| MONTHLY PHYSICAL AND FINANCIAL PROGRESS REPORT FOR THE MONTH ENDING JANUARY 2009 | |||||||||||||||||||||||
| Sl.No | Name of Schemes | Length Km / M | Name of Contractor | Plan | Funding Agency | (Head) | SANCTIONED AMOUNT | Date of Commen- cement | Stipulated Date of Completion | Phy Prog-ress in % | Financial Progress | Balance | TOTAL SA-BAL | Remarks | |||||||||
| S. share | C.share | Total | Expenditure till date | ||||||||||||||||||||
| S.Share | C.Share | Total | S.Share | C.Share | Total | ||||||||||||||||||
| A | DISTRICT: NORTH | ||||||||||||||||||||||
| CENTRAL SPONSORED SCHEMES | |||||||||||||||||||||||
| 1 | Construction of app. Road to Thomchi Gumpa. | 0.15 Km | Mr. Tashi Lachungpa | BADP | BADP | 0.00 | 15.69 | 15.69 | 6-Feb-07 | 5-May-07 | 100% | 0.00 | 9.97 | 9.97 | 0.00 | 5.72 | 5.72 | 5.72 | Completed | ||||
| 2 | Construction of new road from Gumpa Golai to Chanzing, Lachen. | 0.48 Km | Mr Nangden Lachungpa | BADP | BADP | 0.00 | 38.10 | 38.10 | - | - | - | 0.00 | 0.00 | 0.00 | 0.00 | 38.10 | 38.10 | 38.10 | Work delay due to land compens-ation | ||||
| 3 | Upgradation / Strengthening and Carpeting of approach road to Latoong Village. | 1Km | Mr Nangden Lachungpa | BADP | BADP | 0.00 | 42.79 | 42.79 | - | - | 70% | 0.00 | 19.40 | 19.40 | 0.00 | 23.39 | 23.39 | 23.39 | work in progress | ||||
| 4 | Construction of Guest House / Inspection Bunglow at Yakthang, Lachen (Thangu). | N/A | - | BADP | BADP | 0.00 | 138.00 | 138.00 | - | - | - | 0.00 | 0.00 | 0.00 | 0.00 | 138.00 | 138.00 | 138.00 | - | ||||
| 5 | Extension of Bakcha -Labi road Km 3rd & 4th. State share of BADP land compansation. | 2Km | Mr. Ugen Nedup Bhutia | BADP | BADP | 0.00 | 50.00 | 50.00 | - | - | 100% | 0.00 | 49.91 | 49.91 | 0.00 | 0.09 | 0.09 | 0.09 | Work Closed | ||||
| 6 | Upgradation & Surface strengthening of Ranka-Sichey road Km 1st to 3rd | 3Km | Mr. Rajesh Agarwal | Tenth Plan | CRF | Removal | 30.78 | 88.26 | 119.04 | 17-Mar-05 | 31-May-06 | 100% | 0.00 | 72.10 | 72.10 | 30.78 | 16.16 | 46.94 | 46.94 | Final bill submitted | |||
| 7 | Upgradation of Phodong -Labrang Gumpa | 2.25 Km | Mr. K.N. Bhutia | Tenth Plan | CRF | CRF | 0.00 | 158.96 | 158.96 | 3-Nov-05 | 2-Oct-06 | 100% | 0.00 | 151.37 | 151.37 | 0.00 | 7.59 | 7.59 | 7.59 | Completed Final bill to be paid | |||
| 8 | Construction of 18 mtrs span Steel Bridge over Rakshey Khola along Penlong - Tintek road at Km 13th, CH: 1 | 18m | - | Tenth Plan | CRF | CRF | 0.00 | 90.99 | 90.99 | 18-Oct-06 | - | 90% | 0.00 | 60.97 | 60.97 | 0.00 | 30.02 | 30.02 | 30.02 | work in progress | |||
| 9 | Widening of upgradation, carpetting, protective of drainage works on approach road to Zimchung Busty from DAC road, Mangan | 2.45 Km | Department. | Tenth Plan | MP (LAPS) | - | 0.00 | 25.00 | 25.00 | - | - | 100% | 0.00 | 0.00 | 0.00 | 0.00 | 25.00 | 25.00 | 25.00 | In Progress | |||
| 10 | Upgradation Ranka - Luing-Gangtok-Burthuk-Road Km 14th to 21st | 7 Km | Mr. Shyam Rai | Tenth Plan | NLCPR | Exp. | 221.54 | 420.00 | 641.54 | 11-Jan-05 | 19-Jul-07 | 68% | 0.00 | 408.00 | 408.00 | 221.54 | 12.00 | 233.54 | 233.54 | work in progress | |||
| 11 | Construction 0f 90m span steel bridge over Takcham Chu along C.R.B.A Road, Km 21st | 90m | Mrs. Meera Rai | Tenth Plan | NEC | Exp. | 0.00 | 476.74 | 476.74 | 9-Jan-06 | 8-Oct-06 | 90% | 0.00 | 324.00 | 324.00 | 0.00 | 152.74 | 152.74 | 152.74 | work in progress Expd. In Purchase of Vechile steel parts | |||
| 12 | Upgradation / carpeting & extension i/c providing drainage and protective works of Marchak - Tumlabong road, Km 1st to 13th in East Sikkim | 13Km | M/s Ladakhi Const. Pvt. Ltd. | Tenth Plan | NEC | Exp. | 0.00 | 1,023.00 | 1,023.00 | 9-Nov-06 | 18-May-08 | 65% | 0.00 | 339.05 | 339.05 | 0.00 | 683.95 | 683.95 | 683.95 | work in progress | |||
| 13 | Construction of steel bridge over Teesta river at Gour | 122m | Mr. Samdup Lepcha | Tenth Plan | NEC | NEC | 0.00 | 488.57 | 488.57 | 21-Jan-06 | 22-Jan-07 | 94% | 0.00 | 404.99 | 404.99 | 0.00 | 83.58 | 83.58 | 83.58 | In Progress | |||
| 14 | Strengthening / drainage carpetting of SBS road to Tingbong high school | 7km | Mr. G.N. Agarwal | Tenth Plan | NEC | NEC / TSP | 401.38 | 401.38 | 802.76 | 29-Apr-05 | 30-Apr-06 | 100% | 401.38 | 367.19 | 768.57 | 0.00 | 34.19 | 34.19 | 34.19 | Completed | |||
| 15 | Construction of Steel Bridge on Approach road to Khedum Village in North Sikkim. | 50m | Mr. Penzong Lachungpa | Tenth Plan | NEC | NEC | 0.00 | 281.51 | 281.51 | 24-Feb-06 | 23-Jan-07 | 94% | 0.00 | 198.75 | 198.75 | 0.00 | 82.76 | 82.76 | 82.76 | In Progress | |||
| 16 | Upgradation of Marchak Tumlabong Road (NEC ) State Share for LC | N/A | Compensatiion | NEC | Removal | 100.00 | 1,023.00 | 1,123.00 | - | - | 37% | 37.00 | 522.75 | 559.75 | 63.00 | 500.25 | 563.25 | 563.25 | work in progress | ||||
| 17 | Construction of road from lower Lingdum to Adampool, Km 3rd & 4th | 2Km | Mr. Ajay Rai | Tenth Plan | NABARD | Exp. | 29.64 | 73.43 | 103.07 | 16-Nov-06 | 15-May-07 | 80% | 18.59 | 73.43 | 92.02 | 11.05 | 0.00 | 11.05 | 11.05 | Work Closed | |||
| 18 | Carpetting of app. Road to Crematorium ground at Jalipool. | 0.28 Km | Mr. Praveen Agarwal | Tenth Plan | NABARD | Exp. | 11.14 | 20.66 | 31.80 | 31-Jan-06 | 15-Jun-06 | 100% | 9.35 | 17.00 | 26.35 | 1.79 | 3.66 | 5.45 | 5.45 | Final bill submitted | |||
| 19 | Construction of Link Road from Takchi Phatak to Upper Luing, Km 1st | 1Km | Mr. Tsweang Rinzing Bhutia | Tenth Plan | NABARD | New Road | 0.00 | 289.930 | 289.930 | 18-Aug-05 | 17-Aug-06 | 90% | 0.00 | 138.17 | 138.17 | 0.00 | 151.76 | 151.76 | 151.76 | work in progress | |||
| 20 | Construction of Link Road from Takchi Phatak to Upper Luing, Km 2 nd | 1Km | Dewjang Bhutia | Tenth Plan | NABARD | New Road | 18-Aug-05 | 17-Aug-06 | 85% | 0.00 | Work just started | ||||||||||||
| 21 | Construction of Link Road from Takchi Phatak to Upper Luing, Km 3rd | 1Km | Tempo Gyatso Bhutia | Tenth Plan | NABARD | New Road | 23-Sep-05 | 22-Sep-06 | 85% | 0.00 | Work just started | ||||||||||||
| 22 | Construction of Link Road from Takchi Phatak to Upper Luing, Km 4th | 1Km | Yangchen Dolma Bhutia | Tenth Plan | NABARD | New Road | 23-Sep-05 | 22-Sep-06 | 0% | 0.00 | work in progress | ||||||||||||
| 23 | Construction of Link Road from Takchi Phatak to Upper Luing, Km 5th | 1Km | Yangchen Dolma Bhutia | NABARD | New Road | 23-Sep-05 | 22-Sep-06 | 0% | 0.00 | work in progress | |||||||||||||
| 24 | Extension of 3rd Km road from 3rd mile turning (Tintek Dikchu road) to Rakshey via Kedangthang Km 4th to 6th | 2Km | Devi Dhakal | Tenth Plan | NABARD | - | 56.17 | 224.460 | 280.630 | 15-May-08 | 15-May-09 | 80% | 0.00 | 62.73 | 62.73 | 56.17 | 161.73 | 217.90 | 217.90 | work in progress | |||
| 25 | Extension of link road fromGRS road Km 12th CH 5 to Tatopani at Rumtek | 1Km | M. Karki | Tenth Plan | NABARD | - | 0.00 | 40.190 | 40.190 | 15-May-08 | 15-May-09 | 20% | 0.00 | 0.18 | 0.18 | 0.00 | 40.01 | 40.01 | 40.01 | work was delay due to objection raised by DCC Rumtek | |||
| 26 | Construction of Link Road from Zimchung to Nampathang KM 1st to 3rd | 3Km | Mr. Zingmee Ongda, Mr. Dawa.Lepcha, Mr. Choppel Tshering | Tenth Plan | RSVY | RSVY | 18.75 | 112.11 | 130.86 | 10-Nov-05 | 10-Nov-06 | 100% | 16.32 | 112.11 | 128.43 | 2.43 | 0.00 | 2.43 | 2.43 | Completed | |||
| 27 | Construction of Link Road from 3rd Mile Turning of Tintek Dikchu road to Rakshey via Kedhangthang. Km 1st to 3rd. | 3Km | Punya Prasad Dhakhal | Tenth Plan | RSVY | New Road | 22.00 | 121.79 | 143.79 | 25-Oct-05 | 31-Jan-07 | 100% | 0.00 | 120.76 | 120.76 | 22.00 | 1.03 | 23.03 | 23.03 | work in progress | |||
| 28 | Construvction of Link Road from Bay to Pentong in North Sikkim. | 3.9 Km | Mr. Bernald Lepcha | Tenth Plan | RSVY | New Road | 37.45 | 150.00 | 187.45 | 22-Sep-05 | 31-Dec-08 | 65% | 0.00 | 128.03 | 128.03 | 37.45 | 21.97 | 59.42 | 59.42 | In Progress | |||
