MONTHLY PHYSICAL AND FINANCIAL  PROGRESS REPORT FOR THE MONTH ENDING JANUARY 2010
   
Sl.No Name of Schemes   Length Km / M Name of Contractor Plan Funding Agency (Head) SANCTIONED  AMOUNT Date of Commen- cement Stipulated Date of Completion Phy Prog-ress               in % Financial Progress Balance  TOTAL SA-BAL Remarks
  S. share C.share Total Expenditure till date  
  S.Share C.Share Total S.Share C.Share Total  
C DISTRICT :  SOUTH      
A. CENTRAL  SPONSORED  SCHEMES                              
1 Construction of Gurassey Road from Bio-Diversity Park (Temi)     Passang Lepcha Tenth Plan EI New Road 245.30 1010.92 1256.22 26-Mar-08 Sept,09 25% 201.43 127.26 328.69 43.87 883.66 927.53 927.53 Work in progress Ravangla CONSTRUCTION ROAD KM
2 Widening, Improvement, protective work, drainage and carpetting of Melli, Phong road, Km. 1st to 24th.   24Km Pawan Kr. AgarwaL Tenth Plan ISC SCP 77.40 1298.61 1376.01 15-Oct-08 14-Oct-09 62% 77.40 235.00 312.40 0.00 1063.61 1063.61 1063.61 Work in progress Jorethang UPGRADATION ROAD 24 KM
3 Upgradation of approach road to Belliong Village Km 1st - 2nd in South Sikkim     Dinesh Kr. Rai Tenth Plan NABARD Exp. 12.86 115.760 128.62 16-Jun-09 15-Dec-10 15% 0.00 0.00 0.00 12.86 115.76 128.62 128.62 Work in progress Jorethang UPGRADATION ROAD 7 KM
4 Construction of trukable road from Tiffin Dara to Lower Tinghrithang  School Km 1st to 7th   7Km Mr. B. Tsh. Bhutia Tenth Plan NABARD New Road 28.26 254.370 282.63 6-Dec-08 12-Dec-07 91% 0.00 205.73 205.73 28.26 48.64 76.90 76.90 Work in progress, Land Comensation paid. Namchi CONSTRUCTION ROAD 7 KM
5 Surfce strengthening, carpetting, drainage and Protective Works along A/R to Buddha Statue (Sakymuni) Ravangla 2Km Pawan Kr. AgarwaL   NABARD Exp. 90.23 360.910 451.14 Feb, 2008 March,09 50% 0.00 198.91 198.91 90.23 162.00 252.23 252.23 Work in progress Ravangla UPGRADATION ROAD 2 KM
6 Surface improvement, Carpetting, Drainage & P/Work along Ben-Thalabari-Mangley road Km 1st to 7th. Ravangla 2Km Mr. Sonam O. Bhutia   NABARD - 0.00 360.930 360.93 March,09 Sept,12 15% 0.00 0.00 0.00 0.00 360.93 360.93 360.93 Work in progress Ravangla UPGRADATION ROAD 2 KM
7 Surfce strengthening, carpetting, drainage and Protective Works along Sangmoo link road 5Km     N.T.Bhtia   NABARD - 0.00 378.000 378.00 March,09 March, 11 20% 0.00 0.00 0.00 0.00 378.00 378.00   Work in progress UPGRADATION ROAD KM
8 Construction of 60m span steel bridge over Kaw Khola on KS road. Ravangla 60m Mr. S.S. Dhakhal Tenth Plan NEC CSS 0.00 164.35 164.35 13-Nov-06 12-Nov-08 86% 0.00 75.00 75.00 0.00 89.35 89.35 89.35 Work in progress Ravangla CONSTRUCTION BRIDGE 60 M
