MONTHLY PHYSICAL AND FINANCIAL  PROGRESS REPORT FOR THE MONTH ENDING DECEMBER 2008
  (Rupees in lakhs)
Sl.No Name of Schemes Name of Contractor Plan Funding Agency (Head) SANCTIONED  AMOUNT Date of Commen- cement Stipulated Date of Completion Physical Progress               in % Financial Progress Remarks
Total C.share S. share Expenditure till date
Total S.Share C.Share
A DISTRICT:  NORTH      
 
CENTRAL  SPONSORED  SCHEMES
         
 
     
1 Upgradation Ranka - Luing-Gangtok-Burthuk-Road Km 14th to 21st Mr. Shyam Rai Tenth Plan NLCPR  Expansion 641.54 420.00 221.54 11-Jan-05 19-Jul-07 68% 406.60 0.00 406.60 work in progress
2 Construction 0f 90m span steel bridge over Takcham Chu along C.R.B.A Road, Km 21st  Mrs. Meera Rai Tenth Plan NEC Expansion 476.74 476.74 0.00 9-Jan-06 8-Oct-06 86% 267.60 0.00 267.60 work in progress Expd. In Purchase of Vechile steel parts
3 Upgradation / carpeting & extension i/c providing drainage and protective works of Marchak - Tumlabong road, Km 1st to 13th in East Sikkim M/s Ladakhi Const. Pvt. Ltd. Tenth Plan NEC Expansion 1,023.00 1,023.00 0.00 9-Nov-06 18-May-08 65% 339.05 0.00 339.05 work in progress
4 Construction of steel bridge over Teesta river at Gour Mr. Samdup Lepcha Tenth Plan NEC NEC 488.57 488.57 0.00 21-Jan-06 22-Jan-07 94% 321.37 0.00 321.37 In Progress
5 Strengthening / drainage carpetting of SBS road to Tingbong high school  Mr. G.N. Agarwal Tenth Plan NEC NEC / TSP 447.74 401.37 46.37 29-Apr-05 30-Apr-06 100% 316.14 0.00 316.14 Completed
6 Construction of Steel Bridge on Approach road to Khedum Village in North Sikkim. Mr. Penzong Lachungpa Tenth Plan NEC NEC 190.68 190.68 0.00 24-Feb-06 23-Jan-07 94% 116.98 0.00 116.98 In Progress
7 Upgradation & Surface strengthening of Ranka-Sichey road Km 1st to 3rd Mr. Rajesh Agarwal Tenth Plan CRF Removal 119.05 88.26 30.79 17-Mar-05 31-May-06 100% 31.03 0.00 31.03 Final bill submitted
8 Upgradation of Phodong -Labrang Gumpa Mr. K.N. Bhutia Tenth Plan CRF CRF 158.96 158.96 0.00 3-Nov-05 2-Oct-06 100% 118.77 0.00 118.77 Completed Final bill to be paid
9 Construction of app. Road to Thomchi Gumpa. Mr. Tashi Lachungpa   BADP BADP 15.69 0.00 15.69 6-Feb-07 5-May-07 100% 15.69 0.00 15.69 Completed
10 Construction of approach road to Thomchi Gumpa.   Tenth Plan BADP BADP 5.00 5.00 0.00 - - 100% 0.00 0.00 0.00  
11 Construction of new road from Gumpa Golai to Chanzing, Lachen. Mr Nangden Lachungpa   BADP BADP 38.10 38.10 0.00 - - - 0.00 0.00 0.00 Work delay due to land compens-ation
12 Upgradation / Strengthening and Carpeting of approach road to Latoong Village. Mr Nangden Lachungpa   BADP BADP 42.79 42.79 0.00 - - 70% 0.00 0.00 0.00 work in progress
13 Extension of Bakcha -Labi road Km 3rd & 4th. State share of BADP land compansation. Mr. Ugen Nedup Bhutia   BADP BADP 0.00 0.00 0.00 - - 100% 0.00 0.00 0.00 Work Completed
14 Construvction of Link Road from Bay to Pentong in North Sikkim. Mr. Bernald Lepcha Tenth Plan RSVY  New Road 187.45 150.00 37.45 22-Sep-05 31-Dec-08 65% 128.03 0.00 128.03 In Progress
15 Construction of Heli Port at Lachung Mr. Nidup Lachungpa Ninth Plan Tourism Other Expenditure 38.89 0.00 38.89 3-Apr-00 2-Jan-01 75% 28.43 0.00 28.43 Defence clearance not yet received
16 Carpetting of app. Road to Crematorium ground at Jalipool. Mr. Praveen Agarwal Tenth Plan NABARD  Expansion 31.80 20.66 11.14 31-Jan-06 15-Jun-06 100% 26.35 9.35 17.00 Final bill  submitted
17 Construction of Link Road from Takchi Phatak to Upper Luing, Km 1st Mr. Tsweang Rinzing Bhutia Tenth Plan NABARD New Road 37.07 0.00 37.067 18-Aug-05 17-Aug-06 80% 70.72 49.82 20.90 work in progress
18 Construction of Link Road from Takchi Phatak to Upper Luing, Km 2 nd Dewjang Bhutia Tenth Plan NABARD New Road 31.82 0.00 31.819 18-Aug-05 17-Aug-06 70% Work just started
19 Construction of Link Road from Takchi Phatak to Upper Luing, Km 3rd Tempo Gyatso Bhutia Tenth Plan NABARD New Road 56.18 0.00 56.176 23-Sep-05 22-Sep-06 70% Work just started
20 Construction of Link Road from Takchi Phatak to Upper Luing, Km 4th Yangchen Dolma Bhutia Tenth Plan NABARD New Road 38.74 0.00 38.740 23-Sep-05 22-Sep-06 0% work in progress
21 Construction of Link Road from Takchi Phatak to Upper Luing, Km 5th Yangchen Dolma Bhutia   NABARD New Road 56.78 0.00 56.780 23-Sep-05 22-Sep-06 0% work in progress
22 Extension of 3rd Km road from 3rd mile turning (Tintek Dikchu road) to Rakshey via Kedangthang Km 4th to 6th Devi Dhakal   NABARD   280.83 224.66 56.170 15-May-08 15-May-09 60% 0.00 0.00 0.00 work in progress
23 Extension of link road fromGRS road to Km 12th CH 5 to Tatopani at Rumtek M. Karki   NABARD   50.24 40.19 10.050 15-May-08 15-May-09 20% 0.00 0.00 0.00 work was delay due to objection raised by DCC Rumtek
  WORKS  SANCTIONED  UNDER  STATE  PLAN                      
24 Premix carpetting, improvement of GRBA road Km 18th to 21st and Assam Pakyong Road Km 1st to 6th. Mr. Amrit Rai Tenth Plan State Plan Removal 254.76 0.00 254.76 25-Aug-04 31-Mar-06 100% 184.20 0.00 184.20 Completed
25 Upgradation of Marchak Tumlabong Road (NEC ) State Share for LC Compensatiion   NEC Removal 100.00 0.00 100.00 - - 37% 37.00 0.00 37.00 work in progress
26 Premix carpetting,on Penlong - Tintek road Km 12th - 20th  Mr. Suresh Mundra Tenth Plan State Plan Expansion 158.79 0.00 158.79 28-Nov-02 31-Mar-06 100% 99.54 0.00 99.54 Final bill to be submitted Discuss Expenditure
27 Const. of GOR Santok road Km. 1st  Mr.Pentok Lepcha Tenth Plan State Plan Expansion 29.76 0.00 29.76 - - 100% 21.61 0.00 21.61 Completed
28 Construction of link road to Aho - Manghim Km 1st Mr. B.K. Upreti Tenth Plan State Plan Link Road 16.88 0.00 16.88 2-Dec-04 15-Jan-07 94% 11.37 0.00 11.37 work in progress
29 Const. of link road to Aho - Manghim Km 2nd BR Subba Tenth Plan State Plan Link Road 18.88 0.00 18.88 2-Dec-04 15-Jan-07 45% 0.00 0.00 0.00 delayed due to land compensation
30 Const. of link road to Aho - Manghim Km 3 rd Beena Subba Tenth Plan State Plan Link Road 19.27 0.00 19.27 1-Dec-04 15-Jan-07 20% 0.00 0.00 0.00 work in progress
31 Construction of app. Road from Samdong Cha Chu to Yumi Samdong, north Sikkim. Km 1st & 2nd Mr. T. Doma Lachungpa Tenth Plan State Plan New Road 54.48 0.00 54.48 21-Jun-04 20-Dec-05 100% 54.48 0.00 54.48 Work Completed
32 Construction of Rest House at Samdong in East Sikkim. Mr. Nitup Lepcha Tenth Plan Addl.Facilities Addl.Facilities 78.70 0.00 78.70 20-May-03 19-Apr-04 100% 75.44 0.00 75.44 Completed, Final bill paid
33 Upgradation,carpetting, protective and drainage of SBS road to Lingtam PHSE Km 1st to 5th. Mr. Samdup Lepcha Eleventh Plan State Plan Strengthning Road Infrastructure 385.54 0.00 385.54 - - 50% 42.22 0.00 42.22 work in progress
34 Upgradation,carpetting, protective and drainage works of DSM road to Gour School Km 1st to 8th. Mr. Soden Gyamptso Bhutia Tenth Plan State Plan Strengthning Road Infrastructure 391.66 0.00 391.66 1-Jun-08 1-Jan-09 40% 57.78 0.00 57.78 work in progress
35 Widening protective work drainage & carpetting work on S.B.S Road Km 10th & 12th Mr. Lobzang Lepcha Tenth Plan State Plan TSP 35.97 0.00 35.97 15-Nov-03 14-Aug-04 73% 14.99 0.00 14.99 Carpetting work to be done.
