| MONTHLY PHYSICAL AND FINANCIAL PROGRESS REPORT FOR THE MONTH ENDING
DECEMBER 2008 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
(Rupees in lakhs) |
|
|
| Sl.No |
Name
of Schemes |
Name
of Contractor |
Plan |
Funding Agency |
(Head) |
SANCTIONED AMOUNT |
Date of Commen-
cement |
Stipulated Date of
Completion |
Physical
Progress in % |
Financial
Progress |
Remarks |
|
|
| Total |
C.share |
S.
share |
Expenditure
till date |
|
|
| Total |
S.Share |
C.Share |
|
|
| A |
DISTRICT: NORTH |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
| CENTRAL SPONSORED
SCHEMES |
|
|
|
|
|
|
|
|
|
|
|
|
| 1 |
Upgradation Ranka - Luing-Gangtok-Burthuk-Road Km 14th to 21st |
Mr. Shyam Rai |
Tenth Plan |
NLCPR |
Expansion |
641.54 |
420.00 |
221.54 |
11-Jan-05 |
19-Jul-07 |
68% |
406.60 |
0.00 |
406.60 |
work in progress |
|
|
| 2 |
Construction 0f 90m span steel bridge over Takcham Chu along
C.R.B.A Road, Km 21st |
Mrs. Meera Rai |
Tenth Plan |
NEC |
Expansion |
476.74 |
476.74 |
0.00 |
9-Jan-06 |
8-Oct-06 |
86% |
267.60 |
0.00 |
267.60 |
work in progress Expd. In Purchase of Vechile steel parts |
|
|
| 3 |
Upgradation / carpeting & extension i/c providing drainage
and protective works of Marchak - Tumlabong road, Km 1st to 13th in East
Sikkim |
M/s Ladakhi Const. Pvt. Ltd. |
Tenth Plan |
NEC |
Expansion |
1,023.00 |
1,023.00 |
0.00 |
9-Nov-06 |
18-May-08 |
65% |
339.05 |
0.00 |
339.05 |
work in progress |
|
|
| 4 |
Construction of steel bridge over Teesta river at Gour |
Mr. Samdup Lepcha |
Tenth Plan |
NEC |
NEC |
488.57 |
488.57 |
0.00 |
21-Jan-06 |
22-Jan-07 |
94% |
321.37 |
0.00 |
321.37 |
In Progress |
|
|
| 5 |
Strengthening / drainage carpetting of SBS road to Tingbong high
school |
Mr. G.N. Agarwal |
Tenth Plan |
NEC |
NEC / TSP |
447.74 |
401.37 |
46.37 |
29-Apr-05 |
30-Apr-06 |
100% |
316.14 |
0.00 |
316.14 |
Completed |
|
|
| 6 |
Construction of Steel Bridge on Approach road to Khedum Village
in North Sikkim. |
Mr. Penzong Lachungpa |
Tenth Plan |
NEC |
NEC |
190.68 |
190.68 |
0.00 |
24-Feb-06 |
23-Jan-07 |
94% |
116.98 |
0.00 |
116.98 |
In Progress |
|
|
| 7 |
Upgradation & Surface strengthening of Ranka-Sichey road Km
1st to 3rd |
Mr. Rajesh Agarwal |
Tenth Plan |
CRF |
Removal |
119.05 |
88.26 |
30.79 |
17-Mar-05 |
31-May-06 |
100% |
31.03 |
0.00 |
31.03 |
Final bill submitted |
|
|
| 8 |
Upgradation of Phodong -Labrang Gumpa |
Mr. K.N. Bhutia |
Tenth Plan |
CRF |
CRF |
158.96 |
158.96 |
0.00 |
3-Nov-05 |
2-Oct-06 |
100% |
118.77 |
0.00 |
118.77 |
Completed Final bill to be paid |
|
|
| 9 |
Construction of app. Road to Thomchi Gumpa. |
Mr. Tashi Lachungpa |
|
BADP |
BADP |
15.69 |
0.00 |
15.69 |
6-Feb-07 |
5-May-07 |
100% |
15.69 |
0.00 |
15.69 |
Completed |
|
|
| 10 |
Construction of approach road to Thomchi Gumpa. |
|
Tenth Plan |
BADP |
BADP |
5.00 |
5.00 |
0.00 |
- |
- |
100% |
0.00 |
0.00 |
0.00 |
|
|
|
| 11 |
Construction of new road from Gumpa Golai to Chanzing, Lachen. |
Mr Nangden Lachungpa |
|
BADP |
BADP |
38.10 |
38.10 |
0.00 |
- |
- |
- |
0.00 |
0.00 |
0.00 |
Work delay due to land compens-ation |
|
|
| 12 |
Upgradation / Strengthening and Carpeting of approach road to
Latoong Village. |
Mr Nangden Lachungpa |
|
BADP |
BADP |
42.79 |
42.79 |
0.00 |
- |
- |
70% |
0.00 |
0.00 |
0.00 |
work in progress |
|
|
| 13 |
Extension of Bakcha -Labi road Km 3rd & 4th. State share of
BADP land compansation. |
Mr. Ugen Nedup Bhutia |
|
BADP |
BADP |
0.00 |
0.00 |
0.00 |
- |
- |
100% |
0.00 |
0.00 |
0.00 |
Work Completed |
|
|
| 14 |
Construvction of Link Road from Bay to Pentong in North Sikkim. |
Mr. Bernald Lepcha |
Tenth Plan |
RSVY |
New Road |
187.45 |
150.00 |
37.45 |
22-Sep-05 |
31-Dec-08 |
65% |
128.03 |
0.00 |
128.03 |
In Progress |
|
|
| 15 |
Construction of Heli Port at Lachung |
Mr. Nidup Lachungpa |
Ninth Plan |
Tourism |
Other Expenditure |
38.89 |
0.00 |
38.89 |
3-Apr-00 |
2-Jan-01 |
75% |
28.43 |
0.00 |
28.43 |
Defence clearance not yet received |
|
|
| 16 |
Carpetting of app. Road to Crematorium ground at Jalipool. |
Mr. Praveen Agarwal |
Tenth Plan |
NABARD |
Expansion |
31.80 |
20.66 |
11.14 |
31-Jan-06 |
15-Jun-06 |
100% |
26.35 |
9.35 |
17.00 |
Final bill submitted |
|
|
| 17 |
Construction of Link Road from Takchi Phatak to Upper Luing, Km
1st |
Mr. Tsweang Rinzing Bhutia |
Tenth Plan |
NABARD |
New Road |
37.07 |
0.00 |
37.067 |
18-Aug-05 |
17-Aug-06 |
80% |
70.72 |
49.82 |
20.90 |
work in progress |
|
|
| 18 |
Construction of Link Road from Takchi Phatak to Upper Luing, Km
2 nd |
Dewjang Bhutia |
Tenth Plan |
NABARD |
New Road |
31.82 |
0.00 |
31.819 |
18-Aug-05 |
17-Aug-06 |
70% |
Work just started |
|
|
| 19 |
Construction of Link Road from Takchi Phatak to Upper Luing, Km
3rd |
Tempo Gyatso Bhutia |
Tenth Plan |
NABARD |
New Road |
56.18 |
0.00 |
56.176 |
23-Sep-05 |
22-Sep-06 |
70% |
Work just started |
|
|
| 20 |
Construction of Link Road from Takchi Phatak to Upper Luing, Km
4th |
Yangchen Dolma Bhutia |
Tenth Plan |
NABARD |
New Road |
38.74 |
0.00 |
38.740 |
23-Sep-05 |
22-Sep-06 |
0% |
work in progress |
|
|
| 21 |
Construction of Link Road from Takchi Phatak to Upper Luing, Km
5th |
Yangchen Dolma Bhutia |
|
NABARD |
New Road |
56.78 |
0.00 |
56.780 |
23-Sep-05 |
22-Sep-06 |
0% |
work in progress |
|
|
| 22 |
Extension of 3rd Km road from 3rd mile turning (Tintek Dikchu
