| DIVISION : EAST | ||||||||||||||||||
| Sl.No | Name of Schemes | Name of Contractor | Funding Agency | SANCTIONED AMOUNT | Date of Commencement | Date of Completion | Physical Progress in % | Financial Progress | Remarks | |||||||||
| Total | C.share | S. share | (Head) | Expenditure till date | ||||||||||||||
| Total | S.Share | C.Share | Work Remrks | Plan | NOT | |||||||||||||
| A. | CENTRAL SPONSORED SCHEMES | |||||||||||||||||
| 1 | Const. of Goshkhan Dara Bridge over River Teesta at Singtam, East Sikkim | M.P Agarwal | NLCPR | 1,337.11 | 1,337.11 | 0.00 | - | 10-Jan-07 | 11-Jun-08 | 35% | 420.00 | 0.00 | 420.00 | work in progress | Eleventh Plan | Spill Over Acct | s | |
| 2 | Const. of diversion road Ranipool-Pakyong road km 1st-3rd. | B.K. Agarwal | NLCPR | 339.85 | 236.87 | 102.98 | Expansion | 21-Feb-05 | 21-Nov-05 | 50% | 225.98 | 64.60 | 161.38 | work in progress | Tenth Plan | Both | P | |
| 3 | Upgradation of Gangtok Burtuk Ranka Road ( 8km ) in East Sikkim. | - | NLCPR | 420.00 | 420.00 | 0.00 | - | 18-May-04 | - | - | 387.11 | 0.00 | 387.11 | - | Tenth Plan | Not in Both | ||
| 4 | Strengthening,drainage and Carpeting and construction of 30m span steel bridge along Assam-Pakyong road km 7th - 15th. | S.K. Agarwal | NEC | 750.76 | 750.76 | 0.00 | - | 6-Nov-06 | 5-May-08 | 60% | 309.05 | 0.00 | 309.05 | work under process | Tenth Plan | Spill Over Acct | ||
| 5 | Construction of major retaining structures on approach road to Raj Bhawan,VIP Complex and TNA Public School Complex | NEC | 106.87 | 106.87 | 0.00 | - | 30-May-05 | 29-May-06 | 100% | 74.24 | 0.00 | 74.24 | completed | Tenth Plan | Spill Over Acct | |||
| 6 | Replacement of Sumin Wooden Suspension Bridge on Sang Khola Sumin Road | NEC | 285.40 | 285.40 | 0.00 | - | 8-Apr-04 | - | - | 231.34 | 0.00 | 231.34 | - | Tenth Plan | Not in Both | |||
| 7 | Strengthening/drainage and P/Wprks for the road from Lal Turning to Bashilakha Road Km 1st to 3rd | G.M Gurung | NABARD | 184.65 | 151.46 | 33.19 | Expansion | 30/09/07 | 31/03/08 | 95% | 143.83 | 0.00 | 143.83 | work under progress | Eleventh Plan | Both | ||
| 8 | Const. of link road from King Stone to Simana Khola Km 1st to 2nd. | Departmental | NABARD | 43.01 | 34.41 | 8.60 | Expansion | - | - | 100% | 31.68 | 0.00 | 31.68 | completed | MPR | |||
| 9 | Construction of Link Road from Sakyong to Beyong km 1st to 2nd (State Share of NABARD) | - | NABARD | 19.47 | 0.00 | 19.47 | Link Road | 2008 | - | 20% | 0.00 | 0.00 | 0.00 | work under progress | Eleventh Plan | MPR | ||
| 10 | Premix Carpetting & protective work along approach road to Crematorium at Jalipool. | NABARD | 20.66 | 0.00 | 20.66 | - | 2005 | - | - | 20.66 | 0.00 | 20.66 | - | Tenth Plan | MPR | |||
| 11 | Construction of link road from Lower Lingdum to Adampool (km 3rd to 4th) | NABARD | 73.43 | 73.43 | 0.00 | - | 2005 | - | - | 73.43 | 0.00 | 73.43 | - | Tenth Plan | MPR | |||
