| DIVISION :- WEST | |||||||||||||||
| Sl.No | Name of Schemes | Name of Contractor | Funding Agency | SANCTIONED AMOUNT | Date of Commencement | Stipulated Date of Completion | Physical Progress in % | Financial Progress | Remarks | ||||||
| Total | C.share | S. share | (Head) | Expenditure till date | |||||||||||
| Total | S.Share | C.Share | Work Remarks | Plan | |||||||||||
| A. | CENTRAL SPONSORED SCHEMES | ||||||||||||||
| 1 | Repalacement of Rathong Suspension bridge by steel bridge on Rimbi-Yoksum road. | Mrs. S. Dolma Bhutia | NLCPR | 327.57 | 327.57 | 0.00 | - | 2-Jun-05 | 31-Aug-06 | 97% | 262.01 | 0.00 | 262.01 | In Progress | Tenth Plan |
| 2 | Repalacement of Rimbi Suspension bridge by steel bridge on Pelling - Rimbi road. | Mr. Keshav Pradhan | NLCPR | - | 2-Jun-05 | 31-Aug-06 | 90% | In Progress | Tenth Plan | ||||||
| 3 | Carpetting and surface improvement of Soreng Budang Road via Malbassy Km 1st - 11th. | Mr. Shankhar Agarwal | NLCPR | 349.51 | 339.00 | 10.51 | Removal | 3-Mar-05 | 6-Jun-06 | 100% | 341.27 | 2.27 | 339.00 | Work completed final bill under preparation | Tenth Plan |
| 4 | Construction of premix carpetting /imp. Dentam Uttrey road Km 1st to 10th. | Mr. C.B. Subba | NLCPR | 399.00 | 399.00 | 0.00 | - | 3-Mar-05 | 31-Aug-06 | 81% | 205.84 | 0.00 | 243.92 | In progress | Tenth Plan |
| 5 | Surface imp/ carpetting i/c drainage works on Pelling Dentam road Km 1st to 9th. | Mr. Anjani Kr. Agarwal | NLCPR | 1,155.48 | 1,050.66 | 104.82 | - | 3-Mar-05 | 31-Aug-06 | 88% | 903.89 | 0.00 | 903.89 | In progress | Tenth Plan |
| 6 | Surface imp/ carpetting i/c drainage works on Pelling Dentam road Km 18th to 20th. | - | NLCPR | - | 3-Mar-05 | 31-Aug-06 | 96% | In progress | Tenth Plan | ||||||
| 7 | Surface imp/ carpetting i/c drainage works on Pelling Dentam road Km 10th to 17th. | Mr. Mahabir Pd. Agarwal | NLCPR | 1,406.79 | 1301.97 | 104.82 | - | 3-Mar-05 | 31-Aug-06 | 86% | 313.02 | 0.00 | 313.02 | In progress | Tenth Plan |
| 8 | Replacement of B.B. Lal Suspension Bridge on Pelling Dentam road along gyalshing Soreng Road. | Mr. Mahabir Pd. Agarwal | NLCPR | 200.30 | 200.30 | 0.00 | - | 3-Mar-05 | 31-Aug-06 | 50% | 75.07 | 0.00 | 75.07 | In progress | Tenth Plan |
| 9 | Slope stablization of Labling land slide on Yoksum - Tashiding road | Mrs Kabita Pradhan | NLCPR | 131.44 | 127.52 | 3.92 | Removal | 22-Apr-05 | 21-Apr-06 | 100% | 2.05 | 2.05 | 0.00 | Work Completed | Tenth Plan |
| 10 | Slope stablization of Chorang land slide on Yoksum - Tashiding road | Mr. U. P. Bhutia (Kazi) | NLCPR | 18.13 | 18.13 | Removal | 22-Apr-05 | 21-Apr-06 | 100% | 61.23 | 10.00 | 51.23 | Work Completed | Tenth Plan | |
| 11 | Construction of strengthening draianage & carpetting of Khanisherbong road fKm 1st -11th. | Mr. B. L. Gurung | NEC | 486.36 | 486.36 | 0.00 | - | 3-Mar-07 | 9-Sep-08 | 33% | 144.11 | 0.00 | 144.11 | In Progress | Eleventh Plan |