| 29 | Upgradation carpetting works of Chaten Khimten Village road in North Sikkim | 0.9 Km | Mr. Janam Lachen | Ninth Plan | RSVY | RSVY | 0.00 | 38.00 | 38.00 | 12-Sep-05 | 11-Aug-06 | 100% | 0.00 | 38.00 | 38.00 | 0.00 | 0.00 | 0.00 | 0.00 | Completed | |||
| 30 | Construction of Heli Port at Lachung | N/A | Mr. Nidup Lachungpa | Ninth Plan | Tourism | Other Expenditure | 38.89 | 0.00 | 38.89 | 3-Apr-00 | 2-Jan-01 | 75% | 0.00 | 28.43 | 28.43 | 38.89 | -28.43 | 10.46 | 10.46 | Defence clearance not yet received | |||
| WORKS SANCTIONED UNDER STATE PLAN | |||||||||||||||||||||||
| 31 | Approach Road to Samdong Rest House at Samdong East Sikkim | 0.15 Km | Mr. Dorjee Choppel | State Plan | Addl.Facilities | 14.04 | 0.00 | 14.04 | 20-May-03 | 19-Apr-04 | 100% | 14.04 | 14.04 | 28.08 | 0.00 | -14.04 | -14.04 | -14.04 | Completed | ||||
| 32 | Construction of Rest House at Samdong in East Sikkim. | N/A | Mr. Nitup Lepcha | Tenth Plan | Addl.Facilities | Addl.Facilities | 78.70 | 0.00 | 78.70 | 20-May-03 | 19-Apr-04 | 100% | 75.32 | 0.00 | 75.32 | 3.38 | 0.00 | 3.38 | 3.38 | Completed, Final bill paid | |||
| 33 | Premix carpetting,on Penlong - Tintek road Km 12th - 20th | 8Km | Mr. Suresh Mundra | Tenth Plan | State Plan | Exp. | 158.79 | 0.00 | 158.79 | 28-Nov-02 | 31-Mar-06 | 100% | 99.54 | 0.00 | 99.54 | 59.25 | 0.00 | 59.25 | 59.25 | Final bill to be submitted | Discuss | Expenditure | |
| 34 | Const. of GOR Santok road Km. 1st | 1Km | Mr.Pentok Lepcha | Tenth Plan | State Plan | Exp. | 29.76 | 0.00 | 29.76 | - | - | 100% | 21.61 | 0.00 | 21.61 | 8.15 | 0.00 | 8.15 | 8.15 | Completed | |||
| 35 | Additional sanction for Land Comensation for the work ' Construction of Link Road Km 1st to 3rd from Ranipool-Pakyong Road to Mangheem at Aho. | 3Km | Land Compensation | Tenth Plan | State Plan | Link Road | 42.02 | 0.00 | 42.02 | 2007 | - | - | 25.00 | 0.00 | 25.00 | 17.02 | 0.00 | 17.02 | 17.02 | - | |||
| 36 | Construction of link road to Aho - Manghim Km 1st | 1Km | Mr. B.K. Upreti | Tenth Plan | State Plan | Link Road | 16.88 | 0.00 | 16.88 | 2-Dec-04 | 15-Jan-07 | 94% | 11.37 | 0.00 | 11.37 | 5.51 | 0.00 | 5.51 | 5.51 | work in progress | |||
| 37 | Const. of link road to Aho - Manghim Km 2nd | 1Km | BR Subba | Tenth Plan | State Plan | Link Road | 18.88 | 0.00 | 18.88 | 2-Dec-04 | 15-Jan-07 | 55% | 0.00 | 0.00 | 0.00 | 18.88 | 0.00 | 18.88 | 18.88 | work in progress | |||
| 38 | Const. of link road to Aho - Manghim Km 3 rd | 1Km | Beena Subba | Tenth Plan | State Plan | Link Road | 19.27 | 0.00 | 19.27 | 1-Dec-04 | 15-Jan-07 | 40% | 0.00 | 0.00 | 0.00 | 19.27 | 0.00 | 19.27 | 19.27 | work in progress | |||
| 39 | Construction of app. Road from Samdong Cha Chu to Yumi Samdong, north Sikkim. Km 1st & 2nd | 2Km | Mr. T. Doma Lachungpa | Tenth Plan | State Plan | New Road | 54.48 | 0.00 | 54.48 | 21-Jun-04 | 20-Dec-05 | 100% | 54.58 | 0.00 | 54.58 | -0.10 | 0.00 | -0.10 | -0.10 | Work Completed | |||
| 40 | Surface renewal / restoration works on approach road to Mission Khoti. | 2Km 13ch | Mr. Ugen palzor | State Plan | Removal | 32.79 | 0.00 | 32.79 | 28-Feb-04 | 27-Aug-04 | 100% | 32.60 | 0.00 | 32.60 | 0.19 | 0.00 | 0.19 | 0.19 | Completed | ||||
| 41 | Premix carpetting p/w approach road to Hee-Gyathang School. | 0.7 Km | Department. | Tenth Plan | State Plan | Removal | 23.01 | 0.00 | 23.01 | - | - | 100% | 19.99 | 0.00 | 19.99 | 3.02 | 0.00 | 3.02 | 3.02 | Completed | |||
| 42 | Premix carpeting on GRBA road KM 1st -10th (Phase I ) Revised | 10Km | Mr. A.N. Upreti | Tenth Plan | State Plan | Removal | 215.65 | 0.00 | 215.65 | 13-Jan-03 | 12-Jul-04 | 96% | 207.01 | 0.00 | 207.01 | 8.64 | 0.00 | 8.64 | 8.64 | Completed | |||
| 43 | Premix carpetting, improvement of GRBA road Km 18th to 21st and Assam Pakyong Road Km 1st to 6th. | 9Km | Mr. Amrit Rai | Tenth Plan | State Plan | Removal | 254.76 | 0.00 | 254.76 | 25-Aug-04 | 31-Mar-06 | 100% | 184.20 | 0.00 | 184.20 | 70.56 | 0.00 | 70.56 | 70.56 | Completed | |||
| 44 | Uplifting & Surface & Drainage works, improvement along approach road to Sichey school. | 0.21 km | Mr. Rohit Pradhan | Tenth Plan | State Plan | Removal | 3.77 | 0.00 | 3.77 | 27-Feb-06 | 29-Dec-06 | 100% | 3.03 | 0.00 | 3.03 | 0.74 | 0.00 | 0.74 | 0.74 | Completed | |||
| 45 | Upgradation and Imp of Rumtek Ranka road Km 18th | 1Km | Department. | Ninth Plan | State Plan | Removal | 1.36 | 0.00 | 1.36 | - | - | 0% | 0.00 | 0.00 | 0.00 | 1.36 | 0.00 | 1.36 | 1.36 | work in progress | |||
| 46 | Construction of 15 mtrs span RCCl Bridge over Khedum Chu | 15m | Gyatso Bhutia | State Plan | Removal | 20.72 | 0.00 | 20.72 | 12-Nov-98 | 11-Mar-99 | 100% | 19.36 | 0.00 | 19.36 | 1.36 | 0.00 | 1.36 | 1.36 | |||||
| 47 | Land Compensation for the work construction of Multi Span Bridge over River Teesta at Gour at Dzongu | N/A | LC | Ninth Plan | State Plan | Removal | 6.84 | 0.00 | 6.84 | - | - | 100% | 6.62 | 0.00 | 6.62 | 0.22 | 0.00 | 0.22 | 0.22 | ||||
| 48 | Construction of 55m Supension Bridge over Khedumcu at Lachung | 55m | Needup Lacungpa | Tenth Plan | State Plan | Removal | 112.31 | 0.00 | 112.31 | 12-Nov-98 | 11-Jul-99 | 100% | 100.09 | 0.00 | 100.09 | 12.22 | 0.00 | 12.22 | 12.22 | Copansation Remaining | |||
| 49 | Upgradation,carpetting, protective and drainage of SBS road to Lingtam PHSE Km 1st to 5th. | 5Km | Mr. Samdup Lepcha | Eleventh Plan | State Plan | Strengthning Road Infrastructure | 385.54 | 0.00 | 385.54 | - | - | 55% | 42.22 | 42.22 | 84.44 | 343.32 | -42.22 | 301.10 | 301.10 | work in progress | |||
| 50 | Upgradation,carpetting, protective and drainage works of DSM road to Gour School Km 1st to 8th. | 8Km | Mr. Soden Gyamptso Bhutia | Tenth Plan | State Plan | Strengthning Road Infrastructure | 391.66 | 0.00 | 391.66 | 1-Jun-08 | 1-Jan-09 | 50% | 57.78 | 57.78 | 115.56 | 333.88 | -57.78 | 276.10 | 276.10 | work in progress | |||
| 51 | Protective Drainage and Carpetting works on SBS Road Km 3 & 4 | 2Km | Mr. Pintso Namgyal | Ninth Plan | State Plan | TSP | 27.19 | 0.00 | 27.19 | 27-Nov-01 | 26-Feb-02 | 100% | 19.37 | 0.00 | 19.37 | 7.82 | 0.00 | 7.82 | 7.82 | Completed | |||
| 52 | Protective Drainage and Carpetting works on SBS Road Km 5 & 6 | 2Km | Mr. Karma Lepcha | Ninth Plan | State Plan | TSP | 23.38 | 0.00 | 23.38 | 11-Jan-03 | 10-Oct-03 | 100% | 16.77 | 0.00 | 16.77 | 6.61 | 0.00 | 6.61 | 6.61 | Completed | |||
| 53 | Protective Drainage and Carpetting works on SBS Road Km 7 | 1Km | Mr. Ten Tsh. Lepcha | Ninth Plan | State Plan | TSP | 11.17 | 0.00 | 11.17 | 27-Nov-01 | 26-Nov-02 | 100% | 7.17 | 0.00 | 7.17 | 4.00 | 0.00 | 4.00 | 4.00 | Completed | |||
| 54 | Protective Drainage and Carpetting works on SBS Road Km 8 | 1Km | Mr. Dupden Lepcha | Ninth Plan | State Plan | TSP | 22.48 | 0.00 | 22.48 | 27-Nov-01 | 27-Nov-02 | 100% | 19.28 | 0.00 | 19.28 | 3.20 | 0.00 | 3.20 | 3.20 | Completed | |||
| 55 | Protective Drainage and Carpetting works on SBS Road Km 9 | 1Km | Mr. Pintso Lepcha | State Plan | TSP | 19.23 | 0.00 | 19.23 | 27-Nov-01 | 28-Nov-02 | 100% | 18.21 | 0.00 | 18.21 | 1.02 | 0.00 | 1.02 | 1.02 | Completed | ||||
| 56 | Construction of Guest House at Pentok, Mangan, North Sikkim. | N/A | - | Eleventh Plan | State Plan | TSP | 187.08 | 0.00 | 187.08 | 2006 | - | - | 0.00 | 0.00 | 0.00 | 187.08 | 0.00 | 187.08 | 187.08 | ||||
| 57 | Widening protective work drainage & carpetting work on S.B.S Road Km 10th & 12th | 2Km | Mr. Lobzang Lepcha | Tenth Plan | State Plan | TSP | 34.51 | 0.00 | 34.51 | 15-Nov-03 | 14-Aug-04 | 73% | 14.99 | 0.00 | 14.99 | 19.52 | 0.00 | 19.52 | 19.52 | Carpetting work to be done. | |||
| 58 | Widening protective work drainage & carpetting work on S.B.S Road Km 13th | 1Km | Mr. Sonam Dorjee | Tenth Plan | State Plan | TSP | 18.68 | 0.00 | 18.68 | 18-Nov-04 | 17-May-05 | 70% | 0.73 | 0.00 | 0.73 | 17.95 | 0.00 | 17.95 | 17.95 | WBM/carpetting work to be done | |||
