of NABARD) | 2Km | KRSharma & TB Pradhan | Eleventh Plan | NABARD | Link Road | 19.47 | 79.51 | 98.98 | 12-Mar-08 | 11-Mar-09 | 85% | 0.00 | 43.42 | 43.42 | 19.47 | 36.09 | 55.56 | 55.56 | Work in progress | |||
| 19 | Construction of Link Road from Sang Dipudara road to Beyong Gumpa Km 1st - 3rd. | 3 Km | Ujwal Pradhan,Pranay Pradhan,Wangdup Tamang | Eleventh Plan | NABARD | 0.00 | 148.95 | 148.95 | 28-Jan-09 | 27-Jan-09 | 5% | 0.00 | 0.00 | 0.00 | 0.00 | 148.95 | 148.95 | 148.95 | Work in progress | ||||
| 20 | Strengthening,drainage and Carpeting and construction of 30m span steel bridge along Assam-Pakyong road km 7th - 15th. | Pakyong | 30m | S.K. Agarwal | Tenth Plan | NEC | - | 0.00 | 750.78 | 750.78 | 6-Nov-06 | 5-May-08 | 80% | 0.00 | 514.44 | 514.44 | 0.00 | 236.34 | 236.34 | 236.34 | Work in progress | Pakyong | |
| 21 | Const. of Goshkhan Dara Bridge over River Teesta at Singtam, East Sikkim | Singtam | 120m | M.P Agarwal | Tenth Plan | NLCPR | - | 0.00 | 1,337.57 | 1,337.57 | 10-Jan-07 | 11-Jun-08 | 40% | 0.00 | 468.00 | 468.00 | 0.00 | 869.57 | 869.57 | 869.57 | Work in progress | ||
| 22 | Construction of diversion road Ranipool -Pakyong road km 1st -3rd | Singtam | 3 Km | B.K.Agarwal | Tenth Plan | NLCPR | - | 0.00 | 251.19 | 251.19 | 21-Feb-05 | 21-Nov-05 | 100% | 0.00 | 251.08 | 251.08 | 0.00 | 0.11 | 0.11 | 0.11 | Phase II Estimate to be submitted | ||
| STATE PLAN | |||||||||||||||||||||||
| 23 | Construction of Helipad at Changu | N/A | Departmental | Tenth Plan | Link Road | Link Road | 43.37 | 0.00 | 43.37 | Mar-07 | Dec-08 | 60% | 17.00 | 0.00 | 10.00 | 26.37 | 0.00 | 33.37 | 33.37 | Work in progress | |||
| 24 | Premix Carpetting and Surface improvement Chewribotay Pendam Km 1st - 6th | Singtam | 6Km | Basudev Pradhan | Tenth Plan | State Plan | Exp. | 117.78 | 0.00 | 117.78 | 29/05/2003 | 31/01/04 | 95% | 96.28 | 0.00 | 96.28 | 21.50 | 0.00 | 21.50 | 21.50 | Case under investigation by Vigilence Deptt.. | ||
| 25 | Ext. of Pakyong-Mamring Tareythang road km 1st | 1Km | Khush N.Adhikari | Tenth Plan | State Plan | Exp. | 104.75 | 0.00 | 104.75 | 1-Jul-05 | 31-Dec-07 | 90% | 103.79 | 0.00 | 103.79 | 0.96 | 0.00 | 0.96 | 0.96 | Work in progress | |||
| 26 | Ext. of Pakyong-Mamring Tareythang road km 2nd | 1Km | Johar Man Rai | Tenth Plan | State Plan | Exp. | 16.61 | 0.00 | 16.61 | 1-Jul-05 | 31-Dec-07 | 90% | 16.37 | 0.00 | 16.37 | 0.24 | 0.00 | 0.24 | 0.24 | Work in progress | |||
| 27 | Ext. of Pakyong-Mamring Tareythang road km 3rd | 1Km | G.K. Pradhan | Tenth Plan | State Plan | Exp. | 22.70 | 0.00 | 22.70 | 1-Jul-05 | 31-Dec-07 | 90% | 22.16 | 0.00 | 22.16 | 0.54 | 0.00 | 0.54 | 0.54 | Work in progress | |||
| 28 | Ext. of Pakyong-Mamring Tareythang road km 4th. | 1Km | Udai Mishara | Tenth Plan | State Plan | Exp. | 17.92 | 0.00 | 17.92 | 1-Jul-05 | 31-Dec-07 | 90% | 17.60 | 0.00 | 17.60 | 0.32 | 0.00 | 0.32 | 0.32 | Work in progress | |||
| 29 | Ext. of Pakyong-Mamring Tareythang road km 5th. | 1Km | K.S.Rai | Tenth Plan | State Plan | Exp. | 27.01 | 0.00 | 27.01 | 1-Jul-05 | 31-Dec-07 | 95% | 16.05 | 0.00 | 16.05 | 10.96 | 0.00 | 10.96 | 10.96 | Work in progress | |||
| 30 | Ext. of Pakyong-Mamring Tareythang road km 6th. | 1Km | Ishore Dakahal | Tenth Plan | State Plan | Exp. | 21.15 | 0.00 | 21.15 | 1-Jul-05 | 31-Dec-07 | 90% | 18.39 | 0.00 | 18.39 | 2.76 | 0.00 | 2.76 | 2.76 | Work in progress | |||
| 31 | Ext. of Pakyong-Mamring Tareythang road km 7th. | 1Km | K.S.Rai | Tenth Plan | State Plan | Exp. | 22.10 | 0.00 | 22.10 | 1-Jul-05 | 31-Dec-07 | 75% | 8.68 | 0.00 | 8.68 | 13.42 | 0.00 | 13.42 | 13.42 | Work in progress | |||
| 32 | Ext. of Pakyong-Mamring Tareythang road km.8th | 1Km | M. K. Pradhan | Tenth Plan | State Plan | Exp. | 21.66 | 0.00 | 21.66 | 1-Jul-05 | 31-Dec-07 | 90% | 11.01 | 0.00 | 11.01 | 10.65 | 0.00 | 10.65 | 10.65 | Work in progress | |||
| 33 | Const. of Song-zingla Martam road km 9th. | 1Km | P.T. Lepcha | Eleventh Plan | State Plan | New Road | 12.45 | 0.00 | 12.45 | 5-Mar-03 | 20-Dec-03 | 100% | 5.63 | 0.00 | 5.63 | 6.82 | 0.00 | 6.82 | 6.82 | Work completed | |||
| 34 | Construction of link road from AssamPakyong road to Kadamtang village Km 3rd & 4th. | Singtam | 1Km | D.P Manger | State Plan | New Road | 41.74 | 0.00 | 41.74 | 7-Jan-05 | 30-Jun-06 | 100% | 29.63 | 0.00 | 29.63 | 12.11 | 0.00 | 12.11 | 12.11 | Work completed, revised estimate submitted | |||