DIVISION  :  EAST                                  
Sl.No Name of Schemes Name of Contractor Funding Agency SANCTIONED  AMOUNT Date of Commencement  Date of Completion Physical Progress               in % Financial Progress Remarks      
Total C.share S. share (Head) Expenditure till date      
Total S.Share C.Share Work Remrks Plan NOT    
A. CENTRAL  SPONSORED  SCHEMES                                  
1 Const. of Goshkhan Dara Bridge over River Teesta at Singtam, East Sikkim M.P Agarwal NLCPR 1,337.11 1,337.11 0.00  - 10-Jan-07 11-Jun-08 35% 420.00 0.00 420.00 work in progress Eleventh Plan Spill Over Acct s  
2 Const. of diversion road Ranipool-Pakyong road km 1st-3rd. B.K. Agarwal NLCPR  339.85 236.87 102.98 Expansion 21-Feb-05 21-Nov-05 50% 225.98 64.60 161.38 work in progress Tenth Plan Both P  
3 Upgradation of Gangtok Burtuk Ranka Road ( 8km ) in East Sikkim. - NLCPR  420.00 420.00 0.00 - 18-May-04 - - 387.11 0.00 387.11 - Tenth Plan Not in Both    
4 Strengthening,drainage and Carpeting and construction of 30m span steel bridge along Assam-Pakyong road km 7th - 15th. S.K. Agarwal NEC 750.76 750.76 0.00  - 6-Nov-06 5-May-08 60% 309.05 0.00 309.05 work under process Tenth Plan Spill Over Acct    
5 Construction of major retaining structures on approach road to Raj Bhawan,VIP Complex and TNA Public School Complex   NEC 106.87 106.87 0.00  - 30-May-05 29-May-06 100% 74.24 0.00 74.24 completed Tenth Plan Spill Over Acct    
6 Replacement of Sumin Wooden Suspension Bridge on Sang Khola Sumin Road   NEC 285.40 285.40 0.00  - 8-Apr-04 - - 231.34 0.00 231.34 - Tenth Plan Not in Both    
7 Strengthening/drainage and P/Wprks for the road from Lal Turning to Bashilakha Road Km 1st to 3rd G.M Gurung NABARD 184.65 151.46 33.19 Expansion 30/09/07 31/03/08 95% 143.83 0.00 143.83 work under progress Eleventh Plan Both    
8 Const. of link road from King Stone to Simana Khola Km 1st to 2nd. Departmental NABARD 43.01 34.41 8.60 Expansion - - 100% 31.68 0.00 31.68 completed   MPR    
9 Construction of Link Road from Sakyong to Beyong km 1st to 2nd (State Share of NABARD) - NABARD 19.47 0.00 19.47 Link Road 2008 - 20% 0.00 0.00 0.00 work under progress Eleventh Plan MPR    
10 Premix Carpetting & protective work along approach road to Crematorium at Jalipool.   NABARD 20.66 0.00 20.66  - 2005 - - 20.66 0.00 20.66 - Tenth Plan MPR    
11 Construction of link road from Lower Lingdum to Adampool (km 3rd to 4th)   NABARD 73.43 73.43 0.00  - 2005 - - 73.43 0.00 73.43 - Tenth Plan MPR    
12 Const. of 12 m span R.C.C. Bridge on Sangkhola Zingla Martam Road at Km 11th ch-3rd. Anita Gurung CRF 38.63 38.63 0.00  - 1-Apr-07 31-Mar-08 35% 0.00 0.00 0.00 work under progress Eleventh Plan Spill Over Acct s  
13 Const. of 12 m span R.C.c. Bridge on Sangkhola Zingla Martam Road at Km 12th ch-4th.. T.B. Pradhan CRF 45.12 45.12 0.00  - 1-Apr-07 31-Mar-08 60% 22.00 0.00 22.00 work under progress Eleventh Plan Spill Over Acct s  
14 Surface improvement and widening of Sang Sirwani Road Km 1st & App Road from Mech Sub Div Office at Dochum Kishor Pradhan CRF 50.20 50.20 0.00  - 10-Oct-07 9-Sep-08 85% 25.71 0.00 25.71 work under progress Eleventh Plan Spill Over Acct s  
