MONTHLY PHYSICAL AND FINANCIAL  PROGRESS REPORT FOR THE MONTH ENDING JANUARY 2009
   
Sl.No Name of Schemes   Length Km / M Name of Contractor Plan Funding Agency (Head) SANCTIONED  AMOUNT Date of Commen- cement Stipulated Date of Completion Phy Prog-ress               in % Financial Progress Balance  TOTAL SA-BAL Remarks
  S. share C.share Total Expenditure till date  
  S.Share C.Share Total S.Share C.Share Total  
A DISTRICT:  NORTH          
  CENTRAL  SPONSORED  SCHEMES                      
1 Construction of app. Road to Thomchi Gumpa.   0.15 Km Mr. Tashi Lachungpa   BADP BADP 0.00 15.69 15.69 6-Feb-07 5-May-07 100% 0.00 9.97 9.97 0.00 5.72 5.72 5.72 Completed
2 Construction of new road from Gumpa Golai to Chanzing, Lachen.   0.48 Km Mr Nangden Lachungpa   BADP BADP 0.00 38.10 38.10 - - - 0.00 0.00 0.00 0.00 38.10 38.10 38.10 Work delay due to land compens-ation
3 Upgradation / Strengthening and Carpeting of approach road to Latoong Village.   1Km Mr Nangden Lachungpa   BADP BADP 0.00 42.79 42.79 - - 70% 0.00 19.40 19.40 0.00 23.39 23.39 23.39 work in progress
4 Construction of Guest House / Inspection Bunglow at Yakthang, Lachen (Thangu).   N/A -   BADP BADP 0.00 138.00 138.00 - - - 0.00 0.00 0.00 0.00 138.00 138.00 138.00 -
5 Extension of Bakcha -Labi road Km 3rd & 4th. State share of BADP land compansation.   2Km Mr. Ugen Nedup Bhutia   BADP BADP 0.00 50.00 50.00 - - 100% 0.00 49.91 49.91 0.00 0.09 0.09 0.09 Work Closed
6 Upgradation & Surface strengthening of Ranka-Sichey road Km 1st to 3rd   3Km Mr. Rajesh Agarwal Tenth Plan CRF Removal 30.78 88.26 119.04 17-Mar-05 31-May-06 100% 0.00 72.10 72.10 30.78 16.16 46.94 46.94 Final bill submitted
7 Upgradation of Phodong -Labrang Gumpa   2.25 Km Mr. K.N. Bhutia Tenth Plan CRF CRF 0.00 158.96 158.96 3-Nov-05 2-Oct-06 100% 0.00 151.37 151.37 0.00 7.59 7.59 7.59 Completed Final bill to be paid
8 Construction of 18 mtrs span Steel Bridge over Rakshey Khola along Penlong - Tintek road at Km 13th, CH: 1   18m - Tenth Plan CRF CRF 0.00 90.99 90.99 18-Oct-06 - 90% 0.00 60.97 60.97 0.00 30.02 30.02 30.02 work in progress
9 Widening of upgradation, carpetting, protective of drainage works on approach road to Zimchung Busty from DAC road, Mangan   2.45 Km Department. Tenth Plan MP (LAPS)  - 0.00 25.00 25.00 - - 100% 0.00 0.00 0.00 0.00 25.00 25.00 25.00 In Progress
10 Upgradation Ranka - Luing-Gangtok-Burthuk-Road Km 14th to 21st   7 Km Mr. Shyam Rai Tenth Plan NLCPR  Exp. 221.54 420.00 641.54 11-Jan-05 19-Jul-07 68% 0.00 408.00 408.00 221.54 12.00 233.54 233.54 work in progress
11 Construction 0f 90m span steel bridge over Takcham Chu along C.R.B.A Road, Km 21st    90m Mrs. Meera Rai Tenth Plan NEC Exp. 0.00 476.74 476.74 9-Jan-06 8-Oct-06 90% 0.00 324.00 324.00 0.00 152.74 152.74 152.74 work in progress Expd. In Purchase of Vechile steel parts
12 Upgradation / carpeting & extension i/c providing drainage and protective works of Marchak - Tumlabong road, Km 1st to 13th in East Sikkim   13Km M/s Ladakhi Const. Pvt. Ltd. Tenth Plan NEC Exp. 0.00 1,023.00 1,023.00 9-Nov-06 18-May-08 65% 0.00 339.05 339.05 0.00 683.95 683.95 683.95 work in progress
13 Construction of steel bridge over Teesta river at Gour   122m Mr. Samdup Lepcha Tenth Plan NEC NEC 0.00 488.57 488.57 21-Jan-06 22-Jan-07 94% 0.00 404.99 404.99 0.00 83.58 83.58 83.58 In Progress
14 Strengthening / drainage carpetting of SBS road to Tingbong high school    7km Mr. G.N. Agarwal Tenth Plan NEC NEC / TSP 401.38 401.38 802.76 29-Apr-05 30-Apr-06 100% 401.38 367.19 768.57 0.00 34.19 34.19 34.19 Completed
15 Construction of Steel Bridge on Approach road to Khedum Village in North Sikkim.   50m Mr. Penzong Lachungpa Tenth Plan NEC NEC 0.00 281.51 281.51 24-Feb-06 23-Jan-07 94% 0.00 198.75 198.75 0.00 82.76 82.76 82.76 In Progress
16 Upgradation of Marchak Tumlabong Road (NEC ) State Share for LC   N/A Compensatiion   NEC Removal 100.00 1,023.00 1,123.00 - - 37% 37.00 522.75 559.75 63.00 500.25 563.25 563.25 work in progress
17 Construction of road from lower Lingdum  to Adampool, Km 3rd & 4th   2Km Mr. Ajay Rai Tenth Plan NABARD  Exp. 29.64 73.43 103.07 16-Nov-06 15-May-07 80% 18.59 73.43 92.02 11.05 0.00 11.05 11.05 Work Closed
18 Carpetting of app. Road to Crematorium ground at Jalipool.   0.28 Km Mr. Praveen Agarwal Tenth Plan NABARD  Exp. 11.14 20.66 31.80 31-Jan-06 15-Jun-06 100% 9.35 17.00 26.35 1.79 3.66 5.45 5.45 Final bill  submitted
19 Construction of Link Road from Takchi Phatak to Upper Luing, Km 1st   1Km Mr. Tsweang Rinzing Bhutia Tenth Plan NABARD New Road 0.00 289.930 289.930 18-Aug-05 17-Aug-06 90% 0.00 138.17 138.17 0.00 151.76 151.76 151.76 work in progress
20 Construction of Link Road from Takchi Phatak to Upper Luing, Km 2 nd   1Km Dewjang Bhutia Tenth Plan NABARD New Road 18-Aug-05 17-Aug-06 85% 0.00 Work just started
21 Construction of Link Road from Takchi Phatak to Upper Luing, Km 3rd   1Km Tempo Gyatso Bhutia Tenth Plan NABARD New Road 23-Sep-05 22-Sep-06 85% 0.00 Work just started
22 Construction of Link Road from Takchi Phatak to Upper Luing, Km 4th   1Km Yangchen Dolma Bhutia Tenth Plan NABARD New Road 23-Sep-05 22-Sep-06 0% 0.00 work in progress
23 Construction of Link Road from Takchi Phatak to Upper Luing, Km 5th   1Km Yangchen Dolma Bhutia   NABARD New Road 23-Sep-05 22-Sep-06 0% 0.00 work in progress
24 Extension of 3rd Km road from 3rd mile turning (Tintek Dikchu road) to Rakshey via Kedangthang Km 4th to 6th   2Km Devi Dhakal Tenth Plan NABARD - 56.17 224.460 280.630 15-May-08 15-May-09 80% 0.00 62.73 62.73 56.17 161.73 217.90 217.90 work in progress
25 Extension of link road fromGRS road Km 12th CH 5 to Tatopani at Rumtek   1Km M. Karki Tenth Plan NABARD - 0.00 40.190 40.190 15-May-08 15-May-09 20% 0.00 0.18 0.18 0.00 40.01 40.01 40.01 work was delay due to objection raised by DCC Rumtek
26 Construction of Link Road from Zimchung to Nampathang KM 1st to 3rd    3Km Mr. Zingmee Ongda, Mr. Dawa.Lepcha, Mr. Choppel Tshering Tenth Plan RSVY  RSVY  18.75 112.11 130.86 10-Nov-05 10-Nov-06 100% 16.32 112.11 128.43 2.43 0.00 2.43 2.43 Completed
27 Construction of Link Road from 3rd Mile Turning of Tintek Dikchu road to Rakshey via Kedhangthang. Km 1st to 3rd.   3Km Punya Prasad Dhakhal Tenth Plan RSVY  New Road 22.00 121.79 143.79 25-Oct-05 31-Jan-07 100% 0.00 120.76 120.76 22.00 1.03 23.03 23.03 work in progress
28 Construvction of Link Road from Bay to Pentong in North Sikkim.   3.9 Km Mr. Bernald Lepcha Tenth Plan RSVY  New Road 37.45 150.00 187.45 22-Sep-05 31-Dec-08 65% 0.00 128.03 128.03 37.45 21.97 59.42 59.42 In Progress