| 12 | Const. of 12 m span R.C.C. Bridge on Sangkhola Zingla Martam Road at Km 11th ch-3rd. | Anita Gurung | CRF | 38.63 | 38.63 | 0.00 | - | 1-Apr-07 | 31-Mar-08 | 35% | 0.00 | 0.00 | 0.00 | work under progress | Eleventh Plan | Spill Over Acct | s | |
| 13 | Const. of 12 m span R.C.c. Bridge on Sangkhola Zingla Martam Road at Km 12th ch-4th.. | T.B. Pradhan | CRF | 45.12 | 45.12 | 0.00 | - | 1-Apr-07 | 31-Mar-08 | 60% | 22.00 | 0.00 | 22.00 | work under progress | Eleventh Plan | Spill Over Acct | s | |
| 14 | Surface improvement and widening of Sang Sirwani Road Km 1st & App Road from Mech Sub Div Office at Dochum | Kishor Pradhan | CRF | 50.20 | 50.20 | 0.00 | - | 10-Oct-07 | 9-Sep-08 | 85% | 25.71 | 0.00 | 25.71 | work under progress | Eleventh Plan | Spill Over Acct | s | |
| 15 | Surface improvement and widening of Sang Sirwani Road Km 2nd & App Road to Mech Workshop Dochum | K.R. Sharma | CRF | 38.49 | 38.49 | 0.00 | - | 10-Oct-07 | 9-Sep-08 | 50% | 12.61 | 0.00 | 12.61 | work under progress | Eleventh Plan | Spill Over Acct | s | |
| 16 | Upgradation of Link Road from NH-31A to Dokey Chisopani Km 1st | CRF | 69.63 | 69.63 | 0.00 | - | 29-Feb-08 | 28-Feb-09 | 15% | 0.00 | 0.00 | 0.00 | Work to Commence | Eleventh Plan | Spill Over Acct | |||
| 17 | Upgradation of Link Road from NH-31A to Dokey Chisopani Km 2nd | CRF | 35.20 | 35.20 | 0.00 | - | 29-Feb-08 | 28-Feb-09 | 5% | 0.00 | 0.00 | 0.00 | work under progress | Eleventh Plan | Spill Over Acct | |||
| 18 | Upgradation of Link Road from NH-31A to Dokey Chisopani Km 3rd | CRF | 43.90 | 43.90 | 0.00 | - | 29-Feb-08 | 28-Feb-09 | 5% | 0.00 | 0.00 | 0.00 | work under progress | Eleventh Plan | Spill Over Acct | |||
| 19 | Const. of link road from Arubotey to Subaneydara km 1st-3rd. | Om Bhd. Gurung | BADP | 29.97 | 29.97 | 0.00 | - | 30-Nov-00 | 16-Mar-01 | 68% | 22.98 | 0.00 | 22.98 | work abondoned | Ninth Plan | Spill Over Acct | ||
| 20 | Const. of link road from sisney to North Regu km 1st -4th. | T.S. Lama | BADP | 30.31 | 30.31 | 0.00 | - | 21-Nov-00 | 5-Mar-01 | 95% | 24.54 | 0.00 | 24.54 | work abondoned | Ninth Plan | Spill Over Acct | ||
| 21 | Premix carpetting and widening work on Sang dipudara road Km 1st to 14th. | Daluram Sarda | EI | 277.44 | 6.95 | 277.44 | Removal | 18/11/2002 | 17/08/2004 | 90% | 233.08 | 233.08 | 0.00 | Sanctioned from EI Rs 6.95 Crore | Tenth Plan | Both | s | |
| 22 | Upgradationand premix carpeting along Duga Pachaykhani road KM 1st-14th. | B.K.Agarwal | EI | 841.38 | 433.77 | 407.61 | Removal | 21-Feb-05 | 5-Mar-08 | 90% | 393.32 | 24.00 | 369.32 | work in progress | Tenth Plan | Both | s | |
| 23 | Construction of Road from Rathong (NH-31A) to Kimchithang Km 1st to 15th (EI) | - | EI | 701.89 | 701.89 | 0.00 | - | 2007 | - | - | 0.00 | 0.00 | 0.00 | New Project | Tenth Plan | Not in Both | ||