36 Widening protective work drainage & carpetting work on S.B.S Road Km 13th  Mr. Sonam Dorjee Tenth Plan State Plan TSP 18.86 0.00 18.86 18-Nov-04 17-May-05 70% 0.73 0.00 0.73 WBM/carpetting work to be done
37 Widening protective work drainage & carpetting work on S.B.S Road Km 14th & 15TH Mr. Topnam Lepcha   State Plan TSP 35.11 0.00 35.11 11-Jan-03 10-Oct-03 80% 19.47 0.00 19.47 Carpetting work to be done.
38 Strengthening, protective / drainage carpetting works on approach road to Ringtham Gumpa Km1st to 3rd  Mangan. K.N. Lachenpa   State Plan TSP 276.00 0.00 276.00 14-Mar-08 18-Sep-09 50% 11.51 0.00 11.51 work in progress
39 Construction approach road to medicine pond B-6 Tempo Lepcha   State Plan TSP 105.00 0.00 105.00 6-Mar-08 7-Mar-09 60% 11.03 0.00 11.03 work in progress
40 Construction approach road to Shakothang at Sarchok village Dawa Gaytmso Lachenpa Tenth Plan State Plan TSP 64.98 0.00 64.98 7-Apr-08 8-Apr-09 32% 3.27 0.00 3.27 work in progress
41 Protective works, widening, drainage and carpeting on Bictchu road Km 1st to 3rd to Gai Gaon at Lachung Needup Lacungpa   State Plan TSP 298.00 0.00 298.00 21-Aug-08 2-Aug-10 35% 0.00 0.00 0.00 work in progress
42 Premix Carpetting imp & widening of D.S.M road km 12th to 16th  Mr. Singhik Lepcha Tenth Plan State Plan TSP 124.05 0.00 124.05 15-Jan-03 14-Jul-04 80% 71.89 0.00 71.89 In Progress
43 Premix Carpetting imp & widening of D.S.M road km 17th  Mr. Chewang Norbu Tenth Plan State Plan TSP 19.41 0.00 19.41 11-Jan-03 10-Oct-03 100% 9.93 0.00 9.93 Final Payment
44 Premix Carpetting imp & widening of D.S.M road km 18th  Mr. Dawa Tshering  Tenth Plan State Plan TSP 19.56 0.00 19.56 11-Jan-03 10-Oct-03 85% 15.10 0.00 15.10 work in progress
45 Premix Carpetting imp & widening of D.S.M road km 19th  Mr. Ongden lepcha Tenth Plan State Plan TSP 20.44 0.00 20.44 11-Jan-03 10-Oct-03 73% 10.59 0.00 10.59 work in progress
46 Premix Carpetting imp & widening of D.S.M road km 20th  Mr. Mingma Tshering Tenth Plan State Plan TSP 20.04 0.00 20.04 11-Jan-03 10-Oct-03 74% 14.12 0.00 14.12 In Progress
47 Premix Carpetting imp & widening of D.S.M road km 21st   Mr. Lobzang Lepcha   State Plan TSP 23.38 0.00 23.38 11-Jan-03 10-Oct-03 75% 18.07 0.00 18.07 In Progress
B DISTRICT :EAST  
  CENTRAL  SPONSORED  SCHEMES                        
1 Const. of Goshkhan Dara Bridge over River Teesta at Singtam, East Sikkim M.P Agarwal Tenth Plan NLCPR  - 1,337.11 1,337.11 0.00 10-Jan-07 11-Jun-08 40% 420.00 0.00 420.00 work in progress
2 Const. of diversion road Ranipool-Pakyong road km 1st-3rd. B.K. Agarwal Tenth Plan NLCPR  Expansion 339.85 236.87 102.98 21-Feb-05 21-Nov-05 70% 225.98 64.60 161.38 work in progress
3 Strengthening,drainage and Carpeting and construction of 30m span steel bridge along Assam-Pakyong road km 7th - 15th. S.K. Agarwal Tenth Plan NEC  - 750.76 750.76 0.00 6-Nov-06 5-May-08 75% 309.05 0.00 309.05 work under process
4 Construction of major retaining structures on approach road to Raj Bhawan,VIP Complex and TNA Public School Complex   Tenth Plan NEC  - 106.87 106.87 0.00 30-May-05 29-May-06 100% 74.24 0.00 74.24 completed
5 Strengthening/drainage and P/Wprks for the road from Lal Turning to Bashilakha Road Km 1st to 3rd G.M Gurung   NABARD Expansion 184.65 151.46 33.19 30/09/07 31/03/08 100% 143.83 0.00 143.83 work in verge completetion
6 Construction of Link Road from Sakyong to Beyong km 1st to 2nd (State Share of NABARD) KRSharma & TB Pradhan Eleventh Plan NABARD Link Road 84.70 0.00 84.70 12-Mar-08 11-Mar-09 75% 0.00 0.00 0.00 work under progress
7 Const. of 12 m span R.C.C. Bridge on Sangkhola Zingla Martam Road at Km 11th ch-3rd. Anita Gurung Eleventh Plan CRF  - 38.63 38.63 0.00 1-Apr-07 31-Mar-08 45% 0.00 0.00 0.00 work under progress
8 Const. of 12 m span R.C.c. Bridge on Sangkhola Zingla Martam Road at Km 12th ch-4th.. T.B. Pradhan Eleventh Plan CRF  - 45.12 45.12 0.00 1-Apr-07 31-Mar-08 60% 22.00 0.00 22.00 work under progress
9 Surface improvement and widening of Sang Sirwani Road Km 1st & App Road from Mech Sub Div Office at Dochum Kishor Pradhan Eleventh Plan CRF  - 50.20 50.20 0.00 10-Oct-07 9-Sep-08 85% 25.71 0.00 25.71 work under progress
10 Surface improvement and widening of Sang Sirwani Road Km 2nd & App Road to Mech Workshop Dochum K.R. Sharma Eleventh Plan CRF  - 38.49 38.49 0.00 10-Oct-07 9-Sep-08 65% 12.61 0.00 12.61 work under progress
11 Upgradation of Link Road from NH-31A to Dokey Chisopani Km 1st  Kishor Pradhan Eleventh Plan CRF  - 69.63 69.63 0.00 29-Feb-08 28-Feb-09 35% 0.00 0.00 0.00 Work to Commence
12 Upgradation of Link Road from NH-31A to Dokey Chisopani Km 2nd  Gopal Sharma Eleventh Plan CRF  - 35.20 35.20 0.00 29-Feb-08 28-Feb-09 30% 0.00 0.00 0.00 work under progress
13 Upgradation of Link Road from NH-31A to Dokey Chisopani Km 3rd Suren Gurung Ninth Plan CRF  - 43.90 43.90 0.00 29-Feb-08 28-Feb-09 45% 0.00 0.00 0.00 work under progress
14 Const. of link road from Arubotey to Subaneydara km 1st-3rd. Om Bhd. Gurung Ninth Plan BADP  - 29.97 29.97 0.00 30-Nov-00 16-Mar-01 68% 22.98 0.00 22.98 work abondoned
15 Const. of link road from sisney to North Regu km 1st -4th. T.S. Lama Tenth Plan BADP  - 30.31 30.31 0.00 21-Nov-00 5-Mar-01 95% 24.54 0.00 24.54 work abondoned
16 Premix carpetting and widening work on Sang dipudara road Km 1st to 14th. Daluram Sarda Tenth Plan EI Removal 277.44 6.95 277.44 18/11/2002 17/08/2004 90% 233.08 233.08 0.00 Sanctioned from EI Rs 6.95 Crore