29 Upgradation carpetting works of Chaten Khimten Village road in North Sikkim    0.9 Km Mr. Janam Lachen Ninth Plan RSVY RSVY 0.00 38.00 38.00 12-Sep-05 11-Aug-06 100% 0.00 38.00 38.00 0.00 0.00 0.00 0.00 Completed
30 Construction of Heli Port at Lachung   N/A Mr. Nidup Lachungpa Ninth Plan Tourism Other Expenditure 38.89 0.00 38.89 3-Apr-00 2-Jan-01 75% 0.00 28.43 28.43 38.89 -28.43 10.46 10.46 Defence clearance not yet received
  WORKS  SANCTIONED  UNDER  STATE  PLAN                              
31 Approach Road to Samdong Rest House at Samdong East Sikkim   0.15 Km Mr. Dorjee Choppel   State Plan Addl.Facilities 14.04 0.00 14.04 20-May-03 19-Apr-04 100% 14.04 14.04 28.08 0.00 -14.04 -14.04 -14.04 Completed
32 Construction of Rest House at Samdong in East Sikkim.   N/A Mr. Nitup Lepcha Tenth Plan Addl.Facilities Addl.Facilities 78.70 0.00 78.70 20-May-03 19-Apr-04 100% 75.32 0.00 75.32 3.38 0.00 3.38 3.38 Completed, Final bill paid
33 Premix carpetting,on Penlong - Tintek road Km 12th - 20th    8Km Mr. Suresh Mundra Tenth Plan State Plan Exp. 158.79 0.00 158.79 28-Nov-02 31-Mar-06 100% 99.54 0.00 99.54 59.25 0.00 59.25 59.25 Final bill to be submitted Discuss Expenditure
34 Const. of GOR Santok road Km. 1st    1Km Mr.Pentok Lepcha Tenth Plan State Plan Exp. 29.76 0.00 29.76 - - 100% 21.61 0.00 21.61 8.15 0.00 8.15 8.15 Completed
35 Additional sanction for Land Comensation for the work ' Construction of Link Road Km 1st to 3rd from Ranipool-Pakyong Road to Mangheem at Aho.   3Km Land Compensation  Tenth Plan State Plan Link Road 42.02 0.00 42.02 2007 - - 25.00 0.00 25.00 17.02 0.00 17.02 17.02 -
36 Construction of link road to Aho - Manghim Km 1st   1Km Mr. B.K. Upreti Tenth Plan State Plan Link Road 16.88 0.00 16.88 2-Dec-04 15-Jan-07 94% 11.37 0.00 11.37 5.51 0.00 5.51 5.51 work in progress
37 Const. of link road to Aho - Manghim Km 2nd   1Km BR Subba Tenth Plan State Plan Link Road 18.88 0.00 18.88 2-Dec-04 15-Jan-07 55% 0.00 0.00 0.00 18.88 0.00 18.88 18.88 work in progress
38 Const. of link road to Aho - Manghim Km 3 rd   1Km Beena Subba Tenth Plan State Plan Link Road 19.27 0.00 19.27 1-Dec-04 15-Jan-07 40% 0.00 0.00 0.00 19.27 0.00 19.27 19.27 work in progress
39 Construction of app. Road from Samdong Cha Chu to Yumi Samdong, north Sikkim. Km 1st & 2nd   2Km Mr. T. Doma Lachungpa Tenth Plan State Plan New Road 54.48 0.00 54.48 21-Jun-04 20-Dec-05 100% 54.58 0.00 54.58 -0.10 0.00 -0.10 -0.10 Work Completed
40 Surface renewal / restoration works on approach road to Mission Khoti.   2Km 13ch Mr. Ugen palzor   State Plan Removal 32.79 0.00 32.79 28-Feb-04 27-Aug-04 100% 32.60 0.00 32.60 0.19 0.00 0.19 0.19 Completed
41 Premix carpetting p/w approach road to Hee-Gyathang School.   0.7 Km Department. Tenth Plan State Plan Removal 23.01 0.00 23.01  -  - 100% 19.99 0.00 19.99 3.02 0.00 3.02 3.02 Completed
42 Premix carpeting on GRBA road KM 1st -10th (Phase I ) Revised   10Km Mr. A.N. Upreti Tenth Plan State Plan Removal 215.65 0.00 215.65 13-Jan-03 12-Jul-04 96% 207.01 0.00 207.01 8.64 0.00 8.64 8.64 Completed
43 Premix carpetting, improvement of GRBA road Km 18th to 21st and Assam Pakyong Road Km 1st to 6th.   9Km Mr. Amrit Rai Tenth Plan State Plan Removal 254.76 0.00 254.76 25-Aug-04 31-Mar-06 100% 184.20 0.00 184.20 70.56 0.00 70.56 70.56 Completed
44 Uplifting & Surface & Drainage works, improvement along approach road to Sichey school.   0.21 km Mr. Rohit Pradhan Tenth Plan State Plan Removal 3.77 0.00 3.77 27-Feb-06 29-Dec-06 100% 3.03 0.00 3.03 0.74 0.00 0.74 0.74 Completed
45 Upgradation and Imp of Rumtek Ranka road Km 18th   1Km Department. Ninth Plan State Plan Removal 1.36 0.00 1.36 - - 0% 0.00 0.00 0.00 1.36 0.00 1.36 1.36 work in progress
46 Construction of 15 mtrs span RCCl Bridge over Khedum Chu   15m Gyatso Bhutia   State Plan Removal 20.72 0.00 20.72 12-Nov-98 11-Mar-99 100% 19.36 0.00 19.36 1.36 0.00 1.36 1.36  
47 Land Compensation for the work construction of Multi Span Bridge over River Teesta at Gour at Dzongu   N/A LC Ninth Plan State Plan Removal 6.84 0.00 6.84 - - 100% 6.62 0.00 6.62 0.22 0.00 0.22 0.22  
48 Construction of 55m Supension Bridge over Khedumcu at Lachung   55m Needup Lacungpa Tenth Plan State Plan Removal 112.31 0.00 112.31 12-Nov-98 11-Jul-99 100% 100.09 0.00 100.09 12.22 0.00 12.22 12.22 Copansation Remaining
49 Upgradation,carpetting, protective and drainage of SBS road to Lingtam PHSE Km 1st to 5th.   5Km Mr. Samdup Lepcha Eleventh Plan State Plan Strengthning Road Infrastructure 385.54 0.00 385.54 - - 55% 42.22 42.22 84.44 343.32 -42.22 301.10 301.10 work in progress
50 Upgradation,carpetting, protective and drainage works of DSM road to Gour School Km 1st to 8th.   8Km Mr. Soden Gyamptso Bhutia Tenth Plan State Plan Strengthning Road Infrastructure 391.66 0.00 391.66 1-Jun-08 1-Jan-09 50% 57.78 57.78 115.56 333.88 -57.78 276.10 276.10 work in progress
51 Protective Drainage and Carpetting works on SBS Road Km 3 & 4    2Km Mr. Pintso Namgyal Ninth Plan State Plan TSP 27.19 0.00 27.19 27-Nov-01 26-Feb-02 100% 19.37 0.00 19.37 7.82 0.00 7.82 7.82 Completed
52 Protective Drainage and Carpetting works on SBS Road Km 5 & 6    2Km Mr. Karma Lepcha Ninth Plan State Plan TSP 23.38 0.00 23.38 11-Jan-03 10-Oct-03 100% 16.77 0.00 16.77 6.61 0.00 6.61 6.61 Completed
53 Protective Drainage and Carpetting works on SBS Road Km 7    1Km Mr. Ten Tsh. Lepcha Ninth Plan State Plan TSP 11.17 0.00 11.17 27-Nov-01 26-Nov-02 100% 7.17 0.00 7.17 4.00 0.00 4.00 4.00 Completed
54 Protective Drainage and Carpetting works on SBS Road Km 8    1Km Mr. Dupden Lepcha Ninth Plan State Plan TSP 22.48 0.00 22.48 27-Nov-01 27-Nov-02 100% 19.28 0.00 19.28 3.20 0.00 3.20 3.20 Completed
55 Protective Drainage and Carpetting works on SBS Road Km 9    1Km Mr. Pintso Lepcha   State Plan TSP 19.23 0.00 19.23 27-Nov-01 28-Nov-02 100% 18.21 0.00 18.21 1.02 0.00 1.02 1.02 Completed
56 Construction of Guest House at Pentok, Mangan, North Sikkim.   N/A - Eleventh Plan State Plan TSP 187.08 0.00 187.08 2006 - - 0.00 0.00 0.00 187.08 0.00 187.08 187.08  
57 Widening protective work drainage & carpetting work on S.B.S Road Km 10th & 12th   2Km Mr. Lobzang Lepcha Tenth Plan State Plan TSP 34.51 0.00 34.51 15-Nov-03 14-Aug-04 73% 14.99 0.00 14.99 19.52 0.00 19.52 19.52 Carpetting work to be done.
58 Widening protective work drainage & carpetting work on S.B.S Road Km 13th    1Km Mr. Sonam Dorjee Tenth Plan State Plan TSP 18.68 0.00 18.68 18-Nov-04 17-May-05 70% 0.73 0.00 0.73 17.95 0.00 17.95 17.95 WBM/carpetting work to be done
59 Widening protective work drainage & carpetting work on S.B.S Road Km 14th & 15TH   2Km Mr. Topnam Lepcha   State Plan TSP 35.15 0.00 35.15 11-Jan-03 10-Oct-03 80% 10.24 0.00 10.24 24.91 0.00 24.91 24.91 Carpetting work to be done.
