| MONTHLY PHYSICAL AND FINANCIAL PROGRESS REPORT FOR THE MONTH ENDING JANUARY 2010 | ||||||||||||||||||||||||||||
| Sl.No | Name of Schemes | Length Km / M | Name of Contractor | Plan | Funding Agency | (Head) | SANCTIONED AMOUNT | Date of Commen- cement | Stipulated Date of Completion | Phy Prog-ress in % | Financial Progress | Balance | TOTAL SA-BAL | Remarks | ||||||||||||||
| S. share | C.share | Total | Expenditure till date | |||||||||||||||||||||||||
| S.Share | C.Share | Total | S.Share | C.Share | Total | |||||||||||||||||||||||
| D | DISTRICT : WEST | |||||||||||||||||||||||||||
| CENTRAL SPONSORED SCHEMES | ||||||||||||||||||||||||||||
| 1 | Restoration of damages, Slip clearence, Drainage &surface improvement works of Geythang-Karmatar road, Singshore diversion road and Utterey-Sopakha road in West Sikkim. | Kaluk | 2 Km | P.K.Subba | BADP | - | 0.00 | 301.86 | 301.86 | 1-Nov-08 | 31-Oct-09 | 50% | 0.00 | 110.00 | 110.00 | 0.00 | 191.86 | 191.86 | 191.86 | Work in progress | Kaluk | UPGRADATION | ROAD | 2 | KM | |||
| 2 | Construction of link road from Legship-Gyalsing road km 13th to Bhanu Sailik Km 1st-2nd. | Geyzing | 2Km | Karna Nanda Subedi | - | CRF | Link Road | 5.61 | 220.11 | 225.72 | 8-Mar-08 | 9-Dec-09 | 60% | 5.61 | 30.00 | 35.61 | 0.00 | 190.11 | 190.11 | 190.11 | Work in progress | Geyzing | CONSTRUCTION | ROAD | 2 | KM | ||
| 3 | Surface improvement and strengthening and premix carpetting of Rimbi Yoksum road Km 1st to 21.70. | Geyzing | 21.70 Km | Mr. K. N. Bhutia | Tenth Plan | EI | Remv. | 96.11 | 219.37 | 315.48 | 7-Feb-04 | 6-Aug-05 | 89% | 54.51 | 219.37 | 273.88 | 41.60 | 0.00 | 41.60 | 41.60 | Work in progress | Geyzing | UPGRADATION | ROAD | 21.7 | KM | ||
| 4 | Construction of road from Salangdang to Ramnam River connecting Lodhama (West Bengal) in West Sikkim. (Part -I) | D.P Deokota | ISC | New Road | 0.00 | 869.00 | 869.00 | April, 09 | Oct, 11 | 15% | 0.00 | 0.00 | 0.00 | 0.00 | 869.00 | 869.00 | 869.00 | Trece cutting started | Soreng | CONSTRUCTION | ROAD | 2 | KM | |||||
| 5 | Construction of road from Salangdang to Ramnam River connecting Lodhama (West Bengal) in West Sikkim in steel bridges excluding steel parts (Part -II) | D.P Deokota | ISC | New Road | 0.00 | 569.00 | 569.00 | April, 09 | Oct, 11 | 0% | 0.00 | 0.00 | 0.00 | 0.00 | 569.00 | 569.00 | 569.00 | Work to be started | Soreng | CONSTRUCTION | ROAD | 2 | KM | |||||
| 6 | App. Road to Rincheypong Gompa / Shreda from Rinchepong Dak Bunglow Road (Km 1st ch 17th ) | Kaluk | 1.1Km | Mr. D. Lachi Bhutia | Tenth Plan | MP LADS | - | 0.00 | 15.00 | 15.00 | 16-Feb-06 | 15-Feb-08 | 89% | 0.00 | 9.90 | 9.90 | 0.00 | 5.10 | 5.10 | 5.10 | Work in progress | Kaluk | UPGRADATION | ROAD | 0.12 | KM | ||
