MONTHLY PHYSICAL AND FINANCIAL  PROGRESS REPORT FOR THE MONTH ENDING JANUARY 2010
   
Sl.No Name of Schemes   Length Km / M Name of Contractor Plan Funding Agency (Head) SANCTIONED  AMOUNT Date of Commen- cement Stipulated Date of Completion Phy Prog-ress               in % Financial Progress Balance  TOTAL SA-BAL Remarks
  S. share C.share Total Expenditure till date  
  S.Share C.Share Total S.Share C.Share Total  
A DISTRICT:  NORTH          
  CENTRAL  SPONSORED  SCHEMES                      
1 Construction of new road from Gumpa Golai to Chanzing, Lachen.   0.48 Km Mr Nangden Lachungpa   BADP BADP 0.00 38.10 38.10 24-Feb-06 23-Jan-07 85% 0.00 19.40 19.40 0.00 18.70 18.70 18.70 Work in progress Mangan CONSTRUCTION ROAD 0.48 KM
2 Upgradation / Strengthening and Carpeting of approach road to Latoong Village.   1Km Mr Nangden Lachungpa   BADP BADP 0.00 42.79 42.79 24-Jan-08 23-Oct-08 90% 0.00 10.00 10.00 0.00 32.79 32.79 32.79 Work in progress Mangan UPGRADATION ROAD 1 KM
3 Construction of Guest House / Inspection Bunglow at Yakthang, Lachen (Thangu).   N/A Mr. Tanam Lachungpa   BADP BADP 0.00 138.00 138.00 26-Feb-09 7-Oct-10 30% 0.00 0.00 0.00 0.00 138.00 138.00 138.00 Non stock material are collecting at site Mangan CONSTRUCTION BUILDING
4 Construction of 18 mtrs span Steel Bridge over Rakshey Khola along Penlong - Tintek road at Km 13th, CH: 1   18m Departmental Tenth Plan CRF CRF 0.00 90.99 90.99 18-Oct-06 18-Aug-09 95% 0.00 75.97 75.97 0.00 15.02 15.02 15.02 Work in progress CONSTRUCTION BRIDGE 18 M
5 Construction of link road from Passingdong PHC to Lingthem Gumpa & Lingthem School Km 1st to 18th   18 Km Mr. Krishna Agarwal Eleventh Plan NLCPR  New Road 484.26 765.00 1,249.26 11-Feb-09 10-Feb-11 25% 0.00 0.00 0.00 484.26 765.00 1,249.26 1,249.26 Work in progress CONSTRUCTION ROAD 18 KM
6 Upgradation Ranka - Luing-Gangtok-Burtuk-Road Km 14th to 21st   7 Km Mr. Shyam Rai Tenth Plan NLCPR  Exp. 221.54 420.00 641.54 11-Jan-05 19-Jul-07 68% 96.51 420.00 516.51 125.03 0.00 125.03 125.03 Work in progress Sub-Div- IV UPGRADATION ROAD 7 KM
7 Upgradation of LLHP to Nandok village road Km 1st to 4th in East Sikkim.   4 Km Jogen Mukhia Tenth Plan NLCPR  CSS 71.72 358.60 430.32 June-09 June-10 20% 0.00 0.00 0.00 71.72 358.60 430.32 430.32 Work in progress Sub-Div- IV UPGRADATION ROAD 4 KM
8 Upgradation and providing premix carpetting  including protective works  and improvement of drainage system to Tintek-Dikchu road, Km 1st to 12th in East Sikkim.   12 Km M/S K.K.Group of Company Tenth Plan NLCPR  CSS 383.41 1,080.53 1,463.94 23-Jun-09 23-Jun-11 30% 0.00 0.00 0.00 383.41 1,080.53 1,463.94 1,463.94 Work in progress Sub-Div- IV UPGRADATION ROAD 12 KM
9 Construction 0f 90m span steel bridge over Takcham Chu along C.R.B.A Road, Km 21st    90m Mrs. Meera Rai Tenth Plan NEC Exp. 0.00 476.74 476.74 9-Jan-06 8-Oct-06 92% 0.00 410.81 410.81 0.00 65.93 65.93 65.93 Work in progress Sub-Div- IV CONSTRUCTION  BRIDGE 90 M
