| MONTHLY PHYSICAL AND FINANCIAL PROGRESS REPORT FOR THE MONTH ENDING JANUARY 2010 | . | ||||||||||||||||||||||||||||
| . | |||||||||||||||||||||||||||||
| Sl.No | Name of Schemes | Length Km / M | Name of Contractor | Plan | Funding Agency | (Head) | SANCTIONED AMOUNT | Date of Commen- cement | Stipulated Date of Completion | Phy Prog-ress in % | Financial Progress | Balance | TOTAL SA-BAL | Remarks | |||||||||||||||
| S. share | C.share | Total | Expenditure till date | ||||||||||||||||||||||||||
| S.Share | C.Share | Total | S.Share | C.Share | Total | ||||||||||||||||||||||||
| B | DISTRICT :EAST | ||||||||||||||||||||||||||||
| CENTRAL SPONSORED SCHEMES | |||||||||||||||||||||||||||||
| 1 | Const. of link road from Arubotey to Subaneydara km 1st-3rd. | Pakyong | 3Km | Mr. Om Bhd. Gurung | Ninth Plan | BADP | - | 0.00 | 29.97 | 29.97 | 30-Nov-00 | 16-Mar-01 | 68% | 0.00 | 22.98 | 22.98 | 0.00 | 6.99 | 6.99 | 6.99 | Work abondoned | Pakyong | CONSTRUCTION | ROAD | 3 | KM | |||
| 2 | Const. of link road from sisney to North Regu km 1st -4th. | Pakyong | 4Km | Mr. T.S. Lama | Tenth Plan | BADP | - | 0.00 | 30.31 | 30.31 | 21-Nov-00 | 5-Mar-01 | 95% | 0.00 | 24.54 | 24.54 | 0.00 | 5.77 | 5.77 | 5.77 | Work abondoned | Pakyong | CONSTRUCTION | ROAD | 4 | KM | |||
| 3 | Construction of 60 m span steel bridge at Bongliung over Rongli Chu in East Sikkim | 60m | Mr. Gazendra Rai | Eleventh Plan | CSS(BRGF) | - | 0.00 | 74.07 | 74.07 | 29-Mar-08 | 29-Sep-09 | 40% | 0.00 | 0.00 | 0.00 | 0.00 | 74.07 | 74.07 | 74.07 | Work in progress | Pakyong | CONSTRUCTION | BRIDGE | 60 | M | ||||
| 4 | Const. of 12 m span R.C.C. Bridge on Sangkhola Zingla Martam Road at Km 11th ch-3rd. | 12m | Mrs. Anita Gurung | Eleventh Plan | CRF | - | 0.00 | 38.63 | 38.63 | 1-Apr-07 | 31-Mar-08 | 95% | 0.00 | 19.23 | 19.23 | 0.00 | 19.40 | 19.40 | 19.40 | Work in progress | CONSTRUCTION | BRIDGE | 12 | M | |||||
| 5 | Const. of 12 m span R.C.c. Bridge on Sangkhola Zingla Martam Road at Km 12th ch-4th.. | 12m | Mr. T.B. Pradhan | Eleventh Plan | CRF | - | 0.00 | 45.12 | 45.12 | 1-Apr-07 | 31-Mar-08 | 95% | 0.00 | 27.70 | 34.20 | 0.00 | 17.42 | 10.92 | 10.92 | Work in progress | CONSTRUCTION | BRIDGE | 12 | M | |||||
| 6 | Surface improvement and widening of Sang Sirwani Road Km 1st-2nd & App Road from Mech Sub Div Office at Dochum | 1Km | Mr. Kishor Pradhan | Eleventh Plan | CRF | - | 0.00 | 95.00 | 95.00 | 10-Oct-07 | 9-Sep-08 | 100% | 0.00 | 74.68 | 74.68 | 0.00 | 20.32 | 20.32 | 20.32 | Work in progress | UPGRADATION | ROAD | 1 | KM | |||||