60 Strengthening, protective / drainage carpetting works on approach road to Ringtham Gumpa Km1st to 3rd  Mangan.   3Km K.N. Lachenpa   State Plan TSP 276.00 0.00 276.00 14-Mar-08 18-Sep-09 55% 11.51 0.00 11.51 264.49 0.00 264.49 264.49 work in progress
61 Construction approach road to medicine pond B-6   0.96 Km Tempo Lepcha   State Plan TSP 105.00 0.00 105.00 6-Mar-08 7-Mar-09 65% 62.73 0.00 62.73 42.27 0.00 42.27 42.27 work in progress
62 Construction approach road to Shakothang at Sarchok village   0.67 Km Dawa Gaytmso Lachenpa Tenth Plan State Plan TSP 64.98 0.00 64.98 7-Apr-08 8-Apr-09 40% 3.27 0.00 3.27 61.71 0.00 61.71 61.71 work in progress
63 Protective works, widening, drainage and carpeting on Bictchu road Km 1st to 3rd to Gai Gaon at Lachung   3Km Needup Lacungpa   State Plan TSP 298.00 0.00 298.00 21-Aug-08 2-Aug-10 40% 86.28 0.00 86.28 211.72 0.00 211.72 211.72 work in progress
64 Premix Carpetting imp & widening of D.S.M road km 12th to 16th    4Km Mr. Singhik Lepcha Tenth Plan State Plan TSP 124.05 0.00 124.05 15-Jan-03 14-Jul-04 80% 54.90 0.00 54.90 69.15 0.00 69.15 69.15 Bill prepared till work done, Road Handed to BRO
65 Premix Carpetting imp & widening of D.S.M road km 17th    1Km Mr. Chewang Norbu Tenth Plan State Plan TSP 19.41 0.00 19.41 11-Jan-03 10-Oct-03 100% 9.93 0.00 9.93 9.48 0.00 9.48 9.48 Final bill to be paid 
66 Premix Carpetting imp & widening of D.S.M road km 18th    1Km Mr. Dawa Tshering  Tenth Plan State Plan TSP 19.56 0.00 19.56 11-Jan-03 10-Oct-03 85% 10.91 0.00 10.91 8.65 0.00 8.65 8.65 Bill prepared till work done, Road Handed to BRO
67 Premix Carpetting imp & widening of D.S.M road km 19th    1Km Mr. Ongden lepcha Tenth Plan State Plan TSP 20.44 0.00 20.44 11-Jan-03 10-Oct-03 73% 7.44 0.00 7.44 13.00 0.00 13.00 13.00
68 Premix Carpetting imp & widening of D.S.M road km 20th    1Km Mr. Mingma Tshering Tenth Plan State Plan TSP 20.04 0.00 20.04 11-Jan-03 10-Oct-03 74% 12.50 0.00 12.50 7.54 0.00 7.54 7.54
69 Premix Carpetting imp & widening of D.S.M road km 21st     1Km Mr. Lobzang Lepcha   State Plan TSP 23.38 0.00 23.38 11-Jan-03 10-Oct-03 75% 13.55 0.00 13.55 9.83 0.00 9.83 9.83
B DISTRICT :EAST      
  CENTRAL  SPONSORED  SCHEMES                                
1 Const. of link road from Arubotey to Subaneydara km 1st-3rd. Pakyong 3Km Om Bhd. Gurung Ninth Plan BADP - 0.00 29.97 29.97 30-Nov-00 16-Mar-01 68% 0.00 22.98 22.98 0.00 6.99 6.99 6.99 work abondoned
2 Const. of link road from sisney to North Regu km 1st -4th. Pakyong 4Km T.S. Lama Tenth Plan BADP - 0.00 30.31 30.31 21-Nov-00 5-Mar-01 95% 0.00 24.54 24.54 0.00 5.77 5.77 5.77 work abondoned
3 Construction of 60 m span steel bridge at Bongliung over Rongli Chu in East Sikkim   60m Gazendra Rai Eleventh Plan CSS   0.00 74.07 74.07 29-Mar-08 29-Sep-09 15% 0.00 0.00 0.00 0.00 74.07 74.07 74.07 work in progress
4 Const. of 12 m span R.C.C. Bridge on Sangkhola Zingla Martam Road at Km 11th ch-3rd.   12m Anita Gurung Eleventh Plan CRF  - 0.00 38.63 38.63 1-Apr-07 31-Mar-08 45% 0.00 10.23 10.23 0.00 28.40 28.40 28.40 work under progress
5 Const. of 12 m span R.C.c. Bridge on Sangkhola Zingla Martam Road at Km 12th ch-4th..   12m T.B. Pradhan Eleventh Plan CRF  - 0.00 45.12 45.12 1-Apr-07 31-Mar-08 60% 0.00 27.70 27.70 0.00 17.42 17.42 17.42 work under progress
6 Surface improvement and widening of Sang Sirwani Road Km 1st & App Road from Mech Sub Div Office at Dochum   1Km Kishor Pradhan Eleventh Plan CRF  - 0.00 155.00 155.00 10-Oct-07 9-Sep-08 85% 0.00 71.18 71.18 0.00 83.82 83.82 83.82 work under progress
7 Surface improvement and widening of Sang Sirwani Road Km 2nd & App Road to Mech Workshop Dochum   1Km K.R. Sharma Eleventh Plan CRF  - 0.00 38.49 38.49 10-Oct-07 9-Sep-08 65% 0.00 12.61 12.61 0.00 25.88 25.88 25.88 work under progress
8 Upgradation of Link Road from NH-31A to Dokey Chisopani Km 1st    1Km Kishor Pradhan Eleventh Plan CRF  - 0.00 152.58 0.00 29-Feb-08 28-Feb-09 35% 0.00 29.41 0.00 0.00 123.17 0.00 0.00 Work to Commence
9 Upgradation of Link Road from NH-31A to Dokey Chisopani Km 2nd  Singtam 1Km Gopal Sharma Eleventh Plan CRF  - 29-Feb-08 28-Feb-09 30% 0.00 work under progress
10 Upgradation of Link Road from NH-31A to Dokey Chisopani Km 3rd Singtam 1Km Suren Gurung Ninth Plan CRF  - 29-Feb-08 28-Feb-09 45% 0.00 work under progress
11 Construction of link road from pakyong  Nop gaon to barpipal Dara, Km 1st-3rd in East-Sikkim Pakyong 3Km Hemandri Adhikari Eleventh Plan CRF CSS 0.00 102.29 102.29 5-Aug-08 5-Mar-10 25% 0.00 0.00 0.00 0.00 102.29 102.29 102.29 work in progress
12 Premix carpetting and widening work on Sang dipudara road Km 1st to 12th.   12Km Daluram Sarda Tenth Plan EI Removal 6.95 277.44 284.39 18/11/2002 17/08/2004 90% 0.00 233.08 233.08 6.95 44.36 51.31 51.31 Sanctioned from EI Rs 6.95 Crore
13 Upgradationand premix carpeting along Duga Pachaykhani road KM 1st-14th. Singtam 14Km B.K.Agarwal Tenth Plan EI Removal 407.61 433.77 841.38 21-Feb-05 5-Mar-08 100% 24.00 433.77 457.77 383.61 0.00 383.61 383.61 Work Completed
14 Construction of Road from Rathong (NH-31A) to Kimchithang Km 1st to 15th (EI)   15Km KK Agarwal Tenth Plan EI - 765.00 701.89 1,466.89 2007 - 30% 0.00 209.91 209.91 765.00 491.98 1,256.98 1,256.98 New Project
15 Improvement of  Sang Dipudara Road (EI)   14Km - Tenth Plan EI - 0.00 347.74 347.74 2007 - 90% 0.00 0.00 0.00 0.00 347.74 347.74 347.74 New Project
16 Improvement of  Pakyong - Karthok - Naya busty - Raigoan  Road (EI)     - Eleventh Plan EI - 0.00 398.42 398.42 2007 - 45% 0.00 160.00 160.00 0.00 238.42 238.42 238.42 New Project
17 Widening, upgradation of pavement & drainage system along  Rangpo Duga Pendam road km 1st - 15th    15Km M/s Apex Project & Investment                 P. Ltd. Eleventh Plan ISC  - 0.00 950.00 950.00 15-Jun-08 16-Dec-08 65% 0.00 303.67 303.67 0.00 646.33 646.33 646.33 work in progress
18 Improvement of Rhenock - Simanakhola Road Km 1st to 3rd. (ISC)   3Km Mr. Kuber Raj Rai Tenth Plan ISC  - 0.00 250.00 250.00 26-Mar-08 - 25% 0.00 49.43 49.43 0.00 200.57 200.57 200.57 work in progress
19 Carpetting of Sirwani Bermoik Phongla Road, S.Sikkim (ISC)   24Km - Tenth Plan ISC  - 0.00 999.08 999.08 26-Jul-05 - 10% 0.00 766.00 766.00 0.00 233.08 233.08 233.08 work in progress
20 Strengthening/drainage and P/Wprks for the road from Lal Turning to Bashilakha Road Km 1st to 3rd Pakyong 3Km G.M Gurung   NABARD Exp. 33.19 125.21 158.40 30/09/07 31/03/08 100% 0.00 124.82 124.82 33.19 0.39 33.58 33.58 Work Completed
21 Const. of link road from King Stone to Simana Khola Km 1st to 2nd.   2Km Departmental Eleventh Plan NABARD Exp. 8.60 34.41 43.01 - - 100% 0.00 31.68 31.68 8.60 2.73 11.33 11.33 completed