17 Upgradationand premix carpeting along Duga Pachaykhani road KM 1st-14th. B.K.Agarwal Tenth Plan EI Removal 841.38 433.77 407.61 21-Feb-05 5-Mar-08 90% 393.32 24.00 369.32 work in progress
18 Construction of Road from Rathong (NH-31A) to Kimchithang Km 1st to 15th (EI) KK Agarwal Tenth Plan EI - 1,466.89 701.89 765.00 2007 - 30% 0.00 0.00 0.00 New Project
19 Improvement of  Sang Dipudara Road (EI) - Tenth Plan EI - 347.74 347.74 0.00 2007 - 90% 0.00 0.00 0.00 New Project
20 Widening, upgradation of pavement & drainage system along  Rangpo Duga Pendam road km 1st - 15th  M/s Apex Project & Investment                 P. Ltd. Eleventh Plan ISC  - 950.00 950.00 0.00 15-Jun-08 16-Dec-08 65% 480.00 0.00 480.00 work in progress
21 Improvement of Rhenock - Simanakhola Road Km 1st to 3rd. (ISC) Mr. Kuber Raj Rai Tenth Plan ISC  - 250.00 250.00 0.00 26-Mar-08 - 25% 236.99 0.00 236.99 work in progress
22 Construction of 60 m span steel bridge at Bongliung over Rongli Chu in East Sikkim Gazendra Rai   Zilla Panchyat    74.07 0.00 74.07 29-Mar-08 29-Sep-09 15% 0.00 0.00 0.00 work in progress
23 Construction of link road from pakyong  Nop gaon to barpipal Dara, Km 1st-3rd in East-Sikkim Hemandri Adhikari   CSS   102.29 0.00 102.29 5-Aug-08 5-Mar-10 10% 0.00 0.00 0.00 work in progress
  STATE PLAN                            
24 Carpeting and surface strengthening, improvement, including drainage works of roads in and around Gangtok. PM Chamling Tenth Plan State Plan Removal    361.89 0.00 361.89 6-Jun-04 5-Sep-05 100% 229.45 229.45 0.00 work completed final bill under preparation
25 Surface strengthening upgradation and carpeting of Pakyong-Karthok Naya Busty road km 5th -7th. Adup Bhutia Tenth Plan State Plan Removal 183.89 0.00 183.89 21/06/05 31-Aug-08 45% 56.58 56.58 0.00 work in progress, Date Extended
26 P/L edging ,soling, metalling, premix carpeting and cross drain of link road from sichey to Indira Bye Pass via Shivalaya Mandir   Mrs Rupa Dhakal Tenth Plan State Plan Removal 8.16 0.00 8.16 1/0/2002 2-Jul-05 80% 5.81 5.81 0.00 work in abeyance due to non availibility of bitumen
27 Upgradation/carpeting P/works and drainage along Pakyong-Karthok road km 1st-4th. P. N. Kazi Tenth Plan State Plan Expansion 129.49 0.00 129.49 28-Mar-05 27-Jul-06 55% 95.08 95.08 0.00 work in progress
28 Upgradation and premix carpeting of Kotlaytar Rai Gaon Road,km 1st & 2nd  Miss Devi Dakhal Tenth Plan State Plan Expansion 57.71 0.00 57.71 28-Mar-05 27-Sep-06 75% 31.05 31.05 0.00 work in progress
29 Premix Carpetting and Surface improvement Chewribotay Pendam  Km 1st - 6th Basudev Pradhan Tenth Plan State Plan Expansion 117.78 0.00 117.78 29/05/2003 31/01/04 95% 83.84 83.84 0.00 work in progress
30 Construction of Bye Pass Road below Mintokgang DB Chettri Tenth Plan State Plan Expansion 80.26 0.00 80.26 26-Feb-04 5-Aug-04 100% 71.46 71.46 0.00 Final bill under process
31 Ext. of Pakyong-Mamring Tareythang road km 1st Khush N.Adhikari Tenth Plan State Plan Expansion 28.91 0.00 28.91 1-Jul-05 31-Dec-07 90% 28.72 28.72 0.00 Revised
32 Ext. of Pakyong-Mamring Tareythang road km 2nd Johar Man Rai Tenth Plan State Plan Expansion 16.61 0.00 16.61 1-Jul-05 31-Dec-07 90% 16.37 16.37 0.00 Revised
33 Ext. of Pakyong-Mamring Tareythang road km 3rd G.K. Pradhan Tenth Plan State Plan Expansion 22.70 0.00 22.70 1-Jul-05 31-Dec-07 90% 12.94 12.94 0.00 Revised Estimate submitted
34 Ext. of Pakyong-Mamring Tareythang road km 4th. Udai Mishara Tenth Plan State Plan Expansion 17.92 0.00 17.92 1-Jul-05 31-Dec-07 90% 12.02 12.02 0.00 Revised Estimate submitted
35 Ext. of Pakyong-Mamring Tareythang road km 5th. K.S.Rai Tenth Plan State Plan Expansion 27.01 0.00 27.01 1-Jul-05 31-Dec-07 90% 16.05 16.05 0.00 Revised Estimate submitted
36 Ext. of Pakyong-Mamring Tareythang road km 6th. Ishore Dakahal Tenth Plan State Plan Expansion 21.15 0.00 21.15 1-Jul-05 31-Dec-07 70% 18.71 18.71 0.00 Revised Estimate submitted
37 Ext. of Pakyong-Mamring Tareythang road km 7th. K.S.Rai Tenth Plan State Plan Expansion 22.10 0.00 22.10 1-Jul-05 31-Dec-07 55% 8.68 8.68 0.00 Revised Estimate submitted
38 Ext. of Pakyong-Mamring Tareythang road km.8th  M. K. Pradhan Tenth Plan State Plan Expansion 21.66 0.00 21.66 1-Jul-05 31-Dec-07 55% 0.00 0.00 0.00 Revised Estimate submitted
39 Ext. of Pakyong-Mamring Tareythang road km.9th  Kamal Adhikari Tenth Plan State Plan Expansion 19.24 0.00 19.24 1-Jul-05 31-Dec-07 100% 8.00 8.00 0.00 Completed, Final bill under process
40 Ext. of Pakyong-Mamring Tareythang road km.10th  Milan Dahal Tenth Plan State Plan Expansion 10.70 0.00 10.70 1-Jul-05 31-Dec-07 100% 0.00 0.00 0.00 Completed
41 Const. of road from Zingla Martam KM 16th-18th (2.36km) i/c LC UP Kazi Tenth Plan State Plan TSP Expansion 92.12 0.00 92.12 3-Oct-05 3-Oct-06 100% 83.16 83.16 0.00 work in progress
42 Construction of 20 chain road Bio Control Laboratory to Phewk Busty road  Mr. G.K.Rai Tenth Plan State Plan Link Road 25.03 0.00 25.03 28-Sep-05 27-Mar-05 85% 9.00 9.00 0.00 Revised estimate under process
43 Const. of link road from Basilakhs to Middle camp via Rodongtar km 6th  Justin Rai Tenth Plan State Plan New Road 17.93 0.00 17.93 5-Oct-05 9-Feb-05 75% 14.93 14.93 0.00 work in progress