| 12 | Replacement of Ringyang suspension bridge over Ringyang Khola on Soreng-Sombaria road. | Mr. Sanjay Chandak | NEC | 332.02 | 332.02 | 0.00 | - | 8-Aug-05 | 10-Oct-06 | 100% | 328.94 | 0.00 | 328.94 | completed | Tenth Plan |
| 13 | Strengthening draianage & carpetting of Sombaria Hilley road Km 1st- 26th | Mr. Kamal Kr. Rai | NEC | 845.68 | 845.68 | 0.00 | - | 1-Nov-06 | 10-Oct-08 | 60% | 208.01 | 0.00 | 208.01 | In progress | Tenth Plan |
| 14 | Strengthening and carpetting, protection and drainage of Bermiock Legship road Km. 1st to 9th | Mr. Atul Dhanotia | NEC | 449.46 | 449.46 | 0.00 | - | 16-Feb-06 | 15-Feb-08 | 77% | 167.33 | 0.00 | 167.33 | In progress | Tenth Plan |
| 15 | Surface improvement and strengthening and premix carpetting of Rimbi Yoksum road Km 1st to 21.70. | Mr. K. N. Bhutia | EI | 315.48 | 219.37 | 96.11 | Removal | 7-Feb-04 | 6-Aug-05 | 87% | 248.86 | 50.82 | 198.04 | In Progress | Tenth Plan |
| 16 | Carpetting of Gyalshing Pelling Road, W.Sikkim (EI) | Mr. K. N. Bhutia | EI | 87.86 | 87.86 | 0.00 | - | 7-Feb-04 | 6-Aug-05 | 100% | 87.86 | 0.00 | 87.86 | Work Completed | Tenth Plan |
| 17 | Widening carpetting & drainage system on Legship - Tashiding road Km 1st-6th. | Mr. P. K. Agarwal | NABARD | 67.82 | 67.82 | 0.00 | - | 2-Jan-01 | 12-May-01 | 100% | 66.86 | 0.00 | 66.86 | Work Completed | Tenth Plan |
| 18 | Widening carpetting & drainage system on Legship - Tashiding road Km 7th - 12th. | Mr. S. D. Bhutia | NABARD | 57.52 | 57.52 | 0.00 | - | 2-Jan-01 | 12-May-01 | 100% | 56.41 | 0.00 | 56.41 | Work Completed | Tenth Plan |
| 19 | Widening carpetting & drainage system on Legship - Tashiding road Km 1st-6th.Revised | Mr. P. K. Agarwal | NABARD | 6.00 | 6.00 | 0.00 | - | 2-Jan-01 | 12-May-01 | 95% | 66.86 | 0.00 | 66.86 | Work will be resumed sonner | Tenth Plan |
| 20 | Widening carpetting & drainage system on Legship - Tashiding road Km 7th - 12th.Revised | Mr. S. D. Bhutia | NABARD | 9.25 | 9.25 | 0.00 | - | 2-Jan-01 | 12-May-01 | 98% | 56.41 | 0.00 | 56.41 | Work will be resumed sonner | Tenth Plan |
| 21 | Surface imrovement & P/W from Lunchuk to Salangdang road Km 1st-4th. | Mr. P.K. Chandak | NABARD | 128.03 | 84.32 | 43.71 | Expansion | 6-Jun-05 | 6-Jun-06 | 100% | 127.21 | 43.71 | 83.50 | completed | Tenth Plan |
| 22 | Link Road from Alpine CF to Kaluk Dentam Road | - | NABARD | 96.77 | 96.77 | 0.00 | - | - | - | - | 0.00 | 0.00 | 0.00 | completed | Tenth Plan |
| 23 | Construction of 65m Span Steel Bridge over Rangit river in between Mengnem & Phamtam | Mr. U. P. Bhutia (Kazi) | RSVY | 272.78 | 148.93 | 123.85 | - | 23-Nov-05 | 22-May-07 | 60% | 136.56 | 0.00 | 136.56 | In Progress | Tenth Plan |
| 24 | Construction of link road from Kaluk to Lower Shribadam via Samdong Km 1st to 5th. | Mr. K. T. Bhutia | RSVY | 167.87 | 150.00 | 17.87 | - | 12-Dec-05 | 6-Jun-07 | 100% | 150.00 | 0.00 | 150.00 | Final Bill | Tenth Plan |
| 25 | Construction of link road from Kaluk to Lower Sribadam via Samdong km 1st to 5th. | RSVY | 1.88 | 150.00 | 0.00 | 150.00 | 0.00 | 150.00 | Tenth Plan | ||||||