22 Construction of Link Road from Sakyong to Beyong km 1st to 2nd (State Share of NABARD)   2Km KRSharma & TB Pradhan Eleventh Plan NABARD Exp. 0.00 79.51 79.51 12-Mar-08 11-Mar-09 75% 0.00 23.59 23.59 0.00 55.92 55.92 55.92 work under progress
23 Strengthening,drainage and Carpeting and construction of 30m span steel bridge along Assam-Pakyong road km 7th - 15th. Pakyong 30m S.K. Agarwal Tenth Plan NEC  - 0.00 750.76 750.76 6-Nov-06 5-May-08 75% 0.00 465.96 465.96 0.00 284.80 284.80 284.80 work under process
24 Construction of major retaining structures on approach road to Raj Bhawan,VIP Complex and TNA Public School Complex   N/A   Tenth Plan NEC  - 0.00 110.58 110.58 30-May-05 29-May-06 100% 0.00 99.67 99.67 0.00 10.91 10.91 10.91 completed
25 Replacement of Sumin Wooden Suspension Bridge on Sang Khola Sumin Road       Eleventh Plan NEC  - 0.00 285.40 285.40 8-Apr-04 - - 0.00 233.00 233.00 0.00 52.40 52.40 52.40 -
26 Const. of Goshkhan Dara Bridge over River Teesta at Singtam, East Sikkim Singtam 120m M.P Agarwal Tenth Plan NLCPR  - 0.00 1,337.11 1,337.11 10-Jan-07 11-Jun-08 40% 0.00 468.00 468.00 0.00 869.11 869.11 869.11 work in progress
27 Const. of diversion road Ranipool-Pakyong road km 1st-3rd. Pakyong 3Km B.K. Agarwal Tenth Plan NLCPR  Exp. 102.98 236.87 339.85 21-Feb-05 21-Nov-05 80% 64.60 170.78 235.38 38.38 66.09 104.47 104.47 work in progress
28 Extension of Link Road to Dokey Chisopani Pry School    ( State Share of RSVY Scheme)   0.81Km Nabin Rai Eleventh Plan RSVY New Road 1.72 25.00 26.72 17-Oct-05 27-Mar-06 85% 0.00 25.00 25.00 1.72 0.00 1.72 1.72 in progress
  STATE PLAN                                        
29 Repairs of IETC SMITE Overhead crane station at 5th Mile Tadong   N/A Departmental Tenth Plan State Plan Addl.Facilities 1.35 0.00 1.35 20-Jul-06 - 5% 1.35 0.00 1.35 0.00 0.00 0.00 0.00 work in progress
30 Fencing around SPWD Mech. Workshop Tadong   N/A Departmental Eleventh Plan State Plan Addl.Facilities 2.74 0.00 2.74 31-Aug-06 - 5% 2.73 0.00 2.73 0.01 0.00 0.01 0.01 work in progress
31 Additonal facilities installation of portable magazine at Sirwani-Singtam   N/A Departmental Tenth Plan State Plan Addl.Facilities 10.00 0.00 10.00 22-Aug-07 - 5% 9.45 0.00 9.45 0.55 0.00 0.55 0.55 work in progress
32 Premix carpetting/Imp. Of Rongli Rorathang road, Km 1st - 11th.( Revised)   11Km Kuber Raj Rai Tenth Plan State Plan Exp. 254.00 0.00 254.00 1-Jan-03 3-Apr-06 100% 215.36 0.00 215.36 38.64 0.00 38.64 38.64 completed
33 Upgradation/carpeting P/works and drainage along Pakyong-Karthok road km 1st-4th. Pakyong 4Km P. N. Kazi Tenth Plan State Plan Exp. 286.69 0.00 286.69 28-Mar-05 27-Jul-06 55% 95.08 0.00 95.08 191.61 0.00 191.61 191.61 work in progress
34 Upgradation and premix carpeting of Kotlaytar Rai Gaon Road,km 1st & 2nd  Pakyong 2Km Miss Devi Dakhal Tenth Plan State Plan Exp. 146.88 0.00 146.88 28-Mar-05 27-Sep-06 75% 31.05 0.00 31.05 115.83 0.00 115.83 115.83 Revised estimate submitted
35 Upgradation and premix carpeting of Kotlaytar Rai Gaon Road,km 3rd Pakyong 1Km Mr. G.K. Pradhan Tenth Plan State Plan Exp. 22.70 0.00 22.70 1-Jul-05 31-Dec-07 90% 22.13 0.00 22.13 0.57 0.00 0.57 0.57 work taken up departmentaly
36 Upgradation and premix carpeting of Kotlaytar Rai Gaon Road,km 4th Pakyong 1Km XXX Tenth Plan State Plan Exp. 17.92 0.00 17.92 1-Jul-05 31-Dec-07 90% 17.60 0.00 17.60 0.32 0.00 0.32 0.32 Revised estimate submitted
37 Upgradation and premix carpeting of Kotlaytar Rai Gaon Road,km 5th Pakyong 1Km K.S.Rai Tenth Plan State Plan Exp. 27.01 0.00 27.01 1-Jul-05 31-Dec-07 90% 16.04 0.00 16.04 10.97 0.00 10.97 10.97 Revised estimate submitted
38 Upgradation and premix carpeting of Kotlaytar Rai Gaon Road,km 6th Pakyong 1Km Ishore Dakahal Tenth Plan State Plan Exp. 21.15 0.00 21.15 1-Jul-05 31-Dec-07 70% 17.79 0.00 17.79 3.36 0.00 3.36 3.36 Revised estimate submitted
39 Upgradation and premix carpeting of Kotlaytar Rai Gaon Road,km 7th Pakyong 1Km K.S.Rai Tenth Plan State Plan Exp. 22.10 0.00 22.10 1-Jul-05 31-Dec-07 55% 8.68 0.00 8.68 13.42 0.00 13.42 13.42 Revised estimate submitted
40 Upgradation and premix carpeting of Kotlaytar Rai Gaon Road,km 8th Pakyong 1Km Mr. M.K. Pradhan Tenth Plan State Plan Exp. 21.66 0.00 21.66 1-Jul-05 31-Dec-07 55% 17.06 0.00 17.06 4.60 0.00 4.60 4.60 Revised estimate submitted
41 Premix Carpetting and Surface improvement Chewribotay Pendam  Km 1st - 6th Singtam 6Km Basudev Pradhan Tenth Plan State Plan Exp. 117.78 0.00 117.78 29/05/2003 31/01/04 95% 83.84 0.00 83.84 33.94 0.00 33.94 33.94 work in progress
42 Construction of Bye Pass Road below Mintokgang Station 0.30Km DB Chettri Tenth Plan State Plan Exp. 80.26 0.00 80.26 26-Feb-04 5-Aug-04 100% 71.46 0.00 71.46 8.80 0.00 8.80 8.80 Final bill under process
43 Premix carpetting & Surface Imp.of KLT 16th to 26th Km (Revised)   10Km P.D. Denzongpa Tenth Plan State Plan Exp. 260.57 0.00 260.57 2003 - 100% 252.36 0.00 252.36 8.21 0.00 8.21 8.21 completed
44 Premix carpetting & Surface Imp.of KLT 7th to 15th Km (Revised)   8Km L.N. Sarda Tenth Plan State Plan Exp. 232.83 0.00 232.83 2003 - 100% 214.16 0.00 214.16 18.67 0.00 18.67 18.67 completed
45 Ext. of Pakyong-Mamring Tareythang road km 1st   1Km Khush N.Adhikari Tenth Plan State Plan Exp. 28.91 0.00 28.91 1-Jul-05 31-Dec-07 90% 28.72 0.00 28.72 0.19 0.00 0.19 0.19 Revised
46 Ext. of Pakyong-Mamring Tareythang road km 2nd   1Km Johar Man Rai Tenth Plan State Plan Exp. 16.61 0.00 16.61 1-Jul-05 31-Dec-07 90% 16.37 0.00 16.37 0.24 0.00 0.24 0.24 Revised
47 Ext. of Pakyong-Mamring Tareythang road km 3rd   1Km G.K. Pradhan Tenth Plan State Plan Exp. 22.70 0.00 22.70 1-Jul-05 31-Dec-07 90% 12.94 0.00 12.94 9.76 0.00 9.76 9.76 Revised Estimate submitted
48 Ext. of Pakyong-Mamring Tareythang road km 4th.   1Km Udai Mishara Tenth Plan State Plan Exp. 17.92 0.00 17.92 1-Jul-05 31-Dec-07 90% 12.02 0.00 12.02 5.90 0.00 5.90 5.90 Revised Estimate submitted
49 Ext. of Pakyong-Mamring Tareythang road km 5th.   1Km K.S.Rai Tenth Plan State Plan Exp. 27.01 0.00 27.01 1-Jul-05 31-Dec-07 90% 16.05 0.00 16.05 10.96 0.00 10.96 10.96 Revised Estimate submitted
50 Ext. of Pakyong-Mamring Tareythang road km 6th.   1Km Ishore Dakahal Tenth Plan State Plan Exp. 21.15 0.00 21.15 1-Jul-05 31-Dec-07 70% 18.71 0.00 18.71 2.44 0.00 2.44 2.44 Revised Estimate submitted
51 Ext. of Pakyong-Mamring Tareythang road km 7th.   1Km K.S.Rai Tenth Plan State Plan Exp. 22.10 0.00 22.10 1-Jul-05 31-Dec-07 55% 8.68 0.00 8.68 13.42 0.00 13.42 13.42 Revised Estimate submitted
52 Ext. of Pakyong-Mamring Tareythang road km.8th    1Km M. K. Pradhan Tenth Plan State Plan Exp. 21.66 0.00 21.66 1-Jul-05 31-Dec-07 55% 0.00 0.00 0.00 21.66 0.00 21.66 21.66 Revised Estimate submitted