44 Const. of link road from Basilakhs to Middle camp via Rodongtar km 8th  Paul Rai Tenth Plan State Plan New Road 21.36 0.00 21.36 5-Oct-05 9-Feb-05 100% 10.01 10.01 0.00 work in progress
45 Const. of 10m span RCC Culvert on Basilakha to middle camp km 8th. Patrush Subba Tenth Plan State Plan New Road 12.32 0.00 12.32 5-Oct-05 9-Feb-05 75% 0.00 0.00 0.00 work in progress
46 Const. of link road from Assam-Pakyong road to Kadamtam village km.3rd & 4th. D.P. Mangar   State Plan New Road 41.74 0.00 41.74 1-Jul-05 30-Jun-06 75% 24.66 24.66 0.00 Revised Est Submitted
47 Construction of road from Chandmari village to Jawaharlall Nehru road  K Wangchuk   State Plan New Road 30.63 0.00 30.63 31-May-05 30-Nov-05 100% 23.76 23.76 0.00 work completed final bill under process
48 Const. of Song-zingla Martam road km 9th. P.T. Lepcha Eleventh Plan State Plan New Road 12.45 0.00 12.45 5-Mar-03 20-Dec-03 80% 5.63 5.63 0.00  In progress
49 Const.of Song-Zingla Martam road km 14th  Tenging Bhutia Eleventh Plan State Plan New Road 25.54 0.00 25.54 6-Mar-03 6-Dec-03 100% 19.63 19.63 0.00  In progress
50 Const. of Song-Zingla Martam road km 15th. S.K.Chettri   State Plan New Road 26.75 0.00 26.75 6-Mar-03 6-Dec-03 95% 19.95 19.95 0.00  In progress
C DISTRICT :  SOUTH  
A. CENTRAL  SPONSORED  SCHEMES                      
1 Surface strengthening drainage & P. Works on Namchi- Damthang Ravangla road- Km 1st -26th. - Tenth Plan NLCPR Removal  1,668.61 1,207.00 461.61 1-Jan-05 1-Feb-07 94% 1,259.76 224.94 1,034.82 in progress
2 Replacement of existing Sikkip Suspension Bridge over Rangit River Mr. Chandra Khaling Tenth Plan NLCPR Replacement 78.13 53.66 24.47 15-Dec-03 30-Mar-07 100% 65.43 11.78 53.65 work completed
3 Upgradation, Surface strengthening, drainage & P/W on Ravangla Makha Road Km 10th,11th,12th and 13th. Smt. Sonam Doma Bhutia Tenth Plan NLCPR - 119.05 119.05 0.00 15-Jan-03 30-Nov-06 100% 116.17 0.00 116.17 completed
4 Upgradation, Surface strengthening, drainage & P/W on Ravangla Makha Road Km 18th to 21st Mr. S. B. Chamling Tenth Plan NLCPR - 109.18 109.18 0.00 15-Jan-03 30-Nov-06 100% 102.96 0.00 102.96 completed
5 Truakable road from 10th mile to Tingmoo villageKm 1st, 2nd and 7th Mr. Nim S. Sherpa Tenth Plan NEC   468.29 468.29 0.00 4-Apr-06 4-Apr-07 60% 89.89 0.00 89.89 in progress
6 Truakable road from 10th mile to Tingmoo villageKm 3rd and 6th Mr. Sonam O. Bhutia Tenth Plan NEC   4-Apr-06 4-Apr-07 53% in progress
7 Truakable road from 10th mile to Tingmoo villageKm 4th and 5th Mr. Lhendup D. Kaleon Tenth Plan NEC   5-Apr-06 4-Apr-07 43% in progress
8 Truakable road from 10th mile to Tingmoo villageKm 8th. Mr. Bala R. Limboo Tenth Plan NEC - 9-Apr-06 4-Apr-07 60% in progress
9 Strengthening / drainage carpetting of Ralang-Phamthang road Km 14th to 26th & Replacement of Two existing Bridges over Bermali & Chil Khola in South Sikkim. Mr. N.T. Bhutia Tenth Plan NEC Removal 1,200.83 1200.83 0.00 11-Nov-06 5-May-08 41% 213.00 0.00 213.00 in progress
10 Construction of 40m Span Bridge over Lower Ben Khola at Saino Tar along Pabong - Simchuthang - Yangang road, South Sikkim. Mr. Anjani Kr, Agarwal Tenth Plan NEC - 137.34 137.34 0.00 2-Sep-05 - 100% 98.11 0.00 98.11 completed
11 Construction of 60m span steel bridge over Kaw Khola on KS road. Mr. S.S. Dhakhal Tenth Plan NEC - 164.35 0.00 164.35 13-Nov-06 12-Nov-08 76% 75.00 0.00 75.00 in progress
12 Imp drainage, carpetting works Km 1st -14th and replacement of Rangla Khola bridge on Kimotey Sokpay roads. Mr. Sunil Kr. Agarwal Tenth Plan NEC Removal 1,180.89 0.00 1180.89 13-Nov-06 12-Nov-08 60% 322.22 0.00 322.22 work under progress
13 Replacement of 110m Span Suspension Bridge over Rabi Khola in Melli Phong road Km 9th in S/Sikkim.  Mr. Om Agarwal Tenth Plan NEC  - 497.30 497.30 0.00 39125.00 12-Feb-08 35% 30.03 0.00 30.03 in progress
14 Construction of link road Turung School to Suminkhor Primary School. Mr. Subaash Kharel Tenth Plan NEC New Road 381.24 358.45 22.79 39428.00 6-Jun-09 69% 50.00 0.00 50.00 in progress
15 Construction of 30m Span Steel Bridges Over Rinzi Khola at Kolagari along Namchi-Vok Road Bhupal Chamling Tenth Plan NEC Replacement 185.84 157.50 28.34 12-Dec-07 6-Jun-09 100% 206.54 0.00 206.54 Completed, Final bill to be paid
16 Construction of Steel Bridge over Upper Ben Khola on G.L.V.C. road. - Tenth Plan NEC - 90.83 90.83 0.00 14-Feb-06 - - 81.77 0.00 81.77 -
17 Construction of Makha Suspension Bridge over Tista Khola at Tanak on Makha -Lingi -Yangang- Ravangla Road in South Sikkim.(NEC) R.N. Chamling Tenth Plan NEC - 495.25 495.25 0.00 25-Aug-06 - 10% 30.23 0.00 30.23 -
18 Surface Improvement, Drainage & Protective works on Namchi-Rong Road, 13 km  Mr. MP Agarwal Tenth Plan NEC - 498.60 498.60 83.89 20-Nov-03 -   505.03 10.91 494.12 -
19 Improvement of Ralang - Phamtam Road  - Eleventh Plan NEC - 1,183.00 1183.00 0.00 25-Aug-06 -   222.01 0.00 222.01 -
20 Upgradation & carpetting of Bhaisalgoan to Salghari road Km 1st to 2nd in South Sikkim. Mr. Hanuman Das Agarwal Tenth Plan NABARD Expansion 82.32 63.41 18.91 12-Feb-07 11-Jan-08 100% 45.00 0.00 45.00 completed, final bill submitted
21 Construction of trukable road from Tiffin Dara to Lower Tinghrithang  School Km 1st to 7th - Tenth Plan NABARD New Road 211.30 183.040 28.26 6-Jun-06 12-Dec-07 55% 28.53 0.00 28.53 in progress
