| MONTHLY PHYSICAL AND FINANCIAL PROGRESS REPORT FOR THE MONTH ENDING JANUARY 2010 | ||||||||||||||||||||||||||||
| Sl.No | Name of Schemes | Length Km / M | Name of Contractor | Plan | Funding Agency | (Head) | SANCTIONED AMOUNT | Date of Commen- cement | Stipulated Date of Completion | Phy Prog-ress in % | Financial Progress | Balance | TOTAL SA-BAL | Remarks | ||||||||||||||
| S. share | C.share | Total | Expenditure till date | |||||||||||||||||||||||||
| S.Share | C.Share | Total | S.Share | C.Share | Total | |||||||||||||||||||||||
| C | DISTRICT : SOUTH | |||||||||||||||||||||||||||
| A. | CENTRAL SPONSORED SCHEMES | |||||||||||||||||||||||||||
| 1 | Construction of Gurassey Road from Bio-Diversity Park (Temi) | Passang Lepcha | Tenth Plan | EI | New Road | 245.30 | 1010.92 | 1256.22 | 26-Mar-08 | Sept,09 | 25% | 201.43 | 127.26 | 328.69 | 43.87 | 883.66 | 927.53 | 927.53 | Work in progress | Ravangla | CONSTRUCTION | ROAD | KM | |||||
| 2 | Widening, Improvement, protective work, drainage and carpetting of Melli, Phong road, Km. 1st to 24th. | 24Km | Pawan Kr. AgarwaL | Tenth Plan | ISC | SCP | 77.40 | 1298.61 | 1376.01 | 15-Oct-08 | 14-Oct-09 | 62% | 77.40 | 235.00 | 312.40 | 0.00 | 1063.61 | 1063.61 | 1063.61 | Work in progress | Jorethang | UPGRADATION | ROAD | 24 | KM | |||
| 3 | Upgradation of approach road to Belliong Village Km 1st - 2nd in South Sikkim | Dinesh Kr. Rai | Tenth Plan | NABARD | Exp. | 12.86 | 115.760 | 128.62 | 16-Jun-09 | 15-Dec-10 | 15% | 0.00 | 0.00 | 0.00 | 12.86 | 115.76 | 128.62 | 128.62 | Work in progress | Jorethang | UPGRADATION | ROAD | 7 | KM | ||||
| 4 | Construction of trukable road from Tiffin Dara to Lower Tinghrithang School Km 1st to 7th | 7Km | Mr. B. Tsh. Bhutia | Tenth Plan | NABARD | New Road | 28.26 | 254.370 | 282.63 | 6-Dec-08 | 12-Dec-07 | 91% | 0.00 | 205.73 | 205.73 | 28.26 | 48.64 | 76.90 | 76.90 | Work in progress, Land Comensation paid. | Namchi | CONSTRUCTION | ROAD | 7 | KM | |||
| 5 | Surfce strengthening, carpetting, drainage and Protective Works along A/R to Buddha Statue (Sakymuni) | Ravangla | 2Km | Pawan Kr. AgarwaL | NABARD | Exp. | 90.23 | 360.910 | 451.14 | Feb, 2008 | March,09 | 50% | 0.00 | 198.91 | 198.91 | 90.23 | 162.00 | 252.23 | 252.23 | Work in progress | Ravangla | UPGRADATION | ROAD | 2 | KM | |||
| 6 | Surface improvement, Carpetting, Drainage & P/Work along Ben-Thalabari-Mangley road Km 1st to 7th. | Ravangla | 2Km | Mr. Sonam O. Bhutia | NABARD | - | 0.00 | 360.930 | 360.93 | March,09 | Sept,12 | 15% | 0.00 | 0.00 | 0.00 | 0.00 | 360.93 | 360.93 | 360.93 | Work in progress | Ravangla | UPGRADATION | ROAD | 2 | KM | |||