| 24 | Improvement of Sang Dipudara Road (EI) | - | EI | 347.74 | 347.74 | 0.00 | - | 2007 | - | - | 0.00 | 0.00 | 0.00 | New Project | Tenth Plan | Not in Both | ||
| 25 | Improvement of Pakyong - Karthok - Naya busty - Raigoan Road (EI) | - | EI | 398.42 | 398.42 | 0.00 | - | 2007 | - | - | 0.00 | 0.00 | 0.00 | New Project | Tenth Plan | Not in Both | ||
| 26 | Widening, upgradation of pavement & drainage system along Rangpo Duga Pendam road km 1st - 15th | M/s Apex Project & Investment P. Ltd. | ISC | 950.00 | 950.00 | 0.00 | - | 15-Jun-08 | 16-Dec-08 | 55% | 480.00 | 0.00 | 480.00 | work in progress | Eleventh Plan | Spill Over Acct | s | |
| 27 | Improvement of Rhenock - Simanakhola Road Km 1st to 3rd. (ISC) | - | ISC | 250.00 | 250.00 | 0.00 | - | 26-Mar-08 | - | 10% | 236.99 | 0.00 | 236.99 | work in progress | Eleventh Plan | Spill Over Acct | ||
| 28 | Carpetting of Sirwani Bermoik Phongla Road, S.Sikkim (ISC) | - | ISC | 999.08 | 999.08 | 0.00 | - | 26-Jul-05 | - | 10% | 766.00 | 0.00 | 766.00 | work in progress | Tenth Plan | Not in Both | ||
| 29 | Extension of Link Road to Dokey Chisopani Pry School ( State Share of RSVY Scheme) | Nabin Rai | RSVY | 3.72 | 2.00 | 1.72 | New Road | 17-Oct-05 | 27-Mar-06 | 85% | 0.00 | 0.00 | 0.00 | work in progress | Tenth Plan | MPR | ||
| STATE PLAN | ||||||||||||||||||
| 30 | Carpeting and surface strengthening, improvement, including drainage works of roads in and around Gangtok. | State Plan | 361.89 | 0.00 | 361.89 | Removal | 6-Jun-04 | 5-Sep-05 | 100% | 229.45 | 229.45 | 0.00 | work completed final bill under process | Tenth Plan | Both | g | ||
| 31 | Premix carpetting and widening work on Sang dipudara road Km 1st to 14th. | Daluram Sarda | EI | 284.39 | 6.95 | 277.44 | Removal | 18/11/2002 | 17/08/2004 | 80% | 233.08 | 233.08 | 0.00 | Sanctioned from EI Rs 6.95 Crore | Tenth Plan | Both | s | |
| 32 | Upgradationand premix carpeting along Duga Pachaykhani road KM 1st-14th. | B.K.Agarwal | EI | 841.38 | 433.77 | 407.61 | Removal | 21-Feb-05 | 5-Mar-08 | 90% | 393.32 | 24.00 | 369.32 | work in progress | Tenth Plan | Both | s | |
| 33 | Surface strengthening upgradation and carpeting of Pakyong-Karthok Naya Busty road km 5th -7th. | State Plan | 183.89 | 0.00 | 183.89 | Removal | 21/06/05 | 31-Aug-08 | 45% | 56.58 | 56.58 | 0.00 | work in progress, Date Extended | Tenth Plan | Both | P | ||
| 34 | P/L edging ,soling, metalling, premix carpeting and cross drain of link road from sichey to Indira Bye Pass via Shivalaya Mandir | State Plan | 8.16 | 0.00 | 8.16 | Removal | 1/0/2002 | 2-Jul-05 | 80% | 5.81 | 5.81 | 0.00 | work in abeyance due to non availibility of bitumen | Tenth Plan | Both | g | ||
| 35 | Surface stregenthening , upgradation and carpeting of Roads during the visit of His Holiness the Dalai Lama | Departmental | State Plan | 40.35 | 0.00 | 40.35 | Removal | 2005 | - | 100% | 38.79 | 38.79 | 0.00 | completed | Tenth Plan | MPR | ||
