| DIVISION :
NORTH |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Sl.No |
Name
of Schemes |
Name
of Contractor |
Funding
Agency |
SANCTIONED AMOUNT |
Date
of Commencement |
Stipulated
Date of Completion |
Physical
Progress in % |
Financial
Progress |
Remarks |
|
|
|
|
| Total |
C.share |
S.
share |
(Head) |
Expenditure
till date |
|
|
|
|
| Total |
S.Share |
C.Share |
Work
Remrks |
Plan |
|
|
|
|
| |
CENTRAL SPONSORED
SCHEMES |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 1 |
Upgradation
Ranka - Luing-Gangtok-Burthuk-Road Km 14th to 21st |
Mr.
Shyam Rai |
NLCPR |
641.54 |
420.00 |
221.54 |
Expansion |
11-Jan-05 |
19-Jul-07 |
68% |
399.34 |
12.23 |
387.11 |
work
in progress |
Tenth
Plan |
Spill
Over Acct |
|
|
|
| 2 |
Construction
0f 90m span steel bridge over Takcham Chu along C.R.B.A Road, Km 21st |
Mrs.
Meera Rai |
NEC |
476.74 |
476.74 |
0.00 |
Expansion |
9-Jan-06 |
8-Oct-06 |
80% |
267.60 |
0.00 |
267.60 |
work
in progress |
Tenth
Plan |
Spill
Over Acct |
|
|
|
| 3 |
Upgradation
/ carpeting & extension i/c providing drainage and protective works of
Marchak - Tumlabong road, Km 1st to 13th in East Sikkim |
M/s
Ladakhi Const. Pvt. Ltd. |
NEC |
1,023.00 |
1,023.00 |
0.00 |
Expansion |
9-Nov-06 |
18-May-08 |
58% |
339.05 |
0.00 |
339.05 |
work
in progress |
Tenth
Plan |
Spill
Over Acct |
|
|
|
| 4 |
Construction
of steel bridge over Teesta river at Gour |
Mr.
Samdup Lepcha |
NEC |
488.57 |
488.57 |
0.00 |
NEC |
21-Jan-06 |
22-Jan-07 |
92% |
321.37 |
0.00 |
321.37 |
In
Progress |
Tenth
Plan |
Spill
Over Acct |
MPR |
|
|
| 5 |
Strengthening
/ drainage carpetting of SBS road to Tingbong high school |
Mr.
G.N. Agarwal |
NEC |
447.74 |
401.37 |
46.37 |
NEC |
29-Apr-05 |
30-Apr-06 |
100% |
316.14 |
0.00 |
316.14 |
Completed |
Tenth
Plan |
Spill
Over Acct |
MPR |
|
|
| 6 |
Construction
of Steel Bridge on Approach road to Khedum Village in North Sikkim. |
Mr.
Penzong Lachungpa |
NEC |
190.68 |
190.68 |
0.00 |
NEC |
24-Feb-06 |
23-Jan-07 |
92% |
116.98 |
0.00 |
116.98 |
In
Progress |
Tenth
Plan |
Spill
Over Acct |
MPR |
|
|
| 7 |
Upgradation
& Surface strengthening of Ranka-Sichey road Km 1st to 3rd |
Mr.
Rajesh Agarwal |
CRF |
119.05 |
88.26 |
30.79 |
Removal |
17-Mar-05 |
31-May-06 |
100% |
31.03 |
0.00 |
31.03 |
Final
Payment to be made |
Tenth
Plan |
Both |
Sub
Div - IV |
|
|
| 8 |
Upgradation
of Phodong -Labrang Gumpa |
Mr.
K.N. Bhutia |
CRF |
158.96 |
158.96 |
0.00 |
CRF |
3-Nov-05 |
2-Oct-06 |
100% |
118.77 |
0.00 |
118.77 |
Completed |
Tenth
Plan |
Spill
Over Acct |
MPR |
|
|
| 9 |
Construction
of 18 mtrs span Steel Bridge over Rakshey Khola along Penlong - Tintek road
at Km 13yh, CH: 1 |
- |
CRF |
90.99 |
90.99 |
0.00 |
CRF |
18-Oct-06 |
- |
- |
35.97 |
0.00 |
35.97 |
work
in progress |
Tenth
Plan |
Not
in Both |
|
|
|
| 10 |
Construction
of app. Road to Thomchi Gumpa. |
Mr.