| 59 | Widening protective work drainage & carpetting work on S.B.S Road Km 14th & 15TH | 2Km | Mr. Topnam Lepcha | State Plan | TSP | 35.15 | 0.00 | 35.15 | 11-Jan-03 | 10-Oct-03 | 80% | 10.24 | 0.00 | 10.24 | 24.91 | 0.00 | 24.91 | 24.91 | Carpetting work to be done. | ||||
| 60 | Strengthening, protective / drainage carpetting works on approach road to Ringtham Gumpa Km1st to 3rd Mangan. | 3Km | K.N. Lachenpa | State Plan | TSP | 276.00 | 0.00 | 276.00 | 14-Mar-08 | 18-Sep-09 | 55% | 11.51 | 0.00 | 11.51 | 264.49 | 0.00 | 264.49 | 264.49 | work in progress | ||||
| 61 | Construction approach road to medicine pond B-6 | 0.96 Km | Tempo Lepcha | State Plan | TSP | 105.00 | 0.00 | 105.00 | 6-Mar-08 | 7-Mar-09 | 65% | 62.73 | 0.00 | 62.73 | 42.27 | 0.00 | 42.27 | 42.27 | work in progress | ||||
| 62 | Construction approach road to Shakothang at Sarchok village | 0.67 Km | Dawa Gaytmso Lachenpa | Tenth Plan | State Plan | TSP | 64.98 | 0.00 | 64.98 | 7-Apr-08 | 8-Apr-09 | 40% | 3.27 | 0.00 | 3.27 | 61.71 | 0.00 | 61.71 | 61.71 | work in progress | |||
| 63 | Protective works, widening, drainage and carpeting on Bictchu road Km 1st to 3rd to Gai Gaon at Lachung | 3Km | Needup Lacungpa | State Plan | TSP | 298.00 | 0.00 | 298.00 | 21-Aug-08 | 2-Aug-10 | 40% | 86.28 | 0.00 | 86.28 | 211.72 | 0.00 | 211.72 | 211.72 | work in progress | ||||
| 64 | Premix Carpetting imp & widening of D.S.M road km 12th to 16th | 4Km | Mr. Singhik Lepcha | Tenth Plan | State Plan | TSP | 124.05 | 0.00 | 124.05 | 15-Jan-03 | 14-Jul-04 | 80% | 54.90 | 0.00 | 54.90 | 69.15 | 0.00 | 69.15 | 69.15 | Bill prepared till work done, Road Handed to BRO | |||
| 65 | Premix Carpetting imp & widening of D.S.M road km 17th | 1Km | Mr. Chewang Norbu | Tenth Plan | State Plan | TSP | 19.41 | 0.00 | 19.41 | 11-Jan-03 | 10-Oct-03 | 100% | 9.93 | 0.00 | 9.93 | 9.48 | 0.00 | 9.48 | 9.48 | Final bill to be paid | |||
| 66 | Premix Carpetting imp & widening of D.S.M road km 18th | 1Km | Mr. Dawa Tshering | Tenth Plan | State Plan | TSP | 19.56 | 0.00 | 19.56 | 11-Jan-03 | 10-Oct-03 | 85% | 10.91 | 0.00 | 10.91 | 8.65 | 0.00 | 8.65 | 8.65 | Bill prepared till work done, Road Handed to BRO | |||
| 67 | Premix Carpetting imp & widening of D.S.M road km 19th | 1Km | Mr. Ongden lepcha | Tenth Plan | State Plan | TSP | 20.44 | 0.00 | 20.44 | 11-Jan-03 | 10-Oct-03 | 73% | 7.44 | 0.00 | 7.44 | 13.00 | 0.00 | 13.00 | 13.00 | ||||
| 68 | Premix Carpetting imp & widening of D.S.M road km 20th | 1Km | Mr. Mingma Tshering | Tenth Plan | State Plan | TSP | 20.04 | 0.00 | 20.04 | 11-Jan-03 | 10-Oct-03 | 74% | 12.50 | 0.00 | 12.50 | 7.54 | 0.00 | 7.54 | 7.54 | ||||
| 69 | Premix Carpetting imp & widening of D.S.M road km 21st | 1Km | Mr. Lobzang Lepcha | State Plan | TSP | 23.38 | 0.00 | 23.38 | 11-Jan-03 | 10-Oct-03 | 75% | 13.55 | 0.00 | 13.55 | 9.83 | 0.00 | 9.83 | 9.83 | |||||
| B | DISTRICT :EAST | ||||||||||||||||||||||
| CENTRAL SPONSORED SCHEMES | |||||||||||||||||||||||
| 1 | Const. of link road from Arubotey to Subaneydara km 1st-3rd. | Pakyong | 3Km | Om Bhd. Gurung | Ninth Plan | BADP | - | 0.00 | 29.97 | 29.97 | 30-Nov-00 | 16-Mar-01 | 68% | 0.00 | 22.98 | 22.98 | 0.00 | 6.99 | 6.99 | 6.99 | work abondoned | ||
| 2 | Const. of link road from sisney to North Regu km 1st -4th. | Pakyong | 4Km | T.S. Lama | Tenth Plan | BADP | - | 0.00 | 30.31 | 30.31 | 21-Nov-00 | 5-Mar-01 | 95% | 0.00 | 24.54 | 24.54 | 0.00 | 5.77 | 5.77 | 5.77 | work abondoned | ||
| 3 | Construction of 60 m span steel bridge at Bongliung over Rongli Chu in East Sikkim | 60m | Gazendra Rai | Eleventh Plan | CSS | 0.00 | 74.07 | 74.07 | 29-Mar-08 | 29-Sep-09 | 15% | 0.00 | 0.00 | 0.00 | 0.00 | 74.07 | 74.07 | 74.07 | work in progress | ||||
| 4 | Const. of 12 m span R.C.C. Bridge on Sangkhola Zingla Martam Road at Km 11th ch-3rd. | 12m | Anita Gurung | Eleventh Plan | CRF | - | 0.00 | 38.63 | 38.63 | 1-Apr-07 | 31-Mar-08 | 45% | 0.00 | 10.23 | 10.23 | 0.00 | 28.40 | 28.40 | 28.40 | work under progress | |||
| 5 | Const. of 12 m span R.C.c. Bridge on Sangkhola Zingla Martam Road at Km 12th ch-4th.. | 12m | T.B. Pradhan | Eleventh Plan | CRF | - | 0.00 | 45.12 | 45.12 | 1-Apr-07 | 31-Mar-08 | 60% | 0.00 | 27.70 | 27.70 | 0.00 | 17.42 | 17.42 | 17.42 | work under progress | |||
| 6 | Surface improvement and widening of Sang Sirwani Road Km 1st & App Road from Mech Sub Div Office at Dochum | 1Km | Kishor Pradhan | Eleventh Plan | CRF | - | 0.00 | 155.00 | 155.00 | 10-Oct-07 | 9-Sep-08 | 85% | 0.00 | 71.18 | 71.18 | 0.00 | 83.82 | 83.82 | 83.82 | work under progress | |||
| 7 | Surface improvement and widening of Sang Sirwani Road Km 2nd & App Road to Mech Workshop Dochum | 1Km | K.R. Sharma | Eleventh Plan | CRF | - | 0.00 | 38.49 | 38.49 | 10-Oct-07 | 9-Sep-08 | 65% | 0.00 | 12.61 | 12.61 | 0.00 | 25.88 | 25.88 | 25.88 | work under progress | |||
| 8 | Upgradation of Link Road from NH-31A to Dokey Chisopani Km 1st | 1Km | Kishor Pradhan | Eleventh Plan | CRF | - | 0.00 | 152.58 | 0.00 | 29-Feb-08 | 28-Feb-09 | 35% | 0.00 | 29.41 | 0.00 | 0.00 | 123.17 | 0.00 | 0.00 | Work to Commence | |||
| 9 | Upgradation of Link Road from NH-31A to Dokey Chisopani Km 2nd | Singtam | 1Km | Gopal Sharma | Eleventh Plan | CRF | - | 29-Feb-08 | 28-Feb-09 | 30% | 0.00 | work under progress | |||||||||||
| 10 | Upgradation of Link Road from NH-31A to Dokey Chisopani Km 3rd | Singtam | 1Km | Suren Gurung | Ninth Plan | CRF | - | 29-Feb-08 | 28-Feb-09 | 45% | 0.00 | work under progress | |||||||||||
| 11 | Construction of link road from pakyong Nop gaon to barpipal Dara, Km 1st-3rd in East-Sikkim | Pakyong | 3Km | Hemandri Adhikari | Eleventh Plan | CRF | CSS | 0.00 | 102.29 | 102.29 | 5-Aug-08 | 5-Mar-10 | 25% | 0.00 | 0.00 | 0.00 | 0.00 | 102.29 | 102.29 | 102.29 | work in progress | ||
| 12 | Premix carpetting and widening work on Sang dipudara road Km 1st to 12th. | 12Km | Daluram Sarda | Tenth Plan | EI | Removal | 6.95 | 277.44 | 284.39 | 18/11/2002 | 17/08/2004 | 90% | 0.00 | 233.08 | 233.08 | 6.95 | 44.36 | 51.31 | 51.31 | Sanctioned from EI Rs 6.95 Crore | |||
| 13 | Upgradationand premix carpeting along Duga Pachaykhani road KM 1st-14th. | Singtam | 14Km | B.K.Agarwal | Tenth Plan | EI | Removal | 407.61 | 433.77 | 841.38 | 21-Feb-05 | 5-Mar-08 | 100% | 24.00 | 433.77 | 457.77 | 383.61 | 0.00 | 383.61 | 383.61 | Work Completed | ||
| 14 | Construction of Road from Rathong (NH-31A) to Kimchithang Km 1st to 15th (EI) | 15Km | KK Agarwal | Tenth Plan | EI | - | 765.00 | 701.89 | 1,466.89 | 2007 | - | 30% | 0.00 | 209.91 | 209.91 | 765.00 | 491.98 | 1,256.98 | 1,256.98 | New Project | |||
| 15 | Improvement of Sang Dipudara Road (EI) | 14Km | - | Tenth Plan | EI | - | 0.00 | 347.74 | 347.74 | 2007 | - | 90% | 0.00 | 0.00 | 0.00 | 0.00 | 347.74 | 347.74 | 347.74 | New Project | |||
| 16 | Improvement of Pakyong - Karthok - Naya busty - Raigoan Road (EI) | - | Eleventh Plan | EI | - | 0.00 | 398.42 | 398.42 | 2007 | - | 45% | 0.00 | 160.00 | 160.00 | 0.00 | 238.42 | 238.42 | 238.42 | New Project | ||||
| 17 | Widening, upgradation of pavement & drainage system along Rangpo Duga Pendam road km 1st - 15th | 15Km | M/s Apex Project & Investment P. Ltd. | Eleventh Plan | ISC | - | 0.00 | 950.00 | 950.00 | 15-Jun-08 | 16-Dec-08 | 65% | 0.00 | 303.67 | 303.67 | 0.00 | 646.33 | 646.33 | 646.33 | work in progress | |||
| 18 | Improvement of Rhenock - Simanakhola Road Km 1st to 3rd. (ISC) | 3Km | Mr. Kuber Raj Rai | Tenth Plan | ISC | - | 0.00 | 250.00 | 250.00 | 26-Mar-08 | - | 25% | 0.00 | 49.43 | 49.43 | 0.00 | 200.57 | 200.57 | 200.57 | work in progress | |||