road) to Rakshey via Kedangthang Km 4th to 6th |
Devi Dhakal |
|
NABARD |
|
280.83 |
224.66 |
56.170 |
15-May-08 |
15-May-09 |
60% |
0.00 |
0.00 |
0.00 |
work in progress |
|
|
| 23 |
Extension of link road fromGRS road to Km 12th CH 5 to Tatopani
at Rumtek |
M. Karki |
|
NABARD |
|
50.24 |
40.19 |
10.050 |
15-May-08 |
15-May-09 |
20% |
0.00 |
0.00 |
0.00 |
work was delay due to objection raised by DCC Rumtek |
|
|
| |
WORKS
SANCTIONED UNDER STATE
PLAN |
|
|
|
|
|
|
|
|
|
|
|
|
|
| 24 |
Premix carpetting, improvement of GRBA road Km 18th to 21st and
Assam Pakyong Road Km 1st to 6th. |
Mr. Amrit Rai |
Tenth Plan |
State Plan |
Removal |
254.76 |
0.00 |
254.76 |
25-Aug-04 |
31-Mar-06 |
100% |
184.20 |
0.00 |
184.20 |
Completed |
|
|
| 25 |
Upgradation of Marchak Tumlabong Road (NEC ) State Share for LC |
Compensatiion |
|
NEC |
Removal |
100.00 |
0.00 |
100.00 |
- |
- |
37% |
37.00 |
0.00 |
37.00 |
work in progress |
|
|
| 26 |
Premix carpetting,on Penlong - Tintek road Km 12th - 20th |
Mr. Suresh Mundra |
Tenth Plan |
State Plan |
Expansion |
158.79 |
0.00 |
158.79 |
28-Nov-02 |
31-Mar-06 |
100% |
99.54 |
0.00 |
99.54 |
Final bill to be submitted |
Discuss |
Expenditure |
| 27 |
Const. of GOR Santok road Km. 1st |
Mr.Pentok Lepcha |
Tenth Plan |
State Plan |
Expansion |
29.76 |
0.00 |
29.76 |
- |
- |
100% |
21.61 |
0.00 |
21.61 |
Completed |
|
|
| 28 |
Construction of link road to Aho - Manghim Km 1st |
Mr. B.K. Upreti |
Tenth Plan |
State Plan |
Link Road |
16.88 |
0.00 |
16.88 |
2-Dec-04 |
15-Jan-07 |
94% |
11.37 |
0.00 |
11.37 |
work in progress |
|
|
| 29 |
Const. of link road to Aho - Manghim Km 2nd |
BR Subba |
Tenth Plan |
State Plan |
Link Road |
18.88 |
0.00 |
18.88 |
2-Dec-04 |
15-Jan-07 |
45% |
0.00 |
0.00 |
0.00 |
delayed due to land compensation |
|
|
| 30 |
Const. of link road to Aho - Manghim Km 3 rd |
Beena Subba |
Tenth Plan |
State Plan |
Link Road |
19.27 |
0.00 |
19.27 |
1-Dec-04 |
15-Jan-07 |
20% |
0.00 |
0.00 |
0.00 |
work in progress |
|
|
| 31 |
Construction of app. Road from Samdong Cha Chu to Yumi Samdong,
north Sikkim. Km 1st & 2nd |
Mr. T. Doma Lachungpa |
Tenth Plan |
State Plan |
New Road |
54.48 |
0.00 |
54.48 |
21-Jun-04 |
20-Dec-05 |
100% |
54.48 |
0.00 |
54.48 |
Work Completed |
|
|
| 32 |
Construction of Rest House at Samdong in East Sikkim. |
Mr. Nitup Lepcha |
Tenth Plan |
Addl.Facilities |
Addl.Facilities |
78.70 |
0.00 |
78.70 |
20-May-03 |
19-Apr-04 |
100% |
75.44 |
0.00 |
75.44 |
Completed, Final bill paid |
|
|
| 33 |
Upgradation,carpetting, protective and drainage of SBS road to
Lingtam PHSE Km 1st to 5th. |
Mr. Samdup Lepcha |
Eleventh Plan |
State Plan |
Strengthning Road Infrastructure |
385.54 |
0.00 |
385.54 |
- |
- |
50% |
42.22 |
0.00 |
42.22 |
work in progress |
|
|
| 34 |
Upgradation,carpetting, protective and drainage works of DSM
road to Gour School Km 1st to 8th. |
Mr. Soden Gyamptso Bhutia |
Tenth Plan |
State Plan |
Strengthning Road Infrastructure |
391.66 |
0.00 |
391.66 |
1-Jun-08 |
1-Jan-09 |
40% |
57.78 |
0.00 |
57.78 |
work in progress |
|
|
| 35 |
Widening protective work drainage & carpetting work on S.B.S
Road Km 10th & 12th |
Mr. Lobzang Lepcha |
Tenth Plan |
State Plan |
TSP |
35.97 |
0.00 |
35.97 |
15-Nov-03 |
14-Aug-04 |
73% |
14.99 |
0.00 |
14.99 |
Carpetting work to be done. |
|
|
| 36 |
Widening protective work drainage & carpetting work on S.B.S
Road Km 13th |
Mr. Sonam Dorjee |
Tenth Plan |
State Plan |
TSP |
18.86 |
0.00 |
18.86 |
18-Nov-04 |
17-May-05 |
70% |
0.73 |
0.00 |
0.73 |
WBM/carpetting work to be done |
|
|
| 37 |
Widening protective work drainage & carpetting work on S.B.S
Road Km 14th & 15TH |
Mr. Topnam Lepcha |
|
State Plan |
TSP |
35.11 |
0.00 |
35.11 |
11-Jan-03 |
10-Oct-03 |
80% |
19.47 |
0.00 |
19.47 |
Carpetting work to be done. |
|
|
| 38 |
Strengthening, protective / drainage carpetting works on
approach road to Ringtham Gumpa Km1st to 3rd
Mangan. |
K.N. Lachenpa |
|
State Plan |
TSP |
276.00 |
0.00 |
276.00 |
14-Mar-08 |
18-Sep-09 |
50% |
11.51 |
0.00 |
11.51 |
work in progress |
|
|
| 39 |
Construction approach road to medicine pond B-6 |
Tempo Lepcha |
|
State Plan |
TSP |
105.00 |
0.00 |
105.00 |
6-Mar-08 |
7-Mar-09 |
60% |
11.03 |
0.00 |
11.03 |
work in progress |
|
|
| 40 |
Construction approach road to Shakothang at Sarchok village |
Dawa Gaytmso Lachenpa |
Tenth Plan |
State Plan |
TSP |
64.98 |
0.00 |
64.98 |
7-Apr-08 |
8-Apr-09 |
32% |
3.27 |
0.00 |
3.27 |
work in progress |
|
|
| 41 |
Protective works, widening, drainage and carpeting on Bictchu
road Km 1st to 3rd to Gai Gaon at Lachung |
Needup Lacungpa |
|
State Plan |
TSP |
298.00 |
0.00 |
298.00 |
21-Aug-08 |
2-Aug-10 |
35% |
0.00 |
0.00 |
0.00 |
work in progress |
|
|
| 42 |
Premix Carpetting imp & widening of D.S.M road km 12th to
16th |
Mr. Singhik Lepcha |
Tenth Plan |
State Plan |
TSP |
124.05 |
0.00 |
124.05 |
15-Jan-03 |
14-Jul-04 |
80% |
71.89 |
0.00 |
71.89 |
In Progress |
|
|
| 43 |
Premix Carpetting imp & widening of D.S.M road km 17th |
Mr. Chewang Norbu |
Tenth Plan |
State Plan |
TSP |
19.41 |
0.00 |
19.41 |
11-Jan-03 |
10-Oct-03 |
100% |
9.93 |
0.00 |
9.93 |
Final Payment |
|
|
| 44 |
Premix Carpetting imp & widening of D.S.M road km 18th |
Mr. Dawa Tshering |
Tenth Plan |
State Plan |
TSP |
19.56 |
0.00 |
19.56 |
11-Jan-03 |
10-Oct-03 |
85% |
15.10 |
0.00 |
15.10 |