| 7 | Surfce strengthening, carpetting, drainage and Protective Works along Sangmoo link road 5Km | N.T.Bhtia | NABARD | - | 0.00 | 378.000 | 378.00 | March,09 | March, 11 | 20% | 0.00 | 0.00 | 0.00 | 0.00 | 378.00 | 378.00 | Work in progress | UPGRADATION | ROAD | KM | ||||||||
| 8 | Construction of 60m span steel bridge over Kaw Khola on KS road. | Ravangla | 60m | Mr. S.S. Dhakhal | Tenth Plan | NEC | CSS | 0.00 | 164.35 | 164.35 | 13-Nov-06 | 12-Nov-08 | 86% | 0.00 | 75.00 | 75.00 | 0.00 | 89.35 | 89.35 | 89.35 | Work in progress | Ravangla | CONSTRUCTION | BRIDGE | 60 | M | ||
| 9 | Srengthening, Drainage & Carpetting of Ralang Phamtam Road Km 14th to 26th & Replacement of Two existing Bridgees over Bermali & Chilli Khola in South Sikkim. | Mr. N.T. Bhutia | NEC | Remv. | 100.00 | 1183.00 | 1,283.00 | 11-Nov-06 | 5-May-08 | 58% | 0.00 | 304.44 | 304.44 | 100.00 | 878.56 | 978.56 | 978.56 | Work in progress | Ravangla | UPGRADATION | BRIDGE | M | ||||||
| 10 | Truakable road from 10th mile to Tingmoo villageKm 1st, 2nd and 7th | Ravangla | 3Km | Mr. Nim S. Sherpa | Tenth Plan | NEC | CSS | 0.00 | 468.29 | 468.29 | 04-Apr-06 | 04-Apr-07 | 73% | 0.00 | 207.16 | 207.16 | 0.00 | 261.13 | 261.13 | 261.13 | Work in progress | Ravangla | CONSTRUCTION | ROAD | 3 | KM | ||
| 11 | Truakable road from 10th mile to Tingmoo villageKm 3rd and 6th | Ravangla | 2Km | Mr. Sonam O. Bhutia | Tenth Plan | NEC | CSS | 04-Apr-06 | 04-Apr-07 | 70% | 0.00 | Work in progress | Ravangla | CONSTRUCTION | ROAD | 2 | KM | |||||||||||
| 12 | Truakable road from 10th mile to Tingmoo villageKm 4th and 5th | Ravangla | 2Km | Mr. Lhendup D. Kaleon | Tenth Plan | NEC | CSS | 05-Apr-06 | 04-Apr-07 | 61% | 0.00 | Work in progress | Ravangla | CONSTRUCTION | ROAD | 2 | KM | |||||||||||
| 13 | Truakable road from 10th mile to Tingmoo villageKm 8th. | Ravangla | 1Km | Mr. Bala R. Limboo | Tenth Plan | NEC | CSS | 09-Apr-06 | 04-Apr-07 | 68% | 0.00 | Work in progress | Ravangla | CONSTRUCTION | ROAD | 1 | KM | |||||||||||
| 14 | Imp drainage, carpetting works Km 1st -14th and replacement of Rangla Khola bridge on Kimotey Sokpay roads. | Ravangla | 14Km | Mr. Sunil Kr. Agarwal | Tenth Plan | NEC | Remv. | 0.00 | 1180.00 | 1180.00 | 13-Nov-06 | 12-Nov-08 | 75% | 0.00 | 433.33 | 433.33 | 0.00 | 746.67 | 746.67 | 746.67 | Work in progress | Ravangla | UPGRADATION | ROAD | 14 | KM | ||
| 15 | Replacement of 110m Span Suspension Bridge over Rabi Khola in Melli Phong road Km 9th in S/Sikkim. | 110m | Mr. Om Agarwal | Tenth Plan | NEC | CSS | 0.00 | 497.30 | 497.30 | 12-Feb-07 | 12-Feb-08 | 70% | 0.00 | 144.11 | 144.11 | 0.00 | 353.19 | 353.19 | 353.19 | Work in progress | Jorethang | UPGRADATION | BRIDGE | 110 | M | |||
| 16 | Construction of link road Turung School to Suminkhor Primary School. | 4.75 Km | Mr. Subaash Kharel | Tenth Plan | NEC | New Road | 22.79 | 358.66 | 381.45 | Dec, 07 | June, 09 | 81% | 20.79 | 169.05 | 189.84 | 2.00 | 189.61 | 191.61 | 191.61 | Work in progress | Namchi | CONSTRUCTION | ROAD | 4.75 | KM | |||