| 19 | Carpetting of Sirwani Bermoik Phongla Road, S.Sikkim (ISC) | 24Km | - | Tenth Plan | ISC | - | 0.00 | 999.08 | 999.08 | 26-Jul-05 | - | 10% | 0.00 | 766.00 | 766.00 | 0.00 | 233.08 | 233.08 | 233.08 | work in progress | |||
| 20 | Strengthening/drainage and P/Wprks for the road from Lal Turning to Bashilakha Road Km 1st to 3rd | Pakyong | 3Km | G.M Gurung | NABARD | Exp. | 33.19 | 125.21 | 158.40 | 30/09/07 | 31/03/08 | 100% | 0.00 | 124.82 | 124.82 | 33.19 | 0.39 | 33.58 | 33.58 | Work Completed | |||
| 21 | Const. of link road from King Stone to Simana Khola Km 1st to 2nd. | 2Km | Departmental | Eleventh Plan | NABARD | Exp. | 8.60 | 34.41 | 43.01 | - | - | 100% | 0.00 | 31.68 | 31.68 | 8.60 | 2.73 | 11.33 | 11.33 | completed | |||
| 22 | Construction of Link Road from Sakyong to Beyong km 1st to 2nd (State Share of NABARD) | 2Km | KRSharma & TB Pradhan | Eleventh Plan | NABARD | Exp. | 0.00 | 79.51 | 79.51 | 12-Mar-08 | 11-Mar-09 | 75% | 0.00 | 23.59 | 23.59 | 0.00 | 55.92 | 55.92 | 55.92 | work under progress | |||
| 23 | Strengthening,drainage and Carpeting and construction of 30m span steel bridge along Assam-Pakyong road km 7th - 15th. | Pakyong | 30m | S.K. Agarwal | Tenth Plan | NEC | - | 0.00 | 750.76 | 750.76 | 6-Nov-06 | 5-May-08 | 75% | 0.00 | 465.96 | 465.96 | 0.00 | 284.80 | 284.80 | 284.80 | work under process | ||
| 24 | Construction of major retaining structures on approach road to Raj Bhawan,VIP Complex and TNA Public School Complex | N/A | Tenth Plan | NEC | - | 0.00 | 110.58 | 110.58 | 30-May-05 | 29-May-06 | 100% | 0.00 | 99.67 | 99.67 | 0.00 | 10.91 | 10.91 | 10.91 | completed | ||||
| 25 | Replacement of Sumin Wooden Suspension Bridge on Sang Khola Sumin Road | Eleventh Plan | NEC | - | 0.00 | 285.40 | 285.40 | 8-Apr-04 | - | - | 0.00 | 233.00 | 233.00 | 0.00 | 52.40 | 52.40 | 52.40 | - | |||||
| 26 | Const. of Goshkhan Dara Bridge over River Teesta at Singtam, East Sikkim | Singtam | 120m | M.P Agarwal | Tenth Plan | NLCPR | - | 0.00 | 1,337.11 | 1,337.11 | 10-Jan-07 | 11-Jun-08 | 40% | 0.00 | 468.00 | 468.00 | 0.00 | 869.11 | 869.11 | 869.11 | work in progress | ||
| 27 | Const. of diversion road Ranipool-Pakyong road km 1st-3rd. | Pakyong | 3Km | B.K. Agarwal | Tenth Plan | NLCPR | Exp. | 102.98 | 236.87 | 339.85 | 21-Feb-05 | 21-Nov-05 | 80% | 64.60 | 170.78 | 235.38 | 38.38 | 66.09 | 104.47 | 104.47 | work in progress | ||
| 28 | Extension of Link Road to Dokey Chisopani Pry School ( State Share of RSVY Scheme) | 0.81Km | Nabin Rai | Eleventh Plan | RSVY | New Road | 1.72 | 25.00 | 26.72 | 17-Oct-05 | 27-Mar-06 | 85% | 0.00 | 25.00 | 25.00 | 1.72 | 0.00 | 1.72 | 1.72 | in progress | |||
| STATE PLAN | |||||||||||||||||||||||
| 29 | Repairs of IETC SMITE Overhead crane station at 5th Mile Tadong | N/A | Departmental | Tenth Plan | State Plan | Addl.Facilities | 1.35 | 0.00 | 1.35 | 20-Jul-06 | - | 5% | 1.35 | 0.00 | 1.35 | 0.00 | 0.00 | 0.00 | 0.00 | work in progress | |||
| 30 | Fencing around SPWD Mech. Workshop Tadong | N/A | Departmental | Eleventh Plan | State Plan | Addl.Facilities | 2.74 | 0.00 | 2.74 | 31-Aug-06 | - | 5% | 2.73 | 0.00 | 2.73 | 0.01 | 0.00 | 0.01 | 0.01 | work in progress | |||
| 31 | Additonal facilities installation of portable magazine at Sirwani-Singtam | N/A | Departmental | Tenth Plan | State Plan | Addl.Facilities | 10.00 | 0.00 | 10.00 | 22-Aug-07 | - | 5% | 9.45 | 0.00 | 9.45 | 0.55 | 0.00 | 0.55 | 0.55 | work in progress | |||
| 32 | Premix carpetting/Imp. Of Rongli Rorathang road, Km 1st - 11th.( Revised) | 11Km | Kuber Raj Rai | Tenth Plan | State Plan | Exp. | 254.00 | 0.00 | 254.00 | 1-Jan-03 | 3-Apr-06 | 100% | 215.36 | 0.00 | 215.36 | 38.64 | 0.00 | 38.64 | 38.64 | completed | |||
| 33 | Upgradation/carpeting P/works and drainage along Pakyong-Karthok road km 1st-4th. | Pakyong | 4Km | P. N. Kazi | Tenth Plan | State Plan | Exp. | 286.69 | 0.00 | 286.69 | 28-Mar-05 | 27-Jul-06 | 55% | 95.08 | 0.00 | 95.08 | 191.61 | 0.00 | 191.61 | 191.61 | work in progress | ||
| 34 | Upgradation and premix carpeting of Kotlaytar Rai Gaon Road,km 1st & 2nd | Pakyong | 2Km | Miss Devi Dakhal | Tenth Plan | State Plan | Exp. | 146.88 | 0.00 | 146.88 | 28-Mar-05 | 27-Sep-06 | 75% | 31.05 | 0.00 | 31.05 | 115.83 | 0.00 | 115.83 | 115.83 | Revised estimate submitted | ||
| 35 | Upgradation and premix carpeting of Kotlaytar Rai Gaon Road,km 3rd | Pakyong | 1Km | Mr. G.K. Pradhan | Tenth Plan | State Plan | Exp. | 22.70 | 0.00 | 22.70 | 1-Jul-05 | 31-Dec-07 | 90% | 22.13 | 0.00 | 22.13 | 0.57 | 0.00 | 0.57 | 0.57 | work taken up departmentaly | ||
| 36 | Upgradation and premix carpeting of Kotlaytar Rai Gaon Road,km 4th | Pakyong | 1Km | XXX | Tenth Plan | State Plan | Exp. | 17.92 | 0.00 | 17.92 | 1-Jul-05 | 31-Dec-07 | 90% | 17.60 | 0.00 | 17.60 | 0.32 | 0.00 | 0.32 | 0.32 | Revised estimate submitted | ||
| 37 | Upgradation and premix carpeting of Kotlaytar Rai Gaon Road,km 5th | Pakyong | 1Km | K.S.Rai | Tenth Plan | State Plan | Exp. | 27.01 | 0.00 | 27.01 | 1-Jul-05 | 31-Dec-07 | 90% | 16.04 | 0.00 | 16.04 | 10.97 | 0.00 | 10.97 | 10.97 | Revised estimate submitted | ||
| 38 | Upgradation and premix carpeting of Kotlaytar Rai Gaon Road,km 6th | Pakyong | 1Km | Ishore Dakahal | Tenth Plan | State Plan | Exp. | 21.15 | 0.00 | 21.15 | 1-Jul-05 | 31-Dec-07 | 70% | 17.79 | 0.00 | 17.79 | 3.36 | 0.00 | 3.36 | 3.36 | Revised estimate submitted | ||
| 39 | Upgradation and premix carpeting of Kotlaytar Rai Gaon Road,km 7th | Pakyong | 1Km | K.S.Rai | Tenth Plan | State Plan | Exp. | 22.10 | 0.00 | 22.10 | 1-Jul-05 | 31-Dec-07 | 55% | 8.68 | 0.00 | 8.68 | 13.42 | 0.00 | 13.42 | 13.42 | Revised estimate submitted | ||
| 40 | Upgradation and premix carpeting of Kotlaytar Rai Gaon Road,km 8th | Pakyong | 1Km | Mr. M.K. Pradhan | Tenth Plan | State Plan | Exp. | 21.66 | 0.00 | 21.66 | 1-Jul-05 | 31-Dec-07 | 55% | 17.06 | 0.00 | 17.06 | 4.60 | 0.00 | 4.60 | 4.60 | Revised estimate submitted | ||
| 41 | Premix Carpetting and Surface improvement Chewribotay Pendam Km 1st - 6th | Singtam | 6Km | Basudev Pradhan | Tenth Plan | State Plan | Exp. | 117.78 | 0.00 | 117.78 | 29/05/2003 | 31/01/04 | 95% | 83.84 | 0.00 | 83.84 | 33.94 | 0.00 | 33.94 | 33.94 | work in progress | ||
| 42 | Construction of Bye Pass Road below Mintokgang | Station | 0.30Km | DB Chettri | Tenth Plan | State Plan | Exp. | 80.26 | 0.00 | 80.26 | 26-Feb-04 | 5-Aug-04 | 100% | 71.46 | 0.00 | 71.46 | 8.80 | 0.00 | 8.80 | 8.80 | Final bill under process | ||
| 43 | Premix carpetting & Surface Imp.of KLT 16th to 26th Km (Revised) | 10Km | P.D. Denzongpa | Tenth Plan | State Plan | Exp. | 260.57 | 0.00 | 260.57 | 2003 | - | 100% | 252.36 | 0.00 | 252.36 | 8.21 | 0.00 | 8.21 | 8.21 | completed | |||
| 44 | Premix carpetting & Surface Imp.of KLT 7th to 15th Km (Revised) | 8Km | L.N. Sarda | Tenth Plan | State Plan | Exp. | 232.83 | 0.00 | 232.83 | 2003 | - | 100% | 214.16 | 0.00 | 214.16 | 18.67 | 0.00 | 18.67 | 18.67 | completed | |||
| 45 | Ext. of Pakyong-Mamring Tareythang road km 1st | 1Km | Khush N.Adhikari | Tenth Plan | State Plan | Exp. | 28.91 | 0.00 | 28.91 | 1-Jul-05 | 31-Dec-07 | 90% | 28.72 | 0.00 | 28.72 | 0.19 | 0.00 | 0.19 | 0.19 | Revised | |||
| 46 | Ext. of Pakyong-Mamring Tareythang road km 2nd | 1Km | Johar Man Rai | Tenth Plan | State Plan | Exp. | 16.61 | 0.00 | 16.61 | 1-Jul-05 | 31-Dec-07 | 90% | 16.37 | 0.00 | 16.37 | 0.24 | 0.00 | 0.24 | 0.24 | Revised | |||
| 47 | Ext. of Pakyong-Mamring Tareythang road km 3rd | 1Km | G.K. Pradhan | Tenth Plan | State Plan | Exp. | 22.70 | 0.00 | 22.70 | 1-Jul-05 | 31-Dec-07 | 90% | 12.94 | 0.00 | 12.94 | 9.76 | 0.00 | 9.76 | 9.76 | Revised Estimate submitted | |||
| 48 | Ext. of Pakyong-Mamring Tareythang road km 4th. | 1Km | Udai Mishara | Tenth Plan | State Plan | Exp. | 17.92 | 0.00 | 17.92 | 1-Jul-05 | 31-Dec-07 | 90% | 12.02 | 0.00 | 12.02 | 5.90 | 0.00 | 5.90 | 5.90 | Revised Estimate submitted | |||