| 26 | Construction of Link Road from Kaluk to Sribadam via Samdong road [State Share of RSVY] | K.T.Bhutia | RSVY | 17.87 | 0.00 | 17.87 | Link Road Plan | 5-Dec-05 | 2-Jun-06 | 100% | 9.24 | 9.24 | 0.00 | Tenth Plan | |
| 27 | Widening carpetting & drainage system on Legship - Tashiding road Km 7th - 12th.(Revised) | Mr. S. D. Bhutia | MP LAPS | 9.25 | 9.25 | 0.00 | - | 2-Jan-01 | 12-May-01 | 96% | 55.41 | 0.00 | 55.41 | In Progress | Ninth Plan |
| 28 | Widening carpetting & drainage system on Legship - Tashiding road Km 1st-6th. (Revised) | Mr. P. K. Agarwal | MP LAPS | 6.00 | 6.00 | 0.00 | - | 2-Jan-01 | 12-May-01 | 95% | 68.86 | 0.00 | 68.86 | In Progress | Ninth Plan |
| 29 | Turning improvement in front of SNT Booking Office & replacement of drainage syatem at outskirt of Gyalshing Bazar. | Mrs. Amrita Gurung | MP LAPS | 9.51 | 0.00 | 9.51 | - | 5-Dec-06 | 4-Mar-07 | 100% | 4.47 | 0.00 | 4.47 | Work Completed, final bill submitted | Tenth Plan |
| 30 | App. Road to Rincheypong Gompa / Shreda from Rinchepong Dak Bunglow Road (Km 1st ch 17th ) | Mr. Atul Dhanotia | MP LAPS | 15.00 | 15.00 | 0.00 | - | 16-Feb-06 | 15-Feb-08 | 67% | 9.90 | 0.00 | 9.90 | In progress | Tenth Plan |
| B. | STATE PLAN | ||||||||||||||
| 31 | Surface improvement and strengthening and premix carpetting of Rimbi Yoksum road Km 1st to 21.70. | Mr. K. N. Bhutia | EI | 315.48 | 219.37 | 96.11 | Removal | 7-Feb-04 | 6-Aug-05 | 87% | 248.86 | 50.82 | 198.04 | In Progress | Tenth Plan |
| 32 | Carpetting and surface improvement of Soreng Budang Road via Malbassy Km 1st - 11th. | Mr. Shankhar Agarwal | NLCPR | 349.51 | 339.00 | 10.51 | Removal | 3-Mar-05 | 6-Jun-06 | 100% | 341.27 | 2.27 | 339.00 | Revised Estimate in Process | Tenth Plan |
| 33 | Providing Box drain including Check wall below approach road to Pelling Helipad. | Suresh Subba | State Plan | 11.25 | 0.00 | 11.25 | Removal | 100% | 9.61 | 9.61 | 0.00 | Tenth Plan | |||
| 34 | Slope stablization of Labling land slide on Yoksum - Tashiding road | Mrs Kabita Pradhan | NLCPR | 131.44 | 127.52 | 3.92 | Removal | 22-Apr-05 | 21-Apr-06 | 200% | - | 2.05 | 123.33 | Work Completed | Tenth Plan |
| 35 | Slope stablization of Chorang land slide on Yoksum - Tashiding road | Mr. U. P. Bhutia (Kazi) | NLCPR | 18.13 | 18.13 | Removal | 22-Apr-05 | 21-Apr-06 | 100% | - | 10.00 | Work Completed | Tenth Plan | ||
| 36 | Widening carpetting & drainage system on Legship - Tashiding road Km 1st - 12th. | Mr. P.K.Agarwal & Mr. S. D. Bhutia | State Plan | 140.19 | 0.00 | 140.19 | Removal | 2-Jan-01 | 12-May-01 | 100% | 138.26 | 138.26 | 0.00 | Work Completed | Ninth Plan |
| 37 | Carpetting of Legship Gyalshing Road km 1st-3rd | N.B.Dahal | State Plan | 24.94 | 0.00 | 24.94 | Removal | 25-Jun-93 | 20-Mar-96 | 100% | 21.75 | 21.75 | 0.00 | Ninth Plan | |
| 38 | Consruction of 13m Span RCC Bridges at Ribing, Khola on Chakhung - Khansirbong road. | Mr. N.T. Tamang | State Plan | 19.28 | 0.00 | 19.28 | Removal | 10-Oct-98 | 5-May-99 | 100% | 8.50 | 8.50 | 0.00 | Work Completed, final bill to be paid | Ninth Plan |