| 7 | Construction of link road from pakyong Nop gaon to barpipal Dara, Km 1st-3rd in East-Sikkim | Pakyong | 3Km | Mr. Hemandri Adhikari | Eleventh Plan | CRF | CSS | 0.00 | 107.92 | 107.92 | 5-Aug-08 | 5-Mar-10 | 90% | 0.00 | 44.50 | 44.50 | 0.00 | 63.42 | 63.42 | 63.42 | Work in progress | Pakyong | CONSTRUCTION | ROAD | 3 | KM | |||
| 8 | Upgradation of Link Road from NH-31A to Dokey Chisopani Km 1st | 1Km | Mr. Kishor Pradhan | Eleventh Plan | CRF | - | 0.00 | 152.58 | 152.58 | 29-Feb-08 | 28-Feb-09 | 45% | 0.00 | 50.24 | 50.24 | 0.00 | 102.34 | 102.34 | 102.34 | Work in progress | UPGRADATION | ROAD | 1 | KM | |||||
| 9 | Upgradation of Link Road from NH-31A to Dokey Chisopani Km 2nd | Singtam | 1Km | Mr. Gopal Sharma | Eleventh Plan | CRF | - | 29-Feb-08 | 28-Feb-09 | 50% | 0.00 | Work in progress | UPGRADATION | ROAD | 1 | KM | |||||||||||||
| 10 | Upgradation of Link Road from NH-31A to Dokey Chisopani Km 3rd | Singtam | 1Km | Mr. Suren Gurung | Ninth Plan | CRF | - | 29-Feb-08 | 28-Feb-09 | 50% | 0.00 | Work in progress | UPGRADATION | ROAD | 1 | KM | |||||||||||||
| 11 | Surface strengthening upgradation and carpeting of Pakyong-Karthok Naya Busty road km 5th -7th. | Pakyong | 2Km | Mr. Adup Bhutia | Tenth Plan | EI | Remv. | 183.89 | 183.89 | 367.78 | 21/06/05 | 31-Aug-08 | 85% | 3.16 | 28.52 | 31.68 | 180.73 | 155.37 | 336.10 | 336.10 | Work in progress | Pakyong | UPGRADATION | ROAD | 2 | KM | |||
| 12 | Upgradation/carpeting P/works and drainage along Pakyong-Karthok road km 1st-4th. | Pakyong | 4Km | Mr. P. N. Kazi | Tenth Plan | EI | Exp. | 143.35 | 143.35 | 286.70 | 28-Mar-05 | 27-Jul-06 | 80% | 38.43 | 47.54 | 85.97 | 104.92 | 95.81 | 200.73 | 200.73 | Work in progress | Pakyong | UPGRADATION | ROAD | 4 | KM | |||
| 13 | Upgradation and premix carpeting of Kotlaytar Rai Gaon Road,km 1st & 2nd | Pakyong | 2Km | Miss Devi Dakhal | Tenth Plan | EI | Exp. | 73.14 | 73.14 | 146.28 | 27-Sep-05 | 27-Sep-06 | 100% | 41.52 | 0.00 | 41.52 | 31.62 | 73.14 | 104.76 | 104.76 | Work in progress | Pakyong | UPGRADATION | ROAD | 2 | KM | |||
| 14 | Construction of Road from Rathong (NH-31A) to Kimchithang Km 1st to 15th (EI) | 15Km | Mr. KK Agarwal | Tenth Plan | EI | New Road | 874.19 | 701.89 | 1,576.08 | 21-Apr-08 | 20-Apr-10 | 50% | 0.63 | 212.00 | 212.63 | 873.56 | 489.89 | 1,363.45 | 1,363.45 | Work in progress | CONSTRUCTION | ROAD | 15 | KM | |||||
| 15 | Improvement of Sang Dipudara Road (EI) | 14Km | Dalu Ram Sharma / Sanjay Kumar | Tenth Plan | EI | Remv. | 277.44 | 347.74 | 625.18 | 18-Nov-02 | 17-Aug-04 | 80% | 233.08 | 0.00 | 233.08 | 44.36 | 347.74 | 392.10 | 392.10 | Work in progress | UPGRADATION | ROAD | 14 | KM | |||||
| 16 | Providing Premix and P/W at Sang Dipudara Road Km1-12th | 14Km | Mr. Sanjay Kumar Prasad | Tenth Plan | EI | Remv. | 0.00 | 100.28 | 100.28 | 12-Jun-09 | 11-Mar-10 | 15% | 0.00 | 0.00 | 0.00 | 0.00 | 100.28 | 100.28 | 100.28 | Work in progress | UPGRADATION | ROAD | 14 | KM | |||||