53 Ext. of Pakyong-Mamring Tareythang road km.9th    1Km Kamal Adhikari Tenth Plan State Plan Exp. 19.24 0.00 19.24 1-Jul-05 31-Dec-07 100% 8.00 0.00 8.00 11.24 0.00 11.24 11.24 Completed, Final bill under process
54 Ext. of Pakyong-Mamring Tareythang road km.10th    1Km Milan Dahal Tenth Plan State Plan Exp. 10.70 0.00 10.70 1-Jul-05 31-Dec-07 100% 0.00 0.00 0.00 10.70 0.00 10.70 10.70 Completed
55 Construction of Arithang Road connecting Indira Bye-Pass Road  Station 0.6Km Departmental Tenth Plan   Exp. 57.47 0.00 57.47 2005 - 100% 55.75 0.00 55.75 1.72 0.00 1.72 1.72 completed
56 Const. of road from Zingla Martam KM 16th-18th (2.36km) i/c LC   2Km UP Kazi Tenth Plan State Plan TSP Exp. 77.96 0.00 77.96 3-Oct-05 3-Oct-06 100% 83.16 0.00 83.16 -5.20 0.00 -5.20 -5.20 work in progress
57 Feeder Raod to development Area( Addl sanction on 9th Paln scheme)  Ssno 1/East/Exp/06-07   0.3Km T. wangchok Tenth Plan   Exp. 5.04 0.00 5.04 2006 - 100% 5.04 0.00 5.04 0.00 0.00 0.00 0.00 Revised
58 Const of 40 Mts span Bridge over Rongli Khola along  arubotey subaney dara Raod Ssno 2/E/exp/06-07   40m Ashok Ts. Bhutia Eleventh Plan   Exp. 16.50 0.00 16.50 2006 - 100% 14.24 0.00 14.24 2.26 0.00 2.26 2.26 completed
59 Immediate Restoration of Mamring Amba Road km 3rd   1Km Departmental Tenth Plan   Exp. 6.77 0.00 6.77 6-Nov-06 5-May-08 100% 6.68 0.00 6.68 0.09 0.00 0.09 0.09 completed
60     Relocation     and extension of HT &LT line and shifting of 25 KVA outdoor   pipe    distribution sub-station at Barchangey Village East.   N/A Power Department Eleventh Plan   Exp. 3.37 0.00 3.37 2006 - 100% 3.37 0.00 3.37 0.00 0.00 0.00 0.00 completed
61 Construction of 20 chain road Bio Control Laboratory to Phewk Busty road  Station 0.60Km Mr. G.K.Rai Tenth Plan State Plan Link Road 25.03 0.00 25.03 28-Sep-05 27-Mar-05 85% 9.00 0.00 9.00 16.03 0.00 16.03 16.03 Revised estimate under process
62 Const. of link road from Basilakhs to Middle camp via Rodongtar km 6th  Pakyong 1Km Justin Rai Tenth Plan State Plan New Road 17.93 0.00 17.93 5-Oct-05 9-Feb-05 75% 12.41 0.00 12.41 5.52 0.00 5.52 5.52 Revised estimate submitted
63 Const. of link road from Basilakhs to Middle camp via Rodongtar km 7th  Pakyong 1Km Jeewan Subba Tenth Plan State Plan New Road 17.23 0.00 17.23 5-Oct-05 9-Feb-05 100% 17.22 0.00 17.22 0.01 0.00 0.01 0.01 completed
64 Const. of link road from Basilakhs to Middle camp via Rodongtar km 8th  Pakyong 1Km Paul Rai Tenth Plan State Plan New Road 21.36 0.00 21.36 5-Oct-05 9-Feb-05 100% 10.01 0.00 10.01 11.35 0.00 11.35 11.35 work in progress
65 Const. of 10m span RCC Culvert on Basilakha to middle camp km 8th.   10m Patrush Subba Tenth Plan State Plan New Road 12.32 0.00 12.32 5-Oct-05 9-Feb-05 75% 0.00 0.00 0.00 12.32 0.00 12.32 12.32 work in progress
66 Const of Approach road to Sivalaya Mandir at pacheykhani Km 1st   1Km R.N. Baral   State Plan New Road 23.51 0.00 23.51 18-Jul-05 15-Jun-06 85% 12.87 0.00 12.87 10.64 0.00 10.64 10.64 work in progress
67 Construction of Link Road from Amba to Taja School 1st and 2nd km   2Km Mon Narayan Dhakal Tenth Plan State Plan New Road 5.06 0.00 5.06 - - 75% 3.96 0.00 3.96 1.10 0.00 1.10 1.10 work in progress
68 Const. of link road from Assam-Pakyong road to Kadamtam village km.1st. Pakyong 1Km M.B.Mangar Tenth Plan State Plan New Road 39.65 0.00 39.65 1-Jul-05 30-Jun-06 100% 39.51 0.00 39.51 0.14 0.00 0.14 0.14 Completed, Final bill under process
69 Const. of link road from Assam-Pakyong road to Kadamtam village km.2nd. Pakyong 1Km Elies Lepcha Tenth Plan State Plan New Road 41.40 0.00 41.40 1-Jul-05 30-Jun-06 100% 41.39 0.00 41.39 0.01 0.00 0.01 0.01 Completed, Final bill under process
70 Const. of link road from Assam-Pakyong road to Kadamtam village km.3rd & 4th. Pakyong 2Km D.P. Mangar Tenth Plan State Plan New Road 41.51 0.00 41.51 1-Jul-05 30-Jun-06 75% 29.71 0.00 29.71 11.80 0.00 11.80 11.80 Revised Est Submitted
71 Const. of link road from Assam-Pakyong road to Kadamtam village km.3rd & 4th.Contingency Rs.4.26 + Land Compansation Pakyong 2Km LC & Contg Tenth Plan State Plan New Road 87.70 0.00 87.70 - - 100% 34.27 0.00 34.27 53.43 0.00 53.43 53.43 completed
72 Construction of road from Chandmari village to Jawaharlall Nehru road  Station 0.38 Km K Wangchuk   State Plan New Road 30.63 0.00 30.63 31-May-05 30-Nov-05 100% 23.76 0.00 23.76 6.87 0.00 6.87 6.87 work completed final bill under process
73 Land compensation for extension of link road from NH-31 A to Chisopani km 2nd   1Km   Tenth Plan State Plan New Road 3.35 0.00 3.35 - - 100% 3.35 0.00 3.35 0.00 0.00 0.00 0.00 completed
74 Land compenstion for construction of Link road from Basilakha to Middle Camp via Radongtar km 6th to 8th & 10th M Span R.C.C Bridge   3Km   Eleventh Plan State Plan New Road 19.47 0.00 19.47 2008 - - 0.00 0.00 0.00 19.47 0.00 19.47 19.47  
75 Const. of Song-zingla Martam road km 9th.   1Km P.T. Lepcha Eleventh Plan State Plan New Road 12.45 0.00 12.45 5-Mar-03 20-Dec-03 80% 5.63 0.00 5.63 6.82 0.00 6.82 6.82  In progress
76 Const. of Sang-Zingla Martam road KM 10th.   1Km P.T. Rongong Eleventh Plan State Plan New Road 14.51 0.00 14.51 6-Mar-03 6-Dec-03 100% 12.45 0.00 12.45 2.06 0.00 2.06 2.06 Final Payment
77 Const. of Song-Zingla Martam road km 11th    1Km Anita Gurung Eleventh Plan State Plan New Road 16.17 0.00 16.17 6-Mar-03 6-Dec-03 100% 12.28 0.00 12.28 3.89 0.00 3.89 3.89 Final Payment
78 Const. of Song-Zingla Martam road km 12th.   1Km U. Lama Eleventh Plan State Plan New Road 17.74 0.00 17.74 6-Mar-03 6-Dec-03 100% 13.11 0.00 13.11 4.63 0.00 4.63 4.63 Final Payment
79 Const.of Song-Zingla Martam road km 14th  Singtam 1Km Tenging Bhutia Eleventh Plan State Plan New Road 25.54 0.00 25.54 6-Mar-03 6-Dec-03 100% 19.63 0.00 19.63 5.91 0.00 5.91 5.91  In progress
80 Const. of Song-Zingla Martam road km 15th. Singtam 1Km S.K.Chettri   State Plan New Road 26.75 0.00 26.75 6-Mar-03 6-Dec-03 95% 19.95 0.00 19.95 6.80 0.00 6.80 6.80  In progress
81 Carpeting and surface strengthening, improvement, including drainage works of roads in and around Gangtok. Station 9.41 Km PM Chamling Tenth Plan State Plan Remv. 361.89 0.00 361.89 6-Jun-04 5-Sep-05 100% 229.45 0.00 229.45 132.44 0.00 132.44 132.44 work completed final bill under preparation
82 Surface strengthening upgradation and carpeting of Pakyong-Karthok Naya Busty road km 5th -7th. Pakyong 2Km Adup Bhutia Tenth Plan State Plan Remv. 220.68 0.00 220.68 21/06/05 31-Aug-08 45% 57.04 0.00 57.04 163.64 0.00 163.64 163.64 work in progress, Date Extended