| 17 | Construction of Makha Suspension Bridge over Tista Khola at Tanak on Makha -Lingi -Yangang- Ravangla Road in South Sikkim.(NEC) | Ravangla | 100m | R.N. Chamling | Tenth Plan | NEC | CSS | 0.00 | 495.25 | 495.25 | 07-Nov-09 | 08-Nov-09 | 16% | 0.00 | 32.28 | 32.28 | 0.00 | 462.97 | 462.97 | 462.97 | Work in progress | Ravangla | CONSTRUCTION | BRIDGE | 100 | M | ||
| 18 | Widening, surface improvement,P/works Namchi Helipad road km 1st to 5th. | 5 Km | Shanker Agarwal | NLCPR | Remv. | 176.33 | 596.95 | 773.28 | March, 2009 | March, 2011 | 30% | 0.00 | 199.00 | 199.00 | 176.33 | 397.95 | 574.28 | 574.28 | Work in progress | Namchi | UPGRADATION | ROAD | 5 | KM | ||||
| 19 | Surface strengthening drainage & P. Works on Namchi- Damthang Ravangla road- Km 1st -26th. | 26Km | Mr. Sunil Kr. Agarwal | Tenth Plan | NLCPR | Remv. | 461.61 | 1207.00 | 1668.61 | 01-Jan-05 | 01-Feb-07 | 100% | 461.61 | 1164.19 | 1625.80 | 0.00 | 42.81 | 42.81 | 42.81 | Work completed | Namchi | UPGRADATION | ROAD | 26 | KM | |||
| 20 | Const. of motorable link road from upper Vok to Ung Raam (Water falls) via Namplang and Rabong village in Omchu | 6Km | Mr. B. Tsh. Bhutia | Tenth Plan | RSVY | New Road | 130.81 | 180.00 | 310.81 | 22-Aug-05 | 21-Aug-07 | 87% | 54.40 | 180.00 | 234.40 | 76.41 | 0.00 | 76.41 | 76.41 | Work in progress | Jorethang | CONSTRUCTION | ROAD | 6 | KM | |||
| STATE PLAN | ||||||||||||||||||||||||||||
| 21 | Construction of Kitchen for PWD Guest House at Temi, South Sikkim. | Ravangla | N/A | Mr. Bindra Kumar Rai | Tenth Plan | State Plan | Addl. Facilities | 11.01 | 0.00 | 11.01 | 02-Feb-07 | 08-Aug-07 | 99% | 0.00 | 0.00 | 0.00 | 11.01 | 0.00 | 11.01 | 11.01 | Work in progress | Ravangla | CONSTRUCTION | BUILDING | - | |||
| 22 | Surface strengthening & drainage on Yang-yang-Rangang road. Km 1st.-2nd | 2Km | Mr. S. B. Chamling | Tenth Plan | State Plan | Exp. | 39.32 | 0.00 | 39.32 | 16-Feb-03 | 11-Jan-06 | 100% | 35.74 | 0.00 | 35.74 | 3.58 | 0.00 | 3.58 | 3.58 | Work completed | Ravangla | UPGRADATION | ROAD | 2 | KM | |||
| 23 | Carpetting, drainage & Protective Works onYangang- Rangang road form Bifurcation Point Km 1st and 2nd | 2Km | S.B.Chamling | Tenth Plan | State Plan | Exp. | 15.96 | 0.00 | 15.96 | 16-Feb-03 | 31-Mar-05 | 95% | 14.25 | 0.00 | 14.25 | 1.71 | 0.00 | 1.71 | 1.71 | Work in progress | Ravangla | UPGRADATION | ROAD | 2 | KM | |||
| 24 | Construction of motorable road from Slap Village (Chettri Gaon) km 1st and 2nd | Ravangla | 2Km | Mr. Lha T. Bhutia | Tenth Plan | State Plan | Exp. | 38.02 | 0.00 | 38.02 | 09-Sep-06 | 02-Feb-07 | 96% | 21.40 | 0.00 | 21.40 | 16.62 | 0.00 | 16.62 | 16.62 | Work in progress | Ravangla | CONSTRUCTION | ROAD | 2 | KM | ||