| 49 | Ext. of Pakyong-Mamring Tareythang road km 5th. | 1Km | K.S.Rai | Tenth Plan | State Plan | Exp. | 27.01 | 0.00 | 27.01 | 1-Jul-05 | 31-Dec-07 | 90% | 16.05 | 0.00 | 16.05 | 10.96 | 0.00 | 10.96 | 10.96 | Revised Estimate submitted | |||
| 50 | Ext. of Pakyong-Mamring Tareythang road km 6th. | 1Km | Ishore Dakahal | Tenth Plan | State Plan | Exp. | 21.15 | 0.00 | 21.15 | 1-Jul-05 | 31-Dec-07 | 70% | 18.71 | 0.00 | 18.71 | 2.44 | 0.00 | 2.44 | 2.44 | Revised Estimate submitted | |||
| 51 | Ext. of Pakyong-Mamring Tareythang road km 7th. | 1Km | K.S.Rai | Tenth Plan | State Plan | Exp. | 22.10 | 0.00 | 22.10 | 1-Jul-05 | 31-Dec-07 | 55% | 8.68 | 0.00 | 8.68 | 13.42 | 0.00 | 13.42 | 13.42 | Revised Estimate submitted | |||
| 52 | Ext. of Pakyong-Mamring Tareythang road km.8th | 1Km | M. K. Pradhan | Tenth Plan | State Plan | Exp. | 21.66 | 0.00 | 21.66 | 1-Jul-05 | 31-Dec-07 | 55% | 0.00 | 0.00 | 0.00 | 21.66 | 0.00 | 21.66 | 21.66 | Revised Estimate submitted | |||
| 53 | Ext. of Pakyong-Mamring Tareythang road km.9th | 1Km | Kamal Adhikari | Tenth Plan | State Plan | Exp. | 19.24 | 0.00 | 19.24 | 1-Jul-05 | 31-Dec-07 | 100% | 8.00 | 0.00 | 8.00 | 11.24 | 0.00 | 11.24 | 11.24 | Completed, Final bill under process | |||
| 54 | Ext. of Pakyong-Mamring Tareythang road km.10th | 1Km | Milan Dahal | Tenth Plan | State Plan | Exp. | 10.70 | 0.00 | 10.70 | 1-Jul-05 | 31-Dec-07 | 100% | 0.00 | 0.00 | 0.00 | 10.70 | 0.00 | 10.70 | 10.70 | Completed | |||
| 55 | Construction of Arithang Road connecting Indira Bye-Pass Road | Station | 0.6Km | Departmental | Tenth Plan | Exp. | 57.47 | 0.00 | 57.47 | 2005 | - | 100% | 55.75 | 0.00 | 55.75 | 1.72 | 0.00 | 1.72 | 1.72 | completed | |||
| 56 | Const. of road from Zingla Martam KM 16th-18th (2.36km) i/c LC | 2Km | UP Kazi | Tenth Plan | State Plan TSP | Exp. | 77.96 | 0.00 | 77.96 | 3-Oct-05 | 3-Oct-06 | 100% | 83.16 | 0.00 | 83.16 | -5.20 | 0.00 | -5.20 | -5.20 | work in progress | |||
| 57 | Feeder Raod to development Area( Addl sanction on 9th Paln scheme) Ssno 1/East/Exp/06-07 | 0.3Km | T. wangchok | Tenth Plan | Exp. | 5.04 | 0.00 | 5.04 | 2006 | - | 100% | 5.04 | 0.00 | 5.04 | 0.00 | 0.00 | 0.00 | 0.00 | Revised | ||||
| 58 | Const of 40 Mts span Bridge over Rongli Khola along arubotey subaney dara Raod Ssno 2/E/exp/06-07 | 40m | Ashok Ts. Bhutia | Eleventh Plan | Exp. | 16.50 | 0.00 | 16.50 | 2006 | - | 100% | 14.24 | 0.00 | 14.24 | 2.26 | 0.00 | 2.26 | 2.26 | completed | ||||
| 59 | Immediate Restoration of Mamring Amba Road km 3rd | 1Km | Departmental | Tenth Plan | Exp. | 6.77 | 0.00 | 6.77 | 6-Nov-06 | 5-May-08 | 100% | 6.68 | 0.00 | 6.68 | 0.09 | 0.00 | 0.09 | 0.09 | completed | ||||
| 60 | Relocation and extension of HT < line and shifting of 25 KVA outdoor pipe distribution sub-station at Barchangey Village East. | N/A | Power Department | Eleventh Plan | Exp. | 3.37 | 0.00 | 3.37 | 2006 | - | 100% | 3.37 | 0.00 | 3.37 | 0.00 | 0.00 | 0.00 | 0.00 | completed | ||||
| 61 | Construction of 20 chain road Bio Control Laboratory to Phewk Busty road | Station | 0.60Km | Mr. G.K.Rai | Tenth Plan | State Plan | Link Road | 25.03 | 0.00 | 25.03 | 28-Sep-05 | 27-Mar-05 | 85% | 9.00 | 0.00 | 9.00 | 16.03 | 0.00 | 16.03 | 16.03 | Revised estimate under process | ||
| 62 | Const. of link road from Basilakhs to Middle camp via Rodongtar km 6th | Pakyong | 1Km | Justin Rai | Tenth Plan | State Plan | New Road | 17.93 | 0.00 | 17.93 | 5-Oct-05 | 9-Feb-05 | 75% | 12.41 | 0.00 | 12.41 | 5.52 | 0.00 | 5.52 | 5.52 | Revised estimate submitted | ||
| 63 | Const. of link road from Basilakhs to Middle camp via Rodongtar km 7th | Pakyong | 1Km | Jeewan Subba | Tenth Plan | State Plan | New Road | 17.23 | 0.00 | 17.23 | 5-Oct-05 | 9-Feb-05 | 100% | 17.22 | 0.00 | 17.22 | 0.01 | 0.00 | 0.01 | 0.01 | completed | ||
| 64 | Const. of link road from Basilakhs to Middle camp via Rodongtar km 8th | Pakyong | 1Km | Paul Rai | Tenth Plan | State Plan | New Road | 21.36 | 0.00 | 21.36 | 5-Oct-05 | 9-Feb-05 | 100% | 10.01 | 0.00 | 10.01 | 11.35 | 0.00 | 11.35 | 11.35 | work in progress | ||
| 65 | Const. of 10m span RCC Culvert on Basilakha to middle camp km 8th. | 10m | Patrush Subba | Tenth Plan | State Plan | New Road | 12.32 | 0.00 | 12.32 | 5-Oct-05 | 9-Feb-05 | 75% | 0.00 | 0.00 | 0.00 | 12.32 | 0.00 | 12.32 | 12.32 | work in progress | |||
| 66 | Const of Approach road to Sivalaya Mandir at pacheykhani Km 1st | 1Km | R.N. Baral | State Plan | New Road | 23.51 | 0.00 | 23.51 | 18-Jul-05 | 15-Jun-06 | 85% | 12.87 | 0.00 | 12.87 | 10.64 | 0.00 | 10.64 | 10.64 | work in progress | ||||
| 67 | Construction of Link Road from Amba to Taja School 1st and 2nd km | 2Km | Mon Narayan Dhakal | Tenth Plan | State Plan | New Road | 5.06 | 0.00 | 5.06 | - | - | 75% | 3.96 | 0.00 | 3.96 | 1.10 | 0.00 | 1.10 | 1.10 | work in progress | |||
| 68 | Const. of link road from Assam-Pakyong road to Kadamtam village km.1st. | Pakyong | 1Km | M.B.Mangar | Tenth Plan | State Plan | New Road | 39.65 | 0.00 | 39.65 | 1-Jul-05 | 30-Jun-06 | 100% | 39.51 | 0.00 | 39.51 | 0.14 | 0.00 | 0.14 | 0.14 | Completed, Final bill under process | ||
| 69 | Const. of link road from Assam-Pakyong road to Kadamtam village km.2nd. | Pakyong | 1Km | Elies Lepcha | Tenth Plan | State Plan | New Road | 41.40 | 0.00 | 41.40 | 1-Jul-05 | 30-Jun-06 | 100% | 41.39 | 0.00 | 41.39 | 0.01 | 0.00 | 0.01 | 0.01 | Completed, Final bill under process | ||
| 70 | Const. of link road from Assam-Pakyong road to Kadamtam village km.3rd & 4th. | Pakyong | 2Km | D.P. Mangar | Tenth Plan | State Plan | New Road | 41.51 | 0.00 | 41.51 | 1-Jul-05 | 30-Jun-06 | 75% | 29.71 | 0.00 | 29.71 | 11.80 | 0.00 | 11.80 | 11.80 | Revised Est Submitted | ||
| 71 | Const. of link road from Assam-Pakyong road to Kadamtam village km.3rd & 4th.Contingency Rs.4.26 + Land Compansation | Pakyong | 2Km | LC & Contg | Tenth Plan | State Plan | New Road | 87.70 | 0.00 | 87.70 | - | - | 100% | 34.27 | 0.00 | 34.27 | 53.43 | 0.00 | 53.43 | 53.43 | completed | ||
| 72 | Construction of road from Chandmari village to Jawaharlall Nehru road | Station | 0.38 Km | K Wangchuk | State Plan | New Road | 30.63 | 0.00 | 30.63 | 31-May-05 | 30-Nov-05 | 100% | 23.76 | 0.00 | 23.76 | 6.87 | 0.00 | 6.87 | 6.87 | work completed final bill under process | |||
| 73 | Land compensation for extension of link road from NH-31 A to Chisopani km 2nd | 1Km | Tenth Plan | State Plan | New Road | 3.35 | 0.00 | 3.35 | - | - | 100% | 3.35 | 0.00 | 3.35 | 0.00 | 0.00 | 0.00 | 0.00 | completed | ||||
| 74 | Land compenstion for construction of Link road from Basilakha to Middle Camp via Radongtar km 6th to 8th & 10th M Span R.C.C Bridge | 3Km | Eleventh Plan | State Plan | New Road | 19.47 | 0.00 | 19.47 | 2008 | - | - | 0.00 | 0.00 | 0.00 | 19.47 | 0.00 | 19.47 | 19.47 | |||||
| 75 | Const. of Song-zingla Martam road km 9th. | 1Km | P.T. Lepcha | Eleventh Plan | State Plan | New Road | 12.45 | 0.00 | 12.45 | 5-Mar-03 | 20-Dec-03 | 80% | 5.63 | 0.00 | 5.63 | 6.82 | 0.00 | 6.82 | 6.82 | In progress | |||
| 76 | Const. of Sang-Zingla Martam road KM 10th. | 1Km | P.T. Rongong | Eleventh Plan | State Plan | New Road | 14.51 | 0.00 | 14.51 | 6-Mar-03 | 6-Dec-03 | 100% | 12.45 | 0.00 | 12.45 | 2.06 | 0.00 | 2.06 | 2.06 | Final Payment | |||
| 77 | Const. of Song-Zingla Martam road km 11th | 1Km | Anita Gurung | Eleventh Plan | State Plan | New Road | 16.17 | 0.00 | 16.17 | 6-Mar-03 | 6-Dec-03 | 100% | 12.28 | 0.00 | 12.28 | 3.89 | 0.00 | 3.89 | 3.89 | Final Payment | |||
| 78 | Const. of Song-Zingla Martam road km 12th. | 1Km | U. Lama | Eleventh Plan | State Plan | New Road | 17.74 | 0.00 | 17.74 | 6-Mar-03 | 6-Dec-03 | 100% | 13.11 | 0.00 | 13.11 | 4.63 | 0.00 | 4.63 | 4.63 | Final Payment | |||