work in progress |
|
|
| 45 |
Premix Carpetting imp & widening of D.S.M road km 19th |
Mr. Ongden lepcha |
Tenth Plan |
State Plan |
TSP |
20.44 |
0.00 |
20.44 |
11-Jan-03 |
10-Oct-03 |
73% |
10.59 |
0.00 |
10.59 |
work in progress |
|
|
| 46 |
Premix Carpetting imp & widening of D.S.M road km 20th |
Mr. Mingma Tshering |
Tenth Plan |
State Plan |
TSP |
20.04 |
0.00 |
20.04 |
11-Jan-03 |
10-Oct-03 |
74% |
14.12 |
0.00 |
14.12 |
In Progress |
|
|
| 47 |
Premix Carpetting imp & widening of D.S.M road km 21st |
Mr. Lobzang Lepcha |
|
State Plan |
TSP |
23.38 |
0.00 |
23.38 |
11-Jan-03 |
10-Oct-03 |
75% |
18.07 |
0.00 |
18.07 |
In Progress |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| B |
DISTRICT :EAST |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
CENTRAL
SPONSORED SCHEMES |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 1 |
Const. of Goshkhan Dara Bridge over River Teesta at Singtam,
East Sikkim |
M.P Agarwal |
Tenth Plan |
NLCPR |
- |
1,337.11 |
1,337.11 |
0.00 |
10-Jan-07 |
11-Jun-08 |
40% |
420.00 |
0.00 |
420.00 |
work in progress |
|
|
| 2 |
Const. of diversion road Ranipool-Pakyong road km 1st-3rd. |
B.K. Agarwal |
Tenth Plan |
NLCPR |
Expansion |
339.85 |
236.87 |
102.98 |
21-Feb-05 |
21-Nov-05 |
70% |
225.98 |
64.60 |
161.38 |
work in progress |
|
|
| 3 |
Strengthening,drainage and Carpeting and construction of 30m
span steel bridge along Assam-Pakyong road km 7th - 15th. |
S.K. Agarwal |
Tenth Plan |
NEC |
- |
750.76 |
750.76 |
0.00 |
6-Nov-06 |
5-May-08 |
75% |
309.05 |
0.00 |
309.05 |
work under process |
|
|
| 4 |
Construction of major retaining structures on approach road to
Raj Bhawan,VIP Complex and TNA Public School Complex |
|
Tenth Plan |
NEC |
- |
106.87 |
106.87 |
0.00 |
30-May-05 |
29-May-06 |
100% |
74.24 |
0.00 |
74.24 |
completed |
|
|
| 5 |
Strengthening/drainage and P/Wprks for the road from Lal Turning
to Bashilakha Road Km 1st to 3rd |
G.M Gurung |
|
NABARD |
Expansion |
184.65 |
151.46 |
33.19 |
30/09/07 |
31/03/08 |
100% |
143.83 |
0.00 |
143.83 |
work in verge completetion |
|
|
| 6 |
Construction of Link Road from Sakyong to Beyong km 1st to 2nd
(State Share of NABARD) |
KRSharma & TB Pradhan |
Eleventh Plan |
NABARD |
Link Road |
84.70 |
0.00 |
84.70 |
12-Mar-08 |
11-Mar-09 |
75% |
0.00 |
0.00 |
0.00 |
work under progress |
|
|
| 7 |
Const. of 12 m span R.C.C. Bridge on Sangkhola Zingla Martam
Road at Km 11th ch-3rd. |
Anita Gurung |
Eleventh Plan |
CRF |
- |
38.63 |
38.63 |
0.00 |
1-Apr-07 |
31-Mar-08 |
45% |
0.00 |
0.00 |
0.00 |
work under progress |
|
|
| 8 |
Const. of 12 m span R.C.c. Bridge on Sangkhola Zingla Martam
Road at Km 12th ch-4th.. |
T.B. Pradhan |
Eleventh Plan |
CRF |
- |
45.12 |
45.12 |
0.00 |
1-Apr-07 |
31-Mar-08 |
60% |
22.00 |
0.00 |
22.00 |
work under progress |
|
|
| 9 |
Surface improvement and widening of Sang Sirwani Road Km 1st
& App Road from Mech Sub Div Office at Dochum |
Kishor Pradhan |
Eleventh Plan |
CRF |
- |
50.20 |
50.20 |
0.00 |
10-Oct-07 |
9-Sep-08 |
85% |
25.71 |
0.00 |
25.71 |
work under progress |
|
|
| 10 |
Surface improvement and widening of Sang Sirwani Road Km 2nd
& App Road to Mech Workshop Dochum |
K.R. Sharma |
Eleventh Plan |
CRF |
- |
38.49 |
38.49 |
0.00 |
10-Oct-07 |
9-Sep-08 |
65% |
12.61 |
0.00 |
12.61 |
work under progress |
|
|
| 11 |
Upgradation of Link Road from NH-31A to Dokey Chisopani Km
1st |
Kishor Pradhan |
Eleventh Plan |
CRF |
- |
69.63 |
69.63 |
0.00 |
29-Feb-08 |
28-Feb-09 |
35% |
0.00 |
0.00 |
0.00 |
Work to Commence |
|
|
| 12 |
Upgradation of Link Road from NH-31A to Dokey Chisopani Km
2nd |
Gopal Sharma |
Eleventh Plan |
CRF |
- |
35.20 |
35.20 |
0.00 |
29-Feb-08 |
28-Feb-09 |
30% |
0.00 |
0.00 |
0.00 |
work under progress |
|
|
| 13 |
Upgradation of Link Road from NH-31A to Dokey Chisopani Km 3rd |
Suren Gurung |
Ninth Plan |
CRF |
- |
43.90 |
43.90 |
0.00 |
29-Feb-08 |
28-Feb-09 |
45% |
0.00 |
0.00 |
0.00 |
work under progress |
|
|
| 14 |
Const. of link road from Arubotey to Subaneydara km 1st-3rd. |
Om Bhd. Gurung |
Ninth Plan |
BADP |
- |
29.97 |
29.97 |
0.00 |
30-Nov-00 |
16-Mar-01 |
68% |
22.98 |
0.00 |
22.98 |
work abondoned |
|
|
| 15 |
Const. of link road from sisney to North Regu km 1st -4th. |
T.S. Lama |
Tenth Plan |
BADP |
- |
30.31 |
30.31 |
0.00 |
21-Nov-00 |
5-Mar-01 |
95% |
24.54 |
0.00 |
24.54 |
work abondoned |
|
|
| 16 |
Premix carpetting and widening work on Sang dipudara road Km 1st
to 14th. |
Daluram Sarda |
Tenth Plan |
EI |
Removal |
277.44 |
6.95 |
277.44 |
18/11/2002 |
17/08/2004 |
90% |
233.08 |
233.08 |
0.00 |
Sanctioned from EI Rs 6.95 Crore |
|
|
| 17 |
Upgradationand premix carpeting along Duga Pachaykhani road KM
1st-14th. |
B.K.Agarwal |
Tenth Plan |
EI |
Removal |
841.38 |
433.77 |
407.61 |
21-Feb-05 |
5-Mar-08 |
90% |
393.32 |
24.00 |
369.32 |
work in progress |
|
|
| 18 |
Construction of Road from Rathong (NH-31A) to Kimchithang Km 1st
to 15th (EI) |
KK Agarwal |
Tenth Plan |
EI |
- |
1,466.89 |
701.89 |
765.00 |
2007 |
- |
30% |
0.00 |
0.00 |
0.00 |
New Project |
|
|
| 19 |
Improvement of Sang
Dipudara Road (EI) |
- |
Tenth Plan |
EI |
- |
347.74 |
347.74 |
0.00 |
2007 |
- |
90% |
0.00 |
0.00 |
0.00 |
New Project |
|
|
| 20 |
Widening, upgradation of pavement & drainage system
along Rangpo Duga Pendam road km 1st -
15th |
M/s Apex Project & Investment P. Ltd. |
Eleventh Plan |