| 39 | Widening, surface improvement, premix carpetting of Sombaria Puretar Km 6th. | Mr. Amrit Subba | - | 9.57 | 0.00 | 9.57 | Removal | 1-Jan-05 | 10-Oct-06 | 100% | 7.85 | 7.85 | 0.00 | Work Completed, final bill to be paid | Tenth Plan |
| 40 | Widening, surface improvement, premix carpetting of Sombaria Puretar Km 7th | Mr. Prakash Subba | - | 21.57 | 0.00 | 21.57 | Removal | 1-Jan-05 | 10-Oct-06 | 100% | 11.72 | 11.72 | 0.00 | Work Completed, final bill to be paid | Tenth Plan |
| 41 | Widening, surface improvement, premix carpetting of Sombaria Puretar Km 8th | " | - | 21.40 | 0.00 | 21.40 | Removal | 1-Jan-05 | 10-Oct-06 | 100% | 10.83 | 10.83 | 0.00 | Work Completed, final bill to be paid | Tenth Plan |
| 42 | Widening, surface improvement, premix carpetting of Sombaria Puretar Km 9th | " | - | 21.73 | 0.00 | 21.73 | Removal | 7-Jul-03 | 6-Jun-04 | 100% | 10.08 | 10.08 | 0.00 | Work Completed, final bill to be paid | Tenth Plan |
| 43 | Widening, surface improvement, premix carpetting of Sombaria Puretar Km 10th | Mrs Sangay Hisi Sherpa | - | 20.35 | 0.00 | 20.35 | Removal | 1-Jan-05 | 10-Oct-06 | 100% | 11.54 | 11.54 | 0.00 | Work Completed, final bill to be paid | Tenth Plan |
| 44 | Widening, surface improvement, premix carpetting of Sombaria Puretar Km 11th | Mr. Passang Dorjee Sherpa | - | 21.81 | 0.000 | 21.81 | Removal | 1-Jan-05 | 10-Oct-06 | 100% | 10.92 | 10.92 | 0.00 | Work Completed, final bill to be paid | Tenth Plan |
| 45 | Widening, surface improvement, premix carpetting of Sombaria Puretar Km 12th | Mrs Sangay Hisi Sherpa | - | 20.95 | 0.00 | 20.95 | Removal | 1-Jan-05 | 10-Oct-06 | 100% | 10.37 | 10.37 | 0.00 | Work Completed, final bill to be paid | Tenth Plan |
| 46 | Widening, surface improvement, premix carpetting of Sombaria Puretar Km 13th | " | - | 11.98 | 0.00 | 11.98 | Removal | 1-Jan-05 | 10-Oct-06 | 100% | 4.68 | 4.68 | 0.00 | Work Completed, final bill to be paid | Tenth Plan |
| 47 | Construction of 25m span suspension bridge at Reshi Khola on Shribadam Deyathang road. | Mr. B.R. Sharma | State Plan | 45.03 | 0.00 | 45.03 | Replacement | 3-Mar-05 | 3-Mar-07 | 80% | - | 27.16 | - | In Progress | Tenth Plan |
| 48 | Renovation of 320"0" span suspension bridge over Ramam river at Jorethang | Mr. Jagdish Agarwal. | - | 15.93 | 0.00 | 15.93 | Replacement | 5-May-06 | 6-Jun-06 | 100% | 14.84 | 14.84 | 0.00 | Revised Estimate in Process | Tenth Plan |
| 49 | Construction of 65m Span Steel Bridge over Rangit river in between Mengnem & Phamtam | Mr. U. P. Bhutia (Kazi) | RSVY | 272.19 | 148.93 | 123.26 | Replacement | 23-Nov-05 | 22-May-07 | 60% | 148.91 | 0.00 | 148.91 | In Progress | Tenth Plan |
| 50 | Renovation of Singsore Bridge along Dentam - Utterey Road | 73.41 | 0.00 | 73.41 | Replacement | 2007 | - | - | 0.00 | 0.00 | 0.00 | Eleventh Plan | |||
| 51 | Approach road to suspension bridge over Ramam river at Jorethang | Mrs. Sapana Sunuwar | - | 1.88 | 0.00 | 1.88 | Replacement | 12-Dec-05 | 2-Feb-06 | 100% | 1.88 | 1.88 | 0.00 | completed | Tenth Plan |