83 P/L edging ,soling, metalling, premix carpeting and cross drain of link road from sichey to Indira Bye Pass via Shivalaya Mandir   Station 0.3Km Mrs Rupa Dhakal Tenth Plan State Plan Remv. 8.16 0.00 8.16 1/0/2002 2-Jul-05 80% 5.81 0.00 5.81 2.35 0.00 2.35 2.35 work in abeyance due to non availibility of bitumen
84 Surface stregenthening , upgradation and carpeting of Roads during the visit of His Holiness the Dalai Lama  Station   Departmental Tenth Plan State Plan Remv. 40.35 0.00 40.35 2005 - 100% 38.79 0.00 38.79 1.56 0.00 1.56 1.56 completed
85 Providing 75mm thick CC pitching over approach raod to Gairi Goan from NH 31A Near Hotel Tashi Targey) Ssno 2/E/Remv/06-07 Station 0.3 Km Departmental Tenth Plan State Plan Remv. 3.40 0.00 3.40 2006 - 0% 0.00 0.00 0.00 3.40 0.00 3.40 3.40  
86 Const of PW along TNSS to Dhupidara Ssno 6/E/Remov/0607 Station N/A   Tenth Plan State Plan Remv. 3.44 0.00 3.44 2006 - 100% 3.42 0.00 3.42 0.02 0.00 0.02 0.02 completed
87 Permanent restoration work of Chief Justic Banglow Road Ssno7/E/Remo/06-07 Station N/A Departmental Tenth Plan State Plan Remv. 11.21 0.00 11.21 2006 - 100% 10.31 0.00 10.31 0.90 0.00 0.90 0.90 completed
88 Immediate protective work to donak khola along tarethang Bering Road km      ch.22nd 23 ch Singtam 0.06 Km Departmental Tenth Plan State Plan Remv. 19.72 0.00 19.72 2006 - 100% 17.65 0.00 17.65 2.07 0.00 2.07 2.07 completed
89 Restoration work at km 8th Ch.4-5 (Namphey khola)along Assam-Pakyong road Pakyong 0.06 Km Departmental Tenth Plan State Plan Remv. 19.93 0.00 19.93 2006 - 100% 19.93 0.00 19.93 0.00 0.00 0.00 0.00 completed
90 Immediate traffic clerance of rest work on lingtam-Agamlok rod km 1st &2nd. Pakyong 2Km Departmental Tenth Plan State Plan Remv. 4.48 0.00 4.48 2006 - 100% 4.48 0.00 4.48 0.00 0.00 0.00 0.00 completed
91 Surface improvement at approach road to MLA Hostel and SLA premises Station 0.6Km Departmental   State Plan Remv. 12.83 0.00 12.83 2006 - 100% 4.00 0.00 4.00 8.83 0.00 8.83 8.83 completed
92 Raising of sunkdown formation of Raley-Kambal Samdong km 6th ch 30-32 Singtam 6.9Km Departmental   State Plan Remv. 3.93 0.00 3.93 - - 100% 3.93 0.00 3.93 0.00 0.00 0.00 0.00 completed
93 Slip clearance along KLT road km 2nd ch 25th & 27th  Singtam N/A Departmental Eleventh Plan State Plan Remv. 3.61 0.00 3.61 - - 100% 3.08 0.00 3.08 0.53 0.00 0.53 0.53 completed
94 Slope stabilisation work km 2nd Ch:6to 8 along Pakyong-Machong Road Pakyong N/A Departmental Eleventh Plan State Plan Remv. 4.68 0.00 4.68 2007 - 100% 0.00 0.00 0.00 4.68 0.00 4.68 4.68 completed
95 Providing protective work at Paemragoan  Pakyong N/A Departmental Tenth Plan State Plan Remv. 2.24 0.00 2.24 2008 - 100% 0.00 0.00 0.00 2.24 0.00 2.24 2.24 completed
                                           
C DISTRICT :  SOUTH      
A. CENTRAL  SPONSORED  SCHEMES                                    
1 Surface strengthening carpetting, drainage and protective work along Tarku-Damthang road Km13th-19th Ravangla 6Km Shri A. Pradhan Tenth Plan ACA CSS 0.00 228.00 228.00 Feb-08 Mar-08 100% 0.00 228.00 228.00 0.00 0.00 0.00 0.00 work completed
2 Construction of 25 m. Span Steel Bridge over Mayalu Jhora at Km 3rd on Melli -Nayabazar road. Namchi 25m Mr. P. C. Mundra Tenth Plan CRF Repl. 3.28 58.97 62.25 12-Mar-04 30-Jun-06 100% 0.00 52.83 52.83 3.28 6.14 9.42 9.42 Final bill submitted
3 Construction of 25 m. Span Steel Bridge over Rolu Khola at Km 9th on Melli -Nayabazar road.  Namchi 25m Mr. G.M. Gurung Eleventh Plan CRF Repl. 3.28 52.60 55.88 22-Jul-04 31-May-06 100% 0.00 48.63 48.63 3.28 3.97 7.25 7.25 Revision under process
4 Upgradation of existing road from Vok to Namchi. Namchi 14.78 Km M.P.Agarwal Tenth Plan CRF Remv. 101.57 365.83 467.40 8-Aug-07 - 100% 74.49 345.42 419.91 27.08 20.41 47.49 47.49 -
5 Construction of Gurassey Road from Bio-Diversity Park (Temi)     Passang Lepcha Tenth Plan EI New Road 0.00 1010.92 1,010.92 26-Mar-08 - - 0.00 127.26 127.26 0.00 883.66 883.66 883.66 -
6 Widening, Improvement, protective work, drainage and carpetting of Melli, Phong road, Km. 1st to 24th.   24Km Pawan Kr. AgarwaL Tenth Plan ISC Remv. 77.40 1298.61 1,376.01 - - 35% 33.11 235.00 268.11 44.29 1,063.61 1,107.90 1,107.90 Payment made to old contractor
7 Widening, surface improvement, p/w & drainage system along Phongla-Bermiock-Sirwani road Km  1st- 28th. Ravangla 28Km Sunil Kr. Agarwal Tenth Plan ISC Remv. 558.00 999.08 1,557.08 Feb-05 Mar-08 100% 30.32 866.00 896.32 527.68 133.08 660.76 660.76 in progress
8 Upgradation & carpetting of Bhaisalgoan to Salghari road Km 1st to 2nd in South Sikkim.   2Km Mr. Hanuman Das Agarwal Tenth Plan NABARD Exp. 18.91 63.41 82.32 12-Feb-07 11-Jan-08 100% 0.00 63.41 63.41 18.91 0.00 18.91 18.91 completed, final bill submitted
9 Construction of trukable road from Tiffin Dara to Lower Tinghrithang  School Km 1st to 7th   7Km - Tenth Plan NABARD New Road 28.26 254.370 282.63 6-Jun-06 12-Dec-07 64% 0.00 135.97 135.97 28.26 118.40 146.66 146.66 in progress
10 Surfce strengthening, carpetting, drainage and Protective Works along A/R to Buddha Statue (Sakymuni) Ravangla 2Km Pawan Kr. AgarwaL   NABARD CSS 0.00 360.910 360.91 - - 44% 0.00 125.00 125.00 0.00 235.91 235.91 235.91 in progress
11 Truakable road from 10th mile to Tingmoo villageKm 1st, 2nd and 7th Ravangla 3Km Mr. Nim S. Sherpa Tenth Plan NEC CSS 0.00 468.29 468.29 4-Apr-06 4-Apr-07 62% 0.00 104.15 104.15 0.00 364.14 364.14 364.14 in progress
12 Truakable road from 10th mile to Tingmoo villageKm 3rd and 6th Ravangla 2Km Mr. Sonam O. Bhutia Tenth Plan NEC CSS 4-Apr-06 4-Apr-07 53% 0.00 in progress
13 Truakable road from 10th mile to Tingmoo villageKm 4th and 5th Ravangla 2Km Mr. Lhendup D. Kaleon Tenth Plan NEC CSS 5-Apr-06 4-Apr-07 43% 0.00 in progress
14 Truakable road from 10th mile to Tingmoo villageKm 8th. Ravangla 1Km Mr. Bala R. Limboo Tenth Plan NEC CSS 9-Apr-06 4-Apr-07 60% 0.00 in progress
15 Strengthening / drainage carpetting of Ralang-Phamthang road Km 14th to 26th & Replacement of Two existing Bridges over Bermali & Chil Khola in South Sikkim. Ravangla 12Km & 65m x 2 nos Mr. N.T. Bhutia Tenth Plan NEC Remv. 100.00 1100.83 1,200.83 11-Nov-06 5-May-08 42% 0.00 213.00 213.00 100.00 887.83 987.83 987.83 in progress
16 Construction of 40m Span Bridge over Lower Ben Khola at Saino Tar along Pabong - Simchuthang - Yangang road, South Sikkim. Ravangla 40m Mr. Anjani Kr, Agarwal Tenth Plan NEC CSS 0.00 137.34 137.34 Sep-05 Jun-06 100% 0.00 107.65 107.65 0.00 29.69 29.69 29.69 completed
17 Construction of 60m span steel bridge over Kaw Khola on KS road. Ravangla 60m Mr. S.S. Dhakhal Tenth Plan NEC CSS 0.00 164.35 164.35 Nov-06 Nov-08 76% 0.00 75.00 75.00 0.00 89.35 89.35 89.35 in progress