10 Upgradation / carpeting & extension i/c providing drainage and protective works of Marchak - Tumlabong road, Km 1st to 13th in East Sikkim   13Km M/s Ladakhi Const. Pvt. Ltd. Tenth Plan NEC Exp. 100.00 1023.00 1123.00 9-Nov-06 18-May-08 75% 0.00 554.44 554.44 100.00 468.56 568.56 568.56 Work in progress Sub-Div- IV UPGRADATION ROAD 13 KM
11 Construction of steel bridge over Teesta river at Gour at Dzongu (LC from SP 6.84)   122m Mr. Samdup Lepcha Tenth Plan NEC NEC 6.84 488.57 495.41 21-Jan-06 22-Jan-07 95% 6.62 404.99 411.61 0.22 83.58 83.80 83.80 Work in progress Mangan CONSTRUCTION  BRIDGE 122 M
12 Construction of Steel Bridge on Approach road to Khedum Village in North Sikkim.   50m Mr. Penzong Lachungpa Tenth Plan NEC Repl. 0.00 281.51 281.51 24-Feb-06 23-Jan-07 98% 0.00 258.81 258.81 0.00 22.70 22.70 22.70 Work in progress Mangan CONSTRUCTION  BRIDGE 50 M
13 Extension of 3rd Km road from 3rd mile turning (Tintek Dikchu road) to Rakshey via Kedangthang Km 4th to 6th   2Km Devi Dhakal Tenth Plan NABARD New Road 64.09 224.660 288.750 15-May-08 15-May-09 100% 21.58 180.61 202.19 42.51 44.05 86.56 86.56 Work completed Sub-Div- IV CONSTRUCTION  ROAD 2 KM
14 Extension of link road fromGRS road Km 12th CH 5 to Tatopani at Rumtek   1Km M. Karki Tenth Plan NABARD Link Road 10.05 40.190 50.240 15-May-08 15-May-09 45% 0.00 0.18 0.18 10.05 40.01 50.06 50.06 Work in progress Sub-Div- IV CONSTRUCTION  ROAD 1 KM
15 Construction of Link Road from Takchi Phatak to Upper Luing, Km 1st   1Km Mr. Tsweang Rinzing Bhutia Tenth Plan NABARD New Road 32.51 289.930 322.440 18-Aug-05 17-Aug-06 95% 22.11 180.79 202.90 10.40 109.14 119.54 119.54 Work in progress Sub-Div- IV CONSTRUCTION  ROAD 1 KM
16 Construction of Link Road from Takchi Phatak to Upper Luing, Km 2 nd   1Km Mr. Dewjang Bhutia Tenth Plan NABARD New Road 18-Aug-05 17-Aug-06 95% 0.00 Work in progress Sub-Div- IV CONSTRUCTION  ROAD 1 KM
17 Construction of Link Road from Takchi Phatak to Upper Luing, Km 3rd   1Km Mr. Tempo Gyatso Bhutia Tenth Plan NABARD New Road 23-Sep-05 22-Sep-06 95% 0.00 Work in progress Sub-Div- IV CONSTRUCTION  ROAD 1 KM
18 Construction of Link Road from Takchi Phatak to Upper Luing, Km 4th   1Km Mrs. Yangchen Dolma Bhutia Tenth Plan NABARD New Road 23-Sep-05 22-Sep-06 80% 0.00 Work in progress Sub-Div- IV CONSTRUCTION  ROAD 1 KM
19 Construction of Link Road from Takchi Phatak to Upper Luing, Km 5th   1Km   NABARD New Road 23-Sep-05 22-Sep-06 80% 0.00 Work in progress Sub-Div- IV CONSTRUCTION  ROAD 1 KM
20 Construvction of Link Road from Bay to Pentong in North Sikkim.   3.9 Km Mr. Bernald Lepcha Tenth Plan RSVY  New Road 59.97 150.00 209.97 22-Sep-05 31-Dec-08 65% 24.56 128.03 152.59 35.41 21.97 57.38 57.38 Work in progress Mangan CONSTRUCTION  ROAD 3.9 KM
21 Construction of Heli Port at Lachung   N/A Mr. Nidup Lachungpa Ninth Plan Tourism Other Expenditure 38.89 0.00 38.89 3-Apr-00 2-Jan-01 72% 28.43 0.00 28.43 10.46 0.00 10.46 10.46 Intimation has been given to contractor to carry out the remaining work wilthin the sanctioned cost. Mangan CONSTRUCTION  PORT - KM
  WORKS  SANCTIONED  UNDER  STATE  PLAN                              