| 36 | Providing 75mm thick CC pitching over approach raod to Gairi Goan from NH 31A Near Hotel Tashi Targey) Ssno 2/E/Remv/06-07 | Departmental | State Plan | 3.40 | 0.00 | 3.40 | Removal | 2006 | - | 0% | 0.00 | 0.00 | 0.00 | Tenth Plan | MPR | |||
| 37 | Const of PW along TNSS to Dhupidara Ssno 6/E/Remov/0607 | State Plan | 3.44 | 0.00 | 3.44 | Removal | 2006 | - | 100% | 3.42 | 3.42 | 0.00 | completed | Tenth Plan | MPR | |||
| 38 | Permanent restoration work of Chief Justic Banglow Road Ssno7/E/Remo/06-07 | Departmental | State Plan | 11.21 | 0.00 | 11.21 | Removal | 2006 | - | 100% | 10.31 | 10.31 | 0.00 | completed | Tenth Plan | MPR | ||
| 39 | Immediate protective work to donak khola along tarethang Bering Road km ch.22nd 23 ch | Departmental | State Plan | 19.72 | 0.00 | 19.72 | Removal | 2006 | - | 100% | 17.65 | 17.65 | 0.00 | completed | Tenth Plan | MPR | ||
| 40 | Restoration work at km 8th Ch.4-5 (Namphey khola)along Assam-Pakyong road | Departmental | State Plan | 19.93 | 0.00 | 19.93 | Removal | 2006 | - | 100% | 19.93 | 19.93 | 0.00 | completed | Tenth Plan | MPR | ||
| 41 | Immediate traffic clerance of rest work on lingtam-Agamlok rod km 1st &2nd. | Departmental | State Plan | 4.48 | 0.00 | 4.48 | Removal | 2006 | - | 100% | 4.48 | 4.48 | 0.00 | completed | Tenth Plan | MPR | ||
| 42 | surface improvement at approach road to MLA Hostel and SLA premises | Departmental | State Plan | 12.83 | 0.00 | 12.83 | Removal | 2006 | - | 100% | 4.00 | 4.00 | 0.00 | completed | Tenth Plan | MPR | ||
| 43 | Raising of sunkdown formation of Raley-Kambal Samdong km 6th ch 30-32 | Departmental | State Plan | 3.93 | 0.00 | 3.93 | Removal | - | - | 100% | 3.93 | 3.93 | 0.00 | completed | MPR | |||
| 44 | Slip clearance along KLT road km 2nd ch 25th & 27th | Departmental | State Plan | 3.61 | 0.00 | 3.61 | Removal | - | - | 100% | 3.08 | 3.08 | 0.00 | completed | MPR | |||
| 45 | Slope stabilisation work km 2nd Ch:6to 8 along Pakyong-Machong Road | Departmental | State Plan | 4.68 | 0.00 | 4.68 | Removal | 2007 | - | 100% | 0.00 | 0.00 | 0.00 | completed | Eleventh Plan | MPR | ||
| 46 | Providing protective work at Paemragoan | Departmental | State Plan | 2.24 | 0.00 | 2.24 | Removal | 2008 | - | 100% | 0.00 | 0.00 | 0.00 | completed | Eleventh Plan | MPR | ||
| 47 | Premix carpetting/Imp. Of Rongli Rorathang road, Km 1st - 11th.( Revised) | Kuber Raj Rai | State Plan | 254.00 | 0.00 | 254.00 | Expansion | 1-Jan-03 | 3-Apr-06 | 100% | 215.36 | 215.36 | 0.00 | completed | Tenth Plan | MPR | ||
| 48 | Upgradation/carpeting P/works and drainage along Pakyong-Karthok road km 1st-4th. | P. N. Kazi | State Plan | 129.49 | 0.00 | 129.49 | Expansion | 28-Mar-05 | 27-Jul-06 | 55% | 95.08 | 95.08 | 0.00 | work in progress | Tenth Plan | Both | p | |