| 17 | Widening, upgradation of pavement & drainage system along Rangpo Duga Pendam road km 1st - 15th | 15Km | M/s Apex Project & Investment P. Ltd. | Eleventh Plan | ISC | - | 0.00 | 950.00 | 950.00 | 15-Jun-08 | 16-Dec-08 | 80% | 0.00 | 303.67 | 303.67 | 0.00 | 646.33 | 646.33 | 646.33 | Work in progress | UPGRADATION | ROAD | 15 | KM | |||||
| 18 | Improvement of Rhenock - Simanakhola Road Km 1st to 3rd. (ISC) | 3Km | Mr. Kuber Raj Rai | Tenth Plan | ISC | - | 0.00 | 250.00 | 250.00 | 26-Mar-08 | 27-Mar-09 | 70% | 0.00 | 50.00 | 50.00 | 0.00 | 200.00 | 200.00 | 200.00 | Work in progress | Pakyong | UPGRADATION | ROAD | 3 | KM | ||||
| 19 | Construction of Link Road from Sakyong to Beyong km 1st to 2nd (State Share of NABARD) | 2Km | KRSharma & TB Pradhan | Eleventh Plan | NABARD | Link Road | 19.47 | 79.51 | 98.98 | 12-Mar-08 | 11-Mar-09 | 93% | 0.00 | 43.42 | 43.42 | 19.47 | 36.09 | 55.56 | 55.56 | Work in progress | CONSTRUCTION | ROAD | 2 | KM | |||||
| 20 | Construction of Link Road from Sang Dipudara road to Beyong Gumpa Km 1st - 3rd. | 3 Km | Ujwal Pradhan,Pranay Pradhan,Wangdup Tamang | Eleventh Plan | NABARD | - | 0.00 | 148.95 | 148.95 | 28-Jan-09 | 27-Jan-11 | 47% | 0.00 | 0.00 | 0.00 | 0.00 | 148.95 | 148.95 | 148.95 | Work in progress | CONSTRUCTION | ROAD | 3 | KM | |||||
| 21 | Construction of new road from Sonamati to Kokoley Pry. School via Lingding Chanday Km 1st-6th. | 3 Km | Mrs. Devi Dhakal | Eleventh Plan | State Plan | Link Road | 340.00 | 0.00 | 340.00 | 1-Jun-09 | 3-Dec-10 | 47% | 41.00 | 0.00 | 41.00 | 299.00 | 0.00 | 299.00 | 299.00 | Work in progress | CONSTRUCTION | ROAD | 3 | KM | |||||
| 22 | Widening,surface strengthening, turning improvement and drainage work along Raley Kambel Samdung road Km 1st - 7th | Singtam | 7Km | Binod Agarwal | NABARD | Remv. | 0.00 | 801.60 | 801.60 | 1-Jun-09 | 31-Dec-10 | 20% | 0.00 | 0.00 | 0.00 | 0.00 | 801.60 | 801.60 | 801.60 | Work in progress | UPGRADATION | ROAD | 7 | KM | |||||
| 23 | Construction of New Road from Sonamati Sr. Sec. School to Lokoley Pry. School via Lingding Chanday Km 1st - 6th. | Singtam | 7Km | Devi Dhakal | NABARD | - | 0.00 | 340.00 | 340.00 | 1-Jun-09 | 31-Dec-10 | 30% | 0.00 | 41.00 | 41.00 | 0.00 | 299.00 | 299.00 | 299.00 | Work in progress | CONSTRUCTION | ROAD | 7 | KM | |||||
| 24 | Strengthening,drainage and Carpeting and construction of 30m span steel bridge along Assam-Pakyong road km 7th - 15th. | Pakyong | 30m | S.K. Agarwal | Tenth Plan | NEC | - | 0.00 | 750.78 | 750.78 | 6-Nov-06 | 5-May-08 | 95% | 0.00 | 514.44 | 514.44 | 0.00 | 236.34 | 236.34 | 236.34 | Work in progress | Pakyong | UPGRADATION | ROAD | 30 | M | |||