15 Surface improvement and widening of Sang Sirwani Road Km 2nd & App Road to Mech Workshop Dochum K.R. Sharma CRF 38.49 38.49 0.00  - 10-Oct-07 9-Sep-08 50% 12.61 0.00 12.61 work under progress Eleventh Plan Spill Over Acct s  
16 Upgradation of Link Road from NH-31A to Dokey Chisopani Km 1st    CRF 69.63 69.63 0.00  - 29-Feb-08 28-Feb-09 15% 0.00 0.00 0.00 Work to Commence Eleventh Plan Spill Over Acct    
17 Upgradation of Link Road from NH-31A to Dokey Chisopani Km 2nd    CRF 35.20 35.20 0.00  - 29-Feb-08 28-Feb-09 5% 0.00 0.00 0.00 work under progress Eleventh Plan Spill Over Acct    
18 Upgradation of Link Road from NH-31A to Dokey Chisopani Km 3rd   CRF 43.90 43.90 0.00  - 29-Feb-08 28-Feb-09 5% 0.00 0.00 0.00 work under progress Eleventh Plan Spill Over Acct    
19 Const. of link road from Arubotey to Subaneydara km 1st-3rd. Om Bhd. Gurung BADP 29.97 29.97 0.00  - 30-Nov-00 16-Mar-01 68% 22.98 0.00 22.98 work abondoned Ninth Plan Spill Over Acct    
20 Const. of link road from sisney to North Regu km 1st -4th. T.S. Lama BADP 30.31 30.31 0.00  - 21-Nov-00 5-Mar-01 95% 24.54 0.00 24.54 work abondoned Ninth Plan Spill Over Acct    
21 Premix carpetting and widening work on Sang dipudara road Km 1st to 14th. Daluram Sarda EI 277.44 6.95 277.44 Removal 18/11/2002 17/08/2004 90% 233.08 233.08 0.00 Sanctioned from EI Rs 6.95 Crore Tenth Plan Both s  
22 Upgradationand premix carpeting along Duga Pachaykhani road KM 1st-14th. B.K.Agarwal EI 841.38 433.77 407.61 Removal 21-Feb-05 5-Mar-08 90% 393.32 24.00 369.32 work in progress Tenth Plan Both s  
23 Construction of Road from Rathong (NH-31A) to Kimchithang Km 1st to 15th (EI) - EI 701.89 701.89 0.00 - 2007 - - 0.00 0.00 0.00 New Project Tenth Plan Not in Both    
24 Improvement of  Sang Dipudara Road (EI) - EI 347.74 347.74 0.00 - 2007 - - 0.00 0.00 0.00 New Project Tenth Plan Not in Both    
25 Improvement of  Pakyong - Karthok - Naya busty - Raigoan  Road (EI) - EI 398.42 398.42 0.00 - 2007 - - 0.00 0.00 0.00 New Project Tenth Plan Not in Both    
26 Widening, upgradation of pavement & drainage system along  Rangpo Duga Pendam road km 1st - 15th  M/s Apex Project & Investment                 P. Ltd. ISC 950.00 950.00 0.00  - 15-Jun-08 16-Dec-08 55% 480.00 0.00 480.00 work in progress Eleventh Plan Spill Over Acct s  
27 Improvement of Rhenock - Simanakhola Road Km 1st to 3rd. (ISC) - ISC 250.00 250.00 0.00  - 26-Mar-08 - 10% 236.99 0.00 236.99 work in progress Eleventh Plan Spill Over Acct    
28 Carpetting of Sirwani Bermoik Phongla Road, S.Sikkim (ISC) - ISC 999.08 999.08 0.00  - 26-Jul-05 - 10% 766.00 0.00 766.00 work in progress Tenth Plan Not in Both    
29 Extension of Link Road to Dokey Chisopani Pry School    ( State Share of RSVY Scheme) Nabin Rai RSVY 3.72 2.00 1.72 New Road 17-Oct-05 27-Mar-06 85% 0.00 0.00 0.00 work in progress Tenth Plan MPR    
  STATE PLAN                                  
30 Carpeting and surface strengthening, improvement, including drainage works of roads in and around Gangtok.   State Plan 361.89 0.00 361.89 Removal    6-Jun-04 5-Sep-05 100% 229.45 229.45 0.00 work completed final bill under process Tenth Plan Both g  
31 Premix carpetting and widening work on Sang dipudara road Km 1st to 14th. Daluram Sarda EI 284.39 6.95 277.44 Removal 18/11/2002 17/08/2004 80% 233.08 233.08 0.00 Sanctioned from EI Rs 6.95 Crore Tenth Plan Both s  