22 Surfce strengthening, carpetting, drainage and Protective Works along A/R to Buddha Statue (Sakymuni) Pawan Kr. AgarwaL   NABARD   457.00 457.000 0.00     42% 0.00 0.00 0.00 in progress
23 Widening, Improvement, protective work, drainage and carpetting of Melli, Phong road, Km. 1st to 24th. Pawan Kr. AgarwaL Tenth Plan ISC Removal 1,376.01 1298.61 77.40 - - 100% 33.11 33.11 0.00 Payment made to old contractor
24 Widening, surface improvement, p/w & drainage system along Phongla-Bermiock-Sirwani road Km  1st- 28th. Sunil Kr. Agarwal Tenth Plan ISC Removal 1,611.78 999.08 612.70 21-Feb-05 21-Mar-07 90% 787.00 21.00 766.00 in progress
25 Construction of Gurassey Road from Bio-Diversity Park (Temi) Passang Lepcha Tenth Plan EI New Road 2,267.14 1010.92 1256.22 26-Mar-08 - - 0.00 0.00 0.00 -
26 Construction of 20 m. Span Steel Bridge over Mayalu Jhora at Km 3rd on Melli -Nayabazar road. Mr. P. C. Mundra Tenth Plan CRF Replacement 62.24 58.96 3.28 12-Mar-04 30-Jun-06 100% 50.61 0.00 50.61 Final bill submitted
27 Construction of 25 m. Span Steel Bridge over Rolu Khola at Km 9th on Melli -Nayabazar road.  Mr. G.M. Gurung Eleventh Plan CRF Replacement 55.88 52.60 3.28 22-Jul-04 31-May-06 100% 48.63 0.00 48.63 Revision under process
28 Upgradation of existing road from Vok to Namchi. M.P.Agarwal Tenth Plan CRF Removal 467.40 365.83 101.57 8-Aug-07 - 100% 419.91 74.49 345.42 -
29 Const. of motorable link road from upper Vok to Ung Raam (Water falls) via Namplang and rabong village in Omchu  Mr. B. Tsh. Bhutia Tenth Plan RSVY  New Road 240.11 180.00 60.11 22-Aug-05 21-Aug-07 85% 234.40 54.40 180.00 in progress
30 Extension of truckable roasd from Borong-Phamtam road to Upper Borong via Gurug Gumpa Km 1st. Shri K. B. Gurung Tenth Plan RSVY - 20.72 20.72 0.00 2-Feb-06 12-Nov-06 100% 0.00 0.00 0.00 work completed
31 Extension of truckable roasd from Borong-Phamtam road to Upper Borong via Gurug Gumpa Km 2nd. Shr. D. M. Gurung Tenth Plan RSVY - 23.79 23.79 0.00 2-Feb-06 13-Nov-06 100% 0.00 0.00 0.00 work completed
32 Extension of truckable road from Borong-Phamtam road to Lower Borong Km 3rd to 4th. Shri Y.C. Bhutia   RSVY - 49.68 49.68 0.00 2-Feb-06 11-Nov-06 100% 0.00 0.00 0.00 work completed
33 Construction of link road to Gagyong village km 3 -   RSVY - 87.00 87.00 0.00 - - 100% 77.71 0.00 77.71 work closed
34 Extension of Bhaisalgoan- Salghari road to Farashey km 1st to 3rd. - Tenth Plan RSVY - 113.55 94.64 18.91 - - 100% 113.55 18.91 94.64 work closed
34 Surface strengthening carpetting, drainage and protective work along Tarku-Damthang road Km13th-19th Shri A. Pradhan   ACA - 228.00 228.00 0.00 2-Feb-08 3-Mar-08 100% 246.91 18.91 228.00 work completed
  STATE PLAN                            
35 Construction of Helipad at Pokhari dara in Upper Yangyang M/s Rinchen Ongmu Bhutia   State Plan - 90.64 0.00 90.640 1-Jul-08 1-Jan-10 80% 43.00 43.00 0.00 in progress
35 Construction of 18ch link road from Helipad to Central University at Yanyang. Mrs. Sumitra Gurung   State Plan - 42.67 0.00 42.670 1-Sep-08 1-Dec-08 80% 0.00 0.00 0.00 in progress
35 Primix Carpeting Imp.of & Strengthening of Sirwani Pabong Tarku (SPT) km 11st to 18th  Prem Kr.Agarwal   State Plan Removal 101.30 0.00 101.300 13-Nov-02 12-Jun-04 100% 0.00 0.00 0.00 old work to be verified
36 Providing Box Drain and Protective work along Pabong Simchuthang Yangang Road Km 15th Ch 1st to 20th Sonam Gyamtso Tenth Plan State Plan Removal 5.25 0.00 5.250     100% 5.04 5.04 0.00 Work Closed
37 Permanent Restoration Work along Kholaghari Jawbari Road Km 2nd & 3rd Bhanu Rai & Others Tenth Plan State Plan Removal 30.98 0.00 30.980 28-Jun-05 - 100% 30.98 30.98 0.00 Work Closed
38 Strengthening, Carpetting and Stabilization of approach Road to Melli - Bazar.(State Share of NABARD) Departmental Tenth Plan State Plan Removal 8.51 0.00 8.51 28-Jun-05 - 100% 0.00 0.00 0.00  
39 Construction of 50 m Span Steel Bridge on Rongpo Khola along Ravangla Yangyang Road Km 8th Departmental Tenth Plan State Plan Replacement 56.61 0.00 56.61 25-Jun-05 - 100% 56.61 56.61 0.00  
40 Immediate. repairs & restoration of 75 mtrs span suspension bridge over Rangla Khola at Kimbuboty Sokpy road, at Km 7th. Mrs Laxumati Rai Tenth Plan State Plan Replacement 4.98 0.00 4.98 23-Apr-05 23-Jan-06 100% 4.98 4.98 0.00 Work Closed
41 Carpetting of Namchi Rong-Sumbuk road Km 1st to 3rd (Soling metalling & Carpetting). [9th plan] P.K.Agarwal, Roshan Agarwal, Anjani Kr Ararwal Ninth Plan State Plan Expansion 64.18 0.00 64.18 22-Jun-05 - 100% 64.18 64.18 0.00 Work Closed
42 Construction of  road from Gurpisey to Phalidara. Km 1st & 2nd. Chung Chung Bhutia Tenth Plan State Plan Expansion 50.32 0.00 50.32 21-Jun-05 - 100% 50.32 50.32 0.00 Work Closed
43 Surface strengthening & drainage on Yang-yang-Rangang road. Km 1st.-2nd Mr. S. B. Chamling Tenth Plan State Plan Expansion 39.32 0.00 39.32 16-Feb-03 11-Jan-06 99% 35.74 35.74 0.00 in progress
44 Carpetting, drainage & Protective Works onYangang- Rangang road form Bifurcation Point Km 1st and 2nd S.B.Chamling Tenth Plan State Plan Expansion 37.80 0.00 37.80 16-Feb-03 31-Mar-05 95% 0.00 0.00 0.00  
45 Premix carpetting,drainage work and protective work on Melli Turuk Sadam Bhanjyang road Km 1st - 16th. Mr. Tej man Rai, Birbal Subba, & Rup Narayan Rai Tenth Plan State Plan Expansion 290.49 0.00 290.49 1-Jan-03 Aug- 31st 100% 261.25 261.25 0.00 Completd,necessary documents collected for final bill.