| 7 | Upgradation of existing Soreng Kaluk Road from Km 1st - 5th (Part - I) | Kaluk | 5 Km | Subash Tamang | NABARD | Remv. | 0.00 | 373.00 | 373.00 | Feb, 09 | Aug, 10 | 9% | 0.00 | 0.00 | 0.00 | 0.00 | 373.00 | 373.00 | 373.00 | Work in progress | Soreng | UPGRADATION | ROAD | 5 | KM | |||
| 8 | Upgradation of existing Soreng Kaluk Road from Km 6th - 16th (Part -II) | Kaluk | 10 Km | S.B. Gurung | NABARD | Remv. | 0.00 | 893.00 | 893.00 | March,09 | March,11 | 24% | 0.00 | 0.00 | 0.00 | 0.00 | 893.00 | 893.00 | 893.00 | Work in progress | Soreng | UPGRADATION | ROAD | 10 | KM | |||
| 9 | Upgradation of existing Chankung Gelling Road from Km 1st - 3rd(Part - I) | Kaluk | 3 Km | Mahindra Lakhotia | NABARD | - | 0.00 | 291.00 | 291.00 | March,09 | March,11 | 30% | 0.00 | 0.00 | 0.00 | 0.00 | 291.00 | 291.00 | 291.00 | Work in progress | Soreng | UPGRADATION | ROAD | 3 | KM | |||
| 10 | Upgradation of existing Chankung Gelling Road from Km 4th-7th(Part -II) | Kaluk | 4 Km | Sanjay Chandak | NABARD | - | 0.00 | 288.00 | 288.00 | March,09 | March,11 | 30% | 0.00 | 0.00 | 0.00 | 0.00 | 288.00 | 288.00 | 288.00 | Work in progress | Soreng | UPGRADATION | ROAD | 4 | KM | |||
| 11 | Carpetting drainage & protective works of approach road from hee pool to Hee Yangthang Sr. Sec School in West Sikkim. | Kaluk | 4 Km | Kundan Limboo | NABARD | - | 11.35 | 56.77 | 68.12 | 17-Mar-09 | 16-Sep-10 | 20% | 0.00 | 0.00 | 0.00 | 11.35 | 56.77 | 68.12 | 68.12 | Work in progress | Soreng | UPGRADATION | ROAD | 4 | KM | |||
| 12 | Strengthening, widening premix carpetting works along Pelling Chumbung Road Km 1st - 4th. | Kaluk | 4 Km | P.C. Lama | NABARD | Exp. | 51.13 | 194.87 | 246.00 | 3-Oct-09 | 9-Sep-10 | 25% | 0.00 | 11.35 | 11.35 | 51.13 | 183.52 | 234.65 | 234.65 | Work in progress | Geyzing | UPGRADATION | ROAD | 4 | KM | |||
| 13 | Construction of link road from Alpinne Cheese factory at kaluk Dentam Road km 19th ch 8th - Lidung Village under Dentam Consituency in West-Sikkim (Km 2nd Ch 3) | Kaluk | 4 Km | Sabitri Thapa | NABARD | - | 0.00 | 56.76 | 56.76 | 6-Feb-09 | 6-Dec-09 | 15% | 0.00 | 0.00 | 0.00 | 0.00 | 56.76 | 56.76 | 56.76 | Work in progress | Geyzing | CONSTRUCTION | ROAD | 4 | KM | |||
| 14 | Construction of strengthening draianage & carpetting of Chakung-Khanisherbong road Km 1st -11th. | Soreng | 11Km | Mr. B. L. Gurung | Eleventh Plan | NEC | - | 0.00 | 486.36 | 486.36 | 3-Mar-07 | 9-Sep-08 | 34% | 0.00 | 227.44 | 227.44 | 0.00 | 258.92 | 258.92 | 258.92 | Work in progress | Soreng | CONSTRUCTION | ROAD | 11 | KM | ||
| 15 | Strengthening draianage & carpetting of Sombaria Hilley road Km 1st- 26th | Soreng | 26Km | Mr. Kamal Kr. Rai | Tenth Plan | NEC | - | 0.00 | 845.68 | 845.68 | 1-Nov-06 | 10-Oct-08 | 90% | 0.00 | 317.22 | 317.22 | 0.00 | 528.46 | 528.46 | 528.46 | Work in progress | Soreng | UPGRADATION | ROAD | 26 | KM | ||