ISC |
- |
950.00 |
950.00 |
0.00 |
15-Jun-08 |
16-Dec-08 |
65% |
480.00 |
0.00 |
480.00 |
work in progress |
|
|
| 21 |
Improvement of Rhenock - Simanakhola Road Km 1st to 3rd. (ISC) |
Mr. Kuber Raj Rai |
Tenth Plan |
ISC |
- |
250.00 |
250.00 |
0.00 |
26-Mar-08 |
- |
25% |
236.99 |
0.00 |
236.99 |
work in progress |
|
|
| 22 |
Construction of 60 m span steel bridge at Bongliung over Rongli
Chu in East Sikkim |
Gazendra Rai |
|
Zilla Panchyat |
|
74.07 |
0.00 |
74.07 |
29-Mar-08 |
29-Sep-09 |
15% |
0.00 |
0.00 |
0.00 |
work in progress |
|
|
| 23 |
Construction of link road from pakyong Nop gaon to barpipal Dara, Km 1st-3rd in
East-Sikkim |
Hemandri Adhikari |
|
CSS |
|
102.29 |
0.00 |
102.29 |
5-Aug-08 |
5-Mar-10 |
10% |
0.00 |
0.00 |
0.00 |
work in progress |
|
|
| |
STATE PLAN |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 24 |
Carpeting and surface strengthening, improvement, including
drainage works of roads in and around Gangtok. |
PM Chamling |
Tenth Plan |
State Plan |
Removal |
361.89 |
0.00 |
361.89 |
6-Jun-04 |
5-Sep-05 |
100% |
229.45 |
229.45 |
0.00 |
work completed final bill under preparation |
|
|
| 25 |
Surface strengthening upgradation and carpeting of
Pakyong-Karthok Naya Busty road km 5th -7th. |
Adup Bhutia |
Tenth Plan |
State Plan |
Removal |
183.89 |
0.00 |
183.89 |
21/06/05 |
31-Aug-08 |
45% |
56.58 |
56.58 |
0.00 |
work in progress, Date Extended |
|
|
| 26 |
P/L edging ,soling, metalling, premix carpeting and cross drain
of link road from sichey to Indira Bye Pass via Shivalaya Mandir |
Mrs Rupa Dhakal |
Tenth Plan |
State Plan |
Removal |
8.16 |
0.00 |
8.16 |
1/0/2002 |
2-Jul-05 |
80% |
5.81 |
5.81 |
0.00 |
work in abeyance due to non availibility of bitumen |
|
|
| 27 |
Upgradation/carpeting P/works and drainage along Pakyong-Karthok
road km 1st-4th. |
P. N. Kazi |
Tenth Plan |
State Plan |
Expansion |
129.49 |
0.00 |
129.49 |
28-Mar-05 |
27-Jul-06 |
55% |
95.08 |
95.08 |
0.00 |
work in progress |
|
|
| 28 |
Upgradation and premix carpeting of Kotlaytar Rai Gaon Road,km
1st & 2nd |
Miss Devi Dakhal |
Tenth Plan |
State Plan |
Expansion |
57.71 |
0.00 |
57.71 |
28-Mar-05 |
27-Sep-06 |
75% |
31.05 |
31.05 |
0.00 |
work in progress |
|
|
| 29 |
Premix Carpetting and Surface improvement Chewribotay
Pendam Km 1st - 6th |
Basudev Pradhan |
Tenth Plan |
State Plan |
Expansion |
117.78 |
0.00 |
117.78 |
29/05/2003 |
31/01/04 |
95% |
83.84 |
83.84 |
0.00 |
work in progress |
|
|
| 30 |
Construction of Bye Pass Road below Mintokgang |
DB Chettri |
Tenth Plan |
State Plan |
Expansion |
80.26 |
0.00 |
80.26 |
26-Feb-04 |
5-Aug-04 |
100% |
71.46 |
71.46 |
0.00 |
Final bill under process |
|
|
| 31 |
Ext. of Pakyong-Mamring Tareythang road km 1st |
Khush N.Adhikari |
Tenth Plan |
State Plan |
Expansion |
28.91 |
0.00 |
28.91 |
1-Jul-05 |
31-Dec-07 |
90% |
28.72 |
28.72 |
0.00 |
Revised |
|
|
| 32 |
Ext. of Pakyong-Mamring Tareythang road km 2nd |
Johar Man Rai |
Tenth Plan |
State Plan |
Expansion |
16.61 |
0.00 |
16.61 |
1-Jul-05 |
31-Dec-07 |
90% |
16.37 |
16.37 |
0.00 |
Revised |
|
|
| 33 |
Ext. of Pakyong-Mamring Tareythang road km 3rd |
G.K. Pradhan |
Tenth Plan |
State Plan |
Expansion |
22.70 |
0.00 |
22.70 |
1-Jul-05 |
31-Dec-07 |
90% |
12.94 |
12.94 |
0.00 |
Revised Estimate submitted |
|
|
| 34 |
Ext. of Pakyong-Mamring Tareythang road km 4th. |
Udai Mishara |
Tenth Plan |
State Plan |
Expansion |
17.92 |
0.00 |
17.92 |
1-Jul-05 |
31-Dec-07 |
90% |
12.02 |
12.02 |
0.00 |
Revised Estimate submitted |
|
|
| 35 |
Ext. of Pakyong-Mamring Tareythang road km 5th. |
K.S.Rai |
Tenth Plan |
State Plan |
Expansion |
27.01 |
0.00 |
27.01 |
1-Jul-05 |
31-Dec-07 |
90% |
16.05 |
16.05 |
0.00 |
Revised Estimate submitted |
|
|
| 36 |
Ext. of Pakyong-Mamring Tareythang road km 6th. |
Ishore Dakahal |
Tenth Plan |
State Plan |
Expansion |
21.15 |
0.00 |
21.15 |
1-Jul-05 |
31-Dec-07 |
70% |
18.71 |
18.71 |
0.00 |
Revised Estimate submitted |
|
|
| 37 |
Ext. of Pakyong-Mamring Tareythang road km 7th. |
K.S.Rai |
Tenth Plan |
State Plan |
Expansion |
22.10 |
0.00 |
22.10 |
1-Jul-05 |
31-Dec-07 |
55% |
8.68 |
8.68 |
0.00 |
Revised Estimate submitted |
|
|
| 38 |
Ext. of Pakyong-Mamring Tareythang road km.8th |
M. K. Pradhan |
Tenth Plan |
State Plan |
Expansion |
21.66 |
0.00 |
21.66 |
1-Jul-05 |
31-Dec-07 |
55% |
0.00 |
0.00 |
0.00 |
Revised Estimate submitted |
|
|
| 39 |
Ext. of Pakyong-Mamring Tareythang road km.9th |
Kamal Adhikari |
Tenth Plan |
State Plan |
Expansion |
19.24 |
0.00 |
19.24 |
1-Jul-05 |
31-Dec-07 |
100% |
8.00 |
8.00 |
0.00 |
Completed, Final bill under process |
|
|
| 40 |
Ext. of Pakyong-Mamring Tareythang road km.10th |
Milan Dahal |
Tenth Plan |
State Plan |
Expansion |
10.70 |
0.00 |
10.70 |
1-Jul-05 |
31-Dec-07 |
100% |
0.00 |
0.00 |
0.00 |
Completed |
|
|
| 41 |
Const. of road from Zingla Martam KM 16th-18th (2.36km) i/c LC |
UP Kazi |
Tenth Plan |
State Plan TSP |
Expansion |
92.12 |
0.00 |
92.12 |
3-Oct-05 |
3-Oct-06 |
100% |
83.16 |
83.16 |
0.00 |
work in progress |
|
|
| 42 |
Construction of 20 chain road Bio Control Laboratory to Phewk
Busty road |
Mr. G.K.Rai |
Tenth Plan |
State Plan |
Link Road |
25.03 |
0.00 |
25.03 |
28-Sep-05 |
27-Mar-05 |
85% |
9.00 |
9.00 |
0.00 |
Revised estimate under process |
|
|
| 43 |
Const. of link road from Basilakhs to Middle camp via Rodongtar