32 Upgradationand premix carpeting along Duga Pachaykhani road KM 1st-14th. B.K.Agarwal EI 841.38 433.77 407.61 Removal 21-Feb-05 5-Mar-08 90% 393.32 24.00 369.32 work in progress Tenth Plan Both s  
33 Surface strengthening upgradation and carpeting of Pakyong-Karthok Naya Busty road km 5th -7th.   State Plan 183.89 0.00 183.89 Removal 21/06/05 31-Aug-08 45% 56.58 56.58 0.00 work in progress, Date Extended Tenth Plan Both P  
34 P/L edging ,soling, metalling, premix carpeting and cross drain of link road from sichey to Indira Bye Pass via Shivalaya Mandir     State Plan 8.16 0.00 8.16 Removal 1/0/2002 2-Jul-05 80% 5.81 5.81 0.00 work in abeyance due to non availibility of bitumen Tenth Plan Both g  
35 Surface stregenthening , upgradation and carpeting of Roads during the visit of His Holiness the Dalai Lama  Departmental State Plan 40.35 0.00 40.35 Removal 2005 - 100% 38.79 38.79 0.00 completed Tenth Plan MPR    
36 Providing 75mm thick CC pitching over approach raod to Gairi Goan from NH 31A Near Hotel Tashi Targey) Ssno 2/E/Remv/06-07 Departmental State Plan 3.40 0.00 3.40 Removal 2006 - 0% 0.00 0.00 0.00   Tenth Plan MPR    
37 Const of PW along TNSS to Dhupidara Ssno 6/E/Remov/0607   State Plan 3.44 0.00 3.44 Removal 2006 - 100% 3.42 3.42 0.00 completed Tenth Plan MPR    
38 Permanent restoration work of Chief Justic Banglow Road Ssno7/E/Remo/06-07 Departmental State Plan 11.21 0.00 11.21 Removal 2006 - 100% 10.31 10.31 0.00 completed Tenth Plan MPR    
39 Immediate protective work to donak khola along tarethang Bering Road km      ch.22nd 23 ch Departmental State Plan 19.72 0.00 19.72 Removal 2006 - 100% 17.65 17.65 0.00 completed Tenth Plan MPR    
40 Restoration work at km 8th Ch.4-5 (Namphey khola)along Assam-Pakyong road Departmental State Plan 19.93 0.00 19.93 Removal 2006 - 100% 19.93 19.93 0.00 completed Tenth Plan MPR    
41 Immediate traffic clerance of rest work on lingtam-Agamlok rod km 1st &2nd. Departmental State Plan 4.48 0.00 4.48 Removal 2006 - 100% 4.48 4.48 0.00 completed Tenth Plan MPR    
42 surface improvement at approach road to MLA Hostel and SLA premises Departmental State Plan 12.83 0.00 12.83 Removal 2006 - 100% 4.00 4.00 0.00 completed Tenth Plan MPR    
43 Raising of sunkdown formation of Raley-Kambal Samdong km 6th ch 30-32 Departmental State Plan 3.93 0.00 3.93 Removal - - 100% 3.93 3.93 0.00 completed   MPR    
44 Slip clearance along KLT road km 2nd ch 25th & 27th  Departmental State Plan 3.61 0.00 3.61 Removal - - 100% 3.08 3.08 0.00 completed   MPR    
45 Slope stabilisation work km 2nd Ch:6to 8 along Pakyong-Machong Road Departmental State Plan 4.68 0.00 4.68 Removal 2007 - 100% 0.00 0.00 0.00 completed Eleventh Plan MPR    
46 Providing protective work at Paemragoan  Departmental State Plan 2.24 0.00 2.24 Removal 2008 - 100% 0.00 0.00 0.00 completed Eleventh Plan MPR    
47 Premix carpetting/Imp. Of Rongli Rorathang road, Km 1st - 11th.( Revised) Kuber Raj Rai State Plan 254.00 0.00 254.00 Expansion 1-Jan-03 3-Apr-06 100% 215.36 215.36 0.00 completed Tenth Plan MPR    
48 Upgradation/carpeting P/works and drainage along Pakyong-Karthok road km 1st-4th. P. N. Kazi State Plan 129.49 0.00 129.49 Expansion 28-Mar-05 27-Jul-06 55% 95.08 95.08 0.00 work in progress Tenth Plan Both p  