Tashi Lachungpa |
BADP |
15.69 |
0.00 |
15.69 |
BADP |
6-Feb-07 |
5-May-07 |
10% |
10.00 |
0.00 |
10.00 |
Completed |
Tenth
Plan |
Spill
Over Acct |
MPR |
|
|
| 11 |
Construction
of new road from Gumpa Golai to Chanzing, Lachen. |
Mr
Nangden Lachungpa |
BADP |
38.10 |
38.10 |
0.00 |
BADP |
- |
- |
- |
0.00 |
0.00 |
0.00 |
work
in progress |
|
Spill
Over Acct |
MPR |
|
|
| 12 |
Construction
of approach road and parking for Gymnasium hall at Chungthang. |
|
BADP |
6.92 |
6.92 |
0.00 |
BADP |
- |
- |
- |
0.00 |
0.00 |
0.00 |
- |
|
Not
in Both |
MPR |
|
|
| 13 |
Upgradation
/ Strengthening and Carpeting of approach road to Latoong Village. |
Mr
Nangden Lachungpa |
BADP |
42.79 |
42.79 |
0.00 |
BADP |
- |
- |
40% |
0.00 |
0.00 |
0.00 |
work
in progress |
|
Spill
Over Acct |
MPR |
|
|
| 14 |
Construction
of Guest House / Inspection Bunglow at Yakthang, Lachen (Thangu). |
|
BADP |
138.00 |
138.00 |
0.00 |
BADP |
- |
- |
- |
0.00 |
0.00 |
0.00 |
- |
|
Not
in Both |
|
|
|
| 15 |
Extension
of Bakcha -Labi road Km 3rd & 4th. State share of BADP land compansation. |
Mr.
Ugen Nedup Bhutia |
BADP |
0.00 |
0.00 |
0.00 |
BADP |
- |
- |
100% |
0.00 |
0.00 |
0.00 |
Forest
compansation to be paid |
|
|
MPR |
|
|
| 16 |
Construction
of approach road to Thomchi Gumpa. |
|
BADP |
5.00 |
5.00 |
0.00 |
BADP |
- |
- |
10% |
0.00 |
0.00 |
0.00 |
|
|
|
|
|
|
| 17 |
Construction
of Link Road from Zimchung to Nampathang KM 1st to 3rd |
Mr.
Zingmee Ongda, Mr. Dawa.Lepcha, Mr. Choppel Tshering |
RSVY |
112.11 |
112.11 |
0.00 |
RSVY |
10-Nov-05 |
10-Nov-06 |
100% |
112.11 |
0.00 |
112.11 |
Completed |
Tenth
Plan |
Spill
Over Acct |
|
|
|
| 18 |
Construction
of Link Road from 3rd Mile Turning of Tintek Dikchu road to Rakshey via
Kedhangthang. Km 1st to 3rd. |
Punya
Prasad Dhakhal |
RSVY |
143.79 |
121.79 |
22.00 |
New
Road |
21-Oct-05 |
31-Jan-07 |
100% |
120.76 |
0.00 |
120.76 |
work
in progress |
Tenth
Plan |
Spill
Over Acct |
|
|
|
| 19 |
Construvction
of Link Road from Bay to Pentong in North Sikkim. |
Mr.
Bernald Lepcha |
RSVY |
187.45 |
150.00 |
37.45 |
New
Road |
22-Sep-05 |
21-Aug-06 |
65% |
128.03 |
0.00 |
128.03 |
In
Progress |
Tenth
Plan |
Spill
Over Acct |
MPR |
|
|
| 20 |
Upgradation
carpetting works of Chaten Khimten Village road in North Sikkim |
Mr.
Janam Lachen |
RSVY |
38.00 |
38.00 |
0.00 |
RSVY |
12-Sep-05 |
11-Aug-06 |
100% |
38.00 |
0.00 |
38.00 |
Completed |
Tenth
Plan |
Not
in Both |
|
|
|
| 21 |
Construction
of Heli Port at Lachung |
Mr.
Nidup Lachungpa |
CSS |
38.89 |
0.00 |
38.89 |
Tourism-800-Others
Exp-78(P) |
3-Apr-00 |
2-Jan-01 |
75% |
28.43 |
0.00 |
28.43 |
Defence
clearance not yet received |
Ninth
Plan |
Spill
Over Acct |
|
|
|
| 22 |
Protective
Drainage and Carpetting works on SBS Road Km 3 & 4 |
Mr.