| 16 | Strengthening and carpetting, protection and drainage of Bermiock Legship road Km. 1st to 9th | Kaluk | 9Km | Mr. Atul Dhanotia | Tenth Plan | NEC | - | 0.00 | 449.46 | 449.46 | 16-Feb-06 | 15-Feb-08 | 89% | 0.00 | 278.44 | 278.44 | 0.00 | 171.02 | 171.02 | 171.02 | Work pending due to non avaibility of bitumen | Kaluk | UPGRADATION | ROAD | 9 | KM | ||
| 17 | Extension of road from Chakung to Khansirbong SPWD road to Majwa village via chota Samdong 3km length along with 2 nos RCC bridge in West Sikkim. | Kaluk | 9Km | Bikash Tamang | Tenth Plan | NLCPR | - | 0.00 | 279.00 | 279.00 | - | - | 0% | 0.00 | 0.00 | 0.00 | 0.00 | 279.00 | 279.00 | 279.00 | Work to be started | Kaluk | CONSTRUCTION | ROAD | 9 | KM | ||
| 18 | Construction of road from Sreebadam to Magalbaria 18.30Km in West-Sikkim. | Geyzing | 18.30 Km | Norden Bhutia | NLCPR | - | 0.00 | 279.00 | 279.00 | - | - | 20% | 0.00 | 0.00 | 0.00 | 0.00 | 279.00 | 279.00 | 279.00 | Work in progress | Soreng | CONSTRUCTION | ROAD | 18.3 | KM | |||
| 19 | Repalacement of Rathong Suspension bridge by steel bridge on Rimbi-Yoksum road. | Geyzing | 60m | Mrs. S. Dolma Bhutia | Tenth Plan | NLCPR | - | 0.00 | 327.57 | 327.57 | 2-Jun-05 | 31-Aug-06 | 100% | 0.00 | 305.31 | 305.31 | 0.00 | 22.26 | 22.26 | Work in progress | Geyzing | UPGRADATION | ROAD | 60 | M | |||
| 20 | Repalacement of Rimbi Suspension bridge by steel bridge on Pelling - Rimbi road. | Geyzing | 45m | Mr. Keshav Pradhan | Tenth Plan | NLCPR | - | 2-Jun-05 | 31-Aug-06 | 91% | Work in progress | Geyzing | UPGRADATION | BRIDGE | 45 | M | ||||||||||||
| 21 | Construction of premix carpetting /imp. Dentam Uttrey road Km 1st to 10th | Kaluk | 10Km | Mr. C.B. Subba | Tenth Plan | NLCPR | - | 0.00 | 342.46 | 342.46 | 3-Mar-05 | 31-Aug-06 | 97% | 0.00 | 282.49 | 282.49 | 0.00 | 59.97 | 59.97 | 59.97 | Work in progress | Kaluk | CONSTRUCTION | ROAD | 10 | KM | ||
| 22 | Replacement of B.B. Lal Suspension Bridge on Pelling Dentam road along Gyalshing Soreng Road. | Kaluk | 68m | Mr. Mahabir Pd. Agarwal | Tenth Plan | NLCPR | - | 0.00 | 158.26 | 158.26 | 3-Mar-05 | 31-Aug-06 | 97% | 0.00 | 157.55 | 157.55 | 0.00 | 0.71 | 0.71 | 0.71 | Work in progress | Kaluk | UPGRADATION | BRIDGE | 68 | M | ||
| 23 | Construction of prestressed bridge over Rangit River on Legship-Tashiding road. | Geyzing | Mahabir Pd. Agarwal | Eleventh Plan | NLCPR | Remv. | 273.03 | 1638.18 | 1,911.21 | 9-Mar-09 | 8-Mar-11 | 5% | 0.00 | 273.03 | 273.03 | 273.03 | 1,365.15 | 1,638.18 | 1,638.18 | Work in progress | Geyzing | CONSTRUCTION | BRIDGE | 55 | M | |||
| 24 | Construction of 65m Span Steel Bridge over Rangit river in between Mengnem & Phamtam | Geyzing | 65m | Mr. U. P. Bhutia (Kazi) | Tenth Plan | RSVY | Repl. | 123.85 | 148.93 | 272.78 | 23-Nov-05 | 22-May-07 | 60% | 29.13 | 136.56 | 165.69 | 94.72 | 12.37 | 107.09 | 107.09 | Work in progress | Geyzing | CONSTRUCTION | BRIDGE | 65 | M | ||