9 Srengthening, Drainage & Carpetting of Ralang Phamtam Road Km 14th to 26th  & Replacement of Two existing Bridgees over  Bermali & Chilli Khola in South  Sikkim.     Mr. N.T. Bhutia   NEC Remv. 100.00 1183.00 1,283.00 11-Nov-06 5-May-08 58% 0.00 304.44 304.44 100.00 878.56 978.56 978.56 Work in progress Ravangla UPGRADATION BRIDGE M
10 Truakable road from 10th mile to Tingmoo villageKm 1st, 2nd and 7th Ravangla 3Km Mr. Nim S. Sherpa Tenth Plan NEC CSS 0.00 468.29 468.29 04-Apr-06 04-Apr-07 73% 0.00 207.16 207.16 0.00 261.13 261.13 261.13 Work in progress Ravangla CONSTRUCTION ROAD 3 KM
11 Truakable road from 10th mile to Tingmoo villageKm 3rd and 6th Ravangla 2Km Mr. Sonam O. Bhutia Tenth Plan NEC CSS 04-Apr-06 04-Apr-07 70% 0.00 Work in progress Ravangla CONSTRUCTION ROAD 2 KM
12 Truakable road from 10th mile to Tingmoo villageKm 4th and 5th Ravangla 2Km Mr. Lhendup D. Kaleon Tenth Plan NEC CSS 05-Apr-06 04-Apr-07 61% 0.00 Work in progress Ravangla CONSTRUCTION ROAD 2 KM
13 Truakable road from 10th mile to Tingmoo villageKm 8th. Ravangla 1Km Mr. Bala R. Limboo Tenth Plan NEC CSS 09-Apr-06 04-Apr-07 68% 0.00 Work in progress Ravangla CONSTRUCTION ROAD 1 KM
14 Imp drainage, carpetting works Km 1st -14th and replacement of Rangla Khola bridge on Kimotey Sokpay roads. Ravangla 14Km Mr. Sunil Kr. Agarwal Tenth Plan NEC Remv. 0.00 1180.00 1180.00 13-Nov-06 12-Nov-08 75% 0.00 433.33 433.33 0.00 746.67 746.67 746.67 Work in progress Ravangla UPGRADATION ROAD 14 KM
15 Replacement of 110m Span Suspension Bridge over Rabi Khola in Melli Phong road Km 9th in S/Sikkim.    110m Mr. Om Agarwal Tenth Plan NEC CSS 0.00 497.30 497.30 12-Feb-07 12-Feb-08 70% 0.00 144.11 144.11 0.00 353.19 353.19 353.19 Work in progress Jorethang UPGRADATION BRIDGE 110 M
16 Construction of link road Turung School to Suminkhor Primary School.   4.75 Km Mr. Subaash Kharel Tenth Plan NEC New Road 22.79 358.66 381.45 Dec, 07 June, 09 81% 20.79 169.05 189.84 2.00 189.61 191.61 191.61 Work in progress Namchi CONSTRUCTION ROAD 4.75 KM
17 Construction of Makha Suspension Bridge over Tista Khola at Tanak on Makha -Lingi -Yangang- Ravangla Road in South Sikkim.(NEC) Ravangla 100m R.N. Chamling Tenth Plan NEC CSS 0.00 495.25 495.25 07-Nov-09 08-Nov-09 16% 0.00 32.28 32.28 0.00 462.97 462.97 462.97 Work in progress Ravangla CONSTRUCTION BRIDGE 100 M
18 Widening, surface improvement,P/works Namchi Helipad road km 1st to 5th.   5 Km Shanker Agarwal   NLCPR Remv. 176.33 596.95 773.28 March, 2009 March, 2011 30% 0.00 199.00 199.00 176.33 397.95 574.28 574.28 Work in progress Namchi UPGRADATION ROAD 5 KM
19 Surface strengthening drainage & P. Works on Namchi- Damthang Ravangla road- Km 1st -26th.   26Km Mr. Sunil Kr. Agarwal Tenth Plan NLCPR Remv. 461.61 1207.00 1668.61 01-Jan-05 01-Feb-07 100% 461.61 1164.19 1625.80 0.00 42.81 42.81 42.81 Work completed Namchi UPGRADATION ROAD 26 KM