| 25 | Const. of Goshkhan Dara Bridge over River Teesta at Singtam, East Sikkim | Singtam | 120m | M.P Agarwal | Tenth Plan | NLCPR | - | 0.00 | 1,337.57 | 1,337.57 | 10-Jan-07 | 11-Jun-08 | 45% | 0.00 | 468.00 | 468.00 | 0.00 | 869.57 | 869.57 | 869.57 | Work in progress | CONSTRUCTION | BRIDGE | 120 | M | ||||
| 26 | Construction of diversion road Ranipool -Pakyong road km 1st -3rd | Singtam | 3 Km | B.K.Agarwal | Tenth Plan | NLCPR | - | 0.00 | 251.19 | 251.19 | 21-Feb-05 | 21-Nov-05 | 100% | 0.00 | 251.08 | 251.08 | 0.00 | 0.11 | 0.11 | 0.11 | Work completed | CONSTRUCTION | ROAD | 3 | KM | ||||
| 27 | Upgradation/carpeting and drainage along Pakyong-Mac hong Rolep Km 1st-19th. | Pakyong | 4Km | M/s Sangrila Trade Network P. Ltd. | NLCPR | Exp. | 778.31 | 0.00 | 778.31 | 25-Feb-09 | 24-Feb-11 | 5% | 0.00 | 0.00 | 0.00 | 778.31 | 0.00 | 778.31 | 778.31 | Work in progress | Pakyong | UPGRADATION | ROAD | 4 | KM | ||||
| 28 | Upgradation/carpeting and drainage along Pakyong-Mac hong Rolep Km 20th-35th. | M/s Apex Project & Investment P. Ltd. | NLCPR | Exp. | 695.24 | 0.00 | 695.24 | 25-Feb-09 | 24-Feb-11 | 5% | 0.00 | 0.00 | 0.00 | 695.24 | 0.00 | 695.24 | 695.24 | Work in progress | |||||||||||
| STATE PLAN | |||||||||||||||||||||||||||||
| 29 | Premix Carpetting and Surface improvement Chewribotay Pendam Km 1st - 6th | Singtam | 6Km | Basudev Pradhan | Tenth Plan | State Plan | Exp. | 117.78 | 0.00 | 117.78 | 29/05/2003 | 31/01/04 | 95% | 96.28 | 0.00 | 96.28 | 21.50 | 0.00 | 21.50 | 21.50 | Case under investigation by Vigilence Deptt.. | UPGRADATION | ROAD | 6 | KM | ||||
| 30 | Ext. of Pakyong-Mamring Tareythang road km 1st | 1Km | Khush N.Adhikari | Tenth Plan | State Plan | Exp. | 104.75 | 0.00 | 104.75 | 1-Jul-05 | 31-Dec-07 | 90% | 103.79 | 0.00 | 103.79 | 0.96 | 0.00 | 0.96 | 0.96 | Work in progress | CONSTRUCTION | ROAD | 1 | KM | |||||
| 31 | Ext. of Pakyong-Mamring Tareythang road km 2nd | 1Km | Johar Man Rai | Tenth Plan | State Plan | Exp. | 16.61 | 0.00 | 16.61 | 1-Jul-05 | 31-Dec-07 | 90% | 16.37 | 0.00 | 16.37 | 0.24 | 0.00 | 0.24 | 0.24 | Work in progress | CONSTRUCTION | ROAD | 1 | KM | |||||
| 32 | Ext. of Pakyong-Mamring Tareythang road km 3rd | 1Km | G.K. Pradhan | Tenth Plan | State Plan | Exp. | 22.70 | 0.00 | 22.70 | 1-Jul-05 | 31-Dec-07 | 100% | 22.16 | 0.00 | 22.16 | 0.54 | 0.00 | 0.54 | 0.54 | Final bill submitted | CONSTRUCTION | ROAD | 1 | KM | |||||
| 33 | Ext. of Pakyong-Mamring Tareythang road km 4th. | 1Km | Udai Mishara | Tenth Plan | State Plan | Exp. | 17.92 | 0.00 | 17.92 | 1-Jul-05 | 31-Dec-07 | 90% | 17.60 | 0.00 | 17.60 | 0.32 | 0.00 | 0.32 | 0.32 | Work in progress | CONSTRUCTION | ROAD | 1 | KM | |||||