49 Upgradation and premix carpeting of Kotlaytar Rai Gaon Road,km 1st & 2nd  Miss Devi Dakhal State Plan 57.71 0.00 57.71 Expansion 28-Mar-05 27-Sep-06 75% 31.05 31.05 0.00 work in progress Tenth Plan Both p  
50 Premix Carpetting and Surface improvement Chewribotay Pendam  Km 1st - 6th Basudev Pradhan State Plan 117.78 0.00 117.78 Expansion 29/05/2003 31/01/04 95% 83.84 83.84 0.00 work in progress Tenth Plan Both s  
51 Construction of Bye Pass Road below Mintokgang   State Plan 80.26 0.00 80.26 Expansion 26-Feb-04 5-Aug-04 100% 71.46 71.46 0.00 Final bill under process Tenth Plan Both g  
52 Premix carpetting & Surface Imp.of KLT 16th to 26th Km (Revised) P.D. Denzongpa State Plan 260.57 0.00 260.57 Expansion 2003 - 100% 252.36 252.36 0.00 completed Tenth Plan MPR    
53 Premix carpetting & Surface Imp.of KLT 7th to 15th Km (Revised) L.N. Sarda State Plan 232.83 0.00 232.83 Expansion 2003 - 100% 214.16 214.16 0.00 completed Tenth Plan MPR    
54 Const. of link road from King Stone to Simana Khola Km 1st to 2nd. Departmental NABARD 43.01 34.41 8.60 Expansion - - 100% 31.68 0.00 31.68 completed Tenth Plan MPR    
55 Const. of diversion road Ranipool-Pakyong road km 1st-3rd. B.K. Agarwal NLCPR  339.85 236.87 102.98 Expansion 21-Feb-05 21-Nov-05 50% 225.98 64.60 161.38 work in progress Tenth Plan Both P  
56 Ext. of Pakyong-Mamring Tareythang road km 1st Khush N.Adhikari State Plan 28.91 0.00 28.91 Expansion 1-Jul-05 31-Dec-07 90% 28.72 28.72 0.00 Revised Tenth Plan MPR p  
57 Ext. of Pakyong-Mamring Tareythang road km 2nd Johar Man Rai State Plan 16.61 0.00 16.61 Expansion 1-Jul-05 31-Dec-07 90% 16.37 16.37 0.00 Revised Tenth Plan MPR p  
58 Ext. of Pakyong-Mamring Tareythang road km 3rd G.K. Pradhan State Plan 22.70 0.00 22.70 Expansion 1-Jul-05 31-Dec-07 90% 12.94 12.94 0.00 Revised Estimate submitted Tenth Plan Both p  
59 Ext. of Pakyong-Mamring Tareythang road km 4th. Udai Mishara State Plan 17.92 0.00 17.92 Expansion 1-Jul-05 31-Dec-07 90% 12.02 12.02 0.00 Revised Estimate submitted Tenth Plan Both p  
60 Ext. of Pakyong-Mamring Tareythang road km 5th. K.S.Rai State Plan 27.01 0.00 27.01 Expansion 1-Jul-05 31-Dec-07 90% 16.05 16.05 0.00 Revised Estimate submitted Tenth Plan Both p  
61 Ext. of Pakyong-Mamring Tareythang road km 6th. Ishore Dakahal State Plan 21.15 0.00 21.15 Expansion 1-Jul-05 31-Dec-07 70% 18.71 18.71 0.00 Revised Estimate submitted Tenth Plan Both p  
62 Ext. of Pakyong-Mamring Tareythang road km 7th. K.S.Rai State Plan 22.10 0.00 22.10 Expansion 1-Jul-05 31-Dec-07 50% 8.68 8.68 0.00 Revised Estimate submitted Tenth Plan Both p  
63 Ext. of Pakyong-Mamring Tareythang road km.8th  M. K. Pradhan State Plan 21.66 0.00 21.66 Expansion 1-Jul-05 31-Dec-07 30% 0.00 0.00 0.00 Revised Estimate submitted Tenth Plan Both p  
64 Ext. of Pakyong-Mamring Tareythang road km.9th  Kamal Adhikari State Plan 19.24 0.00 19.24 Expansion 1-Jul-05 31-Dec-07 100% 8.00 8.00 0.00 Completed, Final bill under process Tenth Plan Both p  
65 Ext. of Pakyong-Mamring Tareythang road km.10th  Milan Dahal State Plan 10.70 0.00 10.70 Expansion 1-Jul-05 31-Dec-07 100% 0.00 0.00 0.00 Completed Tenth Plan Both p  