| 25 | Diversion of turning at Km 14 th to 18th on Ravangla - Zarong Road in S-Sikkim | 4Km | Smt. Ratna Kum. Rai | Tenth Plan | State Plan | Exp. | 104.72 | 0.00 | 104.72 | 01-Jun-05 | 09-Mar-08 | 100% | 54.11 | 0.00 | 54.11 | 50.61 | 0.00 | 50.61 | 50.61 | Work completed | Ravangla | CONSTRUCTION | ROAD | 4 | KM | |||
| 26 | Construction of Kink road from Kateng Bokrang to Namthang South Sikkim. | 8 Km | Buddha Singh Tamang | Tenth Plan | State Plan | Link Road | 426.21 | 0.00 | 426.21 | 12-Dec-08 | 12-Dec-10 | 50% | 0.00 | 0.00 | 0.00 | 426.21 | 0.00 | 426.21 | 426.21 | Work in progress | Jorethang | CONSTRUCTION | ROAD | 8 | KM | |||
| 27 | Construction of truckable road from Lingi Paiyong Govt. Jr. high School Km 2nd (I/c 17.71 lac Comp.+2.62 Forest Comp) | Ravangla | 1Km | S.S.Dhakal | Tenth Plan | State Plan | New Road | 79.11 | 0.00 | 79.11 | March-03 | February-04 | 93% | 47.54 | 0.00 | 47.54 | 31.57 | 0.00 | 31.57 | 31.57 | Work in progress | Ravangla | CONSTRUCTION | ROAD | 1 | KM | ||
| 28 | Construction of 30m Span Steel Bridge at Khundrekay along Yangyang-Makh road Km 4th Ch 4-5. | Ravangla | 60m | Kul Brd Gurung | Tenth Plan | State Plan | Repl. | 97.58 | 0.00 | 97.58 | March, 09 | 01-Aug-10 | 16% | 0.00 | 0.00 | 0.00 | 97.58 | 0.00 | 97.58 | 97.58 | Work in progress | Ravangla | CONSTRUCTION | BRIDGE | 60 | M | ||
| 29 | Immediate widening of narrow portion of Naya Bazar Namchi road at Tri Junction of RAC, Karefactor, in South Sikkim. | Ravangla | 60m | Nigam Subba | Tenth Plan | State Plan | Remv. | 5.60 | 0.00 | 5.60 | 15-Jul-09 | 14-Oct-09 | 100% | 0.00 | 0.00 | 0.00 | 5.60 | 0.00 | 5.60 | 5.60 | Work completed | Jorethang | UPGRADATION | ROAD | 60 | M | ||
| 30 | Upgradation, carpetting, P/Works & Drainage works at Namchi-Kopchey road to L/Boomtar via Singithang South Sikkim. | - | Parsuram Agarwal | Eleventh Plan | State Plan | SCP | 260.00 | 0.00 | 260.00 | March, 2009 | Sep, 2010 | 65% | 44.00 | 0.00 | 44.00 | 216.00 | 0.00 | 216.00 | 216.00 | Work in progress | Namchi | UPGRADATION | ROAD | KM | ||||
| 31 | Permanent restoration works Phongla Mamring road km 14th. | 1km | R.Chamling | Eleventh Plan | State Plan | SCP | 35.00 | 0.00 | 35.00 | Feb, 2009 | Aug, 2009 | 65% | 5.90 | 0.00 | 5.90 | 29.10 | 0.00 | 29.10 | 29.10 | Work in progress | Namchi | UPGRADATION | ROAD | 1 | KM | |||
| 32 | Construction of road from Sinithang Boomtar in South Sikkim. | - | Bharat Rai | Eleventh Plan | State Plan | STIDF | 39.67 | 0.00 | 39.67 | March, 2009 | Sep, 2010 | 88% | 24.50 | 0.00 | 24.50 | 15.17 | 0.00 | 15.17 | 15.17 | Work in progress | Namchi | CONSTRUCTION | ROAD | KM | ||||