Pintso Namgyal |
Central
plan Scheme |
27.19 |
27.19 |
0.00 |
- |
27-Nov-01 |
26-Feb-02 |
100% |
19.37 |
0.00 |
19.37 |
Completed |
Ninth
Plan |
|
|
|
|
| 23 |
Protective
Drainage and Carpetting works on SBS Road Km 5 & 6 |
Mr.
Karma Lepcha |
Central
plan Scheme |
23.38 |
23.38 |
0.00 |
- |
11-Jan-03 |
10-Oct-03 |
100% |
16.77 |
0.00 |
16.77 |
Completed |
Ninth
Plan |
|
|
|
|
| 24 |
Protective
Drainage and Carpetting works on SBS Road Km 7 |
Mr.
Ten Tsh. Lepcha |
Central
plan Scheme |
11.17 |
11.17 |
0.00 |
- |
27-Nov-01 |
26-Nov-02 |
100% |
7.17 |
0.00 |
7.17 |
Completed |
Ninth
Plan |
|
|
|
|
| 25 |
Protective
Drainage and Carpetting works on SBS Road Km 8 |
Mr.
Dupden Lepcha |
Central
plan Scheme |
22.48 |
22.48 |
0.00 |
- |
27-Nov-01 |
27-Nov-02 |
100% |
19.28 |
0.00 |
19.28 |
Completed |
Ninth
Plan |
|
|
|
|
| 26 |
Protective
Drainage and Carpetting works on SBS Road Km 9 |
Mr.
Pintso Lepcha |
Central
plan Scheme |
19.23 |
19.23 |
0.00 |
- |
27-Nov-01 |
28-Nov-02 |
100% |
18.21 |
0.00 |
18.21 |
Completed |
Ninth
Plan |
|
|
|
|
| 27 |
Widening
of upgradation, carpetting, protective of drainage wors on approach road to
Zimchung Busty from DAC road, Mangan |
Department. |
MP
(LAPS) |
25.00 |
25.00 |
0.00 |
- |
- |
- |
100% |
0.00 |
0.00 |
0.00 |
In
Progress |
|
Spill
Over Acct |
MPR |
|
|
| 28 |
Construction
of road from lower Lingdum to
Adampool, Km 3rd & 4th |
Mr.
Ajay Rai |
NABARD |
103.07 |
73.43 |
29.64 |
Expansion |
16-Nov-06 |
15-May-07 |
80% |
92.02 |
18.59 |
73.43 |
In
Progress |
Tenth
Plan |
Not
in Both |
|
|
|
| 29 |
Carpetting
of app. Road to Crematorium ground at Jalipool. |
Mr.
Praveen Agarwal |
NABARD |
31.80 |
20.66 |
11.14 |
Expansion |
31-Jan-06 |
15-Jun-06 |
100% |
30.01 |
9.35 |
20.66 |
Final
Payment to be made |
Tenth
Plan |
Both |
MPR |
|
|
| 30 |
Construction
of Link Road from Takchi Phatak to Upper Luing, Km 1st |
Mr.
Tsweang Rinzing Bhutia |
|
322.84 |
289.93 |
32.910 |
New
Road |
18-Aug-05 |
17-Aug-06 |
|
70.72 |
20.90 |
49.82 |
work
in progress |
Tenth
Plan |
Both |
|
|
|
| 31 |
Construction
of Link Road from Takchi Phatak to Upper Luing, Km 2 nd |
Dewjang
Bhutia |
NABARD |
New
Road |
18-Aug-05 |
17-Aug-06 |
5% |
Work
just started |
Tenth
Plan |
Both |
|
|
|
| 32 |
Construction
of Link Road from Takchi Phatak to Upper Luing, Km 3rd |
Tempo
Gyatso Bhutia |
NABARD |
New
Road |
23-Sep-05 |
22-Sep-06 |
25% |
Work
just started |
Tenth
Plan |
Both |
|
|
|
| 33 |
Construction
of Link Road from Takchi Phatak to Upper Luing, Km 4th |
Yangchen
Dolma Bhutia |
NABARD |
New
Road |
23-Sep-05 |
22-Sep-06 |
0% |
work
in progress |
Tenth
Plan |
Both |
|
|
|
| 34 |
Construction
of Link Road from Takchi Phatak to Upper Luing, Km 5th |
Yangchen
Dolma Bhutia |
NABARD |
New
Road |
23-Sep-05 |
22-Sep-06 |
0% |
work
in progress |
Tenth
Plan |
Both |
|
|
|
| |
WORKS SANCTIONED
UNDER STATE PLAN |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 35 |
Surface
renewal / restoration works on approach road to Mission Khoti. |
Mr.