66 Construction of Arithang Road connecting Indira Bye-Pass Road  Departmental   57.47 0.00 57.47 Expansion 2005 - 100% 55.75 55.75 0.00 completed Tenth Plan MPR    
67 Const. of road from Zingla Martam KM 16th-18th (2.36km)   State Plan TSP 77.96 0.00 77.96 Expansion 3-Oct-05 3-Oct-06 100% 69.00 69.00 0.00 work in progress Tenth Plan Both s  
68 Const. of road from Zingla Martam KM 16th-18th (2.36km) Land Compensation Land Compensation State Plan 14.16 0.00 14.16 Expansion 3-Oct-05 3-Oct-06 - 14.16 14.16 0.00 work in progress Tenth Plan Both s  
69 Feeder Raod to development Area( Addl sanction on 9th Paln scheme)  Ssno 1/East/Exp/06-07 T. wangchok   5.04 0.00 5.04 Expansion 2006 - 100% 5.04 5.04 0.00 Revised Tenth Plan MPR    
70 Const of 40 Mts span Bridge over Rongli Khola along  arubotey subaney dara Raod Ssno 2/E/exp/06-07 Ashok Ts. Bhutia   16.50 0.00 16.50 Expansion 2006 - 100% 14.24 14.24 0.00 completed Tenth Plan MPR    
71 Strengthening/drainage and P/Wprks for the road from Lal Turning to Bashilakha Road Km 1st to 3rd G.M Gurung NABARD 184.65 151.46 33.19 Expansion 30/09/07 31/03/08 95% 143.83 0.00 143.83 work under progress Eleventh Plan Both    
72 Immediate Restoration of Mamring Amba Road km 3rd Departmental   6.77 0.00 6.77 Expansion 6-Nov-06 5-May-08 100% 6.68 6.68 0.00 completed Tenth Plan MPR    
73     Relocation     and extension of HT &LT line and shifting of 25 KVA outdoor   pipe    distribution sub-station at Barchangey Village East. Power Department   3.37 0.00 3.37 Expansion 2006 - 100% 3.37 3.37 0.00 completed Tenth Plan MPR    
74 Construction of Link Road from Sakyong to Beyong km 1st to 2nd (State Share of NABARD) - NABARD 19.47 0.00 19.47 Link Road 2008 - 20% 0.00 0.00 0.00 work under progress Eleventh Plan MPR    
75 Construction of 20 chain road Bio Control Laboratory to Phewk Busty road  Mr. G.K.Chettri State Plan 72.02 0.00 72.02 Link Road 28-Sep-05 27-Mar-05 85% 21.15 21.15 0.00 Revised estimate  Tenth Plan Both g  
76 Repairs of IETC SMITE Overhead crane station at 5th Mile Tadong Departmental State Plan 1.35 0.00 1.35 Addl.Facilities 20-Jul-06 - 5% 1.35 1.35 0.00 work in progress Tenth Plan MPR    
77 Fencing around SPWD Mech. Workshop Tadong Departmental State Plan 2.74 0.00 2.74 Addl.Facilities 31-Aug-06 - 5% 2.73 2.73 0.00 work in progress Tenth Plan MPR    
78 Additonal facilities installation of portable magazine at Sirwani-Singtam Departmental State Plan 10.00 0.00 10.00 Addl.Facilities 22-Aug-07 - 5% 9.45 9.45 0.00 work in progress Eleventh Plan MPR    
79 Const. of link road from Basilakhs to Middle camp via Rodongtar km 6th  Justin Rai State Plan 17.93 0.00 17.93 New Road 5-Oct-05 9-Feb-05 75% 14.93 14.93 0.00 work in progress Tenth Plan Both p  
80 Const. of link road from Basilakhs to Middle camp via Rodongtar km 7th  Jeewan Subba State Plan 17.23 0.00 17.23 New Road 5-Oct-05 9-Feb-05 100% 17.22 17.22 0.00 completed Tenth Plan Both p  
81 Const. of link road from Basilakhs to Middle camp via Rodongtar km 8th  Paul Rai State Plan 21.36 0.00 21.36 New Road 5-Oct-05 9-Feb-05 100% 10.01 10.01 0.00 work in progress Tenth Plan Both p  
82 Const. of 10m span RCC Culvert on Basilakha to middle camp km 8th. Patrush Subba State Plan 12.32 0.00 12.32 New Road 5-Oct-05 9-Feb-05 75% 0.00 0.00 0.00 work in progress Tenth Plan Both p  