20 Const. of motorable link road from upper Vok to Ung Raam (Water falls) via Namplang and Rabong village in Omchu    6Km Mr. B. Tsh. Bhutia Tenth Plan RSVY  New Road 130.81 180.00 310.81 22-Aug-05 21-Aug-07 87% 54.40 180.00 234.40 76.41 0.00 76.41 76.41 Work in progress Jorethang CONSTRUCTION ROAD 6 KM
  STATE PLAN                                        
21 Construction of Kitchen for PWD Guest House at Temi, South Sikkim. Ravangla N/A Mr. Bindra Kumar Rai Tenth Plan State Plan Addl. Facilities 11.01 0.00 11.01 02-Feb-07 08-Aug-07 99% 0.00 0.00 0.00 11.01 0.00 11.01 11.01 Work in progress Ravangla CONSTRUCTION BUILDING -
22 Surface strengthening & drainage on Yang-yang-Rangang road. Km 1st.-2nd   2Km Mr. S. B. Chamling Tenth Plan State Plan Exp. 39.32 0.00 39.32 16-Feb-03 11-Jan-06 100% 35.74 0.00 35.74 3.58 0.00 3.58 3.58 Work completed Ravangla UPGRADATION ROAD 2 KM
23 Carpetting, drainage & Protective Works onYangang- Rangang road form Bifurcation Point Km 1st and 2nd   2Km S.B.Chamling Tenth Plan State Plan Exp. 15.96 0.00 15.96 16-Feb-03 31-Mar-05 95% 14.25 0.00 14.25 1.71 0.00 1.71 1.71 Work in progress Ravangla UPGRADATION ROAD 2 KM
24 Construction of motorable road from Slap Village (Chettri Gaon) km 1st and 2nd Ravangla 2Km Mr. Lha T. Bhutia Tenth Plan State Plan Exp. 38.02 0.00 38.02 09-Sep-06 02-Feb-07 96% 21.40 0.00 21.40 16.62 0.00 16.62 16.62 Work in progress Ravangla CONSTRUCTION ROAD 2 KM
25 Diversion of turning at Km 14 th to 18th on Ravangla - Zarong Road in S-Sikkim   4Km Smt. Ratna Kum. Rai Tenth Plan State Plan Exp. 104.72 0.00 104.72 01-Jun-05 09-Mar-08 100% 54.11 0.00 54.11 50.61 0.00 50.61 50.61 Work completed Ravangla CONSTRUCTION ROAD 4 KM
26 Construction of Kink road from Kateng Bokrang to Namthang South Sikkim.   8 Km Buddha Singh Tamang Tenth Plan State Plan Link Road 426.21 0.00 426.21 12-Dec-08 12-Dec-10 50% 0.00 0.00 0.00 426.21 0.00 426.21 426.21 Work in progress Jorethang CONSTRUCTION ROAD 8 KM
27 Construction of truckable road from Lingi Paiyong Govt. Jr. high School Km 2nd (I/c 17.71 lac Comp.+2.62 Forest Comp) Ravangla 1Km S.S.Dhakal Tenth Plan State Plan New Road 79.11 0.00 79.11 March-03 February-04 93% 47.54 0.00 47.54 31.57 0.00 31.57 31.57 Work in progress Ravangla CONSTRUCTION ROAD 1 KM
28 Construction of 30m Span Steel Bridge at Khundrekay along Yangyang-Makh road Km 4th Ch 4-5. Ravangla 60m Kul Brd Gurung Tenth Plan State Plan Repl. 97.58 0.00 97.58 March, 09 01-Aug-10 16% 0.00 0.00 0.00 97.58 0.00 97.58 97.58 Work in progress Ravangla CONSTRUCTION BRIDGE 60 M
29 Immediate widening of narrow portion of Naya Bazar Namchi road at Tri Junction of RAC, Karefactor, in South Sikkim. Ravangla 60m Nigam Subba Tenth Plan State Plan Remv. 5.60 0.00 5.60 15-Jul-09 14-Oct-09 100% 0.00 0.00 0.00 5.60 0.00 5.60 5.60 Work completed Jorethang UPGRADATION ROAD 60 M