| 52 | Construction of 25m span suspension bridge at Reshi Khola on Shribadam Deyathang road. | Mr. B.R. Sharma | State Plan | 45.03 | 0.00 | 45.03 | Replacement | 3-Mar-05 | 3-Mar-07 | 46% | - | 27.16 | - | In Progress | Tenth Plan |
| 53 | Renovation of 320"0" span suspension bridge over Ramam river at Jorethang | Mr. Jagdish Agarwal. | - | 15.93 | 0.00 | 15.93 | Replacement | 5-May-06 | 6-Jun-06 | 100% | 15.43 | 15.43 | 0.00 | completed | Tenth Plan |
| 54 | Approach road to suspension bridge over Ramam river at Jorethang | Mrs. Sapana Sunuwar | - | 1.88 | 0.00 | 1.88 | Replacement | 12-Dec-05 | 2-Feb-06 | 100% | 1.88 | 1.88 | 0.00 | completed | Tenth Plan |
| 55 | Surface imrovement & P/W from Lunchuk to Salangdang road Km 1st-4th. | Mr. P.K. Chandak | NABARD | 128.03 | 84.32 | 43.71 | Expansion | 6-Jun-05 | 6-Jun-06 | 100% | 127.21 | 43.71 | 83.50 | completed | Tenth Plan |
| 56 | 20mm thick premix crpetting along link road to Manglabaria Km 1st to 3rd. | Mrs. Karma Uden Bhutia | State Plan | 27.72 | 0.00 | 27.72 | Expansion | 23-Dec-02 | 22-Apr-03 | 93% | 25.74 | 25.74 | 0.00 | In progress | Tenth Plan |
| 57 | Construction of Motorable Road from Reshi-Khaniserbong, Km 7th- 8th. | State Plan | 20.61 | 0.00 | 20.61 | Expansion | - | - | 70% | 8.09 | 8.09 | 0.00 | Tenth Plan | ||
| 58 | Surface Improvement, Protective works & drainage of Lungchuk Salangdang road.[State Share of NABARD] | P.K.Chandak | State Plan | 43.71 | 0.00 | 43.71 | Expansion | 25-Jun-05 | 26-Jun-06 | 100% | 41.86 | 41.86 | 0.00 | Tenth Plan | |
| 59 | Premix carpetting & Improvement of Pelling - Rimbi road Km 1st-12th .[Additional Sanction] | K.N.Bhutia, P.T.Bhutia, S.W.Bhutia | State Plan | 16.12 | 0.00 | 16.12 | Expansion | - | - | 100% | 12.36 | 12.36 | 0.00 | Tenth Plan | |
| 60 | Premix carpetting works on Gyalshing Pelling road Km 1st & 9th. [State Share of EI] | Phurden Lama & Palchen Yongda | State Plan | 146.37 | 0.00 | 146.37 | Expansion | 15-Oct-03 | 14-Jul-04 | 100% | 134.19 | 134.19 | 0.00 | Tenth Plan | |
| 61 | Construction & Protective wall on Kalej Khola Power House to Uttarey Road. | State Plan | 3.99 | 0.00 | 3.99 | Expansion | - | - | 0.00 | 0.00 | 0.00 | Tenth Plan | |||
| 62 | Surface Improvement , widening carpetting & Bridge Replacement on Pelling Dentam road & BB Lal suspension bridge.[State Share of NLCPR] | M.P.Agarwal, A.K.Agarwal | State Plan | 104.81 | 0.00 | 104.81 | Expansion | 3-Mar-05 | 31-Aug-06 | 73% | 0.00 | 0.00 | 0.00 | Tenth Plan | |
| 63 | Extension of Ribdi Bharang road Km 3rd to 4th.[9th plan] | N.T.Sherpa | State Plan | 18.96 | 0.00 | 18.96 | Expansion | Feb'99 | May'2002 | 100% | 17.97 | 17.97 | 0.00 | Ninth Plan | |
| 64 | Premix carpetting, drainage & Protective Works on Sombaria-Soreng road Km 1st-8th. | C.B.Subba | State Plan | 181.90 | 0.00 | 181.90 | Expansion | 25-Feb-04 | 24-Mar-05 | 100% | 168.90 | 168.90 | 0.00 | Tenth Plan | |