22 Construction of link road to Aho - Manghim Km 1st - 3rd (L.C = 42.02)   3 Km Mr. B.K. Upreti / BR Subba / Beena Subba Tenth Plan State Plan Link Road 177.37 0.00 177.37 2-Dec-04 15-Jan-07 71% 84.87 0.00 84.87 92.50 0.00 92.50 92.50 Work in progress Sub-Div- IV CONSTRUCTION  ROAD 3 KM
23 Upgradation,carpetting, protective and drainage of SBS road to Lingtam PHSE Km 1st to 5th.   5Km Mr. Samdup Lepcha Eleventh Plan State Plan Strengthning Road Infrastructure Dzongu 385.54 0.00 385.54 22-Nov-03 27-Jun-09 70% 167.60 0.00 167.60 217.94 0.00 217.94 217.94 Work in progress Mangan UPGRADATION ROAD 5 KM
24 Upgradation,carpetting, protective and drainage works of DSM road to Gour School Km 1st to 8th.   8Km Mr. Soden Gyamptso Bhutia Tenth Plan State Plan 391.66 0.00 391.66 1-Jun-08 1-Jan-09 65% 166.13 0.00 166.13 225.53 0.00 225.53 225.53 Work in progress Mangan UPGRADATION ROAD 8 KM
25 Construction of Guest House at Pentok, Mangan, North Sikkim.   N/A Mr. K.J Lachenpa Eleventh Plan State Plan TSP 187.08 0.00 187.08 23-Feb-09 22-Jan-10 10% 0.00 0.00 0.00 187.08 0.00 187.08 187.08 Non stock material are collecting at site Mangan CONSTRUCTION  BUILDING
26 Widening protective work drainage & carpetting work on S.B.S Road Km 10th & 12th   2Km Mr. Lobzang Lepcha Tenth Plan State Plan TSP 19.52 0.00 19.52 15-Nov-03 14-Aug-04 73% 0.00 0.00 0.00 19.52 0.00 19.52 19.52 Work in progress Mangan UPGRADATION ROAD 2 KM
27 Widening protective work drainage & carpetting work on S.B.S Road Km 13th    1Km Mr. Sonam Dorjee Tenth Plan State Plan TSP 17.95 0.00 17.95 18-Nov-04 17-May-05 70% 8.57 0.00 8.57 9.38 0.00 9.38 9.38 Work in progress Mangan UPGRADATION ROAD 1 KM
28 Widening protective work drainage & carpetting work on S.B.S Road Km 14th & 15th    2Km Mr. Topnam Lepcha Tenth Plan State Plan TSP 35.11 0.00 35.11 11-Jan-03 10-Oct-03 90% 19.47 0.00 19.47 15.64 0.00 15.64 15.64 Work in progress Mangan UPGRADATION ROAD 2 KM
29 Strengthening, protective / drainage carpetting works on approach road to Ringtham Gumpa Km1st to 3rd  Mangan.   3Km K.N. Lachenpa   State Plan TSP 268.00 0.00 268.00 14-Mar-08 18-Sep-09 70% 179.06 0.00 179.06 88.94 0.00 88.94 88.94 Work in progress Mangan UPGRADATION ROAD 3 KM
30 Construction approach road to medicine pond B-6   0.96 Km Mr. Tempo Lepcha   State Plan TSP 105.00 0.00 105.00 6-Mar-08 7-Mar-09 72% 79.41 0.00 79.41 25.59 0.00 25.59 25.59 Work in progress Mangan CONSTRUCTION  ROAD 0.96 KM
31 Construction of approach road to Shakothang at Sarchok village   0.67 Km Mr. Dawa Gaytmso Lachenpa Tenth Plan State Plan TSP 64.90 0.00 64.90 7-Apr-08 8-Apr-09 71% 38.51 0.00 38.51 26.39 0.00 26.39 26.39 Work in progress Mangan CONSTRUCTION  ROAD 0.67 KM
32 Protective works, widening, drainage and carpeting on Bictchu road Km 1st to 3rd to Gai Gaon at Lachung   3Km Mr. Needup Lacungpa   State Plan TSP 298.00 0.00 298.00 21-Aug-08 2-Aug-10 65% 165.81 0.00 165.81 132.19 0.00 132.19 132.19 Work in progress Mangan UPGRADATION ROAD 3 KM
CONSTRUCTION  ROAD 35.01 KM 13 NOS.
UPGRADATION ROAD 61 KM 12 NOS.
CONSTRUCTION  BUILDING 2 NOS. 2 NOS.
CONSTRUCTION  BRIDGE 280 M 4 NOS.
CONSTRUCTION  HELI PORT 1 NOS. 1 NOS.
32 NOS.