30 Upgradation, carpetting, P/Works & Drainage works at Namchi-Kopchey road to L/Boomtar via Singithang South Sikkim.   - Parsuram Agarwal Eleventh Plan State Plan SCP 260.00 0.00 260.00 March, 2009 Sep, 2010 65% 44.00 0.00 44.00 216.00 0.00 216.00 216.00 Work in progress Namchi UPGRADATION ROAD KM
31 Permanent restoration works Phongla Mamring road km 14th.   1km R.Chamling Eleventh Plan State Plan SCP 35.00 0.00 35.00 Feb, 2009 Aug, 2009 65% 5.90 0.00 5.90 29.10 0.00 29.10 29.10 Work in progress Namchi UPGRADATION ROAD 1 KM
32 Construction of road from Sinithang Boomtar in South Sikkim.   - Bharat Rai Eleventh Plan State Plan STIDF 39.67 0.00 39.67 March, 2009 Sep, 2010 88% 24.50 0.00 24.50 15.17 0.00 15.17 15.17 Work in progress Namchi CONSTRUCTION ROAD KM
33 Construction of road along Namchi Vok road from Mamley to Nandang Village Km 1st to 5th in South Sikkim.   5km Indra Rai Eleventh Plan State Plan STIDF 274.00 0.00 274.00 March, 2009 Sep, 2010 52% 50.00 0.00 50.00 224.00 0.00 224.00 224.00 Work in progress Namchi CONSTRUCTION ROAD 5 KM
34 Construction of truckable road Turung Suminkhor road to Kanam Busty.   1km Norchhyo Lepcha Eleventh Plan State Plan TSP 96.00 0.00 96.00 March, 2009 March, 2010 85% 50.00 0.00 50.00 46.00 0.00 46.00 46.00 Work in progress Namchi CONSTRUCTION ROAD 1 KM
35 Extension of I.B Golai-Peku road to Ben School link road 1 Km.     B.D. Rai   State Plan TSP 80.00 0.00 80.00 17-Mar-09 June, 09 20% 11.74 0.00 11.74 68.26 0.00 68.26 68.26 Work in progress CONSTRUCTION ROAD 1 KM
36 Construction of Link Road from Lower Rayong to Sardong Km 1st  & 2nd    1km Norden Dorjee Sangdarpa Eleventh Plan State Plan Major Work 107.82 0.00 107.82 March, 2009 Sept, 2010 17% 0.00 0.00 0.00 107.82 0.00 107.82 107.82 Work in progress Ravangla CONSTRUCTION ROAD 1 KM
37 Construction of Link Road from Lower Rayong to Sardong Km 3rd  & 5th.    1km Norden Dorjee Sangdarpa Eleventh Plan State Plan Major Work 128.12 0.00 128.12 March, 2009 Sept, 2010 10% 0.00 0.00 0.00 128.12 0.00 128.12 128.12 Work in progress Ravangla CONSTRUCTION ROAD 1 KM
38 Slope Stablization, slip aressting and benching work, permanent restoration catch water drain along various roads under South Circle, Salalay & Rabong Legship.     Mr. R. N. Chamling   State Plan Major Work 598.00 0.00 598.00 March, 2009 Sept, 2010, Oct 2010 46% 0.00 0.00 0.00 598.00 0.00 598.00 598.00 Work in progress UPGRADATION DRAIN KM
39 Slope Stablization, works on Namchi-Vok road at Terrikhola slip.     Mr. R. N. Chamling   State Plan Major Work 50.00 0.00 50.00 March, 2009 Sept, 2010 50% 23.38 0.00 23.38 26.62 0.00 26.62 26.62 Work in progress