| 33 | Construction of road along Namchi Vok road from Mamley to Nandang Village Km 1st to 5th in South Sikkim. | 5km | Indra Rai | Eleventh Plan | State Plan | STIDF | 274.00 | 0.00 | 274.00 | March, 2009 | Sep, 2010 | 52% | 50.00 | 0.00 | 50.00 | 224.00 | 0.00 | 224.00 | 224.00 | Work in progress | Namchi | CONSTRUCTION | ROAD | 5 | KM | |||
| 34 | Construction of truckable road Turung Suminkhor road to Kanam Busty. | 1km | Norchhyo Lepcha | Eleventh Plan | State Plan | TSP | 96.00 | 0.00 | 96.00 | March, 2009 | March, 2010 | 85% | 50.00 | 0.00 | 50.00 | 46.00 | 0.00 | 46.00 | 46.00 | Work in progress | Namchi | CONSTRUCTION | ROAD | 1 | KM | |||
| 35 | Extension of I.B Golai-Peku road to Ben School link road 1 Km. | B.D. Rai | State Plan | TSP | 80.00 | 0.00 | 80.00 | 17-Mar-09 | June, 09 | 20% | 11.74 | 0.00 | 11.74 | 68.26 | 0.00 | 68.26 | 68.26 | Work in progress | CONSTRUCTION | ROAD | 1 | KM | ||||||
| 36 | Construction of Link Road from Lower Rayong to Sardong Km 1st & 2nd | 1km | Norden Dorjee Sangdarpa | Eleventh Plan | State Plan | Major Work | 107.82 | 0.00 | 107.82 | March, 2009 | Sept, 2010 | 17% | 0.00 | 0.00 | 0.00 | 107.82 | 0.00 | 107.82 | 107.82 | Work in progress | Ravangla | CONSTRUCTION | ROAD | 1 | KM | |||
| 37 | Construction of Link Road from Lower Rayong to Sardong Km 3rd & 5th. | 1km | Norden Dorjee Sangdarpa | Eleventh Plan | State Plan | Major Work | 128.12 | 0.00 | 128.12 | March, 2009 | Sept, 2010 | 10% | 0.00 | 0.00 | 0.00 | 128.12 | 0.00 | 128.12 | 128.12 | Work in progress | Ravangla | CONSTRUCTION | ROAD | 1 | KM | |||
| 38 | Slope Stablization, slip aressting and benching work, permanent restoration catch water drain along various roads under South Circle, Salalay & Rabong Legship. | Mr. R. N. Chamling | State Plan | Major Work | 598.00 | 0.00 | 598.00 | March, 2009 | Sept, 2010, Oct 2010 | 46% | 0.00 | 0.00 | 0.00 | 598.00 | 0.00 | 598.00 | 598.00 | Work in progress | UPGRADATION | DRAIN | KM | |||||||
| 39 | Slope Stablization, works on Namchi-Vok road at Terrikhola slip. | Mr. R. N. Chamling | State Plan | Major Work | 50.00 | 0.00 | 50.00 | March, 2009 | Sept, 2010 | 50% | 23.38 | 0.00 | 23.38 | 26.62 | 0.00 | 26.62 | 26.62 | Work in progress | ||||||||||
| 40 | Slope Stablization, works on Namchi-Vok road at Km 2nd. | Mr. R. N. Chamling | State Plan | Major Work | 30.00 | 0.00 | 30.00 | March, 2009 | Sept, 2010 | 100% | 19.22 | 0.00 | 19.22 | 10.78 | 0.00 | 10.78 | 10.78 | Work completed | ||||||||||
| 41 | Slope Stablization, slip aressting and benching work, permanent restoration catch water drain along various roads under South Circle, Namchi-Phong road. | Mr. R. N. Chamling | State Plan | Major Work | 70.00 | 0.00 | 70.00 | March, 2009 | Sept, 2010 | 60% | 38.00 | 0.00 | 38.00 | 32.00 | 0.00 | 32.00 | 32.00 | Work in progress | ||||||||||