| 34 | Ext. of Pakyong-Mamring Tareythang road km 5th. | 1Km | K.S.Rai | Tenth Plan | State Plan | Exp. | 27.01 | 0.00 | 27.01 | 1-Jul-05 | 31-Dec-07 | 100% | 16.05 | 0.00 | 16.05 | 10.96 | 0.00 | 10.96 | 10.96 | Final bill submitted | CONSTRUCTION | ROAD | 1 | KM | |||||
| 35 | Ext. of Pakyong-Mamring Tareythang road km 6th. | 1Km | Ishore Dakahal | Tenth Plan | State Plan | Exp. | 21.15 | 0.00 | 21.15 | 1-Jul-05 | 31-Dec-07 | 90% | 18.39 | 0.00 | 18.39 | 2.76 | 0.00 | 2.76 | 2.76 | Work in progress | CONSTRUCTION | ROAD | 1 | KM | |||||
| 36 | Ext. of Pakyong-Mamring Tareythang road km 7th. | 1Km | K.S.Rai | Tenth Plan | State Plan | Exp. | 22.10 | 0.00 | 22.10 | 1-Jul-05 | 31-Dec-07 | 85% | 8.68 | 0.00 | 8.68 | 13.42 | 0.00 | 13.42 | 13.42 | Work in progress | CONSTRUCTION | ROAD | 1 | KM | |||||
| 37 | Ext. of Pakyong-Mamring Tareythang road km.8th | 1Km | M. K. Pradhan | Tenth Plan | State Plan | Exp. | 21.66 | 0.00 | 21.66 | 1-Jul-05 | 31-Dec-07 | 95% | 11.01 | 0.00 | 11.01 | 10.65 | 0.00 | 10.65 | 10.65 | Work in progress | CONSTRUCTION | ROAD | 1 | KM | |||||
| 38 | Const. of Song-zingla Martam road km 9th. | 1Km | P.T. Lepcha | Eleventh Plan | State Plan | TSP | 12.45 | 0.00 | 12.45 | 5-Mar-03 | 20-Dec-03 | 100% | 5.63 | 0.00 | 5.63 | 6.82 | 0.00 | 6.82 | 6.82 | Work completed | CONSTRUCTION | ROAD | 1 | KM | |||||
| 39 | Surface strengthening premix carpeting along approach road to Sumick village Km 1st - 2nd. | 1Km | Punya Prasad Dhakal | Eleventh Plan | State Plan | SCSP | 12.45 | 0.00 | 12.45 | 5-Mar-03 | 20-Dec-03 | 55% | 5.63 | 0.00 | 5.63 | 6.82 | 0.00 | 6.82 | 6.82 | Work completed | UPGRADATION | ROAD | 1 | KM | |||||
| 40 | Construction of link road from Chewribotey to Sawney Pry. School. | 1Km | Ms. Mera Thapa | Eleventh Plan | State Plan | SCSP | 27.00 | 0.00 | 27.00 | 10-Aug-09 | 9-Aug-10 | 5% | 0.00 | 0.00 | 0.00 | 27.00 | 0.00 | 27.00 | 27.00 | Work in progress | UPGRADATION | ROAD | 1 | KM | |||||
| 41 | Construction of link road from AssamPakyong road to Kadamtang village Km 3rd & 4th. | Singtam | 1Km | D.P Manger | State Plan | New Road | 41.74 | 0.00 | 41.74 | 7-Jan-05 | 30-Jun-06 | 100% | 29.63 | 0.00 | 29.63 | 12.11 | 0.00 | 12.11 | 12.11 | Work completed, revised estimate submitted | CONSTRUCTION | ROAD | 1 | KM | |||||
| 42 | Construction of Mechanical Complex at Sirwani in East Sikkim. | Singtam | 1Km | Mukesh Agarwal | State Plan | Remv. | 133.00 | 0.00 | 133.00 | 1-Jun-09 | 31-May-10 | 5% | 0.00 | 0.00 | 0.00 | 133.00 | 0.00 | 133.00 | 133.00 | Work in progress | UPGRADATION | ROAD | 1 | KM | |||||
| CONSTRUCTION | HELI PORT | 1 | NOS. | 1 | NOS. | ||||||||||||||||||||||||
| #REF! | NOS. | ||||||||||||||||||||||||||||