| 25 | Surface imp/ carpetting i/c drainage works on Pelling Dentam road Km 1st to 9th | Kaluk | 9Km | Mr. Anjani Kr. Agarwal | Tenth Plan | NLCPR | - | 104.82 | 1,250.95 | 1,355.77 | 3-Mar-05 | 31-Aug-06 | 97% | 70.79 | 1,045.24 | 1,116.03 | 34.03 | 205.71 | 239.74 | 239.74 | Work pending due to non avaibility of bitumen | Kaluk | UPGRADATION | ROAD | 9 | KM | ||
| 26 | Surface imp/ carpetting i/c drainage works on Pelling Dentam road Km 10th to 17th. | Kaluk | 7Km | Mr. Mahabir Pd. Agarwal | Tenth Plan | NLCPR | - | 3-Mar-05 | 31-Aug-06 | 93% | 0.00 | Kaluk | UPGRADATION | ROAD | 7 | KM | ||||||||||||
| 27 | Surface imp/ carpetting i/c drainage works on Pelling Dentam road Km 18th to 20th | Kaluk | 2Km | CB Subba | Tenth Plan | NLCPR | - | 3-Mar-05 | 31-Aug-06 | 100% | 0.00 | Work completed | Kaluk | UPGRADATION | ROAD | 2 | KM | |||||||||||
| STATE PLAN | ||||||||||||||||||||||||||||
| 28 | Slope stablization, slip aressting & benching works, permanent restoration, catch water drain works at Gundrukey on Legship-Tashiding road. | Daramdin | Sandeep Kr. Sharma | Eleventh Plan | ACA | ACA | 115.00 | 0.00 | 115.00 | 13-Feb-09 | 12-Feb-10 | 61% | 1.88 | 0.00 | 1.88 | 113.12 | 0.00 | 113.12 | 113.12 | Work in progress | Geyzing | UPGRADATION | ROAD | 1 | KM | |||
| 29 | Slope stablization, slip aressting & benching works, permanent restoration, catch water drain works at Nauley Bhir on Gyalshing Pelling road and protgection of Class IV Govt. Qtr near mechanical turning on Gyalshing-Pelling road. | Geyzing | Deepak Kr. Pradhan | Eleventh Plan | ACA | ACA | 200.00 | 0.00 | 200.00 | 12-Feb-09 | 12-Feb-10 | 0% | 0.00 | 0.00 | 0.00 | 200.00 | 0.00 | 200.00 | 200.00 | Work not yet started | Geyzing | UPGRADATION | ROAD | 1 | KM | |||
| 30 | Slope stablization, restoration of road at Ringyang and Mandu on Tashiding-Kongree Labdong road. | Geyzing | Bikash Subedi | Eleventh Plan | ACA | ACA | 350.00 | 0.00 | 350.00 | 2-Mar-09 | 30-Nov-09 | 5% | 0.00 | 0.00 | 0.00 | 350.00 | 0.00 | 350.00 | 350.00 | Work in progress | Geyzing | UPGRADATION | ROAD | 1 | KM | |||
| 31 | Slope stablization & benching works, GEO grid netting permanent restoration, catch water drain works at Rimbi-Kchepadi road | Daramdin | Tara Sharma | Eleventh Plan | ACA | ACA | 184.96 | 0.00 | 184.96 | 20-Apr-09 | 19-Feb-10 | 80% | 0.00 | 0.00 | 0.00 | 184.96 | 0.00 | 184.96 | 184.96 | Work in progress | Geyzing | UPGRADATION | ROAD | 1 | KM | |||
| 32 | Slope stablization & slip aressting & benching works, permanent restoration, catch water drain works 12 mile slide on Rimbi-Yoksum road | Daramdin | D.K Pradhan | Eleventh Plan | ACA | ACA | 135.86 | 0.00 | 135.86 | 15-Jun-09 | 14-Mar-10 | 15% | 0.00 | 0.00 | 0.00 | 135.86 | 0.00 | 135.86 | 135.86 | Work in progress | Geyzing | UPGRADATION | ROAD | 1 | KM | |||