| 42 | Slope Stablization, works on Namchi-Damthang road Km 4th at Tiffindara in Sikkim. | Mr. M.P. Agarwal | State Plan | Major Work | 150.00 | 0.00 | 150.00 | 03-Mar-09 | 02-Nov-09 | 100% | 137.55 | 0.00 | 137.55 | 12.45 | 0.00 | 12.45 | 12.45 | Work completed | ||||||||||
| 43 | Slope Stablization, works on Namchi-Damthang road Km 7th at Dabuwa in Sikkim. | Mr. M.P. Agarwal | State Plan | Major Work | 25.00 | 0.00 | 25.00 | 03-Mar-09 | 02-Nov-09 | 100% | 20.42 | 0.00 | 20.42 | 4.58 | 0.00 | 4.58 | 4.58 | Work completed | ||||||||||
| 44 | Namcho Rong road at Manpur Bridge Point. | Mr. M.P. Agarwal | State Plan | Major Work | 100.00 | 0.00 | 100.00 | 03-Mar-09 | 02-Nov-09 | 100% | 100.00 | 0.00 | 100.00 | 0.00 | 0.00 | 0.00 | 0.00 | Work completed | ||||||||||
| 45 | Upgradation,Surface improvement, Widening carpetting, P/Works & Drainage works along LD Kazi Bridge Phatak and Pabong-Simchuthang-Namphok-Yangyang Road Km 1st to 6th & 1st to 11th in South Sikkim. | 17KM | K.K Group Pvt. Ltd. | Eleventh Plan | State Plan | Sikkim University Yangyang(Paln) | 1997.75 | 0.00 | 1997.75 | Feb, 09 | Feb, 2011 | 8% | 0.00 | 0.00 | 0.00 | 1997.75 | 0.00 | 1997.75 | 1997.75 | Work in progress | Ravangla | UPGRADATION | ROAD | 17 | KM | |||
| 46 | Upgradation,Surface improvement, Widening carpetting, P/Works & Drainage works along LD Kazi Bridge Phatak and Pabong-Simchuthang-Namphok-Yangyang Road Km 12th to 19th in South Sikkim. | 7KM | Ashok Chamling | Eleventh Plan | State Plan | Sikkim University Yangyang(Paln) | 718.87 | 0.00 | 718.87 | Feb, 09 | Aug, 2010 | 19% | 0.00 | 0.00 | 0.00 | 718.87 | 0.00 | 718.87 | 718.87 | Work in progress | Ravangla | UPGRADATION | ROAD | 7 | KM | |||
| 47 | Construction of Link Road from upper Yangyang to Bhutia Gumpa (Ch1-10) | 1km | D.Basnett | Eleventh Plan | State Plan | TSP | 49.72 | 0.00 | 49.72 | Feb, 09 | Feb, 10 | 95% | 0.00 | 0.00 | 0.00 | 49.72 | 0.00 | 49.72 | 49.72 | Work in progress | Ravangla | CONSTRUCTION | ROAD | KM | ||||
| 48 | Construction of Link Road from upper Yangyang to Bhutia Gumpa (Ch11-22) | Karma P. Bhutia | Eleventh Plan | State Plan | TSP | 42.43 | 0.00 | 42.43 | Feb, 09 | Feb, 10 | 66% | 0.00 | 0.00 | 0.00 | 42.43 | 0.00 | 42.43 | 42.43 | Work in progress | Ravangla | CONSTRUCTION | ROAD | ||||||
| 49 | Construction of Link Road from upper Yangyang to Bhutia Gumpa (Ch23-33) | Chumden Bhutia | Eleventh Plan | State Plan | TSP | 13.96 | 0.00 | 13.96 | March, 09 | March, 10 | 82% | 0.00 | 0.00 | 0.00 | 13.96 | 0.00 | 13.96 | 13.96 | Work in progress | Ravangla | CONSTRUCTION | ROAD | ||||||
| CONSTRUCTION | ROAD | #REF! | KM | 20 | NOS. | |||||||||||||||||||||||
| UPGRADATION | ROAD | 169 | KM | 15 | NOS. | |||||||||||||||||||||||
| CONSTRUCTION | BUILDING | 1 | NOS. | 1 | NOS. | |||||||||||||||||||||||