40 Slope Stablization, works on Namchi-Vok road at Km 2nd.     Mr. R. N. Chamling   State Plan Major Work 30.00 0.00 30.00 March, 2009 Sept, 2010 100% 19.22 0.00 19.22 10.78 0.00 10.78 10.78 Work completed
41 Slope Stablization, slip aressting and benching work, permanent restoration catch water drain along various roads under South Circle, Namchi-Phong road.     Mr. R. N. Chamling   State Plan Major Work 70.00 0.00 70.00 March, 2009 Sept, 2010 60% 38.00 0.00 38.00 32.00 0.00 32.00 32.00 Work in progress
42 Slope Stablization, works on Namchi-Damthang  road Km 4th at Tiffindara in Sikkim.     Mr. M.P. Agarwal   State Plan Major Work 150.00 0.00 150.00 03-Mar-09 02-Nov-09 100% 137.55 0.00 137.55 12.45 0.00 12.45 12.45 Work completed
43 Slope Stablization, works on Namchi-Damthang  road Km 7th at Dabuwa in Sikkim.     Mr. M.P. Agarwal   State Plan Major Work 25.00 0.00 25.00 03-Mar-09 02-Nov-09 100% 20.42 0.00 20.42 4.58 0.00 4.58 4.58 Work completed
44 Namcho Rong road at Manpur Bridge Point.     Mr. M.P. Agarwal   State Plan Major Work 100.00 0.00 100.00 03-Mar-09 02-Nov-09 100% 100.00 0.00 100.00 0.00 0.00 0.00 0.00 Work completed
45 Upgradation,Surface improvement, Widening  carpetting, P/Works & Drainage works along LD Kazi Bridge Phatak and Pabong-Simchuthang-Namphok-Yangyang Road Km 1st to 6th & 1st to 11th in South Sikkim.   17KM K.K Group Pvt. Ltd. Eleventh Plan State Plan Sikkim University  Yangyang(Paln) 1997.75 0.00 1997.75 Feb, 09 Feb, 2011 8% 0.00 0.00 0.00 1997.75 0.00 1997.75 1997.75 Work in progress Ravangla UPGRADATION ROAD 17 KM
46 Upgradation,Surface improvement, Widening  carpetting, P/Works & Drainage works along LD Kazi Bridge Phatak and Pabong-Simchuthang-Namphok-Yangyang Road Km 12th to 19th in South Sikkim.   7KM Ashok Chamling Eleventh Plan State Plan Sikkim University  Yangyang(Paln) 718.87 0.00 718.87 Feb, 09 Aug, 2010 19% 0.00 0.00 0.00 718.87 0.00 718.87 718.87 Work in progress Ravangla UPGRADATION ROAD 7 KM
47 Construction of Link Road from upper Yangyang to Bhutia Gumpa (Ch1-10)   1km D.Basnett Eleventh Plan State Plan TSP 49.72 0.00 49.72 Feb, 09 Feb, 10 95% 0.00 0.00 0.00 49.72 0.00 49.72 49.72 Work in progress Ravangla CONSTRUCTION ROAD KM
48 Construction of Link Road from upper Yangyang to Bhutia Gumpa (Ch11-22)   Karma P. Bhutia Eleventh Plan State Plan TSP 42.43 0.00 42.43 Feb, 09 Feb, 10 66% 0.00 0.00 0.00 42.43 0.00 42.43 42.43 Work in progress Ravangla CONSTRUCTION ROAD
49 Construction of Link Road from upper Yangyang to Bhutia Gumpa (Ch23-33)   Chumden Bhutia Eleventh Plan State Plan TSP 13.96 0.00 13.96 March, 09 March, 10 82% 0.00 0.00 0.00 13.96 0.00 13.96 13.96 Work in progress Ravangla CONSTRUCTION ROAD
                                           
CONSTRUCTION  ROAD #REF! KM 20 NOS.
UPGRADATION ROAD 169 KM 15 NOS.
CONSTRUCTION  BUILDING 1 NOS. 1 NOS.