| 49 | Upgradation and premix carpeting of Kotlaytar Rai Gaon Road,km 1st & 2nd | Miss Devi Dakhal | State Plan | 57.71 | 0.00 | 57.71 | Expansion | 28-Mar-05 | 27-Sep-06 | 75% | 31.05 | 31.05 | 0.00 | work in progress | Tenth Plan | Both | p | |
| 50 | Premix Carpetting and Surface improvement Chewribotay Pendam Km 1st - 6th | Basudev Pradhan | State Plan | 117.78 | 0.00 | 117.78 | Expansion | 29/05/2003 | 31/01/04 | 95% | 83.84 | 83.84 | 0.00 | work in progress | Tenth Plan | Both | s | |
| 51 | Construction of Bye Pass Road below Mintokgang | State Plan | 80.26 | 0.00 | 80.26 | Expansion | 26-Feb-04 | 5-Aug-04 | 100% | 71.46 | 71.46 | 0.00 | Final bill under process | Tenth Plan | Both | g | ||
| 52 | Premix carpetting & Surface Imp.of KLT 16th to 26th Km (Revised) | P.D. Denzongpa | State Plan | 260.57 | 0.00 | 260.57 | Expansion | 2003 | - | 100% | 252.36 | 252.36 | 0.00 | completed | Tenth Plan | MPR | ||
| 53 | Premix carpetting & Surface Imp.of KLT 7th to 15th Km (Revised) | L.N. Sarda | State Plan | 232.83 | 0.00 | 232.83 | Expansion | 2003 | - | 100% | 214.16 | 214.16 | 0.00 | completed | Tenth Plan | MPR | ||
| 54 | Const. of link road from King Stone to Simana Khola Km 1st to 2nd. | Departmental | NABARD | 43.01 | 34.41 | 8.60 | Expansion | - | - | 100% | 31.68 | 0.00 | 31.68 | completed | Tenth Plan | MPR | ||
| 55 | Const. of diversion road Ranipool-Pakyong road km 1st-3rd. | B.K. Agarwal | NLCPR | 339.85 | 236.87 | 102.98 | Expansion | 21-Feb-05 | 21-Nov-05 | 50% | 225.98 | 64.60 | 161.38 | work in progress | Tenth Plan | Both | P | |
| 56 | Ext. of Pakyong-Mamring Tareythang road km 1st | Khush N.Adhikari | State Plan | 28.91 | 0.00 | 28.91 | Expansion | 1-Jul-05 | 31-Dec-07 | 90% | 28.72 | 28.72 | 0.00 | Revised | Tenth Plan | MPR | p | |
| 57 | Ext. of Pakyong-Mamring Tareythang road km 2nd | Johar Man Rai | State Plan | 16.61 | 0.00 | 16.61 | Expansion | 1-Jul-05 | 31-Dec-07 | 90% | 16.37 | 16.37 | 0.00 | Revised | Tenth Plan | MPR | p | |
| 58 | Ext. of Pakyong-Mamring Tareythang road km 3rd | G.K. Pradhan | State Plan | 22.70 | 0.00 | 22.70 | Expansion | 1-Jul-05 | 31-Dec-07 | 90% | 12.94 | 12.94 | 0.00 | Revised Estimate submitted | Tenth Plan | Both | p | |
| 59 | Ext. of Pakyong-Mamring Tareythang road km 4th. | Udai Mishara | State Plan | 17.92 | 0.00 | 17.92 | Expansion | 1-Jul-05 | 31-Dec-07 | 90% | 12.02 | 12.02 | 0.00 | Revised Estimate submitted | Tenth Plan | Both | p | |
| 60 | Ext. of Pakyong-Mamring Tareythang road km 5th. | K.S.Rai | State Plan | 27.01 | 0.00 | 27.01 | Expansion | 1-Jul-05 | 31-Dec-07 | 90% | 16.05 | 16.05 | 0.00 | Revised Estimate submitted | Tenth Plan | Both | p | |
| 61 | Ext. of Pakyong-Mamring Tareythang road km 6th. | Ishore Dakahal | State Plan | 21.15 | 0.00 | 21.15 | Expansion | 1-Jul-05 | 31-Dec-07 | 70% | 18.71 | 18.71 | 0.00 | Revised Estimate submitted | Tenth Plan | Both | p | |