| 65 | Land/Damaged Compensation of Link Road to Gitang - Karmatar | Compensation | State Plan | 2.65 | 0.00 | 2.65 | Expansion | - | - | 100% | 2.65 | 2.65 | 0.00 | ||
| 66 | Construction of Link Road from Thongling to Lower Dodak Km 1st | State Plan | 35.37 | 0.00 | 35.37 | Expansion | - | - | 100% | 29.87 | 29.87 | 0.00 | |||
| 67 | Construction of Link Road from Anden Gumpa to Upper Rumbuk Km 1st | P.T.Sherpa | State Plan | 7.68 | 0.00 | 7.68 | Expansion | Mar-95 | Mar-96 | 100% | 5.62 | 5.62 | 0.00 | Ninth Plan | |
| 68 | Premix carpetting & improvement of Pelling Rimbi Road Km 1st-12th (Additional Sanction) | Mr. K.N.Bhutia, Mr. P.T.Bhutia, Mr. S.W.Bhutia | State Plan | 1,155.42 | 1,050.60 | 104.82 | Expansion | - | - | 100% | 839.72 | 12.38 | 827.34 | Work Completed | |
| 69 | Construction of Link Road from Angden Gumpa to Upper Rumbuk School Km 1st. | Mr. P. T. Sherpa | State Plan | 7.68 | 0.00 | 7.68 | Expansion | 3-Mar-95 | 3-Mar-96 | 100% | 5.62 | 5.62 | 0.00 | Revised Estimate in Process | Ninth Plan |
| 70 | Carpetting of Ribdi Bharang Road km 1st | Mr.N. T. Sherpa | State Plan | 8.17 | 0.00 | 8.17 | Expansion | 2-Feb-99 | 5-May-02 | 100% | 8.17 | 8.17 | 0.00 | completed | Ninth Plan |
| 71 | Carpetting and P/W on Sombaria Soreng Road Km 1st - 8th. | Mr. C. B. Subba | - | 181.90 | 0.00 | 181.90 | Expansion | 2-Feb-04 | 3-Mar-05 | 100% | 168.90 | 168.90 | 0.00 | completed | Tenth Plan |
| 72 | Construction of link road from Kongri -Labdong road Km 1st - 5th. | Mr. B.P. Pradhan, Mr. O.P. Pradhan | State Plan | 26.38 | 0.00 | 26.38 | Link Road Plan | 12-Jun-96 | 11-Apr-97 | 100% | 15.69 | 12.69 | 0.00 | Work Completed | Ninth Plan |
| 73 | Construction of Link Road from Kaluk to Sribadam via Samdong road [State Share of RSVY] | K.T.Bhutia | RSVY | 17.87 | 0.00 | 17.87 | Link Road Plan | 5-Dec-05 | 2-Jun-06 | 100% | 9.24 | 9.24 | 0.00 | Tenth Plan | |
| 74 | Construction of Link Road from Chota Samdong to Majuwa km 3rd. | Land Compensation | State Plan | 17.57 | 0.00 | 17.57 | Link Road Plan | Sept.2007 | - | 100% | 17.57 | 17.57 | 0.00 | Eleventh Plan | |
| 75 | Construction of New road from Rinchenpong Yangsum to Ambetar Km 1st - 4th. | Land Compensation | State Plan | 47.14 | 0.00 | 47.14 | New Road | Oct-07 | - | - | 25.00 | 25.00 | 0.00 | Ninth Plan | |
| 76 | Construction of motorable road from Pokhari to Karjee Km 1st | Mr. L.D. Bhutia | State Plan | 36.28 | 0.00 | 36.28 | New Road | 27-Feb-03 | 26-Dec-03 | 98% | 22.97 | 22.97 | 0.00 | In Progress | Tenth Plan |
| 77 | Construction of motorable road from Pokhari to Karjee Km 2nd | Mr. G.S. Subbba | State Plan | 40.86 | 0.00 | 40.86 | New Road | 27-Feb-03 | 26-Dec-03 | 100% | 32.28 | 32.28 | 0.00 | Work Completed | Tenth Plan |
| 78 | Construction of motorable road from Pokhari to Karjee Km 3rd | Mr. G.S. Subbba | State Plan | 33.08 | 0.00 | 33.08 | New Road | 27-Feb-03 | 26-Dec-03 | 100% | 30.59 | 30.59 | 0.00 | Work Completed | Tenth Plan |