Ugen palzor |
State
Plan |
32.79 |
0.00 |
32.79 |
Removal |
28-Feb-04 |
27-Aug-04 |
100% |
32.60 |
32.60 |
0.00 |
Final
Payment |
Tenth
Plan |
MPR |
Magan |
|
|
| 36 |
Premix
carpetting p/w approach road to Hee-Gyathang School. |
Department. |
State
Plan |
23.01 |
0.00 |
23.01 |
Removal |
- |
- |
100% |
19.99 |
19.99 |
0.00 |
Completed |
|
MPR |
Magan |
MPR |
|
| 37 |
Premix
carpeting on GRBA road KM 1st -10th (Phase I ) Revised |
Mr.
A.N. Upreti |
State
Plan |
215.65 |
0.00 |
215.65 |
Removal |
13-Jan-03 |
12-Jul-04 |
96% |
207.01 |
207.01 |
0.00 |
work
in progress |
Tenth
Plan |
MPR |
Sub
Div - IV |
MPR |
|
| 38 |
Premix
carpetting, improvement of GRBA road Km 18th to 21st and Assam Pakyong Road
Km 1st to 6th. |
Mr.
Amrit Rai |
State
Plan |
254.76 |
0.00 |
254.76 |
Removal |
25-Aug-04 |
31-Mar-06 |
100% |
184.20 |
184.20 |
0.00 |
Final
Payment to be made |
Tenth
Plan |
Both |
Sub
Div - IV |
MPR |
|
| 39 |
Uplifting
& Surface & Drainage works, improvement along approach road to Sichey
school. |
Mr.
Rohit Pradhan |
State
Plan |
3.77 |
0.00 |
3.77 |
Removal |
27-Feb-06 |
29-Dec-06 |
100% |
0.00 |
3.03 |
0.00 |
Final
Payment to be made |
Tenth
Plan |
MPR |
Sub
Div - IV |
|
|
| 40 |
Upgradation
& Surface strengthening of Ranka-Sichey road Km 1st to 3rd |
Mr.
Rajesh Agarwal |
CRF |
119.05 |
88.26 |
30.79 |
Removal |
17-Mar-05 |
31-May-06 |
100% |
31.03 |
0.00 |
31.03 |
Final
Payment to be made |
Tenth
Plan |
Both |
Sub
Div - IV |
|
|
| 41 |
Upgradation
of Marchak Tumlabong Road (NEC ) State Share for LC |
Compensatiion |
State
Plan |
100.00 |
0.00 |
100.00 |
Removal |
- |
- |
37% |
37.00 |
37.00 |
0.00 |
work
in progress |
|
MPR |
Sub
Div - IV |
|
|
| 42 |
Upgradation
and Imp of Rumtek Ranka road Km 18th |
Department. |
State
Plan |
1.36 |
0.00 |
1.36 |
Removal |
- |
- |
0% |
0.00 |
0.00 |
0.00 |
work
in progress |
|
MPR |
Sub
Div - IV |
|
|
| 43 |
Construction
of 15 mtrs span RCCl Bridge over Khedum Chu |
Gyatso
Bhutia |
State
Plan |
20.72 |
0.00 |
20.72 |
Removal |
12-Nov-98 |
11-Mar-99 |
100% |
19.36 |
19.36 |
0.00 |
|
Ninth
Plan |
Not
in Both |
Magan |
|
|
| 44 |
Land
Compensation for the work construction of Multi Span Bridge over River Teesta
at Gour at Dzongu |
LC |
State
Plan |
6.84 |
0.00 |
6.84 |
Removal |
- |
- |
100% |
6.62 |
6.62 |
0.00 |
|
|
Not
in Both |
Magan |
|
|
| 45 |
Construction
of 55m Supension Bridge over Khedumcu at Lachung |
Needup
Lacungpa |
State
Plan |
112.31 |
0.00 |
112.31 |
Removal |
12-Nov-98 |
11-Jul-99 |
100% |
100.09 |
100.09 |
0.00 |
Copansation
Remaining |
Ninth
Plan |
Not
in Both |
Magan |
|
|
| 46 |
Premix
carpetting,on Penlong - Tintek road Km 12th - 20th |
Mr.