| 33 | Construction of motorable road from Relli Khola to Phamtam Km 14th - 17th. | Geyzing | 3Km | Mr. K.N.Bhutia | Tenth Plan | State Plan | New Road | 125.19 | 0.00 | 125.19 | 4-Mar-03 | 1-Mar-04 | 85.5% | 111.05 | 0.00 | 111.05 | 14.14 | 0.00 | 14.14 | 14.14 | Work in progress | Geyzing | CONSTRUCTION | ROAD | 3 | KM | ||
| 34 | Construction of motorable road from Relli Khola to Phamtam Km 18th-21st. | Geyzing | 3Km | Mr. A.P. Pradhan | Tenth Plan | State Plan | New Road | 131.74 | 0.00 | 131.74 | 4-Mar-03 | 1-Mar-04 | 99% | 121.25 | 0.00 | 121.25 | 10.49 | 0.00 | 10.49 | 10.49 | Work in progress | Geyzing | CONSTRUCTION | ROAD | 3 | KM | ||
| 35 | Construction of road from Upper Rumbuk to Tereybair in West Sikkim Km 3rd. | Soreng | 1Km | Mr. Phurdiki Sherpa | Tenth Plan | State Plan | New Road | 24.73 | 0.00 | 24.73 | 1-Jan-05 | 4-Apr-06 | 85% | 20.13 | 0.00 | 20.13 | 4.60 | 0.00 | 4.60 | 4.60 | Work in progress | Soreng | CONSTRUCTION | ROAD | 1 | KM | ||
| 36 | Construction of road from Upper Rumbuk to Tereybair in West Sikkim Km 4th. | Soreng | 1Km | Mr. Lakpa Sherpa | Tenth Plan | State Plan | New Road | 22.36 | 0.00 | 22.36 | 1-Jan-05 | 4-Apr-06 | 70% | 19.56 | 0.00 | 19.56 | 2.80 | 0.00 | 2.80 | 2.80 | Soreng | CONSTRUCTION | ROAD | 1 | KM | |||
| 37 | Construction of road from Upper Rumbuk to Tereybair in West Sikkim Km 5th. | Soreng | 1Km | Mr. Lakpa Sherpa | Tenth Plan | State Plan | New Road | 24.45 | 0.00 | 24.45 | 1-Jan-05 | 4-Apr-06 | 85% | 20.05 | 0.00 | 20.05 | 4.40 | 0.00 | 4.40 | 4.40 | Work in progress | Soreng | CONSTRUCTION | ROAD | 1 | KM | ||
| 38 | Construction of road from Upper Rumbuk to Tereybair in West Sikkim Km 6th. | Soreng | 1Km | Mr. Lakpa Sherpa | Tenth Plan | State Plan | New Road | 22.75 | 0.00 | 22.75 | 1-Jan-05 | 4-Apr-06 | 80% | 15.00 | 0.00 | 15.00 | 7.75 | 0.00 | 7.75 | 7.75 | Soreng | CONSTRUCTION | ROAD | 1 | KM | |||
| 39 | Construction of 1.60 Km approach road to 50m Span Steel BridgeOver Rangit river at Phamtam | Geyzing | 1.6 Km | Departmental | - | State Plan | New Road | 149.03 | 0.00 | 149.03 | 01-Jun-08 | 01-Mar-09 | 28% | 32.32 | 0.00 | 32.32 | 116.71 | 0.00 | 116.71 | 116.71 | Work in progress | Geyzing | CONSTRUCTION | ROAD | 1.6 | KM | ||
| 40 | Construction of approach road to Phamtam road point to 50m Span Steel BridgeOver Rangit river. | Geyzing | 50m | Departmental | - | State Plan | New Road | 37.52 | 0.00 | 37.52 | 10-Jun-08 | 02-Mar-09 | 98.5% | 29.67 | 0.00 | 29.67 | 7.85 | 0.00 | 7.85 | 7.85 | Work in progress | Geyzing | CONSTRUCTION | ROAD | 50 | M | ||
| 41 | Providing breast wall along approach road tolower Rumbuk School from Saili Gaon Km 1st Ch 21 | Geyzing | 50m | Sukmit Lepcha | - | State Plan | Remv. | 6.15 | 0.00 | 6.15 | Feb, 09 | Aug,09 | 50% | 4.36 | 0.00 | 4.36 | 1.79 | 0.00 | 1.79 | 1.79 | Work in progress | Geyzing | CONSTRUCTION | ROAD | 50 | M | ||