18 Imp drainage, carpetting works Km 1st -14th and replacement of Rangla Khola bridge on Kimotey Sokpay roads. Ravangla 14Km Mr. Sunil Kr. Agarwal Tenth Plan NEC Remv. 0.00 680.00 680.00 Nov-06 Nov-08 70% 0.00 268.00 268.00 0.00 412.00 412.00 412.00 work under progress
19 Replacement of 110m Span Suspension Bridge over Rabi Khola in Melli Phong road Km 9th in S/Sikkim.    110m Mr. Om Agarwal Tenth Plan NEC CSS 0.00 497.30 497.30 39125.00 12-Feb-08 45% 0.00 144.11 144.11 0.00 353.19 353.19 353.19 in progress
20 Construction of link road Turung School to Suminkhor Primary School.     Mr. Subaash Kharel Tenth Plan NEC New Road 22.79 358.66 381.45 39428.00 6-Jun-09 75% 0.00 169.05 169.05 22.79 189.61 212.40 212.40 in progress
21 Construction of 30m Span Steel Bridges Over Rinzi Khola at Kolagari along Namchi-Vok Road   30m Bhupal Chamling Tenth Plan NEC Rep. 28.34 157.50 185.84 12-Dec-07 6-Jun-09 100% 0.00 109.03 109.03 28.34 48.47 76.81 76.81 Completed, Final bill to be paid
22 Construction of Steel Bridge over Upper Ben Khola on G.L.V.C. road.     - Tenth Plan NEC CSS 0.00 90.83 90.83 14-Feb-06 - - 0.00 81.77 81.77 0.00 9.06 9.06 9.06 -
23 Construction of Makha Suspension Bridge over Tista Khola at Tanak on Makha -Lingi -Yangang- Ravangla Road in South Sikkim.(NEC) Ravangla 100m R.N. Chamling Tenth Plan NEC CSS 0.00 495.25 495.25 25-Aug-06 - 10% 0.00 32.28 32.28 0.00 462.97 462.97 462.97 in progress
24 Surface Improvement, Drainage & Protective works on Namchi-Rong Road, 13 km    13Km Mr. MP Agarwal Tenth Plan NEC   83.89 498.60 582.49 20-Nov-03 -   10.91 498.60 509.51 72.98 0.00 72.98 72.98 -
25 Improvement of Ralang - Phamtam Road      - Eleventh Plan NEC CSS 0.00 1183.00 1,183.00 25-Aug-06 -   0.00 269.13 269.13 0.00 913.87 913.87 913.87 -
26 Surface strengthening drainage & P. Works on Namchi- Damthang Ravangla road- Km 1st -26th.   26Km - Tenth Plan NLCPR Remv. 461.61 1,207.00 1,668.61 1-Jan-05 1-Feb-07 98% 224.94 1,164.19 1,389.13 236.67 42.81 279.48 279.48 in progress
27 Replacement of existing Sikkip Suspension Bridge over Rangit River   82m Mr. Chandra Khaling Tenth Plan NLCPR Repl. 24.47 53.66 78.13 15-Dec-03 30-Mar-07 100% 11.78 53.65 65.43 12.69 0.01 12.70 12.70 work completed
28 Upgradation, Surface strengthening, drainage & P/W on Ravangla Makha Road Km 10th,11th,12th and 13th.   4Km Smt. Sonam Doma Bhutia Tenth Plan NLCPR CSS 0.00 119.05 119.05 15-Jan-03 30-Nov-06 100% 0.00 116.17 116.17 0.00 2.88 2.88 2.88 completed
29 Upgradation, Surface strengthening, drainage & P/W on Ravangla Makha Road Km 18th to 21st   3Km Mr. S. B. Chamling Tenth Plan NLCPR CSS 0.00 109.18 109.18 15-Jan-03 30-Nov-06 100% 0.00 102.96 102.96 0.00 6.22 6.22 6.22 completed
30 Const. of motorable link road from upper Vok to Ung Raam (Water falls) via Namplang and rabong village in Omchu    6Km Mr. B. Tsh. Bhutia Tenth Plan RSVY  New Road 60.11 180.00 240.11 22-Aug-05 21-Aug-07 85% 54.40 180.00 234.40 5.71 0.00 5.71 5.71 in progress
31 Construction of truckable roasd from Borong-Phamtam road to Upper Borong via Gurug Gumpa Km 1st.   1Km Shri K. B. Gurung Tenth Plan RSVY CSS 0.00 64.00 64.00 2-Feb-06 12-Nov-06 100% 0.00 63.98 63.98 0.00 0.02 0.02 0.02 work completed
32 Construction of truckable roasd from Borong-Phamtam road to Upper Borong via Gurug Gumpa Km 2nd.   1Km Shr. D. M. Gurung Tenth Plan RSVY CSS 2-Feb-06 13-Nov-06 100% 0.00
33 Extension of truckable road from Borong-Phamtam road to Lower Borong Km 3rd to 4th.   2Km Shri Y.C. Bhutia   RSVY CSS 0.00 70.32 70.32 2-Feb-06 11-Nov-06 100% 0.00 70.32 70.32 0.00 0.00 0.00 0.00 work completed
34 Construction of link road to Gagyong village km 3   3Km -   RSVY CSS 0.00 87.00 87.00 - - 100% 0.00 77.71 77.71 0.00 9.29 9.29 9.29 work closed
35 Extension of Bhaisalgoan- Salghari road to Farashey km 1st to 3rd.   3Km Mr. Dhan Pd. Rai, Mr. Purna Bhd. Bishkarma, Ratan Kr. Agarwal. Tenth Plan RSVY CSS 0.00 94.64 94.64 11-Nov-05 - 100% 0.00 94.64 94.64 0.00 0.00 0.00 0.00 work closed
  STATE PLAN                                        
36 Construction of Guest house at Yangang in South Sikkim.     Mr. Pawan Kr. Agarwal Tenth Plan State Plan Addl. Facilities 47.31 0.00 47.31 10-Oct-03 30-Jun-05 100% 0.00 57.17 57.17 47.31 -57.17 -9.86 -9.86 completed
37 Construction of Link Road from Rangang to Yangang-Makha via Majuwa : Km 1st and 2nd Ravangla 2Km Mr. S. B. Chamling Tenth Plan State Plan Addl. Facilities 62.36 0.00 62.36 1-Jan-05 10-Oct-05 99% 53.95 0.00 53.95 8.41 0.00 8.41 8.41 in progress
38 Construction of Link Road from Rangang to Yangang-Makha via Majuwa : Km 3rd. Ravangla 1Km Mr. Nar Bhd. Gurung Tenth Plan State Plan Addl. Facilities 22.83 0.00 22.83 1-Jan-05 10-Oct-05 100% 16.17 0.00 16.17 6.66 0.00 6.66 6.66 in progress
39 Construction of Kitchen for PWD Guest House at Temi, South Sikkim. Ravangla N/A Mr. Bindra Kumar Rai Tenth Plan State Plan Addl. Facilities 11.01 0.00 11.01 2-Feb-07 8-Aug-07 95% 0.00 0.00 0.00 11.01 0.00 11.01 11.01 in progress
40 Construction of Helipad at Pokhari dara in Upper Yangyang Ravangla N/A M/s Rinchen Ongmu Bhutia Eleventh Plan State Plan Helipad 90.640 0.00 90.64 1-Jul-08 1-Jan-10 80% 43.00 0.00 43.00 47.64 0.00 47.64 47.64 in progress
41 Construction of 18ch link road from Helipad to Central University at Yanyang. Ravangla 0.54Km Mrs. Sumitra Gurung Eleventh Plan State Plan Helipad 42.670 0.00 42.67 1-Sep-08 1-Dec-08 80% 0.00 0.00 0.00 42.67 0.00 42.67 42.67 in progress
42 Carpetting of Namchi Rong-Sumbuk road Km 1st to 3rd (Soling metalling & Carpetting). [9th plan]   3Km P.K.Agarwal, Roshan Agarwal, Anjani Kr Ararwal Ninth Plan State Plan Exp. 64.18 0.00 64.18 22-Jun-05 - 100% 64.18 0.00 64.18 0.00 0.00 0.00 0.00 Work Closed
43 Construction of  road from Gurpisey to Phalidara. Km 1st & 2nd.   2Km Chung Chung Bhutia Tenth Plan State Plan Exp. 50.32 0.00 50.32 21-Jun-05 - 100% 50.32 0.00 50.32 0.00 0.00 0.00 0.00 Work Closed
44 Surface strengthening & drainage on Yang-yang-Rangang road. Km 1st.-2nd   2Km Mr. S. B. Chamling Tenth Plan State Plan Exp. 39.32 0.00 39.32 16-Feb-03 11-Jan-06 99% 35.74 0.00 35.74 3.58 0.00 3.58 3.58 in progress
45 Carpetting, drainage & Protective Works onYangang- Rangang road form Bifurcation Point Km 1st and 2nd   2Km S.B.Chamling Tenth Plan State Plan Exp. 37.80 0.00 37.80 16-Feb-03 31-Mar-05 95% 0.00 0.00 0.00 37.80 0.00 37.80 37.80 -
46 Premix carpetting,drainage work and protective work on Melli Turuk Sadam Bhanjyang road Km 1st - 16th.   16Km Mr. Tej man Rai, Birbal Subba, & Rup Narayan Rai Tenth Plan State Plan Exp. 290.49 0.00 290.49 1-Jan-03 Aug- 31st 100% 248.50 0.00 248.50 41.99 0.00 41.99 41.99 Completd,necessary documents collected for final bill.