Suresh Mundra |
State
Plan |
158.79 |
0.00 |
158.79 |
Expansion |
28-Nov-02 |
31-Mar-06 |
100% |
99.64 |
99.64 |
0.00 |
Final
bill to be paid |
Tenth
Plan |
Both |
Magan |
|
|
| 47 |
Upgradation
Ranka - Luing-Gangtok-Burthuk-Road Km 14th to 21st |
Mr.
Shyam Rai |
NLCPR |
641.54 |
420.00 |
221.54 |
Expansion |
11-Jan-05 |
19-Jul-07 |
68% |
399.34 |
12.23 |
387.11 |
work
in progress |
Tenth
Plan |
Spill
Over Acct |
|
|
|
| 48 |
Construction
of road from lower Lingdum to
Adampool, Km 3rd & 4th |
Mr.
Ajay Rai |
NABARD |
103.07 |
73.43 |
29.64 |
Expansion |
16-Nov-06 |
15-May-07 |
80% |
92.02 |
18.59 |
73.43 |
In
Progress |
Tenth
Plan |
Not
in Both |
|
|
|
| 49 |
Carpetting
of app. Road to Crematorium ground at Jalipool. |
Mr.
Praveen Agarwal |
NABARD |
31.80 |
20.66 |
11.14 |
Expansion |
31-Jan-06 |
15-Jun-06 |
100% |
30.01 |
9.35 |
20.66 |
Final
Payment to be made |
Tenth
Plan |
Both |
|
|
|
| 50 |
Adjustment
of STCS bill for the work Carpeting at Chandey Golai |
- |
State
Plan |
- |
- |
- |
Expansion |
- |
- |
100% |
0.50 |
0.50 |
0.00 |
- |
|
Not
in Both |
|
|
|
| 51 |
Const. of GOR Santok road Km.
1st |
Mr.Pentok
Lepcha |
State
Plan |
29.76 |
0.00 |
29.76 |
Expansion |
|
|
100% |
21.61 |
21.61 |
0.00 |
Completed |
|
Not
in Both |
|
|
|
| 52 |
Construction
of link road to Aho - Manghim Km 1st |
Mr.
B.K. Upreti |
State
Plan |
16.88 |
0.00 |
16.88 |
Link
Road |
2-Dec-04 |
15-Jan-07 |
94% |
|
|
|
work
in progress |
Tenth
Plan |
|
|
|
|
| 53 |
Const.
of link road to Aho - Manghim Km 2nd |
Mr.
K. Vijayan |
State
Plan |
18.88 |
0.00 |
18.88 |
Link
Road |
2-Dec-04 |
15-Jan-07 |
15% |
11.37 |
11.37 |
0.00 |
delayed
due to land compensation |
Tenth
Plan |
|
|
|
|
| 54 |
Const.
of link road to Aho - Manghim Km 3 rd |
Mr.
K. Vijayan |
State
Plan |
19.27 |
0.00 |
19.27 |
Link
Road |
1-Dec-04 |
15-Jan-07 |
2% |
|
|
|
work
in progress |
Tenth
Plan |
|
|
|
|
| 55 |
Construction
of app. Road from Samdong Cha Chu to Yumi Samdong, north Sikkim. Km 1st &
2nd |
Mr.
T. Doma Lachungpa |
State
Plan |
54.48 |
0.00 |
54.48 |
New
Road |
21-Jun-04 |
20-Dec-05 |
36% |
31.57 |
31.57 |
0.00 |
In
Progress |
Tenth
Plan |
Both |
|
|
|
| 56 |
Construction
of Rest House at Samdong in East Sikkim. |
Mr.
Nitup Lepcha |
Addl.Facilities |
78.70 |
0.00 |
78.70 |
Addl.Facilities |
20-May-03 |
19-Apr-04 |
100% |
75.44 |
75.44 |
0.00 |
Completed,
Final bill paid |
Tenth
Plan |
Both |
|
|
|
| 57 |
Approach
Road to Samdong Rest House at Samdong East Sikkim |
Mr.
Dorjee Choppel |
State
Plan |
14.04 |
0.00 |
14.04 |
Addl.Facilities |
20-May-03 |
19-Apr-04 |
100% |
14.04 |
14.04 |
0.00 |
Completed |
Tenth
Plan |
|
|
|
|
| 58 |
Upgradation,carpetting,
protective and drainage of SBS road to Lingtam PHSE Km 1st to 5th. |
Mr.