| 62 | Ext. of Pakyong-Mamring Tareythang road km 7th. | K.S.Rai | State Plan | 22.10 | 0.00 | 22.10 | Expansion | 1-Jul-05 | 31-Dec-07 | 50% | 8.68 | 8.68 | 0.00 | Revised Estimate submitted | Tenth Plan | Both | p | |
| 63 | Ext. of Pakyong-Mamring Tareythang road km.8th | M. K. Pradhan | State Plan | 21.66 | 0.00 | 21.66 | Expansion | 1-Jul-05 | 31-Dec-07 | 30% | 0.00 | 0.00 | 0.00 | Revised Estimate submitted | Tenth Plan | Both | p | |
| 64 | Ext. of Pakyong-Mamring Tareythang road km.9th | Kamal Adhikari | State Plan | 19.24 | 0.00 | 19.24 | Expansion | 1-Jul-05 | 31-Dec-07 | 100% | 8.00 | 8.00 | 0.00 | Completed, Final bill under process | Tenth Plan | Both | p | |
| 65 | Ext. of Pakyong-Mamring Tareythang road km.10th | Milan Dahal | State Plan | 10.70 | 0.00 | 10.70 | Expansion | 1-Jul-05 | 31-Dec-07 | 100% | 0.00 | 0.00 | 0.00 | Completed | Tenth Plan | Both | p | |
| 66 | Construction of Arithang Road connecting Indira Bye-Pass Road | Departmental | 57.47 | 0.00 | 57.47 | Expansion | 2005 | - | 100% | 55.75 | 55.75 | 0.00 | completed | Tenth Plan | MPR | |||
| 67 | Const. of road from Zingla Martam KM 16th-18th (2.36km) | State Plan TSP | 77.96 | 0.00 | 77.96 | Expansion | 3-Oct-05 | 3-Oct-06 | 100% | 69.00 | 69.00 | 0.00 | work in progress | Tenth Plan | Both | s | ||
| 68 | Const. of road from Zingla Martam KM 16th-18th (2.36km) Land Compensation | Land Compensation | State Plan | 14.16 | 0.00 | 14.16 | Expansion | 3-Oct-05 | 3-Oct-06 | - | 14.16 | 14.16 | 0.00 | work in progress | Tenth Plan | Both | s | |
| 69 | Feeder Raod to development Area( Addl sanction on 9th Paln scheme) Ssno 1/East/Exp/06-07 | T. wangchok | 5.04 | 0.00 | 5.04 | Expansion | 2006 | - | 100% | 5.04 | 5.04 | 0.00 | Revised | Tenth Plan | MPR | |||
| 70 | Const of 40 Mts span Bridge over Rongli Khola along arubotey subaney dara Raod Ssno 2/E/exp/06-07 | Ashok Ts. Bhutia | 16.50 | 0.00 | 16.50 | Expansion | 2006 | - | 100% | 14.24 | 14.24 | 0.00 | completed | Tenth Plan | MPR | |||
| 71 | Strengthening/drainage and P/Wprks for the road from Lal Turning to Bashilakha Road Km 1st to 3rd | G.M Gurung | NABARD | 184.65 | 151.46 | 33.19 | Expansion | 30/09/07 | 31/03/08 | 95% | 143.83 | 0.00 | 143.83 | work under progress | Eleventh Plan | Both | ||
| 72 | Immediate Restoration of Mamring Amba Road km 3rd | Departmental | 6.77 | 0.00 | 6.77 | Expansion | 6-Nov-06 | 5-May-08 | 100% | 6.68 | 6.68 | 0.00 | completed | Tenth Plan | MPR | |||
| 73 | Relocation and extension of HT < line and shifting of 25 KVA outdoor pipe distribution sub-station at Barchangey Village East. | Power Department | 3.37 | 0.00 | 3.37 | Expansion | 2006 | - | 100% | 3.37 | 3.37 | 0.00 | completed | Tenth Plan | MPR | |||
| 74 | Construction of Link Road from Sakyong to Beyong km 1st to 2nd (State Share of NABARD) | - | NABARD | 19.47 | 0.00 | 19.47 | Link Road | 2008 | - | 20% | 0.00 | 0.00 | 0.00 | work under progress | Eleventh Plan | MPR | ||