| 42 | Construction of motorable road from Khanisirbong to kamling. 13th - 21st | Soreng | 1Km | Mr. N.T. Tamang | Tenth Plan | State Plan | Remv. | 105.56 | 0.00 | 105.56 | 1-Jan-05 | 11-Nov-06 | 10% | 23.50 | 0.00 | 23.50 | 82.06 | 0.00 | 82.06 | 82.06 | Work order cancelled | Soreng | CONSTRUCTION | ROAD | 1 | KM | ||
| 43 | Widening, surface improvement, premix carpetting of Sombaria Puretar Km 6th to 13th | Soreng | 7Km | Mr. Amrit Subba, Prakash Subba, S.H. Sherpa, P.D. Sherpa | Tenth Plan | State Plan | Remv. | 128.00 | 0.00 | 128.00 | 1-Jan-05 | 10-Oct-06 | 100% | 124.92 | 0.00 | 124.92 | 3.08 | 0.00 | 3.08 | 3.08 | Work completed | Soreng | CONSTRUCTION | ROAD | 7 | KM | ||
| 44 | Technical Surveillance and rehabilitation of Singshore Suspensiopn Bridge along Dentam Uttarey Road | Kaluk | N/A | AS Bumper | State Plan | Repl. | 110.00 | 0.000 | 110.00 | 7-Jun-06 | 7-Nov-08 | 60% | 67.70 | 0.00 | 67.70 | 42.30 | 0.00 | 42.30 | 42.30 | Work in progress | Kaluk | UPGRADATION | ROAD | KM | ||||
| 45 | Construction of 25m span suspension bridge at Reshi Khola on Shribadam Deyathang road. | Soreng | 25m | Mr. B.R. Sharma | Tenth Plan | State Plan | Repl. | 45.03 | 0.00 | 45.03 | 3-Mar-05 | 3-Mar-07 | 66% | 27.11 | 0.00 | 27.11 | 17.92 | 0.00 | 17.92 | 17.92 | Work in progress | Soreng | CONSTRUCTION | ROAD | 25 | KM | ||
| 46 | Construction of road from Rinnchenpong Magalbaria -Deorali to Upper & Lower Chuchen village via Mangbir in West Sikkim. | Khusendra Sharma | State Plan | STIDF | 1024.97 | 0.00 | 1,024.97 | 17-Mar-09 | June, 11 | 10% | 0.00 | 0.00 | 0.00 | 1,024.97 | 0.00 | 1,024.97 | 1,024.97 | Work in progress | Kaluk | CONSTRUCTION | ROAD | KM | ||||||
| 47 | Construction of 55.00m Steel Bridge over Rateypani Khola along Mangley Chuchen Road. | Bir Man Rai | State Plan | STIDF | 17-Jun-09 | June, 11 | 0% | 0.00 | Documents under process. | Kaluk | CONSTRUCTION | BRIDGE | 55 | M | ||||||||||||||
| 48 | Construction of 30.00m Steel Bridge over Rateypani Khola along Mangley Chuchen Road. | Bir Man Rai | State Plan | STIDF | 17-Jun-09 | June, 11 | 0% | 0.00 | Documents under process. | Kaluk | CONSTRUCTION | BRIDGE | 30 | M | ||||||||||||||
| 49 | Construction of 10.00m Steel Bridge over Rateypani Khola along Mangley Chuchen Road. | Bir Man Rai | State Plan | STIDF | 17-Jun-09 | June, 11 | 0% | 0.00 | Documents under process. | Kaluk | CONSTRUCTION | BRIDGE | 10 | M | ||||||||||||||
| 50 | Construction of road from Kalez khola Power House intake to Jhakridunga via Ferek Km 1st - 9th in West-Sikkim. | Kamal Singh Gurung | State Plan | STIDF | 912.87 | 0.00 | 912.87 | 15-Mar-09 | March,11 | 0% | 0.00 | 0.00 | 0.00 | 912.87 | 0.00 | 912.87 | 912.87 | Documents under process. | Kaluk | CONSTRUCTION | ROAD | 9 | KM | |||||