Samdup Lepcha |
State
Plan |
385.54 |
0.00 |
385.54 |
Strengthning
Road Infrastructure |
- |
- |
20% |
42.22 |
42.22 |
0.00 |
work
in progress |
|
Spill
Over Acct |
MPR |
|
|
| 59 |
Upgradation,carpetting,
protective and drainage works of DSM road to Gour School Km 1st to 8th. |
Mr.
Soden Gyamptso Bhutia |
State
Plan |
391.66 |
0.00 |
391.66 |
Strengthning
Road Infrastructure |
1-Jun-08 |
1-Jan-09 |
25% |
57.78 |
57.78 |
0.00 |
work
in progress |
Eleventh
Plan |
|
MPR |
|
|
| 60 |
Extension
of Link Road from Gangtok-Rumtek-Sang Road Km 12th Ch: 7 to Tatopani Rumtek
Road. |
- |
State
Plan |
10.05 |
0.00 |
10.05 |
Link
Road |
2007 |
- |
5% |
0.00 |
0.00 |
0.00 |
work
in progress |
Tenth
Plan |
|
|
|
|
| 61 |
Additional
sanction for Land Comensation for the work ' Construction of Link Road Km 1st
to 3rd from Ranipool-Pakyong Road to Mangheem at Aho. |
Land Compensation |
State
Plan |
42.02 |
0.00 |
42.02 |
Link
Road |
2007 |
- |
- |
25.00 |
25.00 |
0.00 |
- |
Tenth
Plan |
|
|
|
|
| 62 |
Construction
of Rest House at Samdong in East Sikkim. |
Mr.
Nitup Lepcha |
Addl.Facilities |
78.70 |
0.00 |
78.70 |
Addl.Facilities |
20-May-03 |
19-Apr-04 |
100% |
75.44 |
75.44 |
0.00 |
Completed,
Final bill paid |
Tenth
Plan |
Both |
|
|
|
| 63 |
Construction
of Guest House at Pentok, Mangan, North Sikkim. |
- |
Addl.Facilities |
187.08 |
0.00 |
187.08 |
Addl.Facilities |
2006 |
- |
- |
0.00 |
0.00 |
0.00 |
|
Tenth
Plan |
MPR |
|
|
|
| 64 |
Premix
Carpetting imp & widening of D.S.M road km 1st -8th |
Songden
Gyamtso Bhutia |
State
Plan |
391.66 |
0.00 |
391.66 |
Strengthening
Road Infrastructure In Dzongu |
1-Feb-08 |
1-Jan-09 |
15% |
57.78 |
57.78 |
0.00 |
work
in progress |
Eleventh
Plan |
|
|
Earlier it was at expansion |
MPR |
| 65 |
Strengthening
Carpeting and P/W on Lingtam to Lindem Road Km 1st-5th |
Samdup
Lepcha |
State
Plan |
385.54 |
0.00 |
385.54 |
Strengthening
Road Infrastructure In Dzongu |
- |
- |
11% |
42.22 |
42.22 |
0.00 |
work
in progress |
Tenth
Plan |
|
|
|
|
| 66 |
Widening
protective work drainage & carpetting work on S.B.S Road Km 10th |
Mr.
Lobzang Lepcha |
State
Plan |
17.11 |
0.00 |
17.11 |
TSP |
15-Nov-03 |
14-Aug-04 |
73% |
6.36 |
6.36 |
0.00 |
Carpetting
work to be done. |
Tenth
Plan |
Spill
Over Acct |
MPR |
|
|
| 67 |
Widening
protective work drainage & carpetting work on S.B.S Road Km 12th |
" |
State
Plan |
18.86 |
0.00 |
18.86 |
TSP |
15-Nov-03 |
14-Aug-04 |
72% |
8.63 |
8.63 |
0.00 |
Carpetting
work to be done. |
Tenth
Plan |
Spill
Over Acct |
MPR |
|
|
| 68 |
Widening
protective work drainage & carpetting work on S.B.S Road Km 13th |
Mr.