km 6th |
Justin Rai |
Tenth Plan |
State Plan |
New Road |
17.93 |
0.00 |
17.93 |
5-Oct-05 |
9-Feb-05 |
75% |
14.93 |
14.93 |
0.00 |
work in progress |
|
|
| 44 |
Const. of link road from Basilakhs to Middle camp via Rodongtar
km 8th |
Paul Rai |
Tenth Plan |
State Plan |
New Road |
21.36 |
0.00 |
21.36 |
5-Oct-05 |
9-Feb-05 |
100% |
10.01 |
10.01 |
0.00 |
work in progress |
|
|
| 45 |
Const. of 10m span RCC Culvert on Basilakha to middle camp km
8th. |
Patrush Subba |
Tenth Plan |
State Plan |
New Road |
12.32 |
0.00 |
12.32 |
5-Oct-05 |
9-Feb-05 |
75% |
0.00 |
0.00 |
0.00 |
work in progress |
|
|
| 46 |
Const. of link road from Assam-Pakyong road to Kadamtam village
km.3rd & 4th. |
D.P. Mangar |
|
State Plan |
New Road |
41.74 |
0.00 |
41.74 |
1-Jul-05 |
30-Jun-06 |
75% |
24.66 |
24.66 |
0.00 |
Revised Est Submitted |
|
|
| 47 |
Construction of road from Chandmari village to Jawaharlall Nehru
road |
K Wangchuk |
|
State Plan |
New Road |
30.63 |
0.00 |
30.63 |
31-May-05 |
30-Nov-05 |
100% |
23.76 |
23.76 |
0.00 |
work completed final bill under process |
|
|
| 48 |
Const. of Song-zingla Martam road km 9th. |
P.T. Lepcha |
Eleventh Plan |
State Plan |
New Road |
12.45 |
0.00 |
12.45 |
5-Mar-03 |
20-Dec-03 |
80% |
5.63 |
5.63 |
0.00 |
In progress |
|
|
| 49 |
Const.of Song-Zingla Martam road km 14th |
Tenging Bhutia |
Eleventh Plan |
State Plan |
New Road |
25.54 |
0.00 |
25.54 |
6-Mar-03 |
6-Dec-03 |
100% |
19.63 |
19.63 |
0.00 |
In progress |
|
|
| 50 |
Const. of Song-Zingla Martam road km 15th. |
S.K.Chettri |
|
State Plan |
New Road |
26.75 |
0.00 |
26.75 |
6-Mar-03 |
6-Dec-03 |
95% |
19.95 |
19.95 |
0.00 |
In progress |
|
|
| C |
DISTRICT
: SOUTH |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| A. |
CENTRAL
SPONSORED SCHEMES |
|
|
|
|
|
|
|
|
|
|
|
|
|
| 1 |
Surface strengthening drainage & P. Works on Namchi-
Damthang Ravangla road- Km 1st -26th. |
- |
Tenth Plan |
NLCPR |
Removal |
1,668.61 |
1,207.00 |
461.61 |
1-Jan-05 |
1-Feb-07 |
94% |
1,259.76 |
224.94 |
1,034.82 |
in progress |
|
|
| 2 |
Replacement of existing Sikkip Suspension Bridge over Rangit
River |
Mr. Chandra Khaling |
Tenth Plan |
NLCPR |
Replacement |
78.13 |
53.66 |
24.47 |
15-Dec-03 |
30-Mar-07 |
100% |
65.43 |
11.78 |
53.65 |
work completed |
|
|
| 3 |
Upgradation, Surface strengthening, drainage & P/W on
Ravangla Makha Road Km 10th,11th,12th and 13th. |
Smt. Sonam Doma Bhutia |
Tenth Plan |
NLCPR |
- |
119.05 |
119.05 |
0.00 |
15-Jan-03 |
30-Nov-06 |
100% |
116.17 |
0.00 |
116.17 |
completed |
|
|
| 4 |
Upgradation, Surface strengthening, drainage & P/W on
Ravangla Makha Road Km 18th to 21st |
Mr. S. B. Chamling |
Tenth Plan |
NLCPR |
- |
109.18 |
109.18 |
0.00 |
15-Jan-03 |
30-Nov-06 |
100% |
102.96 |
0.00 |
102.96 |
completed |
|
|
| 5 |
Truakable road from 10th mile to Tingmoo villageKm 1st, 2nd and
7th |
Mr. Nim S. Sherpa |
Tenth Plan |
NEC |
|
468.29 |
468.29 |
0.00 |
4-Apr-06 |
4-Apr-07 |
60% |
89.89 |
0.00 |
89.89 |
in progress |
|
|
| 6 |
Truakable road from 10th mile to Tingmoo villageKm 3rd and 6th |
Mr. Sonam O. Bhutia |
Tenth Plan |
NEC |
|
4-Apr-06 |
4-Apr-07 |
53% |
in progress |
|
|
| 7 |
Truakable road from 10th mile to Tingmoo villageKm 4th and 5th |
Mr. Lhendup D. Kaleon |
Tenth Plan |
NEC |
|
5-Apr-06 |
4-Apr-07 |
43% |
in progress |
|
|
| 8 |
Truakable road from 10th mile to Tingmoo villageKm 8th. |
Mr. Bala R. Limboo |
Tenth Plan |
NEC |
- |
9-Apr-06 |
4-Apr-07 |
60% |
in progress |
|
|
| 9 |
Strengthening / drainage carpetting of Ralang-Phamthang road Km
14th to 26th & Replacement of Two existing Bridges over Bermali &
Chil Khola in South Sikkim. |
Mr. N.T. Bhutia |
Tenth Plan |
NEC |
Removal |
1,200.83 |
1200.83 |
0.00 |
11-Nov-06 |
5-May-08 |
41% |
213.00 |
0.00 |
213.00 |
in progress |
|
|
| 10 |
Construction of 40m Span Bridge over Lower Ben Khola at Saino
Tar along Pabong - Simchuthang - Yangang road, South Sikkim. |
Mr. Anjani Kr, Agarwal |
Tenth Plan |
NEC |
- |
137.34 |
137.34 |
0.00 |
2-Sep-05 |
- |
100% |
98.11 |
0.00 |
98.11 |
completed |
|
|
| 11 |
Construction of 60m span steel bridge over Kaw Khola on KS road. |
Mr. S.S. Dhakhal |
Tenth Plan |
NEC |
- |
164.35 |
0.00 |
164.35 |
13-Nov-06 |
12-Nov-08 |
76% |
75.00 |
0.00 |
75.00 |
in progress |
|
|
| 12 |
Imp drainage, carpetting works Km 1st -14th and replacement of
Rangla Khola bridge on Kimotey Sokpay roads. |
Mr. Sunil Kr. Agarwal |
Tenth Plan |
NEC |
Removal |
1,180.89 |
0.00 |
1180.89 |
13-Nov-06 |
12-Nov-08 |
60% |
322.22 |
0.00 |
322.22 |
work under progress |
|
|
| 13 |
Replacement of 110m Span Suspension Bridge over Rabi Khola in
Melli Phong road Km 9th in S/Sikkim. |
Mr. Om Agarwal |
Tenth Plan |
NEC |
- |
497.30 |
497.30 |
0.00 |
39125.00 |
12-Feb-08 |
35% |
30.03 |
0.00 |
30.03 |
in progress |
|
|
| 14 |
Construction of link road Turung School to Suminkhor Primary
School. |
Mr. Subaash Kharel |
Tenth Plan |
NEC |
New Road |
381.24 |
358.45 |
22.79 |
39428.00 |
6-Jun-09 |
69% |
50.00 |
0.00 |
50.00 |
in progress |
|
|
| 15 |
Construction of 30m Span Steel Bridges Over Rinzi Khola at
Kolagari along Namchi-Vok Road |
Bhupal Chamling |
Tenth Plan |
NEC |
Replacement |
185.84 |
157.50 |
28.34 |
12-Dec-07 |
6-Jun-09 |
100% |
206.54 |
0.00 |
206.54 |
Completed, Final bill to be paid |
|
|
| 16 |
Construction of Steel Bridge over Upper Ben Khola on G.L.V.C.