46 Construction of Bye Pass road from Agam Singh Path to Damthang road 3Km. Shri Bhupal Chamling Tenth Plan State Plan Expansion 160.94 0.00 160.94 3-Mar-04 3-Mar-05 100% 123.88 123.88 0.00 work completed
47 Surface Improvement of  Approach Road to Rock Garden from Debrong Golai-Namchi-Damthang road Km 1st & 2nd. Dikila Bhutia Tenth Plan State Plan Expansion 70.22 0.00 70.22 18-Mar-04 18-Mar-05 100% 67.05 67.05 0.00  
48 Premix carpetting, drainage & P/works work  on Yangang Makha road Km 1st-21st [S.Share of NLCPR] [Revised] Passang Lepcha Tenth Plan State Plan Expansion 54.13 0.00 54.13 - - 100% 54.13 54.13 0.00 Work Closed
49 Premix carpetting  on Ravangla Zarrong road km 1st-11th. Shreekishan Agarwal Tenth Plan State Plan Expansion 0.00 0.00   24-Jun-05 - - 0.00 0.00 0.00 Transferred to TSP
50 Construction of link road Rangang road-Yang Yang Makha via Mazuwa Gaon, 3 kms       Rs. 9.49 (LC)] Santa Bdr. Chamling, Nar Bdr. Gurung Tenth Plan State Plan Expansion 88.30 0.00 88.30 6-Jun-05 6-Sep-06 100% 80.25 80.25 0.00  
51 Providing premix carpetting on Approach road & Yard to Palchen Choling Monastry [New Gumpa] at Ralang Departmental Tenth Plan State Plan Expansion 14.65 0.00 14.65 18-Jun-05 18-Dec-05 100% 14.26 14.26 0.00 Work Closed
52 Restoration work on Namchi-Phong km. 3rd ch. 30 South Sikkim. Departmental Tenth Plan State Plan Expansion 2.90 0.00 2.90 27-Jun-05 - 100% 0.00 0.00 0.00  
53 Immediate restoration work on Namchi-Rong-Sumbuk road km. 7th-13th. Departmental Tenth Plan State Plan Expansion 2.63 0.00 2.63 2005 - 100% 0.00 0.00 0.00  
54 Extension of Ravongla Biring road to Legship Tashiding road 5th kms in South Sikkim.   Tenth Plan State Plan Expansion 119.40 0.00 119.40 2005 - 100% 43.94 43.94 0.00  
55 Diversion of turning at Km 13 on Ravangla - Zarong Road in S-Sikkim Smt. R K  Rai Tenth Plan State Plan Expansion 6.93 0.00 6.93 1-Apr-06 9-Sep-06 99% 4.00 4.00 0.00 work completed
56 Construction of Namchi - Rong - Sumbuk Road Km 3rd to 15th. Land Compensation Eleventh Plan State Plan Expansion 16.48 0.00 16.48 2007 - 100% 16.48 16.48 0.00  
57 Carpeting & Protective Work on Rabong -Ralong Road Km 1st to 3rd Binod Gurung   State Plan Expansion 6.42 0.00 6.42 - - 100% 0.00 0.00 0.00  
58 Carpeting & Protective Work on Rabong -Ralong Road Km 4th to 6th N.T.Bhutia   State Plan Expansion 11.10 0.00 11.10 - - 100% 0.00 0.00 0.00  
59 Carpeting & Protective Work on Rabong -Ralong Road Km 7th to 10th Roshan Lall Agarwal   State Plan Expansion 8.18 0.00 8.18 - - 100% 0.00 0.00 0.00  
60 Carpeting & Protective Work on Rabong -Ralong Road Km 11th to 13th Tshering Gyatso Kaleon Tenth Plan State Plan Expansion 3.63 0.00 3.63 - - 100% 0.00 0.00 0.00  
61 Construction of link road from Kholaghari to Jaubari, Km 3rd 4th to 9th. (LC = Rs. 170.52 lakh) Bhanu Rai & Lakpa Chuki Sherpa Tenth Plan State Plan Link Road 276.13 0.00 276.13 18-Mar-03 18-Dec-04 100% 172.04 172.04 0.00  
62 Construction of link road from Namchi-Kopchey road to Singithang Km 1st & 2nd. (LC = 20.76 lakh) Chandra Bir Rai & D.P.Rai Tenth Plan State Plan Link Road 64.36 0.00 64.36 15-Mar-04 15/12/2004 100% 41.78 41.78 0.00  
63 Construction of Truckable road from Rong Sadhu Gaon 2km. [Lungkhiya] (LC = 17.45 lakh) Suk Deo Rai Tenth Plan State Plan Link Road 53.59 0.00 53.59 15-Mar-04 15/12/2004 100% 52.29 52.29 0.00 Work Closed
64 Construction of truckable road from Rong to Khani Gaon 2Km.  -   State Plan Link Road 43.13 0.00 43.13 6-Jun-04 6-Jun-06 100% 20.18 20.18 0.00 in progress
65 Compensation for Construction of Namchi-Nayabazar road to Harrabotey Km 1st to 2nd Compensation   State Plan Link Road 10.07 0.00 10.07 - -   3.39 3.39 0.00  
66 Construction of Kitchen for PWD Guest House at Temi, South Sikkim. Mr. Bindra Kumar Rai Tenth Plan State Plan Addl. Facilities 11.01 0.00 11.01 2-Feb-07 8-Aug-07 95% 0.00 0.00 0.00 in progress
67 Construction of Link road from Ben-Thalbari to Mangley km 1st-14th ( LC = Rs. 73.56 lakh) Chumden Kaleon Tenth Plan State Plan New Road 313.80 0.00 313.80 8-Dec-03 27-Dec-04 100% 259.82 259.82 0.00 completed, final bill submitted
68 Construction of truckable road from Ben to Namprik Km 1st. Chumden Kaleon Tenth Plan State Plan New Road 20.85 0.00 20.85 2002 - 100% 20.85 20.85 0.00 completed, final bill submitted
69 Construction of approach road to Khamdong Village. Bampoo Namgyal Tenth Plan State Plan New Road 9.64 0.00 9.64 2002 - 100% 9.64 9.64 0.00  
70 Construction of truckable road from Lingi Paiyong Govt. Jr. high School Km 2nd (I/c 17.71 lac Comp.+2.62 Forest Comp) S.S.Dhakal Tenth Plan State Plan New Road 78.11 0.00 78.11 2002 - 79% 44.92 44.92 0.00  
71 Const. of motorable link road from upper Vok to Ung Raam (Water falls) via Namplang and rabong village in Omchu  Mr. B. Tsh. Bhutia Tenth Plan RSVY  New Road 318.31 180.00 138.31 22-Aug-05 21-Aug-07 85% 234.40 54.40 180.00 in progress
72 Construction of truckable  roads from Kholaghari to Jawbari Km 10th & 11th (14th Chain)  Departmental Tenth Plan State Plan New Road 44.09 0.00 44.09 2005 - 90% 25.54 25.54 0.00  
73 Construction of Truckable Road from Assangthang to Salghari Compensation Eleventh Plan State Plan New Road 54.87 0.00 54.87 2007 -   40.00 40.00 0.00  
74 New cutting of Sangmoo link road Km 4th Mr. K. Bhutia Tenth Plan State Plan Expansion 6.97 0.00 6.97 1-Nov-97   - 0.00 0.00 0.00  
75 Extension of Truakable road from Ravangla Bining Road to Tashiding Km 14th. Mr. Loden C. Bhutia Tenth Plan State Plan Expansion 22.02 0.00 22.02 6-Jun-05 12-Dec-06 94% 16.83 16.83 0.00 in progress
76 Extension of Truakable road from Ravangla Bining Road to Tashiding Km 15th. Mr. Lha T. Bhutia Tenth Plan State Plan Expansion 20.89 0.00 20.89 6-Jun-05 13-Dec-06 94% 12.01 12.01 0.00 in progress
77 Extension of Truakable road from Ravangla Bining Road to Tashiding Km 16th. Mr. Loden C. Bhutia   State Plan Expansion 22.63 0.00 22.63 6-Jun-05 14-Dec-06 95% 9.90 9.90 0.00 in progress
78 Extension of Truakable road from Ravangla Bining Road to Tashiding Km 17th. Mr. Lha T. Bhutia Tenth Plan State Plan Expansion 19.87 0.00 19.87 6-Jun-05 15-Dec-06 95% 9.77 9.77 0.00 in progress
79 Extension of Truakable road from Ravangla Bining Road to Tashiding Km 18th. Mr. Lha T. Bhutia Tenth Plan State Plan Expansion 19.31 0.00 19.31 6-Jun-05 16-Dec-06 97% 5.60 5.60 0.00 in progress
80 Construction of motorable road from Slap Village (Chettri Gaon) km 1st and 2nd Mr. Lha T. Bhutia Tenth Plan State Plan Expansion 38.02 0.00 38.02 9-Sep-06 2-Feb-07 76% 21.40 21.40 0.00 in progress