| 75 | Construction of 20 chain road Bio Control Laboratory to Phewk Busty road | Mr. G.K.Chettri | State Plan | 72.02 | 0.00 | 72.02 | Link Road | 28-Sep-05 | 27-Mar-05 | 85% | 21.15 | 21.15 | 0.00 | Revised estimate | Tenth Plan | Both | g | |
| 76 | Repairs of IETC SMITE Overhead crane station at 5th Mile Tadong | Departmental | State Plan | 1.35 | 0.00 | 1.35 | Addl.Facilities | 20-Jul-06 | - | 5% | 1.35 | 1.35 | 0.00 | work in progress | Tenth Plan | MPR | ||
| 77 | Fencing around SPWD Mech. Workshop Tadong | Departmental | State Plan | 2.74 | 0.00 | 2.74 | Addl.Facilities | 31-Aug-06 | - | 5% | 2.73 | 2.73 | 0.00 | work in progress | Tenth Plan | MPR | ||
| 78 | Additonal facilities installation of portable magazine at Sirwani-Singtam | Departmental | State Plan | 10.00 | 0.00 | 10.00 | Addl.Facilities | 22-Aug-07 | - | 5% | 9.45 | 9.45 | 0.00 | work in progress | Eleventh Plan | MPR | ||
| 79 | Const. of link road from Basilakhs to Middle camp via Rodongtar km 6th | Justin Rai | State Plan | 17.93 | 0.00 | 17.93 | New Road | 5-Oct-05 | 9-Feb-05 | 75% | 14.93 | 14.93 | 0.00 | work in progress | Tenth Plan | Both | p | |
| 80 | Const. of link road from Basilakhs to Middle camp via Rodongtar km 7th | Jeewan Subba | State Plan | 17.23 | 0.00 | 17.23 | New Road | 5-Oct-05 | 9-Feb-05 | 100% | 17.22 | 17.22 | 0.00 | completed | Tenth Plan | Both | p | |
| 81 | Const. of link road from Basilakhs to Middle camp via Rodongtar km 8th | Paul Rai | State Plan | 21.36 | 0.00 | 21.36 | New Road | 5-Oct-05 | 9-Feb-05 | 100% | 10.01 | 10.01 | 0.00 | work in progress | Tenth Plan | Both | p | |
| 82 | Const. of 10m span RCC Culvert on Basilakha to middle camp km 8th. | Patrush Subba | State Plan | 12.32 | 0.00 | 12.32 | New Road | 5-Oct-05 | 9-Feb-05 | 75% | 0.00 | 0.00 | 0.00 | work in progress | Tenth Plan | Both | p | |
| 83 | Const of Approach road to Sivalaya Mandir at pacheykhani Km 1st | R.N. Baral | State Plan | 23.51 | 0.00 | 23.51 | New Road | 18-Jul-05 | 15-Jun-06 | 85% | 12.87 | 12.87 | 0.00 | work in progress | Tenth Plan | MPR | ||
| 84 | Construction of Link Road from Amba to Taja School 1st and 2nd km | Mon Narayan Dhakal | State Plan | 5.06 | 0.00 | 5.06 | New Road | - | - | 75% | 3.96 | 3.96 | 0 | work in progress | MPR | |||
| 85 | Const. of link road from Assam-Pakyong road to Kadamtam village km.1st. | M.B.Mangar | State Plan | 39.65 | 0.00 | 39.65 | New Road | 1-Jul-05 | 30-Jun-06 | 100% | 39.51 | 39.51 | 0.00 | Completed, Final bill under process | Tenth Plan | Both | p | |
| 86 | Const. of link road from Assam-Pakyong road to Kadamtam village km.2nd. | Elies Lepcha | State Plan | 41.40 | 0.00 | 41.40 | New Road | 1-Jul-05 | 30-Jun-06 | 100% | 41.39 | 41.39 | 0.00 | Completed, Final bill under process | Tenth Plan | Both | p | |