road. |
- |
Tenth Plan |
NEC |
- |
90.83 |
90.83 |
0.00 |
14-Feb-06 |
- |
- |
81.77 |
0.00 |
81.77 |
- |
|
|
| 17 |
Construction of Makha Suspension Bridge over Tista Khola at
Tanak on Makha -Lingi -Yangang- Ravangla Road in South Sikkim.(NEC) |
R.N. Chamling |
Tenth Plan |
NEC |
- |
495.25 |
495.25 |
0.00 |
25-Aug-06 |
- |
10% |
30.23 |
0.00 |
30.23 |
- |
|
|
| 18 |
Surface Improvement, Drainage & Protective works on
Namchi-Rong Road, 13 km |
Mr. MP Agarwal |
Tenth Plan |
NEC |
- |
498.60 |
498.60 |
83.89 |
20-Nov-03 |
- |
|
505.03 |
10.91 |
494.12 |
- |
|
|
| 19 |
Improvement of Ralang - Phamtam Road |
- |
Eleventh Plan |
NEC |
- |
1,183.00 |
1183.00 |
0.00 |
25-Aug-06 |
- |
|
222.01 |
0.00 |
222.01 |
- |
|
|
| 20 |
Upgradation & carpetting of Bhaisalgoan to Salghari road Km
1st to 2nd in South Sikkim. |
Mr. Hanuman Das Agarwal |
Tenth Plan |
NABARD |
Expansion |
82.32 |
63.41 |
18.91 |
12-Feb-07 |
11-Jan-08 |
100% |
45.00 |
0.00 |
45.00 |
completed, final bill submitted |
|
|
| 21 |
Construction of trukable road from Tiffin Dara to Lower
Tinghrithang School Km 1st to 7th |
- |
Tenth Plan |
NABARD |
New Road |
211.30 |
183.040 |
28.26 |
6-Jun-06 |
12-Dec-07 |
55% |
28.53 |
0.00 |
28.53 |
in progress |
|
|
| 22 |
Surfce strengthening, carpetting, drainage and Protective Works
along A/R to Buddha Statue (Sakymuni) |
Pawan Kr. AgarwaL |
|
NABARD |
|
457.00 |
457.000 |
0.00 |
|
|
42% |
0.00 |
0.00 |
0.00 |
in progress |
|
|
| 23 |
Widening, Improvement, protective work, drainage and carpetting
of Melli, Phong road, Km. 1st to 24th. |
Pawan Kr. AgarwaL |
Tenth Plan |
ISC |
Removal |
1,376.01 |
1298.61 |
77.40 |
- |
- |
100% |
33.11 |
33.11 |
0.00 |
Payment made to old contractor |
|
|
| 24 |
Widening, surface improvement, p/w & drainage system along
Phongla-Bermiock-Sirwani road Km 1st-
28th. |
Sunil Kr. Agarwal |
Tenth Plan |
ISC |
Removal |
1,611.78 |
999.08 |
612.70 |
21-Feb-05 |
21-Mar-07 |
90% |
787.00 |
21.00 |
766.00 |
in progress |
|
|
| 25 |
Construction of Gurassey Road from Bio-Diversity Park (Temi) |
Passang Lepcha |
Tenth Plan |
EI |
New Road |
2,267.14 |
1010.92 |
1256.22 |
26-Mar-08 |
- |
- |
0.00 |
0.00 |
0.00 |
- |
|
|
| 26 |
Construction of 20 m. Span Steel Bridge over Mayalu Jhora at Km
3rd on Melli -Nayabazar road. |
Mr. P. C. Mundra |
Tenth Plan |
CRF |
Replacement |
62.24 |
58.96 |
3.28 |
12-Mar-04 |
30-Jun-06 |
100% |
50.61 |
0.00 |
50.61 |
Final bill submitted |
|
|
| 27 |
Construction of 25 m. Span Steel Bridge over Rolu Khola at Km
9th on Melli -Nayabazar road. |
Mr. G.M. Gurung |
Eleventh Plan |
CRF |
Replacement |
55.88 |
52.60 |
3.28 |
22-Jul-04 |
31-May-06 |
100% |
48.63 |
0.00 |
48.63 |
Revision under process |
|
|
| 28 |
Upgradation of existing road from Vok to Namchi. |
M.P.Agarwal |
Tenth Plan |
CRF |
Removal |
467.40 |
365.83 |
101.57 |
8-Aug-07 |
- |
100% |
419.91 |
74.49 |
345.42 |
- |
|
|
| 29 |
Const. of motorable link road from upper Vok to Ung Raam (Water
falls) via Namplang and rabong village in Omchu |
Mr. B. Tsh. Bhutia |
Tenth Plan |
RSVY |
New Road |
240.11 |
180.00 |
60.11 |
22-Aug-05 |
21-Aug-07 |
85% |
234.40 |
54.40 |
180.00 |
in progress |
|
|
| 30 |
Extension of truckable roasd from Borong-Phamtam road to Upper
Borong via Gurug Gumpa Km 1st. |
Shri K. B. Gurung |
Tenth Plan |
RSVY |
- |
20.72 |
20.72 |
0.00 |
2-Feb-06 |
12-Nov-06 |
100% |
0.00 |
0.00 |
0.00 |
work completed |
|
|
| 31 |
Extension of truckable roasd from Borong-Phamtam road to Upper
Borong via Gurug Gumpa Km 2nd. |
Shr. D. M. Gurung |
Tenth Plan |
RSVY |
- |
23.79 |
23.79 |
0.00 |
2-Feb-06 |
13-Nov-06 |
100% |
0.00 |
0.00 |
0.00 |
work completed |
|
|
| 32 |
Extension of truckable road from Borong-Phamtam road to Lower
Borong Km 3rd to 4th. |
Shri Y.C. Bhutia |
|
RSVY |
- |
49.68 |
49.68 |
0.00 |
2-Feb-06 |
11-Nov-06 |
100% |
0.00 |
0.00 |
0.00 |
work completed |
|
|
| 33 |
Construction of link road to Gagyong village km 3 |
- |
|
RSVY |
- |
87.00 |
87.00 |
0.00 |
- |
- |
100% |
77.71 |
0.00 |
77.71 |
work closed |
|
|
| 34 |
Extension of Bhaisalgoan- Salghari road to Farashey km 1st to
3rd. |
- |
Tenth Plan |
RSVY |
- |
113.55 |
94.64 |
18.91 |
- |
- |
100% |
113.55 |
18.91 |
94.64 |
work closed |
|
|
| 34 |
Surface strengthening carpetting, drainage and protective work
along Tarku-Damthang road Km13th-19th |
Shri A. Pradhan |
|
ACA |
- |
228.00 |
228.00 |
0.00 |
2-Feb-08 |
3-Mar-08 |
100% |
246.91 |
18.91 |
228.00 |
work completed |
|
|
| |
STATE PLAN |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 35 |
Construction of Helipad at Pokhari dara in Upper Yangyang |
M/s Rinchen Ongmu Bhutia |
|
State Plan |
- |
90.64 |
0.00 |
90.640 |
1-Jul-08 |
1-Jan-10 |
80% |
43.00 |
43.00 |
0.00 |
in progress |
|
|
| 35 |
Construction of 18ch link road from Helipad to Central
University at Yanyang. |
Mrs. Sumitra Gurung |
|
State Plan |
- |
42.67 |
0.00 |
42.670 |
1-Sep-08 |
1-Dec-08 |
80% |
0.00 |
0.00 |
0.00 |
in progress |
|
|
| 35 |
Primix Carpeting Imp.of & Strengthening of Sirwani Pabong
Tarku (SPT) km 11st to 18th |
Prem Kr.Agarwal |
|
State Plan |
Removal |
101.30 |
0.00 |
101.300 |
13-Nov-02 |
12-Jun-04 |
100% |
0.00 |
0.00 |
0.00 |
old work to be verified |
|
|
| 36 |
Providing Box Drain and Protective work along Pabong Simchuthang
Yangang Road Km 15th Ch 1st to 20th |
Sonam Gyamtso |
Tenth Plan |
State Plan |
Removal |
5.25 |
0.00 |
5.250 |
|
|
100% |
5.04 |
5.04 |
0.00 |
Work Closed |
|
|
| 37 |
Permanent Restoration Work along Kholaghari Jawbari Road Km 2nd
& 3rd |
Bhanu Rai & Others |
Tenth Plan |
State Plan |
Removal |
30.98 |
0.00 |
30.980 |
28-Jun-05 |
- |
100% |
30.98 |
30.98 |
0.00 |
Work Closed |
|
|
| 38 |
Strengthening, Carpetting and Stabilization of approach Road to
Melli - Bazar.(State Share of NABARD) |
Departmental |
Tenth Plan |
State Plan |
Removal |
8.51 |
0.00 |
8.51 |
28-Jun-05 |
- |
100% |
0.00 |
0.00 |
0.00 |
|
|
|
| 39 |
Construction of 50 m Span Steel Bridge on Rongpo Khola along
Ravangla Yangyang Road Km 8th |
Departmental |
Tenth Plan |
State Plan |
Replacement |
56.61 |
0.00 |
56.61 |
25-Jun-05 |
- |
100% |
56.61 |
56.61 |
0.00 |
|
|
|
| 40 |
Immediate. repairs & restoration of 75 mtrs span suspension
bridge over Rangla Khola at Kimbuboty Sokpy road, at Km 7th. |
Mrs Laxumati Rai |
Tenth Plan |
State Plan |
Replacement |
4.98 |
0.00 |
4.98 |
23-Apr-05 |
23-Jan-06 |
100% |
4.98 |
4.98 |
0.00 |
Work Closed |
|
|
| 41 |
Carpetting of Namchi Rong-Sumbuk road Km 1st to 3rd (Soling
metalling & Carpetting). [9th plan] |
P.K.Agarwal, Roshan Agarwal, Anjani Kr Ararwal |
Ninth Plan |
State Plan |
Expansion |
64.18 |
0.00 |
64.18 |
22-Jun-05 |
- |
100% |
64.18 |
64.18 |
0.00 |
Work Closed |
|
|
| 42 |
Construction of road from
Gurpisey to Phalidara. Km 1st & 2nd. |
Chung Chung Bhutia |
Tenth Plan |
State Plan |
Expansion |
50.32 |
0.00 |
50.32 |
21-Jun-05 |
- |
100% |
50.32 |
50.32 |
0.00 |
Work Closed |
|
|
| 43 |
Surface strengthening & drainage on Yang-yang-Rangang road.