81 Surface strengthening & drainage on Yang-yang-Rangang road. Km 2nd. Ch-12 Mr. S. B. Chamling Tenth Plan State Plan Expansion 36.19 0.00 36.19 16-Feb-03 11-Jan-06 99% 12.00 12.00 0.00 in progress
82 Construction of Guest house at Yangang in South Sikkim. Mr. Pawan Kr. Agarwal Tenth Plan State Plan Addl. Facilities
47.31
0.00 47.31 10-Oct-03 30-Jun-05 100%
57.17
0.00 57.17 completed
83 Construction of Link Road from Rangang to Yangang-Makha via Majuwa : Km 1st and 2nd Mr. S. B. Chamling Tenth Plan State Plan Addl. Facilities 62.36 0.00 62.36 1-Jan-05 10-Oct-05 94% 53.95 0.00 53.95 in progress
84 Construction of Link Road from Rangang to Yangang-Makha via Majuwa : Km 3rd. Mr. Nar Bhd. Gurung Tenth Plan State Plan Addl. Facilities 22.83 0.00 22.83 1-Jan-05 10-Oct-05 95% 16.17 0.00 16.17 in progress
85 Construction of truckable road from Kholaghari to Jaubari Km 10th & 11th (14 Chain). - Tenth Plan State Plan New Road 44.09 0.00 44.09 - - 90% 39.87 39.87 0.00 in progress
86 Construction of truckable road from Lingi Payong Govt. jr. high School Km 2nd . Mr. S. S. Dhakal   State Plan New Road 57.78 0.00 57.78 1-Mar-03 28-Feb-04 90% 27.21 27.21 0.00 in progress
86 Construction of Kink road from Kateng Bokrang to Namthang South Sikkim. Buddha Singh Tamang   State Plan Link Road 53.65 0.00 53.65 12-Dec-08 12-Dec-10   0.00 0.00 0.00 in progress
87 Diversion of turning at Km 14 th to 18th on Ravangla - Zarong Road in S-Sikkim Smt. Ratna Kum. Rai Tenth Plan State Plan Expansion 104.72 0.00 104.72 Jun-05 Mar-08 87% 54.11 54.11 0.00 in progress
D DISTRICT : WEST
  CENTRAL  SPONSORED  SCHEMES                      
1 Repalacement of Rathong Suspension bridge by steel bridge on Rimbi-Yoksum road. Mrs. S. Dolma Bhutia Tenth Plan NLCPR - 327.57 327.57 0.00 2-Jun-05 31-Aug-06 97% 262.01 0.00 262.01 In Progress
2 Repalacement of Rimbi Suspension bridge by steel bridge on Pelling - Rimbi road. Mr. Keshav Pradhan Tenth Plan NLCPR - 2-Jun-05 31-Aug-06 90% In Progress
3 Carpetting and surface improvement of Soreng Budang Road via Malbassy Km 1st - 11th. Mr. Shankhar Agarwal Tenth Plan NLCPR Removal 398.46 387.95 10.51 3-Mar-05 6-Jun-06 100% 341.27 2.27 339.00 Work completed final bill under preparation
4 Construction of premix carpetting /imp. Dentam Uttrey road Km 1st to 10th  Mr. C.B. Subba Tenth Plan NLCPR - 399.00 399.00 0.00 3-Mar-05 31-Aug-06 92% 205.84 0.00 205.84 5th a/c bill paid to the contractor
5 Surface imp/ carpetting i/c drainage works on Pelling Dentam road Km 1st to 9th  Mr. Anjani Kr. Agarwal Tenth Plan NLCPR - 606.54 606.54 0.00 3-Mar-05 31-Aug-06 94% 611.86 0.00 611.86 4th a/c bill paid 
6 Surface imp/ carpetting i/c drainage works on Pelling Dentam road Km  18th to 20th CB Subba Tenth Plan NLCPR - 91.30 91.30 0.00 3-Mar-05 31-Aug-06 99% 78.00 0.00 78.00 4th a/c bill paid 
7 Surface imp/ carpetting i/c drainage works on Pelling Dentam road Km 10th to 17th. Mr. Mahabir Pd. Agarwal Tenth Plan NLCPR - 406.79 301.97 104.82 3-Mar-05 31-Aug-06 93% 387.98 0.00 387.98 4th a/c bill paid 
8 Replacement of B.B. Lal Suspension Bridge on Pelling Dentam road along Gyalshing Soreng Road.  Mr. Mahabir Pd. Agarwal Tenth Plan NLCPR - 200.30 200.30 0.00 3-Mar-05 31-Aug-06 96% 75.07 0.00 75.07 In progress
9 Slope stablization of Labling land slide on Yoksum - Tashiding road Mrs Kabita Pradhan Tenth Plan NLCPR Removal 149.57 127.52 3.92 22-Apr-05 21-Apr-06 100% 2.05 2.05 0.00 Work Completed
10 Slope stablization of Chorang land slide on Yoksum - Tashiding road Mr. U. P. Bhutia (Kazi) Tenth Plan NLCPR Removal 18.13 22-Apr-05 21-Apr-06 100% 61.23 10.00 51.23 Work Completed
11 Construction of strengthening draianage & carpetting of Khanisherbong road fKm 1st -11th. Mr. B. L. Gurung Eleventh Plan NEC - 486.36 486.36 0.00 3-Mar-07 9-Sep-08 45% 144.11 0.00 144.11 In Progress
12 Replacement  of Ringyang suspension bridge over Ringyang Khola on Soreng-Sombaria road. Mr. Sanjay Chandak Tenth Plan NEC - 332.02 332.02 0.00 8-Aug-05 10-Oct-06 100% 328.94 0.00 328.94 completed
13 Strengthening draianage & carpetting of Sombaria Hilley road Km 1st- 26th Mr. Kamal Kr. Rai Tenth Plan NEC - 845.68 845.68 0.00 1-Nov-06 10-Oct-08 66% 208.01 0.00 208.01 In progress
14 Strengthening and carpetting, protection and drainage of Bermiock Legship road Km. 1st to 9th Mr. Atul Dhanotia  Tenth Plan NEC - 449.46 449.46 0.00 16-Feb-06 15-Feb-08 86% 194.24 0.00 194.24 In progress
15 Surface improvement and strengthening and premix carpetting of Rimbi Yoksum road Km 1st to 21.70. Mr. K. N. Bhutia Tenth Plan EI - 315.48 219.37 96.11 7-Feb-04 6-Aug-05 87% 248.86 50.82 198.04 In Progress
16 Carpetting of Gyalshing Pelling Road, W.Sikkim (EI) Mr. K. N. Bhutia Tenth Plan EI - 87.86 87.86 0.00 7-Feb-04 6-Aug-05 100% 87.86 0.00 87.86 Work Completed
17 Widening carpetting & drainage system on Legship  - Tashiding road Km 1st-6th. Mr. P. K. Agarwal Tenth Plan NABARD - 73.82 73.82 0.00 2-Jan-01 12-May-01 95% 66.86 0.00 66.86 Work Completed
18 Widening carpetting & drainage system on Legship - Tashiding road Km 7th - 12th. Mr. S. D. Bhutia Tenth Plan NABARD - 66.77 66.77 0.00 2-Jan-01 12-May-01 98% 56.41 0.00 56.41 Work Completed
19 Surface imrovement & P/W from Lunchuk to Salangdang road Km 1st-4th. Mr. P.K. Chandak Tenth Plan NABARD Expansion 128.03 84.32 43.71 6-Jun-05 6-Jun-06 100% 127.21 43.71 83.50 completed
20 Link Road from Alpine CF to Kaluk Dentam Road - Tenth Plan NABARD - 96.77 96.77 0.00 - - - 0.00 0.00 0.00 completed
21 Construction of 65m Span Steel Bridge over Rangit river in between Mengnem & Phamtam Mr. U. P. Bhutia (Kazi) Tenth Plan RSVY - 272.78 148.93 123.85 23-Nov-05 22-May-07 60% 136.56 0.00 136.56 In Progress
22 Construction of link road from Kaluk to Lower Shribadam via Samdong Km 1st to 5th. Mr. K. T. Bhutia Tenth Plan RSVY - 167.87 150.00 17.87 12-Dec-05 6-Jun-07 100% 159.24 9.24 150.00 Final Bill
23 Turning improvement in front of SNT Booking Office & replacement of drainage syatem at outskirt of Gyalshing Bazar.   Mrs. Amrita Gurung Tenth Plan MP LAPS - 9.51 0.00 9.51 5-Dec-06 4-Mar-07 100% 4.47 0.00 4.47 Work Completed, final bill submitted
24 App. Road to Rincheypong Gompa / Shreda from Rinchepong Dak Bunglow Road (Km 1st ch 17th ) Mr. D. Lachi Bhutia Tenth Plan MP LADS - 15.00 15.00 0.00 16-Feb-06 15-Feb-08 85% 9.90 0.00 9.90 In progress
25 Restoration of damages, Slip clearence, Drainage &surface improvement works of Geythang-Karmatar road, Singshore diversion road and Utterey-Sopakha road in West Sikkim. P.K.Subba   BADP - 300.00 300.00 0.00 1-Nov-08 31-Oct-09 20% 0.00 0.00 0.00 Agreement preparation