| 79 | Construction of motorable road from Pokhari to Karjee Km 4th | Mr. B.P. Pradhan | State Plan | 28.08 | 0.00 | 28.080 | New Road | 27-Feb-03 | 26-Dec-03 | 98% | 20.84 | 20.84 | 0.00 | In Progress | Tenth Plan |
| 80 | Construction of motorable road from U/Labdong to L/Labdong Km 1st. | Mr. D.K. Pradhan | State Plan | 29.68 | 0.00 | 29.680 | New Road | 27-Feb-03 | 26-Dec-03 | 100% | 20.14 | 20.14 | 0.00 | Work Completed | Tenth Plan |
| 81 | Construction of motorable road from U/Labdong to L/Labdong Km 2nd. | Mr. G.S. Subbba | State Plan | 31.44 | 0.00 | 31.440 | New Road | 27-Feb-03 | 26-Dec-03 | 100% | 20.35 | 20.35 | 0.00 | Work Completed | Tenth Plan |
| 82 | Construction of motorable road from U/Labdong to L/Labdong Km 3rd. | Mr. G.S. Subbba | State Plan | 30.95 | 0.00 | 30.950 | New Road | 27-Feb-03 | 26-Dec-03 | 98% | 27.33 | 27.33 | 0.00 | In Progress | Tenth Plan |
| 83 | Construction of motorable road from U/Labdong to L/Labdong Km 4th. | Mrs. Sabita Subba | State Plan | 20.61 | 0.00 | 20.610 | New Road | 27-Feb-03 | 26-Dec-03 | 98% | 17.21 | 17.21 | 0.00 | In Progress | Tenth Plan |
| 84 | Construction of motorable road from Relli Khola to Phamtam Km 1st - 5th. | Mr. T.B. Chettri | State Plan | 169.31 | 0.00 | 169.31 | New Road | 3-Mar-03 | 2-Jan-04 | 99% | 98.78 | 98.78 | 0.00 | In Progress | Tenth Plan |
| 85 | Construction of motorable road from Relli Khola to Phamtam Km 6th - 9th. | Mr. G. S. Subba | State Plan | 135.46 | 0.00 | 135.46 | New Road | 3-Mar-03 | 2-Jan-04 | 99% | 112.18 | 112.18 | 0.00 | In Progress | Tenth Plan |
| 86 | Construction of motorable road from Relli Khola to Phamtam Km 10th - 13th. | Mr. D.T. Bhutia | State Plan | 135.22 | 0.00 | 135.22 | New Road | 4-Mar-03 | 1-Mar-04 | 85% | 111.42 | 110.40 | 0.00 | In Progress | Tenth Plan |
| 87 | Construction of motorable road from Relli Khola to Phamtam Km 14th - 17th. | Mr. K.N.Bhutia | State Plan | 136.62 | 0.00 | 136.62 | New Road | 4-Mar-03 | 1-Mar-04 | 81% | 67.70 | 67.70 | 0.00 | In Progress | Tenth Plan |
| 88 | Construction of motorable road from Relli Khola to Phamtam Km 18th - 21st. | Mr. A.P. Pradhan | State Plan | 142.99 | 0.00 | 142.99 | New Road | 4-Mar-03 | 1-Mar-04 | 98% | 81.85 | 81.85 | 0.00 | In Progress | Tenth Plan |
| 89 | Construction of road for recreation center on Chakung Chumbung road Km 2nd (Tanki Dara). | Mr. R.B. Rai | State Plan | 11.57 | 0.00 | 11.57 | New Road | 4-Apr-05 | 10-Oct-06 | 100% | 10.77 | 10.77 | 0.00 | Work stopped due to nonavailibity of Bitumin | Tenth Plan |
| 90 | Construction of road from Upper Rumbuk to Tereybair in West Sikkim Km 3rd. | Mr. Phurdiki Sherpa | - | 24.73 | 0.00 | 24.73 | New Road | 1-Jan-05 | 4-Apr-06 | 85% | 20.13 | 20.13 | 0.00 | in progress | Tenth Plan |
| 91 | Construction of road from Upper Rumbuk to Tereybair in West Sikkim Km 4th. | Mr. Lakpa Sherpa | - | 22.36 | 0.00 | 22.36 | New Road | 1-Jan-05 | 4-Apr-06 | 70% | 19.56 | 19.56 | 0.00 | in progress | Tenth Plan |
| 92 | Construction of road from Upper Rumbuk to Tereybair in West Sikkim Km 5th. | " | State Plan | 24.45 | 0.00 | 24.45 | New Road | 1-Jan-05 | 4-Apr-06 | 70% | 7.92 | 7.92 | 0.00 | in progress | Tenth Plan |