| 79 | Const.of Song-Zingla Martam road km 14th | Singtam | 1Km | Tenging Bhutia | Eleventh Plan | State Plan | New Road | 25.54 | 0.00 | 25.54 | 6-Mar-03 | 6-Dec-03 | 100% | 19.63 | 0.00 | 19.63 | 5.91 | 0.00 | 5.91 | 5.91 | In progress | ||
| 80 | Const. of Song-Zingla Martam road km 15th. | Singtam | 1Km | S.K.Chettri | State Plan | New Road | 26.75 | 0.00 | 26.75 | 6-Mar-03 | 6-Dec-03 | 95% | 19.95 | 0.00 | 19.95 | 6.80 | 0.00 | 6.80 | 6.80 | In progress | |||
| 81 | Carpeting and surface strengthening, improvement, including drainage works of roads in and around Gangtok. | Station | 9.41 Km | PM Chamling | Tenth Plan | State Plan | Remv. | 361.89 | 0.00 | 361.89 | 6-Jun-04 | 5-Sep-05 | 100% | 229.45 | 0.00 | 229.45 | 132.44 | 0.00 | 132.44 | 132.44 | work completed final bill under preparation | ||
| 82 | Surface strengthening upgradation and carpeting of Pakyong-Karthok Naya Busty road km 5th -7th. | Pakyong | 2Km | Adup Bhutia | Tenth Plan | State Plan | Remv. | 220.68 | 0.00 | 220.68 | 21/06/05 | 31-Aug-08 | 45% | 57.04 | 0.00 | 57.04 | 163.64 | 0.00 | 163.64 | 163.64 | work in progress, Date Extended | ||
| 83 | P/L edging ,soling, metalling, premix carpeting and cross drain of link road from sichey to Indira Bye Pass via Shivalaya Mandir | Station | 0.3Km | Mrs Rupa Dhakal | Tenth Plan | State Plan | Remv. | 8.16 | 0.00 | 8.16 | 1/0/2002 | 2-Jul-05 | 80% | 5.81 | 0.00 | 5.81 | 2.35 | 0.00 | 2.35 | 2.35 | work in abeyance due to non availibility of bitumen | ||
| 84 | Surface stregenthening , upgradation and carpeting of Roads during the visit of His Holiness the Dalai Lama | Station | Departmental | Tenth Plan | State Plan | Remv. | 40.35 | 0.00 | 40.35 | 2005 | - | 100% | 38.79 | 0.00 | 38.79 | 1.56 | 0.00 | 1.56 | 1.56 | completed | |||
| 85 | Providing 75mm thick CC pitching over approach raod to Gairi Goan from NH 31A Near Hotel Tashi Targey) Ssno 2/E/Remv/06-07 | Station | 0.3 Km | Departmental | Tenth Plan | State Plan | Remv. | 3.40 | 0.00 | 3.40 | 2006 | - | 0% | 0.00 | 0.00 | 0.00 | 3.40 | 0.00 | 3.40 | 3.40 | |||
| 86 | Const of PW along TNSS to Dhupidara Ssno 6/E/Remov/0607 | Station | N/A | Tenth Plan | State Plan | Remv. | 3.44 | 0.00 | 3.44 | 2006 | - | 100% | 3.42 | 0.00 | 3.42 | 0.02 | 0.00 | 0.02 | 0.02 | completed | |||
| 87 | Permanent restoration work of Chief Justic Banglow Road Ssno7/E/Remo/06-07 | Station | N/A | Departmental | Tenth Plan | State Plan | Remv. | 11.21 | 0.00 | 11.21 | 2006 | - | 100% | 10.31 | 0.00 | 10.31 | 0.90 | 0.00 | 0.90 | 0.90 | completed | ||
| 88 | Immediate protective work to donak khola along tarethang Bering Road km ch.22nd 23 ch | Singtam | 0.06 Km | Departmental | Tenth Plan | State Plan | Remv. | 19.72 | 0.00 | 19.72 | 2006 | - | 100% | 17.65 | 0.00 | 17.65 | 2.07 | 0.00 | 2.07 | 2.07 | completed | ||
| 89 | Restoration work at km 8th Ch.4-5 (Namphey khola)along Assam-Pakyong road | Pakyong | 0.06 Km | Departmental | Tenth Plan | State Plan | Remv. | 19.93 | 0.00 | 19.93 | 2006 | - | 100% | 19.93 | 0.00 | 19.93 | 0.00 | 0.00 | 0.00 | 0.00 | completed | ||
| 90 | Immediate traffic clerance of rest work on lingtam-Agamlok rod km 1st &2nd. | Pakyong | 2Km | Departmental | Tenth Plan | State Plan | Remv. | 4.48 | 0.00 | 4.48 | 2006 | - | 100% | 4.48 | 0.00 | 4.48 | 0.00 | 0.00 | 0.00 | 0.00 | completed | ||
| 91 | Surface improvement at approach road to MLA Hostel and SLA premises | Station | 0.6Km | Departmental | State Plan | Remv. | 12.83 | 0.00 | 12.83 | 2006 | - | 100% | 4.00 | 0.00 | 4.00 | 8.83 | 0.00 | 8.83 | 8.83 | completed | |||
| 92 | Raising of sunkdown formation of Raley-Kambal Samdong km 6th ch 30-32 | Singtam | 6.9Km | Departmental | State Plan | Remv. | 3.93 | 0.00 | 3.93 | - | - | 100% | 3.93 | 0.00 | 3.93 | 0.00 | 0.00 | 0.00 | 0.00 | completed | |||
| 93 | Slip clearance along KLT road km 2nd ch 25th & 27th | Singtam | N/A | Departmental | Eleventh Plan | State Plan | Remv. | 3.61 | 0.00 | 3.61 | - | - | 100% | 3.08 | 0.00 | 3.08 | 0.53 | 0.00 | 0.53 | 0.53 | completed | ||
| 94 | Slope stabilisation work km 2nd Ch:6to 8 along Pakyong-Machong Road | Pakyong | N/A | Departmental | Eleventh Plan | State Plan | Remv. | 4.68 | 0.00 | 4.68 | 2007 | - | 100% | 0.00 | 0.00 | 0.00 | 4.68 | 0.00 | 4.68 | 4.68 | completed | ||
| 95 | Providing protective work at Paemragoan | Pakyong | N/A | Departmental | Tenth Plan | State Plan | Remv. | 2.24 | 0.00 | 2.24 | 2008 | - | 100% | 0.00 | 0.00 | 0.00 | 2.24 | 0.00 | 2.24 | 2.24 | completed | ||
| C | DISTRICT : SOUTH | ||||||||||||||||||||||
| A. | CENTRAL SPONSORED SCHEMES | ||||||||||||||||||||||
| 1 | Surface strengthening carpetting, drainage and protective work along Tarku-Damthang road Km13th-19th | Ravangla | 6Km | Shri A. Pradhan | Tenth Plan | ACA | CSS | 0.00 | 228.00 | 228.00 | Feb-08 | Mar-08 | 100% | 0.00 | 228.00 | 228.00 | 0.00 | 0.00 | 0.00 | 0.00 | work completed | ||
| 2 | Construction of 25 m. Span Steel Bridge over Mayalu Jhora at Km 3rd on Melli -Nayabazar road. | Namchi | 25m | Mr. P. C. Mundra | Tenth Plan | CRF | Repl. | 3.28 | 58.97 | 62.25 | 12-Mar-04 | 30-Jun-06 | 100% | 0.00 | 52.83 | 52.83 | 3.28 | 6.14 | 9.42 | 9.42 | Final bill submitted | ||
| 3 | Construction of 25 m. Span Steel Bridge over Rolu Khola at Km 9th on Melli -Nayabazar road. | Namchi | 25m | Mr. G.M. Gurung | Eleventh Plan | CRF | Repl. | 3.28 | 52.60 | 55.88 | 22-Jul-04 | 31-May-06 | 100% | 0.00 | 48.63 | 48.63 | 3.28 | 3.97 | 7.25 | 7.25 | Revision under process | ||
| 4 | Upgradation of existing road from Vok to Namchi. | Namchi | 14.78 Km | M.P.Agarwal | Tenth Plan | CRF | Remv. | 101.57 | 365.83 | 467.40 | 8-Aug-07 | - | 100% | 74.49 | 345.42 | 419.91 | 27.08 | 20.41 | 47.49 | 47.49 | - | ||
| 5 | Construction of Gurassey Road from Bio-Diversity Park (Temi) | Passang Lepcha | Tenth Plan | EI | New Road | 0.00 | 1010.92 | 1,010.92 | 26-Mar-08 | - | - | 0.00 | 127.26 | 127.26 | 0.00 | 883.66 | 883.66 | 883.66 | - | ||||
| 6 | Widening, Improvement, protective work, drainage and carpetting of Melli, Phong road, Km. 1st to 24th. | 24Km | Pawan Kr. AgarwaL | Tenth Plan | ISC | Remv. | 77.40 | 1298.61 | 1,376.01 | - | - | 35% | 33.11 | 235.00 | 268.11 | 44.29 | 1,063.61 | 1,107.90 | 1,107.90 | Payment made to old contractor | |||
| 7 | Widening, surface improvement, p/w & drainage system along Phongla-Bermiock-Sirwani road Km 1st- 28th. | Ravangla | 28Km | Sunil Kr. Agarwal | Tenth Plan | ISC | Remv. | 558.00 | 999.08 | 1,557.08 | Feb-05 | Mar-08 | 100% | 30.32 | 866.00 | 896.32 | 527.68 | 133.08 | 660.76 | 660.76 | in progress | ||
| 8 | Upgradation & carpetting of Bhaisalgoan to Salghari road Km 1st to 2nd in South Sikkim. | 2Km | Mr. Hanuman Das Agarwal | Tenth Plan | NABARD | Exp. | 18.91 | 63.41 | 82.32 | 12-Feb-07 | 11-Jan-08 | 100% | 0.00 | 63.41 | 63.41 | 18.91 | 0.00 | 18.91 | 18.91 | completed, final bill submitted | |||
| 9 | Construction of trukable road from Tiffin Dara to Lower Tinghrithang School Km 1st to 7th | 7Km | - | Tenth Plan | NABARD | New Road | 28.26 | 254.370 | 282.63 | 6-Jun-06 | 12-Dec-07 | 64% | 0.00 | 135.97 | 135.97 | 28.26 | 118.40 | 146.66 | 146.66 | in progress | |||
| 10 | Surfce strengthening, carpetting, drainage and Protective Works along A/R to Buddha Statue (Sakymuni) | Ravangla | 2Km | Pawan Kr. AgarwaL | NABARD | CSS | 0.00 | 360.910 | 360.91 | - | - | 44% | 0.00 | 125.00 | 125.00 | 0.00 | 235.91 | 235.91 | 235.91 | in progress | |||
| 11 | Truakable road from 10th mile to Tingmoo villageKm 1st, 2nd and 7th | Ravangla | 3Km | Mr. Nim S. Sherpa | Tenth Plan | NEC | CSS | 0.00 | 468.29 | 468.29 | 4-Apr-06 | 4-Apr-07 | 62% | 0.00 | 104.15 | 104.15 | 0.00 | 364.14 | 364.14 | 364.14 | in progress | ||
| 12 | Truakable road from 10th mile to Tingmoo villageKm 3rd and 6th | Ravangla | 2Km | Mr. Sonam O. Bhutia | Tenth Plan | NEC | CSS | 4-Apr-06 | 4-Apr-07 | 53% | 0.00 | in progress | |||||||||||