| 51 | Construction of 57.00m Steel Bridge over Kalej Khola along Intake Jhakridunga road. | Man Kr. Gurung | State Plan | STIDF | 24-Oct-09 | Oct, 11 | 0% | 0.00 | Documents under process. | Kaluk | CONSTRUCTION | BRIDGE | 57 | M | ||||||||||||||
| 52 | Construction of 25.00m Steel Bridge over Farek Khola along Intake Jhakridunga road. | Gayendra Pd. Basnett | State Plan | STIDF | 12-Aug-09 | Aug, 11 | 0% | 0.00 | Documents under process. | Kaluk | CONSTRUCTION | BRIDGE | 25 | M | ||||||||||||||
| 53 | Surface improvement and strengthening and premix carpetting of Ribdi Bhareng road Km1st to 4th in West Sikkim | Mr. Mohan Prasad Rai | State Plan | TSP | 423.00 | 0.00 | 423.00 | June, 09 | June, 11 | 0% | 0.00 | 0.00 | 0.00 | 423.00 | 0.00 | 423.00 | 423.00 | Work to be started | Kaluk | CONSTRUCTION | ROAD | 4 | KM | |||||
| 54 | Permanent restoration of roads near naya bazar Forest Check Post on NDP road km 2nd. | Prem Kr. Chandak | State Plan | Major Works Plan | 164.66 | 0.00 | 164.66 | Feb, 09 | Aug, 9 | 95% | 161.10 | 0.00 | 161.10 | 3.56 | 0.00 | 3.56 | 3.56 | Work in progress | Kaluk | UPGRADATION | ROAD | 1 | KM | |||||
| 55 | Permanent restoration of Bojeck Slide &b other drainage roads. | Departmental | State Plan | Major Works Plan | 180.00 | 0.00 | 180.00 | Nov, 08 | July, 09 | 100% | 179.96 | 0.00 | 179.96 | 0.04 | 0.00 | 0.04 | 0.04 | Work completed | Kaluk | UPGRADATION | ROAD | 1 | KM | |||||
| 56 | Strengthening, widening premix carpetting works along Darap-Namboo road km 1st- 4th | 4 Km | Laxmi Prasad | State Plan | Major Works Plan | 352.77 | 0.00 | 352.77 | 17-Mar-09 | March,11 | 0% | 0.00 | 0.00 | 0.00 | 352.77 | 0.00 | 352.77 | 352.77 | Work not yet started | Kaluk | CONSTRUCTION | ROAD | KM | |||||
| 57 | Construction of wall on Kalej Khola Uttarey road at Bhandukay and providing protective work on Uttarey Sopkha road in West Sikkim. | Umesh Gurung | State Plan | Major Works Plan | 108.00 | 0.00 | 108.00 | 18-Mar-09 | March,11 | 10% | 0.00 | 0.00 | 0.00 | 108.00 | 0.00 | 108.00 | 108.00 | Work in progress | Kaluk | CONSTRUCTION | ROAD | KM | ||||||
| 58 | Reconstruction of short span RCC bridge bover Jhandy Khola on Soreng Sombarey road. | Departmental | State Plan | Major Works Plan | 25.00 | 0.00 | 25.00 | Jan, 09 | July, 09 | 100% | 24.99 | 0.00 | 24.99 | 0.01 | 0.00 | 0.01 | 0.01 | Work completed | Kaluk | CONSTRUCTION | ROAD | KM | ||||||
| CONSTRUCTION | ROAD | 215.9 | KM | 24 | NOS. | |||||||||||||||||||||||
| UPGRADATION | ROAD | 173.82 | KM | 23 | NOS. | |||||||||||||||||||||||
| UPGRADATION | BRIDGE | 113 | M | 2 | NOS. | |||||||||||||||||||||||
| CONSTRUCTION | BRIDGE | 297 | M | 7 | NOS. | |||||||||||||||||||||||
| Divisional Engineer (Plg) | Assistant Engineer (Plg) | Compiled by | 56 | NOS. | ||||||||||||||||||||||||