83 Const of Approach road to Sivalaya Mandir at pacheykhani Km 1st R.N. Baral State Plan 23.51 0.00 23.51 New Road 18-Jul-05 15-Jun-06 85% 12.87 12.87 0.00 work in progress Tenth Plan MPR    
84 Construction of Link Road from Amba to Taja School 1st and 2nd km Mon Narayan Dhakal State Plan 5.06 0.00 5.06 New Road - - 75% 3.96 3.96 0 work in progress   MPR    
85 Const. of link road from Assam-Pakyong road to Kadamtam village km.1st. M.B.Mangar State Plan 39.65 0.00 39.65 New Road 1-Jul-05 30-Jun-06 100% 39.51 39.51 0.00 Completed, Final bill under process Tenth Plan Both p  
86 Const. of link road from Assam-Pakyong road to Kadamtam village km.2nd. Elies Lepcha State Plan 41.40 0.00 41.40 New Road 1-Jul-05 30-Jun-06 100% 41.39 41.39 0.00 Completed, Final bill under process Tenth Plan Both p  
87 Const. of link road from Assam-Pakyong road to Kadamtam village km.3rd & 4th. D.P. Mangar State Plan 41.74 0.00 41.74 New Road 1-Jul-05 30-Jun-06 65% 24.66 24.66 0.00 Revised Est Submitted Tenth Plan Both p  
88 Const. of link road from Assam-Pakyong road to Kadamtam village km.3rd & 4th.Contingency Rs.4.26 + Land Compansation LC & Contg State Plan 87.70 0.00 87.70 New Road - - 100% 34.27 34.27 0.00 completed   MPR    
89 Construction of road from Chandmari village to Jawaharlall Nehru road    State Plan 30.63 0.00 30.63 New Road 31-May-05 30-Nov-05 90% 23.76 23.76 0.00 Delayed due to unavailability of Bitumin Tenth Plan Both g  
90 Land compensation for extension of link road from NH-31 A to Chisopani km 2nd   State Plan 3.35 0.00 3.35 New Road - - 100% 3.35 3.35 0.00 completed   MPR    
91 Extension of Link Road to Dokey Chisopani Pry School    ( State Share of RSVY Scheme) Nabin Rai RSVY 3.72 2.00 1.72 New Road 17-Oct-05 27-Mar-06 85% 0.00 0.00 0.00 in progress Tenth Plan MPR    
92 Land compenstion for construction of Link road from Basilakha to Middle Camp via Radongtar km 6th to 8th & 10th M Span R.C.C Bridge   State Plan 19.47 0.00 19.47 New Road 2008 - - 0.00 0.00 0.00   Eleventh Plan MPR    
93 Construction of new road from Radong (NH-31A) to Khimsithang via Chuba km 1st to 15th   State Plan 874.19 0.00 874.19 New Road 2008 18-Jan-06 - 0.00 0.00 0.00   Eleventh Plan MPR    
94 Const. of Song-zingla Martam road km 9th. P.T. Lepcha State Plan 12.45 0.00 12.45 New Road 5-Mar-03 20-Dec-03 95% 5.63 5.63 0.00  In progress Eleventh Plan Spill Over Acct s  
95 Const. of Sang-Zingla Martam road KM 10th. P.T. Rongong State Plan 14.51 0.00 14.51 New Road 6-Mar-03 6-Dec-03 100% 12.45 12.45 0.00 Final Payment Eleventh Plan Not in Both s  
96 Const. of Song-Zingla Martam road km 11th  Anita Gurung State Plan 16.17 0.00 16.17 New Road 6-Mar-03 6-Dec-03 100% 12.28 12.28 0.00 Final Payment Eleventh Plan Not in Both s  
97 Const. of Song-Zingla Martam road km 12th. U. Lama State Plan 17.74 0.00 17.74 New Road 6-Mar-03 6-Dec-03 100% 13.11 13.11 0.00 Final Payment Eleventh Plan Not in Both s  
98 Const.of Song-Zingla Martam road km 14th  Tenging Bhutia State Plan 25.54 0.00 25.54 New Road 6-Mar-03 6-Dec-03 75% 19.63 19.63 0.00  In progress Eleventh Plan Spill Over Acct s  
99 Const. of Song-Zingla Martam road km 15th. S.K.Chettri State Plan 26.75 0.00 26.75 New Road 6-Mar-03 6-Dec-03 95% 19.95 19.95 0.00  In progress Eleventh Plan Spill Over Acct s