| 13 | Truakable road from 10th mile to Tingmoo villageKm 4th and 5th | Ravangla | 2Km | Mr. Lhendup D. Kaleon | Tenth Plan | NEC | CSS | 5-Apr-06 | 4-Apr-07 | 43% | 0.00 | in progress | |||||||||||
| 14 | Truakable road from 10th mile to Tingmoo villageKm 8th. | Ravangla | 1Km | Mr. Bala R. Limboo | Tenth Plan | NEC | CSS | 9-Apr-06 | 4-Apr-07 | 60% | 0.00 | in progress | |||||||||||
| 15 | Strengthening / drainage carpetting of Ralang-Phamthang road Km 14th to 26th & Replacement of Two existing Bridges over Bermali & Chil Khola in South Sikkim. | Ravangla | 12Km & 65m x 2 nos | Mr. N.T. Bhutia | Tenth Plan | NEC | Remv. | 100.00 | 1100.83 | 1,200.83 | 11-Nov-06 | 5-May-08 | 42% | 0.00 | 213.00 | 213.00 | 100.00 | 887.83 | 987.83 | 987.83 | in progress | ||
| 16 | Construction of 40m Span Bridge over Lower Ben Khola at Saino Tar along Pabong - Simchuthang - Yangang road, South Sikkim. | Ravangla | 40m | Mr. Anjani Kr, Agarwal | Tenth Plan | NEC | CSS | 0.00 | 137.34 | 137.34 | Sep-05 | Jun-06 | 100% | 0.00 | 107.65 | 107.65 | 0.00 | 29.69 | 29.69 | 29.69 | completed | ||
| 17 | Construction of 60m span steel bridge over Kaw Khola on KS road. | Ravangla | 60m | Mr. S.S. Dhakhal | Tenth Plan | NEC | CSS | 0.00 | 164.35 | 164.35 | Nov-06 | Nov-08 | 76% | 0.00 | 75.00 | 75.00 | 0.00 | 89.35 | 89.35 | 89.35 | in progress | ||
| 18 | Imp drainage, carpetting works Km 1st -14th and replacement of Rangla Khola bridge on Kimotey Sokpay roads. | Ravangla | 14Km | Mr. Sunil Kr. Agarwal | Tenth Plan | NEC | Remv. | 0.00 | 680.00 | 680.00 | Nov-06 | Nov-08 | 70% | 0.00 | 268.00 | 268.00 | 0.00 | 412.00 | 412.00 | 412.00 | work under progress | ||
| 19 | Replacement of 110m Span Suspension Bridge over Rabi Khola in Melli Phong road Km 9th in S/Sikkim. | 110m | Mr. Om Agarwal | Tenth Plan | NEC | CSS | 0.00 | 497.30 | 497.30 | 39125.00 | 12-Feb-08 | 45% | 0.00 | 144.11 | 144.11 | 0.00 | 353.19 | 353.19 | 353.19 | in progress | |||
| 20 | Construction of link road Turung School to Suminkhor Primary School. | Mr. Subaash Kharel | Tenth Plan | NEC | New Road | 22.79 | 358.66 | 381.45 | 39428.00 | 6-Jun-09 | 75% | 0.00 | 169.05 | 169.05 | 22.79 | 189.61 | 212.40 | 212.40 | in progress | ||||
| 21 | Construction of 30m Span Steel Bridges Over Rinzi Khola at Kolagari along Namchi-Vok Road | 30m | Bhupal Chamling | Tenth Plan | NEC | Rep. | 28.34 | 157.50 | 185.84 | 12-Dec-07 | 6-Jun-09 | 100% | 0.00 | 109.03 | 109.03 | 28.34 | 48.47 | 76.81 | 76.81 | Completed, Final bill to be paid | |||
| 22 | Construction of Steel Bridge over Upper Ben Khola on G.L.V.C. road. | - | Tenth Plan | NEC | CSS | 0.00 | 90.83 | 90.83 | 14-Feb-06 | - | - | 0.00 | 81.77 | 81.77 | 0.00 | 9.06 | 9.06 | 9.06 | - | ||||
| 23 | Construction of Makha Suspension Bridge over Tista Khola at Tanak on Makha -Lingi -Yangang- Ravangla Road in South Sikkim.(NEC) | Ravangla | 100m | R.N. Chamling | Tenth Plan | NEC | CSS | 0.00 | 495.25 | 495.25 | 25-Aug-06 | - | 10% | 0.00 | 32.28 | 32.28 | 0.00 | 462.97 | 462.97 | 462.97 | in progress | ||
| 24 | Surface Improvement, Drainage & Protective works on Namchi-Rong Road, 13 km | 13Km | Mr. MP Agarwal | Tenth Plan | NEC | 83.89 | 498.60 | 582.49 | 20-Nov-03 | - | 10.91 | 498.60 | 509.51 | 72.98 | 0.00 | 72.98 | 72.98 | - | |||||
| 25 | Improvement of Ralang - Phamtam Road | - | Eleventh Plan | NEC | CSS | 0.00 | 1183.00 | 1,183.00 | 25-Aug-06 | - | 0.00 | 269.13 | 269.13 | 0.00 | 913.87 | 913.87 | 913.87 | - | |||||
| 26 | Surface strengthening drainage & P. Works on Namchi- Damthang Ravangla road- Km 1st -26th. | 26Km | - | Tenth Plan | NLCPR | Remv. | 461.61 | 1,207.00 | 1,668.61 | 1-Jan-05 | 1-Feb-07 | 98% | 224.94 | 1,164.19 | 1,389.13 | 236.67 | 42.81 | 279.48 | 279.48 | in progress | |||
| 27 | Replacement of existing Sikkip Suspension Bridge over Rangit River | 82m | Mr. Chandra Khaling | Tenth Plan | NLCPR | Repl. | 24.47 | 53.66 | 78.13 | 15-Dec-03 | 30-Mar-07 | 100% | 11.78 | 53.65 | 65.43 | 12.69 | 0.01 | 12.70 | 12.70 | work completed | |||
| 28 | Upgradation, Surface strengthening, drainage & P/W on Ravangla Makha Road Km 10th,11th,12th and 13th. | 4Km | Smt. Sonam Doma Bhutia | Tenth Plan | NLCPR | CSS | 0.00 | 119.05 | 119.05 | 15-Jan-03 | 30-Nov-06 | 100% | 0.00 | 116.17 | 116.17 | 0.00 | 2.88 | 2.88 | 2.88 | completed | |||
| 29 | Upgradation, Surface strengthening, drainage & P/W on Ravangla Makha Road Km 18th to 21st | 3Km | Mr. S. B. Chamling | Tenth Plan | NLCPR | CSS | 0.00 | 109.18 | 109.18 | 15-Jan-03 | 30-Nov-06 | 100% | 0.00 | 102.96 | 102.96 | 0.00 | 6.22 | 6.22 | 6.22 | completed | |||
| 30 | Const. of motorable link road from upper Vok to Ung Raam (Water falls) via Namplang and rabong village in Omchu | 6Km | Mr. B. Tsh. Bhutia | Tenth Plan | RSVY | New Road | 60.11 | 180.00 | 240.11 | 22-Aug-05 | 21-Aug-07 | 85% | 54.40 | 180.00 | 234.40 | 5.71 | 0.00 | 5.71 | 5.71 | in progress | |||
| 31 | Construction of truckable roasd from Borong-Phamtam road to Upper Borong via Gurug Gumpa Km 1st. | 1Km | Shri K. B. Gurung | Tenth Plan | RSVY | CSS | 0.00 | 64.00 | 64.00 | 2-Feb-06 | 12-Nov-06 | 100% | 0.00 | 63.98 | 63.98 | 0.00 | 0.02 | 0.02 | 0.02 | work completed | |||
| 32 | Construction of truckable roasd from Borong-Phamtam road to Upper Borong via Gurug Gumpa Km 2nd. | 1Km | Shr. D. M. Gurung | Tenth Plan | RSVY | CSS | 2-Feb-06 | 13-Nov-06 | 100% | 0.00 | |||||||||||||
| 33 | Extension of truckable road from Borong-Phamtam road to Lower Borong Km 3rd to 4th. | 2Km | Shri Y.C. Bhutia | RSVY | CSS | 0.00 | 70.32 | 70.32 | 2-Feb-06 | 11-Nov-06 | 100% | 0.00 | 70.32 | 70.32 | 0.00 | 0.00 | 0.00 | 0.00 | work completed | ||||
| 34 | Construction of link road to Gagyong village km 3 | 3Km | - | RSVY | CSS | 0.00 | 87.00 | 87.00 | - | - | 100% | 0.00 | 77.71 | 77.71 | 0.00 | 9.29 | 9.29 | 9.29 | work closed | ||||
| 35 | Extension of Bhaisalgoan- Salghari road to Farashey km 1st to 3rd. | 3Km | Mr. Dhan Pd. Rai, Mr. Purna Bhd. Bishkarma, Ratan Kr. Agarwal. | Tenth Plan | RSVY | CSS | 0.00 | 94.64 | 94.64 | 11-Nov-05 | - | 100% | 0.00 | 94.64 | 94.64 | 0.00 | 0.00 | 0.00 | 0.00 | work closed | |||
| STATE PLAN | |||||||||||||||||||||||
| 36 | Construction of Guest house at Yangang in South Sikkim. | Mr. Pawan Kr. Agarwal | Tenth Plan | State Plan | Addl. Facilities | 47.31 | 0.00 | 47.31 | 10-Oct-03 | 30-Jun-05 | 100% | 0.00 | 57.17 | 57.17 | 47.31 | -57.17 | -9.86 | -9.86 | completed | ||||
| 37 | Construction of Link Road from Rangang to Yangang-Makha via Majuwa : Km 1st and 2nd | Ravangla | 2Km | Mr. S. B. Chamling | Tenth Plan | State Plan | Addl. Facilities | 62.36 | 0.00 | 62.36 | 1-Jan-05 | 10-Oct-05 | 99% | 53.95 | 0.00 | 53.95 | 8.41 | 0.00 | 8.41 | 8.41 | in progress | ||
| 38 | Construction of Link Road from Rangang to Yangang-Makha via Majuwa : Km 3rd. | Ravangla | 1Km | Mr. Nar Bhd. Gurung | Tenth Plan | State Plan | Addl. Facilities | 22.83 | 0.00 | 22.83 | 1-Jan-05 | 10-Oct-05 | 100% | 16.17 | 0.00 | 16.17 | 6.66 | 0.00 | 6.66 | 6.66 | in progress | ||
| 39 | Construction of Kitchen for PWD Guest House at Temi, South Sikkim. | Ravangla | N/A | Mr. Bindra Kumar Rai | Tenth Plan | State Plan | Addl. Facilities | 11.01 | 0.00 | 11.01 | 2-Feb-07 | 8-Aug-07 | 95% | 0.00 | 0.00 | 0.00 | 11.01 | 0.00 | 11.01 | 11.01 | in progress | ||
| 40 | Construction of Helipad at Pokhari dara in Upper Yangyang | Ravangla | N/A | M/s Rinchen Ongmu Bhutia | Eleventh Plan | State Plan | Helipad | 90.640 | 0.00 | 90.64 | 1-Jul-08 | 1-Jan-10 | 80% | 43.00 | 0.00 | 43.00 | 47.64 | 0.00 | 47.64 | 47.64 | in progress | ||
| 41 | Construction of 18ch link road from Helipad to Central University at Yanyang. | Ravangla | 0.54Km | Mrs. Sumitra Gurung | Eleventh Plan | State Plan | Helipad | 42.670 | 0.00 | 42.67 | 1-Sep-08 | 1-Dec-08 | 80% | 0.00 | 0.00 | 0.00 | 42.67 | 0.00 | 42.67 | 42.67 | in progress | ||