| 87 | Const. of link road from Assam-Pakyong road to Kadamtam village km.3rd & 4th. | D.P. Mangar | State Plan | 41.74 | 0.00 | 41.74 | New Road | 1-Jul-05 | 30-Jun-06 | 65% | 24.66 | 24.66 | 0.00 | Revised Est Submitted | Tenth Plan | Both | p | |
| 88 | Const. of link road from Assam-Pakyong road to Kadamtam village km.3rd & 4th.Contingency Rs.4.26 + Land Compansation | LC & Contg | State Plan | 87.70 | 0.00 | 87.70 | New Road | - | - | 100% | 34.27 | 34.27 | 0.00 | completed | MPR | |||
| 89 | Construction of road from Chandmari village to Jawaharlall Nehru road | State Plan | 30.63 | 0.00 | 30.63 | New Road | 31-May-05 | 30-Nov-05 | 90% | 23.76 | 23.76 | 0.00 | Delayed due to unavailability of Bitumin | Tenth Plan | Both | g | ||
| 90 | Land compensation for extension of link road from NH-31 A to Chisopani km 2nd | State Plan | 3.35 | 0.00 | 3.35 | New Road | - | - | 100% | 3.35 | 3.35 | 0.00 | completed | MPR | ||||
| 91 | Extension of Link Road to Dokey Chisopani Pry School ( State Share of RSVY Scheme) | Nabin Rai | RSVY | 3.72 | 2.00 | 1.72 | New Road | 17-Oct-05 | 27-Mar-06 | 85% | 0.00 | 0.00 | 0.00 | in progress | Tenth Plan | MPR | ||
| 92 | Land compenstion for construction of Link road from Basilakha to Middle Camp via Radongtar km 6th to 8th & 10th M Span R.C.C Bridge | State Plan | 19.47 | 0.00 | 19.47 | New Road | 2008 | - | - | 0.00 | 0.00 | 0.00 | Eleventh Plan | MPR | ||||
| 93 | Construction of new road from Radong (NH-31A) to Khimsithang via Chuba km 1st to 15th | State Plan | 874.19 | 0.00 | 874.19 | New Road | 2008 | 18-Jan-06 | - | 0.00 | 0.00 | 0.00 | Eleventh Plan | MPR | ||||
| 94 | Const. of Song-zingla Martam road km 9th. | P.T. Lepcha | State Plan | 12.45 | 0.00 | 12.45 | New Road | 5-Mar-03 | 20-Dec-03 | 95% | 5.63 | 5.63 | 0.00 | In progress | Eleventh Plan | Spill Over Acct | s | |
| 95 | Const. of Sang-Zingla Martam road KM 10th. | P.T. Rongong | State Plan | 14.51 | 0.00 | 14.51 | New Road | 6-Mar-03 | 6-Dec-03 | 100% | 12.45 | 12.45 | 0.00 | Final Payment | Eleventh Plan | Not in Both | s | |
| 96 | Const. of Song-Zingla Martam road km 11th | Anita Gurung | State Plan | 16.17 | 0.00 | 16.17 | New Road | 6-Mar-03 | 6-Dec-03 | 100% | 12.28 | 12.28 | 0.00 | Final Payment | Eleventh Plan | Not in Both | s | |
| 97 | Const. of Song-Zingla Martam road km 12th. | U. Lama | State Plan | 17.74 | 0.00 | 17.74 | New Road | 6-Mar-03 | 6-Dec-03 | 100% | 13.11 | 13.11 | 0.00 | Final Payment | Eleventh Plan | Not in Both | s | |
| 98 | Const.of Song-Zingla Martam road km 14th | Tenging Bhutia | State Plan | 25.54 | 0.00 | 25.54 | New Road | 6-Mar-03 | 6-Dec-03 | 75% | 19.63 | 19.63 | 0.00 | In progress | Eleventh Plan | Spill Over Acct | s | |
| 99 | Const. of Song-Zingla Martam road km 15th. | S.K.Chettri | State Plan | 26.75 | 0.00 | 26.75 | New Road | 6-Mar-03 | 6-Dec-03 | 95% | 19.95 | 19.95 | 0.00 | In progress | Eleventh Plan | Spill Over Acct | s | |