Sonam Dorjee |
State
Plan |
18.86 |
0.00 |
18.86 |
TSP |
18-Nov-04 |
17-May-05 |
70% |
0.73 |
0.73 |
0.00 |
WBM/carpetting
work to be done |
Tenth
Plan |
Spill
Over Acct |
MPR |
|
|
| 69 |
Widening
protective work drainage & carpetting work on S.B.S Road Km 14th |
Mr.
Topnam Lepcha |
State
Plan |
19.76 |
0.00 |
19.76 |
TSP |
11-Jan-03 |
10-Oct-03 |
80% |
10.24 |
10.24 |
0.00 |
Carpetting
work to be done. |
Tenth
Plan |
Spill
Over Acct |
MPR |
|
|
| 70 |
Widening
protective work drainage & carpetting work on S.B.S Road Km 15th |
" |
State
Plan |
15.35 |
0.00 |
15.35 |
TSP |
11-Jan-03 |
10-Oct-03 |
80% |
9.23 |
9.23 |
0.00 |
Carpetting
work to be done. |
Tenth
Plan |
Spill
Over Acct |
MPR |
|
|
| 71 |
Strengthening,
protective / drainage carpetting works on approach road to Ringtham Gumpa
Km1st to 3rd Mangan. |
K.N.
Lachenpa |
State
Plan |
276.00 |
0.00 |
276.00 |
TSP |
- |
- |
30% |
11.51 |
11.51 |
0.00 |
work
in progress |
|
Spill
Over Acct |
MPR |
|
|
| 72 |
Construction
approach road to medicine pond B-6 |
Tempo
Lepcha |
State
Plan |
105.00 |
0.00 |
105.00 |
TSP |
- |
- |
10% |
11.03 |
11.03 |
0.00 |
work
in progress |
|
Spill
Over Acct |
MPR |
|
|
| 73 |
Construction
approach road to Shakothang at Sarchok village |
Dawa
Gaytmso Lachenpa |
State
Plan |
64.98 |
0.00 |
64.98 |
TSP |
- |
- |
- |
3.27 |
3.27 |
0.00 |
Delayed
due to land compensation |
|
Spill
Over Acct |
MPR |
|
|
| 74 |
Premix
Carpetting imp & widening of D.S.M road km 12th to 16th |
Mr.
Singhik Lepcha |
State
Plan |
124.05 |
0.00 |
124.05 |
TSP |
15-Jan-03 |
14-Jul-04 |
80% |
71.89 |
71.89 |
0.00 |
In
Progress |
Tenth
Plan |
Spill
Over Acct |
MPR |
|
|
| 75 |
Premix
Carpetting imp & widening of D.S.M road km 17th |
Mr.
Chewang Norbu |
State
Plan |
19.41 |
0.00 |
19.41 |
TSP |
11-Jan-03 |
10-Oct-03 |
100% |
9.93 |
9.93 |
0.00 |
Final
Payment |
Tenth
Plan |
Spill
Over Acct |
MPR |
|
|
| 76 |
Premix
Carpetting imp & widening of D.S.M road km 18th |
Mr. Dawa Tshering |
State
Plan |
19.56 |
0.00 |
19.56 |
TSP |
11-Jan-03 |
10-Oct-03 |
85% |
15.10 |
15.10 |
0.00 |
work
in progress |
Tenth
Plan |
Spill
Over Acct |
MPR |
|
|
| 77 |
Premix
Carpetting imp & widening of D.S.M road km 19th |
Mr.
Ongden lepcha |
State
Plan |
20.44 |
0.00 |
20.44 |
TSP |
11-Jan-03 |
10-Oct-03 |
73% |
10.59 |
10.59 |
0.00 |
work
in progress |
Tenth
Plan |
Spill
Over Acct |
MPR |
|
|
| 78 |
Premix
Carpetting imp & widening of D.S.M road km 20th |
Mr.
Mingma Tshering |
State
Plan |
20.04 |
0.00 |
20.04 |
TSP |
11-Jan-03 |
10-Oct-03 |
74% |
14.12 |
14.12 |
0.00 |
In
Progress |
Tenth
Plan |
Spill
Over Acct |
MPR |
|
|
| 79 |
Premix
Carpetting imp & widening of D.S.M road km 21st |
Mr.
Lobzang Lepcha |
State
Plan |
23.38 |
0.00 |
23.38 |
TSP |
11-Jan-03 |
10-Oct-03 |
75% |
18.07 |
18.07 |
0.00 |
In
Progress |
Tenth
Plan |
Spill
Over Acct |
MPR |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|