Km 1st.-2nd |
Mr. S. B. Chamling |
Tenth Plan |
State Plan |
Expansion |
39.32 |
0.00 |
39.32 |
16-Feb-03 |
11-Jan-06 |
99% |
35.74 |
35.74 |
0.00 |
in progress |
|
|
| 44 |
Carpetting, drainage & Protective Works onYangang- Rangang
road form Bifurcation Point Km 1st and 2nd |
S.B.Chamling |
Tenth Plan |
State Plan |
Expansion |
37.80 |
0.00 |
37.80 |
16-Feb-03 |
31-Mar-05 |
95% |
0.00 |
0.00 |
0.00 |
|
|
|
| 45 |
Premix carpetting,drainage work and protective work on Melli
Turuk Sadam Bhanjyang road Km 1st - 16th. |
Mr. Tej man Rai, Birbal Subba, & Rup Narayan Rai |
Tenth Plan |
State Plan |
Expansion |
290.49 |
0.00 |
290.49 |
1-Jan-03 |
Aug- 31st |
100% |
261.25 |
261.25 |
0.00 |
Completd,necessary documents collected for final bill. |
|
|
| 46 |
Construction of Bye Pass road from Agam Singh Path to Damthang
road 3Km. |
Shri Bhupal Chamling |
Tenth Plan |
State Plan |
Expansion |
160.94 |
0.00 |
160.94 |
3-Mar-04 |
3-Mar-05 |
100% |
123.88 |
123.88 |
0.00 |
work completed |
|
|
| 47 |
Surface Improvement of
Approach Road to Rock Garden from Debrong Golai-Namchi-Damthang road
Km 1st & 2nd. |
Dikila Bhutia |
Tenth Plan |
State Plan |
Expansion |
70.22 |
0.00 |
70.22 |
18-Mar-04 |
18-Mar-05 |
100% |
67.05 |
67.05 |
0.00 |
|
|
|
| 48 |
Premix carpetting, drainage & P/works work on Yangang Makha road Km 1st-21st [S.Share
of NLCPR] [Revised] |
Passang Lepcha |
Tenth Plan |
State Plan |
Expansion |
54.13 |
0.00 |
54.13 |
- |
- |
100% |
54.13 |
54.13 |
0.00 |
Work Closed |
|
|
| 49 |
Premix carpetting on
Ravangla Zarrong road km 1st-11th. |
Shreekishan Agarwal |
Tenth Plan |
State Plan |
Expansion |
0.00 |
0.00 |
|
24-Jun-05 |
- |
- |
0.00 |
0.00 |
0.00 |
Transferred to TSP |
|
|
| 50 |
Construction of link road Rangang road-Yang Yang Makha via
Mazuwa Gaon, 3 kms Rs. 9.49 (LC)] |
Santa Bdr. Chamling, Nar Bdr. Gurung |
Tenth Plan |
State Plan |
Expansion |
88.30 |
0.00 |
88.30 |
6-Jun-05 |
6-Sep-06 |
100% |
80.25 |
80.25 |
0.00 |
|
|
|
| 51 |
Providing premix carpetting on Approach road & Yard to
Palchen Choling Monastry [New Gumpa] at Ralang |
Departmental |
Tenth Plan |
State Plan |
Expansion |
14.65 |
0.00 |
14.65 |
18-Jun-05 |
18-Dec-05 |
100% |
14.26 |
14.26 |
0.00 |
Work Closed |
|
|
| 52 |
Restoration work on Namchi-Phong km. 3rd ch. 30 South Sikkim. |
Departmental |
Tenth Plan |
State Plan |
Expansion |
2.90 |
0.00 |
2.90 |
27-Jun-05 |
- |
100% |
0.00 |
0.00 |
0.00 |
|
|
|
| 53 |
Immediate restoration work on Namchi-Rong-Sumbuk road km.
7th-13th. |
Departmental |
Tenth Plan |
State Plan |
Expansion |
2.63 |
0.00 |
2.63 |
2005 |
- |
100% |
0.00 |
0.00 |
0.00 |
|
|
|
| 54 |
Extension of Ravongla Biring road to Legship Tashiding road 5th
kms in South Sikkim. |
|
Tenth Plan |
State Plan |
Expansion |
119.40 |
0.00 |
119.40 |
2005 |
- |
100% |
43.94 |
43.94 |
0.00 |
|
|
|
| 55 |
Diversion of turning at Km 13 on Ravangla - Zarong Road in
S-Sikkim |
Smt. R K Rai |
Tenth Plan |
State Plan |
Expansion |
6.93 |
0.00 |
6.93 |
1-Apr-06 |
9-Sep-06 |
99% |
4.00 |
4.00 |
0.00 |
work completed |
|
|
| 56 |
Construction of Namchi - Rong - Sumbuk Road Km 3rd to 15th. |
Land Compensation |
Eleventh Plan |
State Plan |
Expansion |
16.48 |
0.00 |
16.48 |
2007 |
- |
100% |
16.48 |
16.48 |
0.00 |
|
|
|
| 57 |
Carpeting & Protective Work on Rabong -Ralong Road Km 1st to
3rd |
Binod Gurung |
|
State Plan |
Expansion |
6.42 |
0.00 |
6.42 |
- |
- |
100% |
0.00 |
0.00 |
0.00 |
|
|
|
| 58 |
Carpeting & Protective Work on Rabong -Ralong Road Km 4th to
6th |
N.T.Bhutia |
|
State Plan |
Expansion |
11.10 |
0.00 |
11.10 |
- |
- |
100% |
0.00 |
0.00 |
0.00 |
|
|
|
| 59 |
Carpeting & Protective Work on Rabong -Ralong Road Km 7th to
10th |
Roshan Lall Agarwal |
|
State Plan |
Expansion |
8.18 |
0.00 |
8.18 |
- |
- |
100% |
0.00 |
0.00 |
0.00 |
|
|
|
| 60 |
Carpeting & Protective Work on Rabong -Ralong Road Km 11th
to 13th |
Tshering Gyatso Kaleon |
Tenth Plan |
State Plan |
Expansion |
3.63 |
0.00 |
3.63 |
- |
- |
100% |
0.00 |
0.00 |
0.00 |
|
|
|
| 61 |
Construction of link road from Kholaghari to Jaubari, Km 3rd 4th
to 9th. (LC = Rs. 170.52 lakh) |
Bhanu Rai & Lakpa Chuki Sherpa |
Tenth Plan |
State Plan |
Link Road |
276.13 |
0.00 |
276.13 |
18-Mar-03 |
18-Dec-04 |
100% |
172.04 |
172.04 |
0.00 |
|
|
|
| 62 |
Construction of link road from Namchi-Kopchey road to Singithang
Km 1st & 2nd. (LC = 20.76 lakh) |
Chandra Bir Rai & D.P.Rai |
Tenth Plan |
State Plan |
Link Road |
64.36 |
0.00 |
64.36 |
15-Mar-04 |
15/12/2004 |
100% |
41.78 |
41.78 |
0.00 |
|
|
|
| 63 |
Construction of Truckable road from Rong Sadhu Gaon 2km.