  STATE PLAN                            
25 Providing Box drain including Check wall below approach road to Pelling Helipad. Suresh Subba Tenth Plan State Plan Removal 11.25 0.00 11.25     100% 9.61 9.61 0.00  
26 Widening carpetting & drainage system on Legship - Tashiding road Km 1st - 12th. Mr. P.K.Agarwal & Mr. S. D. Bhutia Ninth Plan State Plan Removal 261.02 0.00 261.02 2-Jan-01 12-May-01 100% 256.11 0.00 256.11 Work Completed, Balance qty of work to be closed(Revised 66.86+65.98)
27 Carpetting of Legship Gyalshing Road km 1st-3rd N.B.Dahal Ninth Plan State Plan Removal 24.94 0.00 24.94 25-Jun-93 20-Mar-96 100% 21.75 21.75 0.00  
28 Consruction of 13m Span RCC Bridges at Ribing, Khola on Chakhung - Khansirbong road. Mr. N.T. Tamang Ninth Plan State Plan Removal 19.28 0.00 19.28 10-Oct-98 5-May-99 100% 8.50 8.50 0.00 Work Completed, final bill to be paid
29 Widening, surface improvement, premix carpetting of Sombaria Puretar Km 6th to 13th Mr. Amrit Subba, Prakash Subba, S.H. Sherpa, P.D. Sherpa  Tenth Plan - Removal  149.37 0.00 149.37 1-Jan-05 10-Oct-06 100% 77.99 77.99 0.00 Work Completed, final bill to be paid
33 Technical Surveillance and rehabilitation of Saingshore Suspensiopn Bridge along Dentam Uttarey Road  AS Bumper   State Plan Replacement 110.00 0.000 110.00 7-Jun-08 7-Nov-06 60% 77.00 77.00 0.00 1st a/c bill paid
34 Construction of 25m span suspension bridge at Reshi Khola on Shribadam Deyathang road. Mr. B.R. Sharma Tenth Plan State Plan Replacement 45.03 0.00 45.03 3-Mar-05 3-Mar-07 80% 27.16 27.16 0.00 In Progress
35 Renovation of 320"0" span suspension bridge over Ramam river at Jorethang Mr. Jagdish Agarwal. Tenth Plan - Replacement 15.93 0.00 15.93 5-May-06 6-Jun-06 100% 14.84 14.84 0.00 Revised Estimate           in Process
36 Renovation of Singsore Bridge along Dentam - Utterey Road   Eleventh Plan   Replacement 73.41 0.00 73.41 2007 - - 0.00 0.00 0.00  
37 Approach road to suspension bridge over Ramam river at Jorethang Mrs. Sapana Sunuwar Tenth Plan - Replacement 1.88 0.00 1.88 12-Dec-05 2-Feb-06 100% 1.88 1.88 0.00 completed
40 20mm thick premix crpetting along link road to Manglabaria Km 1st to 3rd. Mrs. Karma Uden Bhutia Tenth Plan State Plan Expansion 27.72 0.00 27.72 23-Dec-02 22-Apr-03 100% 25.74 25.74 0.00 Final bill uner procees
41 Construction of Motorable Road from Reshi-Khaniserbong, Km 7th- 8th.   Tenth Plan State Plan Expansion 20.61 0.00 20.61 - - 70% 8.09 8.09 0.00  
42 Premix carpetting & Improvement of Pelling - Rimbi road Km 1st-12th .[Additional Sanction] K.N.Bhutia, P.T.Bhutia, S.W.Bhutia Tenth Plan State Plan Expansion 16.12 0.00 16.12 - - 100% 12.36 12.36 0.00  
43 Premix carpetting works on Gyalshing Pelling road Km 1st & 9th. [State Share of EI] Phurden Lama & Palchen Yongda Tenth Plan State Plan Expansion 146.37 0.00 146.37 15-Oct-03 14-Jul-04 100% 134.19 134.19 0.00  
44 Construction &  Protective wall on Kalej Khola Power House to Uttarey Road.   Tenth Plan State Plan Expansion 3.99 0.00 3.99 - -   0.00 0.00 0.00  
45 Extension of Ribdi Bharang road Km 3rd to 4th.[9th plan] N.T.Sherpa Ninth Plan State Plan Expansion 18.96 0.00 18.96 Feb'99 May'2002 100% 17.97 17.97 0.00  
46 Premix carpetting, drainage & Protective Works on Sombaria-Soreng road Km 1st-8th. C.B.Subba Tenth Plan State Plan Expansion 181.90 0.00 181.90 25-Feb-04 24-Mar-05 100% 168.90 168.90 0.00  
47 Land/Damaged Compensation of Link Road to Gitang - Karmatar Compensation   State Plan Expansion 2.65 0.00 2.65 - - 100% 2.65 2.65 0.00  
48 Construction of Link Road from Thongling to Lower Dodak Km 1st     State Plan Expansion 35.37 0.00 35.37 - - 100% 29.87 29.87 0.00  
49 Premix carpetting & improvement of Pelling Rimbi Road Km 1st-12th (Additional Sanction) Mr. K.N.Bhutia, Mr. P.T.Bhutia, Mr. S.W.Bhutia   State Plan Expansion 1,155.42 1,050.60 104.82 - - 100% 839.72 12.38 827.34 Work Completed
50 Construction of Link Road from Angden Gumpa to Upper Rumbuk School Km 1st. Mr. P. T. Sherpa Ninth Plan State Plan Expansion 7.68 0.00 7.68 3-Mar-95 3-Mar-96 100% 5.62 5.62 0.00 Work Completed, Final bill under process
51 Carpetting of Ribdi Bharang  Road km 1st  Mr.N. T. Sherpa Ninth Plan State Plan Expansion 8.17 0.00 8.17 2-Feb-99 5-May-02 100% 8.17 8.17 0.00 completed
52 Carpetting and P/W on Sombaria  Soreng Road Km 1st - 8th. Mr. C. B. Subba Tenth Plan - Expansion 181.90 0.00 181.90 2-Feb-04 3-Mar-05 100% 168.90 168.90 0.00 completed
53 Construction of link road from Kongri -Labdong road Km 1st - 5th. Mr. B.P. Pradhan,     Mr. O.P. Pradhan Ninth Plan State Plan Link Road Plan 26.38 0.00 26.38 12-Jun-96 11-Apr-97 100% 15.69 15.69 0.00 Work Completed
54 Construction of Link Road from Chota Samdong to Majuwa km 3rd. Land Compensation Eleventh Plan State Plan Link Road Plan 17.57 0.00 17.57 Sept.2007 - 100% 17.57 17.57 0.00  
55 Construction of New road from Rinchenpong Yangsum to Ambetar Km 1st - 4th. Land Compensation Ninth Plan State Plan New Road 47.14 0.00 47.14 Oct-07 - - 25.00 25.00 0.00  
56 Construction of motorable road from Pokhari to Karjee Km 1st Mr. L.D. Bhutia Tenth Plan State Plan New Road 36.28 0.00 36.28 27-Feb-03 26-Dec-03 98% 22.97 22.97 0.00 In Progress
57 Construction of motorable road from Pokhari to Karjee Km 2nd Mr. G.S. Subbba Tenth Plan State Plan New Road 40.86 0.00 40.86 27-Feb-03 26-Dec-03 100% 32.28 32.28 0.00 Work Completed
58 Construction of motorable road from Pokhari to Karjee Km 3rd Mr. G.S. Subbba Tenth Plan State Plan New Road 33.08 0.00 33.08 27-Feb-03 26-Dec-03 100% 30.59 30.59 0.00 Work Completed
59 Construction of motorable road from Pokhari to Karjee Km 4th Mr. B.P. Pradhan Tenth Plan State Plan New Road 28.08 0.00 28.080 27-Feb-03 26-Dec-03 98% 20.84 20.84 0.00 In Progress
60 Construction of motorable road from U/Labdong to L/Labdong Km 1st. Mr. D.K. Pradhan Tenth Plan State Plan New Road 29.68 0.00 29.680 27-Feb-03 26-Dec-03 100% 20.14 20.14 0.00 Work Completed
61 Construction of motorable road from U/Labdong to L/Labdong Km 2nd. Mr. G.S. Subbba Tenth Plan State Plan New Road 31.44 0.00 31.440 27-Feb-03 26-Dec-03 100% 20.35 20.35 0.00 Work Completed
62 Construction of motorable road from U/Labdong to L/Labdong Km 3rd. Mr. G.S. Subbba Tenth Plan State Plan New Road 30.95 0.00 30.950 27-Feb-03 26-Dec-03 98% 27.33 27.33 0.00 In Progress
63 Construction of motorable road from U/Labdong to L/Labdong Km 4th. Mrs. Sabita Subba Tenth Plan State Plan New Road