| 42 | Carpetting of Namchi Rong-Sumbuk road Km 1st to 3rd (Soling metalling & Carpetting). [9th plan] | 3Km | P.K.Agarwal, Roshan Agarwal, Anjani Kr Ararwal | Ninth Plan | State Plan | Exp. | 64.18 | 0.00 | 64.18 | 22-Jun-05 | - | 100% | 64.18 | 0.00 | 64.18 | 0.00 | 0.00 | 0.00 | 0.00 | Work Closed | |||
| 43 | Construction of road from Gurpisey to Phalidara. Km 1st & 2nd. | 2Km | Chung Chung Bhutia | Tenth Plan | State Plan | Exp. | 50.32 | 0.00 | 50.32 | 21-Jun-05 | - | 100% | 50.32 | 0.00 | 50.32 | 0.00 | 0.00 | 0.00 | 0.00 | Work Closed | |||
| 44 | Surface strengthening & drainage on Yang-yang-Rangang road. Km 1st.-2nd | 2Km | Mr. S. B. Chamling | Tenth Plan | State Plan | Exp. | 39.32 | 0.00 | 39.32 | 16-Feb-03 | 11-Jan-06 | 99% | 35.74 | 0.00 | 35.74 | 3.58 | 0.00 | 3.58 | 3.58 | in progress | |||
| 45 | Carpetting, drainage & Protective Works onYangang- Rangang road form Bifurcation Point Km 1st and 2nd | 2Km | S.B.Chamling | Tenth Plan | State Plan | Exp. | 37.80 | 0.00 | 37.80 | 16-Feb-03 | 31-Mar-05 | 95% | 0.00 | 0.00 | 0.00 | 37.80 | 0.00 | 37.80 | 37.80 | - | |||
| 46 | Premix carpetting,drainage work and protective work on Melli Turuk Sadam Bhanjyang road Km 1st - 16th. | 16Km | Mr. Tej man Rai, Birbal Subba, & Rup Narayan Rai | Tenth Plan | State Plan | Exp. | 290.49 | 0.00 | 290.49 | 1-Jan-03 | Aug- 31st | 100% | 248.50 | 0.00 | 248.50 | 41.99 | 0.00 | 41.99 | 41.99 | Completd,necessary documents collected for final bill. | |||
| 47 | Construction of Bye Pass road from Agam Singh Path to Damthang road 3Km. | Shri Bhupal Chamling | Tenth Plan | State Plan | Exp. | 160.94 | 0.00 | 160.94 | 3-Mar-04 | 3-Mar-05 | 100% | 123.88 | 0.00 | 123.88 | 37.06 | 0.00 | 37.06 | 37.06 | work completed | ||||
| 48 | Surface Improvement of Approach Road to Rock Garden from Debrong Golai-Namchi-Damthang road Km 1st & 2nd. | 2Km | Dikila Bhutia | Tenth Plan | State Plan | Exp. | 70.22 | 0.00 | 70.22 | 18-Mar-04 | 18-Mar-05 | 100% | 67.05 | 0.00 | 67.05 | 3.17 | 0.00 | 3.17 | 3.17 | Work completed | |||
| 49 | Premix carpetting, drainage & P/works work on Yangang Makha road Km 1st-21st [S.Share of NLCPR] [Revised] | 21Km | Passang Lepcha | Tenth Plan | State Plan | Exp. | 54.13 | 0.00 | 54.13 | - | - | 100% | 54.13 | 0.00 | 54.13 | 0.00 | 0.00 | 0.00 | 0.00 | Work Closed | |||
| 50 | Premix carpetting on Ravangla Zarrong road km 1st-11th. | Ravangla | 11Km | Shreekishan Agarwal | Tenth Plan | State Plan | Exp. | 0.00 | 0.00 | 0.00 | 24-Jun-05 | - | - | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | Transferred to TSP | ||
| 51 | Construction of link road Rangang road-Yang Yang Makha via Mazuwa Gaon, 3 kms Rs. 9.49 (LC)] | 3Km | Santa Bdr. Chamling, Nar Bdr. Gurung | Tenth Plan | State Plan | Exp. | 88.30 | 0.00 | 88.30 | 6-Jun-05 | 6-Sep-06 | 100% | 80.25 | 0.00 | 80.25 | 8.05 | 0.00 | 8.05 | 8.05 | Work completed | |||
| 52 | Providing premix carpetting on Approach road & Yard to Palchen Choling Monastry [New Gumpa] at Ralang | Departmental | Tenth Plan | State Plan | Exp. | 14.65 | 0.00 | 14.65 | 18-Jun-05 | 18-Dec-05 | 100% | 14.26 | 0.00 | 14.26 | 0.39 | 0.00 | 0.39 | 0.39 | Work Closed | ||||
| 53 | Restoration work on Namchi-Phong km. 3rd ch. 30 South Sikkim. | Departmental | Tenth Plan | State Plan | Exp. | 2.90 | 0.00 | 2.90 | 27-Jun-05 | - | 100% | 0.00 | 0.00 | 0.00 | 2.90 | 0.00 | 2.90 | 2.90 | Work completed | ||||
| 54 | Immediate restoration work on Namchi-Rong-Sumbuk road km. 7th-13th. | 6Km | Departmental | Tenth Plan | State Plan | Exp. | 2.63 | 0.00 | 2.63 | 2005 | - | 100% | 0.00 | 0.00 | 0.00 | 2.63 | 0.00 | 2.63 | 2.63 | Work completed | |||
| 55 | Extension of Ravongla Biring road to Legship Tashiding road 5th kms in South Sikkim. | 5Km | Tenth Plan | State Plan | Exp. | 119.40 | 0.00 | 119.40 | 2005 | - | 100% | 43.94 | 0.00 | 43.94 | 75.46 | 0.00 | 75.46 | 75.46 | Work completed | ||||
| 56 | Diversion of turning at Km 13 on Ravangla - Zarong Road in S-Sikkim | Ravangla | 1Km | Smt. R K Rai | Tenth Plan | State Plan | Exp. | 6.93 | 0.00 | 6.93 | 1-Apr-06 | 9-Sep-06 | 99% | 4.03 | 0.00 | 4.03 | 2.90 | 0.00 | 2.90 | 2.90 | work under progress | ||
| 57 | Construction of Namchi - Rong - Sumbuk Road Km 3rd to 15th. | 12Km | Land Compensation | Eleventh Plan | State Plan | Exp. | 16.48 | 0.00 | 16.48 | 2007 | - | 100% | 16.48 | 0.00 | 16.48 | 0.00 | 0.00 | 0.00 | 0.00 | Work completed | |||
| 58 | Carpeting & Protective Work on Rabong -Ralong Road Km 1st to 3rd | 3Km | Binod Gurung | State Plan | Exp. | 6.42 | 0.00 | 6.42 | - | - | 100% | 0.00 | 0.00 | 0.00 | 6.42 | 0.00 | 6.42 | 6.42 | Work completed | ||||
| 59 | Carpeting & Protective Work on Rabong -Ralong Road Km 4th to 6th | 2Km | N.T.Bhutia | State Plan | Exp. | 11.10 | 0.00 | 11.10 | - | - | 100% | 0.00 | 0.00 | 0.00 | 11.10 | 0.00 | 11.10 | 11.10 | Work completed | ||||
| 60 | Carpeting & Protective Work on Rabong -Ralong Road Km 7th to 10th | 3Km | Roshan Lall Agarwal | State Plan | Exp. | 8.18 | 0.00 | 8.18 | - | - | 100% | 0.00 | 0.00 | 0.00 | 8.18 | 0.00 | 8.18 | 8.18 | Work completed | ||||
| 61 | Carpeting & Protective Work on Rabong -Ralong Road Km 11th to 13th | 2Km | Tshering Gyatso Kaleon | Tenth Plan | State Plan | Exp. | 3.63 | 0.00 | 3.63 | - | - | 100% | 0.00 | 0.00 | 0.00 | 3.63 | 0.00 | 3.63 | 3.63 | Work completed | |||
| 62 | New cutting of Sangmoo link road Km 4th | Mr. K. Bhutia | Tenth Plan | State Plan | Exp. | 6.97 | 0.00 | 6.97 | 1-Nov-97 | - | - | 0.00 | 0.00 | 0.00 | 6.97 | 0.00 | 6.97 | 6.97 | - | ||||
| 63 | Extension of Truakable road from Ravangla Bining Road to Tashiding Km 14th. | Ravangla | 1Km | Mr. Loden C. Bhutia | Tenth Plan | State Plan | Exp. | 22.02 | 0.00 | 22.02 | June-05 | 12-Dec-06 | 94% | 16.83 | 0.00 | 16.83 | 5.19 | 0.00 | 5.19 | 5.19 | in progress | ||
| 64 | Extension of Truakable road from Ravangla Bining Road to Tashiding Km 15th. | Ravangla | 1Km | Mr. Lha T. Bhutia | Tenth Plan | State Plan | Exp. | 20.89 | 0.00 | 20.89 | June-05 | 13-Dec-06 | 94% | 12.01 | 0.00 | 12.01 | 8.88 | 0.00 | 8.88 | 8.88 | in progress | ||
| 65 | Extension of Truakable road from Ravangla Bining Road to Tashiding Km 16th. | Ravangla | 1Km | Mr. Loden C. Bhutia | State Plan | Exp. | 22.63 | 0.00 | 22.63 | June-05 | 14-Dec-06 | 95% | 9.90 | 0.00 | 9.90 | 12.73 | 0.00 | 12.73 | 12.73 | in progress | |||
| 66 | Extension of Truakable road from Ravangla Bining Road to Tashiding Km 17th. | Ravangla | 1Km | Mr. Lha T. Bhutia | Tenth Plan | State Plan | Exp. | 19.87 | 0.00 | 19.87 | June-05 | 15-Dec-06 | 95% | 9.77 | 0.00 | 9.77 | 10.10 | 0.00 | 10.10 | 10.10 | in progress | ||
| 67 | Extension of Truakable road from Ravangla Bining Road to Tashiding Km 18th. | Ravangla | 1Km | Mr. Lha T. Bhutia | Tenth Plan | State Plan | Exp. | 19.31 | 0.00 | 19.31 | June-05 | 16-Dec-06 | 97% | 5.60 | 0.00 | 5.60 | 13.71 | 0.00 | 13.71 | 13.71 | in progress | ||
| 68 | Construction of motorable road from Slap Village (Chettri Gaon) km 1st and 2nd | Ravangla | 2Km | Mr. Lha T. Bhutia | Tenth Plan | State Plan | Exp. | 38.02 | 0.00 | 38.02 | 9-Sep-06 | 2-Feb-07 | 76% | 21.40 | 0.00 | 21.40 | 16.62 | 0.00 | 16.62 | 16.62 | in progress | ||
| 69 | Surface strengthening & drainage on Yang-yang-Rangang road. Km 1st & 2nd. | Ravangla | Mr. S. B. Chamling | Tenth Plan | State Plan | Exp. | 36.19 | 0.00 | 36.19 | 16-Feb-03 | 11-Jan-06 | 99% | 21.03 | 0.00 | 21.03 | 15.16 | 0.00 | 15.16 | 15.16 | in progress | |||
| 70 | Diversion of turning at Km 14 th to 18th on Ravangla - Zarong Road in S-Sikkim | 4Km | Smt. Ratna Kum. Rai | Tenth Plan | State Plan | Exp. | 104.72 | 0.00 | 104.72 | Jun-05 | Mar-08 | 87% | 54.11 | 0.00 | 54.11 | 50.61 | 0.00 | 50.61 | 50.61 | in progress | |||
| 71 | Construction of link road from Kholaghari to Jaubari, Km 3rd 4th to 9th. (LC = Rs. 170.52 lakh) | Bhanu Rai & Lakpa Chuki Sherpa | Tenth Plan | State Plan | Link Road | ||||||||||||||||||