47 Construction of Bye Pass road from Agam Singh Path to Damthang road 3Km.     Shri Bhupal Chamling Tenth Plan State Plan Exp. 160.94 0.00 160.94 3-Mar-04 3-Mar-05 100% 123.88 0.00 123.88 37.06 0.00 37.06 37.06 work completed
48 Surface Improvement of  Approach Road to Rock Garden from Debrong Golai-Namchi-Damthang road Km 1st & 2nd.   2Km Dikila Bhutia Tenth Plan State Plan Exp. 70.22 0.00 70.22 18-Mar-04 18-Mar-05 100% 67.05 0.00 67.05 3.17 0.00 3.17 3.17 Work completed
49 Premix carpetting, drainage & P/works work  on Yangang Makha road Km 1st-21st [S.Share of NLCPR] [Revised]   21Km Passang Lepcha Tenth Plan State Plan Exp. 54.13 0.00 54.13 - - 100% 54.13 0.00 54.13 0.00 0.00 0.00 0.00 Work Closed
50 Premix carpetting  on Ravangla Zarrong road km 1st-11th. Ravangla 11Km Shreekishan Agarwal Tenth Plan State Plan Exp. 0.00 0.00 0.00 24-Jun-05 - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Transferred to TSP
51 Construction of link road Rangang road-Yang Yang Makha via Mazuwa Gaon, 3 kms       Rs. 9.49 (LC)]   3Km Santa Bdr. Chamling, Nar Bdr. Gurung Tenth Plan State Plan Exp. 88.30 0.00 88.30 6-Jun-05 6-Sep-06 100% 80.25 0.00 80.25 8.05 0.00 8.05 8.05 Work completed
52 Providing premix carpetting on Approach road & Yard to Palchen Choling Monastry [New Gumpa] at Ralang     Departmental Tenth Plan State Plan Exp. 14.65 0.00 14.65 18-Jun-05 18-Dec-05 100% 14.26 0.00 14.26 0.39 0.00 0.39 0.39 Work Closed
53 Restoration work on Namchi-Phong km. 3rd ch. 30 South Sikkim.     Departmental Tenth Plan State Plan Exp. 2.90 0.00 2.90 27-Jun-05 - 100% 0.00 0.00 0.00 2.90 0.00 2.90 2.90 Work completed
54 Immediate restoration work on Namchi-Rong-Sumbuk road km. 7th-13th.   6Km Departmental Tenth Plan State Plan Exp. 2.63 0.00 2.63 2005 - 100% 0.00 0.00 0.00 2.63 0.00 2.63 2.63 Work completed
55 Extension of Ravongla Biring road to Legship Tashiding road 5th kms in South Sikkim.   5Km   Tenth Plan State Plan Exp. 119.40 0.00 119.40 2005 - 100% 43.94 0.00 43.94 75.46 0.00 75.46 75.46 Work completed
56 Diversion of turning at Km 13 on Ravangla - Zarong Road in S-Sikkim Ravangla 1Km Smt. R K  Rai Tenth Plan State Plan Exp. 6.93 0.00 6.93 1-Apr-06 9-Sep-06 99% 4.03 0.00 4.03 2.90 0.00 2.90 2.90 work under progress
57 Construction of Namchi - Rong - Sumbuk Road Km 3rd to 15th.   12Km Land Compensation Eleventh Plan State Plan Exp. 16.48 0.00 16.48 2007 - 100% 16.48 0.00 16.48 0.00 0.00 0.00 0.00 Work completed
58 Carpeting & Protective Work on Rabong -Ralong Road Km 1st to 3rd   3Km Binod Gurung   State Plan Exp. 6.42 0.00 6.42 - - 100% 0.00 0.00 0.00 6.42 0.00 6.42 6.42 Work completed
59 Carpeting & Protective Work on Rabong -Ralong Road Km 4th to 6th   2Km N.T.Bhutia   State Plan Exp. 11.10 0.00 11.10 - - 100% 0.00 0.00 0.00 11.10 0.00 11.10 11.10 Work completed
60 Carpeting & Protective Work on Rabong -Ralong Road Km 7th to 10th   3Km Roshan Lall Agarwal   State Plan Exp. 8.18 0.00 8.18 - - 100% 0.00 0.00 0.00 8.18 0.00 8.18 8.18 Work completed
61 Carpeting & Protective Work on Rabong -Ralong Road Km 11th to 13th   2Km Tshering Gyatso Kaleon Tenth Plan State Plan Exp. 3.63 0.00 3.63 - - 100% 0.00 0.00 0.00 3.63 0.00 3.63 3.63 Work completed
62 New cutting of Sangmoo link road Km 4th     Mr. K. Bhutia Tenth Plan State Plan Exp. 6.97 0.00 6.97 1-Nov-97 - - 0.00 0.00 0.00 6.97 0.00 6.97 6.97 -
63 Extension of Truakable road from Ravangla Bining Road to Tashiding Km 14th. Ravangla 1Km Mr. Loden C. Bhutia Tenth Plan State Plan Exp. 22.02 0.00 22.02 June-05 12-Dec-06 94% 16.83 0.00 16.83 5.19 0.00 5.19 5.19 in progress
64 Extension of Truakable road from Ravangla Bining Road to Tashiding Km 15th. Ravangla 1Km Mr. Lha T. Bhutia Tenth Plan State Plan Exp. 20.89 0.00 20.89 June-05 13-Dec-06 94% 12.01 0.00 12.01 8.88 0.00 8.88 8.88 in progress
65 Extension of Truakable road from Ravangla Bining Road to Tashiding Km 16th. Ravangla 1Km Mr. Loden C. Bhutia   State Plan Exp. 22.63 0.00 22.63 June-05 14-Dec-06 95% 9.90 0.00 9.90 12.73 0.00 12.73 12.73 in progress
66 Extension of Truakable road from Ravangla Bining Road to Tashiding Km 17th. Ravangla 1Km Mr. Lha T. Bhutia Tenth Plan State Plan Exp. 19.87 0.00 19.87 June-05 15-Dec-06 95% 9.77 0.00 9.77 10.10 0.00 10.10 10.10 in progress
67 Extension of Truakable road from Ravangla Bining Road to Tashiding Km 18th. Ravangla 1Km Mr. Lha T. Bhutia Tenth Plan State Plan Exp. 19.31 0.00 19.31 June-05 16-Dec-06 97% 5.60 0.00 5.60 13.71 0.00 13.71 13.71 in progress
68 Construction of motorable road from Slap Village (Chettri Gaon) km 1st and 2nd Ravangla 2Km Mr. Lha T. Bhutia Tenth Plan State Plan Exp. 38.02 0.00 38.02 9-Sep-06 2-Feb-07 76% 21.40 0.00 21.40 16.62 0.00 16.62 16.62 in progress
69 Surface strengthening & drainage on Yang-yang-Rangang road. Km 1st & 2nd.  Ravangla   Mr. S. B. Chamling Tenth Plan State Plan Exp. 36.19 0.00 36.19 16-Feb-03 11-Jan-06 99% 21.03 0.00 21.03 15.16 0.00 15.16 15.16 in progress
70 Diversion of turning at Km 14 th to 18th on Ravangla - Zarong Road in S-Sikkim   4Km Smt. Ratna Kum. Rai Tenth Plan State Plan Exp. 104.72 0.00 104.72 Jun-05 Mar-08 87% 54.11 0.00 54.11 50.61 0.00 50.61 50.61 in progress
71 Construction of link road from Kholaghari to Jaubari, Km 3rd 4th to 9th. (LC = Rs. 170.52 lakh)     Bhanu Rai & Lakpa Chuki Sherpa Tenth Plan State Plan Link Road