| 93 | Construction of road from Upper Rumbuk to Tereybair in West Sikkim Km 6th. | " | State Plan | 22.75 | 0.00 | 22.75 | New Road | 1-Jan-05 | 4-Apr-06 | 40% | 7.63 | 7.63 | 0.00 | in progress | Tenth Plan |
| 94 | Construction of road from Upper Rumbuk to Tereybair in West Sikkim Km 7th. | Mr. Samdey Sherpa | State Plan | 21.55 | 0.00 | 21.55 | New Road | 1-Jan-05 | 4-Apr-06 | 100% | 17.83 | 17.83 | 0.00 | completed | Tenth Plan |
| 95 | Additional Sanction for LC on construction of Link Road from Upper Rumbuk to Tareybhir . | Land Compensation | State Plan | 24.80 | 0.00 | 24.80 | New Road | May-06 | - | 100% | 24.77 | 24.77 | 0.00 | 100% paid | Tenth Plan |
| 96 | Construction of link road from Saili Golai to Lower Rumbuk. Km 1st. | Mr. B.B. Subba | State Plan | 50.93 | 31.27 | 19.66 | New Road | 2-Feb-04 | 1-Jan-05 | 100% | 31.27 | 31.27 | 0.00 | completed | Tenth Plan |
| 97 | Construction of link road from Saili Golai to Lower Rumbuk. Km 2nd. | " | State Plan | New Road | 2-Feb-04 | 1-Jan-05 | 100% | completed | Tenth Plan | ||||||
| 98 | Construction of motorable road from Khanisirbong to kamling. 13th | Mr. N.T. Tamang | State Plan | 10.38 | 0.00 | 10.38 | Removal | 1-Jan-05 | 11-Nov-06 | 35% | 3.72 | 3.72 | 0.00 | work withheld due to Land Dispute | Tenth Plan |
| 99 | Construction of motorable road from Khanisirbong to kamling. 14th | Mr. R.K.Rai | State Plan | 17.94 | 0.00 | 17.94 | Removal | 1-Jan-05 | 11-Nov-06 | - | 0.00 | 0.00 | 0.00 | work withheld due to Land Dispute | Tenth Plan |
| 100 | Construction of motorable road from Khanisirbong to kamling. 15th | Mr. B.L. Gurung | State Plan | 18.70 | 0.00 | 18.70 | Removal | 1-Jan-05 | 11-Nov-06 | - | 0.00 | 0.00 | 0.00 | work withheld due to Land Dispute | Tenth Plan |
| 101 | Construction of motorable road from Khanisirbong to kamling. 16th | Mr. R.K.Rai | State Plan | 20.87 | 0.00 | 20.87 | Removal | 1-Jan-05 | 11-Nov-06 | - | 0.00 | 0.00 | 0.00 | work withheld due to Land Dispute | Tenth Plan |
| 102 | Construction of motorable road from Khanisirbong to kamling. 17th | " | State Plan | 17.35 | 0.00 | 17.35 | Removal | 1-Jan-05 | 11-Nov-06 | - | 0.00 | 0.00 | 0.00 | work withheld due to Land Dispute | Tenth Plan |
| 103 | Construction of motorable road from Khanisirbong to kamling. 20th | Mr. B. Kr. Agarwal | State Plan | 25.50 | 0.00 | 25.50 | Removal | 8-Aug-04 | 11-Nov-06 | 100% | 10.80 | 10.80 | 0.00 | work in progress | Tenth Plan |
| 104 | Construction of motorable road from Khanisirbong to kamling. 21st. | " | State Plan | 24.77 | 0.00 | 24.77 | Removal | 1-Jan-05 | 8-Aug-06 | 100% | 0.00 | 0.00 | 0.00 | Final Bill | Tenth Plan |
| 105 | Widening improvement carpetting of approach road to Zilla Sainik Board at Tikjuk in West Sikkim. | Mr. Lakpa Sherpa | State Plan | 4.99 | 0.00 | 4.99 | Deposit Work | 17-May-05 | 16-Aug-05 | 100% | 4.99 | 4.99 | 0.00 | Work Completed | Tenth Plan |