[Lungkhiya] (LC = 17.45 lakh) |
Suk Deo Rai |
Tenth Plan |
State Plan |
Link Road |
53.59 |
0.00 |
53.59 |
15-Mar-04 |
15/12/2004 |
100% |
52.29 |
52.29 |
0.00 |
Work Closed |
|
|
| 64 |
Construction of truckable road from Rong to Khani Gaon 2Km. |
- |
|
State Plan |
Link Road |
43.13 |
0.00 |
43.13 |
6-Jun-04 |
6-Jun-06 |
100% |
20.18 |
20.18 |
0.00 |
in progress |
|
|
| 65 |
Compensation for Construction of Namchi-Nayabazar road to
Harrabotey Km 1st to 2nd |
Compensation |
|
State Plan |
Link Road |
10.07 |
0.00 |
10.07 |
- |
- |
|
3.39 |
3.39 |
0.00 |
|
|
|
| 66 |
Construction of Kitchen for PWD Guest House at Temi, South
Sikkim. |
Mr. Bindra Kumar Rai |
Tenth Plan |
State Plan |
Addl. Facilities |
11.01 |
0.00 |
11.01 |
2-Feb-07 |
8-Aug-07 |
95% |
0.00 |
0.00 |
0.00 |
in progress |
|
|
| 67 |
Construction of Link road from Ben-Thalbari to Mangley km
1st-14th ( LC = Rs. 73.56 lakh) |
Chumden Kaleon |
Tenth Plan |
State Plan |
New Road |
313.80 |
0.00 |
313.80 |
8-Dec-03 |
27-Dec-04 |
100% |
259.82 |
259.82 |
0.00 |
completed, final bill submitted |
|
|
| 68 |
Construction of truckable road from Ben to Namprik Km 1st. |
Chumden Kaleon |
Tenth Plan |
State Plan |
New Road |
20.85 |
0.00 |
20.85 |
2002 |
- |
100% |
20.85 |
20.85 |
0.00 |
completed, final bill submitted |
|
|
| 69 |
Construction of approach road to Khamdong Village. |
Bampoo Namgyal |
Tenth Plan |
State Plan |
New Road |
9.64 |
0.00 |
9.64 |
2002 |
- |
100% |
9.64 |
9.64 |
0.00 |
|
|
|
| 70 |
Construction of truckable road from Lingi Paiyong Govt. Jr. high
School Km 2nd (I/c 17.71 lac Comp.+2.62 Forest Comp) |
S.S.Dhakal |
Tenth Plan |
State Plan |
New Road |
78.11 |
0.00 |
78.11 |
2002 |
- |
79% |
44.92 |
44.92 |
0.00 |
|
|
|
| 71 |
Const. of motorable link road from upper Vok to Ung Raam (Water
falls) via Namplang and rabong village in Omchu |
Mr. B. Tsh. Bhutia |
Tenth Plan |
RSVY |
New Road |
318.31 |
180.00 |
138.31 |
22-Aug-05 |
21-Aug-07 |
85% |
234.40 |
54.40 |
180.00 |
in progress |
|
|
| 72 |
Construction of truckable
roads from Kholaghari to Jawbari Km 10th & 11th (14th Chain) |
Departmental |
Tenth Plan |
State Plan |
New Road |
44.09 |
0.00 |
44.09 |
2005 |
- |
90% |
25.54 |
25.54 |
0.00 |
|
|
|
| 73 |
Construction of Truckable Road from Assangthang to Salghari |
Compensation |
Eleventh Plan |
State Plan |
New Road |
54.87 |
0.00 |
54.87 |
2007 |
- |
|
40.00 |
40.00 |
0.00 |
|
|
|
| 74 |
New cutting of Sangmoo link road Km 4th |
Mr. K. Bhutia |
Tenth Plan |
State Plan |
Expansion |
6.97 |
0.00 |
6.97 |
1-Nov-97 |
|
- |
0.00 |
0.00 |
0.00 |
|
|
|
| 75 |
Extension of Truakable road from Ravangla Bining Road to
Tashiding Km 14th. |
Mr. Loden C. Bhutia |
Tenth Plan |
State Plan |
Expansion |
22.02 |
0.00 |
22.02 |
6-Jun-05 |
12-Dec-06 |
94% |
16.83 |
16.83 |
0.00 |
in progress |
|
|
| 76 |
Extension of Truakable road from Ravangla Bining Road to
Tashiding Km 15th. |
Mr. Lha T. Bhutia |
Tenth Plan |
State Plan |
Expansion |
20.89 |
0.00 |
20.89 |
6-Jun-05 |
13-Dec-06 |
94% |
12.01 |
12.01 |
0.00 |
in progress |
|
|
| 77 |
Extension of Truakable road from Ravangla Bining Road to
Tashiding Km 16th. |
Mr. Loden C. Bhutia |
|
State Plan |
Expansion |
22.63 |
0.00 |
22.63 |
6-Jun-05 |
14-Dec-06 |
95% |
9.90 |
9.90 |
0.00 |
in progress |
|
|
| 78 |
Extension of Truakable road from Ravangla Bining Road to
Tashiding Km 17th. |
Mr. Lha T. Bhutia |
Tenth Plan |
State Plan |
Expansion |
19.87 |
0.00 |
19.87 |
6-Jun-05 |
15-Dec-06 |
95% |
9.77 |
9.77 |
0.00 |
in progress |
|
|
| 79 |
Extension of Truakable road from Ravangla Bining Road to
Tashiding Km 18th. |
Mr. Lha T. Bhutia |
Tenth Plan |
State Plan |
Expansion |
19.31 |
0.00 |
19.31 |
6-Jun-05 |
16-Dec-06 |
97% |
5.60 |
5.60 |
0.00 |
in progress |
|
|
| 80 |
Construction of motorable road from Slap Village (Chettri Gaon)
km 1st and 2nd |
Mr. Lha T. Bhutia |
Tenth Plan |
State Plan |
Expansion |
38.02 |
0.00 |
38.02 |
9-Sep-06 |
2-Feb-07 |
76% |
21.40 |
21.40 |
0.00 |
in progress |
|
|
| 81 |
Surface strengthening & drainage on Yang-yang-Rangang road.
Km 2nd. Ch-12 |
Mr. S. B. Chamling |
Tenth Plan |
State Plan |
Expansion |
36.19 |
0.00 |
36.19 |
16-Feb-03 |
11-Jan-06 |
99% |
12.00 |
12.00 |
0.00 |
in progress |
|
|
| 82 |
Construction of Guest house at Yangang in South Sikkim. |
Mr. Pawan Kr. Agarwal |
Tenth Plan |
State Plan |
Addl. Facilities |
|
0.00 |
47.31 |
10-Oct-03 |
30-Jun-05 |
100% |
|
0.00 |
57.17 |
completed |
|
|
| 83 |
Construction of Link Road from Rangang to Yangang-Makha via
Majuwa : Km 1st and 2nd |
Mr. S. B. Chamling |
Tenth Plan |
State Plan |
Addl. Facilities |
62.36 |
0.00 |
62.36 |
1-Jan-05 |
10-Oct-05 |
94% |
53.95 |
0.00 |
53.95 |
in progress |
|
|
| 84 |
Construction of Link Road from Rangang to Yangang-Makha via
Majuwa : Km 3rd. |
Mr. Nar Bhd. Gurung |
Tenth Plan |
State Plan |
Addl. Facilities |
22.83 |
0.00 |
22.83 |
1-Jan-05 |
10-Oct-05 |
95% |
16.17 |
0.00 |
16.17 |
in progress |
|
|
| 85 |
Construction of truckable road from Kholaghari to Jaubari Km
10th & 11th (14 Chain). |
- |
Tenth Plan |
State Plan |
New Road |
44.09 |
0.00 |
44.09 |
- |
- |
90% |
39.87 |
39.87 |
0.00 |
in progress |
|
|
| 86 |
Construction of truckable road from Lingi Payong Govt. jr. high
School Km 2nd . |
Mr. S. S. Dhakal |
|
State Plan |
New Road |
57.78 |
0.00 |
57.78 |
1-Mar-03 |
28-Feb-04 |
90% |
27.21 |
27.21 |
0.00 |
in progress |
|
|
| 86 |
Construction of Kink road from Kateng Bokrang to Namthang South
Sikkim. |
Buddha Singh Tamang |
|
State Plan |
Link Road |
53.65 |
0.00 |
53.65 |
12-Dec-08 |
12-Dec-10 |
|
0.00 |
0.00 |
0.00 |
in progress |
|
|
| 87 |
Diversion of turning at Km 14 th to 18th on Ravangla - Zarong
Road in S-Sikkim |
Smt. Ratna Kum. Rai |
Tenth Plan |
State Plan |
Expansion |
104.72 |
0.00 |
104.72 |
Jun-05 |
Mar-08 |
87% |
54.11 |
54.11 |
0.00 |
in progress |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| D |
DISTRICT : WEST |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
CENTRAL SPONSORED
SCHEMES |
|
|
|
|
|
|
|
|
|
|
|
|
|
| 1 |
Repalacement of Rathong Suspension bridge by steel bridge on
Rimbi-Yoksum road. |
Mrs. S. Dolma Bhutia |
Tenth Plan |
NLCPR |
- |
327.57 |
327.57 |
0.00 |
2-Jun-05 |
31-Aug-06 |
97% |
262.01 |
0.00 |
262.01 |
In Progress |
|
|
| 2 |
Repalacement of Rimbi Suspension bridge by steel bridge on
Pelling - Rimbi road. |
Mr. Keshav Pradhan |
Tenth Plan |
NLCPR |
- |
2-Jun-05 |
31-Aug-06 |
90% |
In Progress |
|
|
| 3 |
Carpetting and surface improvement of Soreng Budang Road via
Malbassy Km 1st - 11th. |
Mr. Shankhar Agarwal |
Tenth Plan |
NLCPR |
Removal |
398.46 |
387.95 |
10.51 |
3-Mar-05 |
6-Jun-06 |
100% |
341.27 |
2.27 |
339.00 |
Work completed final bill under preparation |
|
|
| 4 |
Construction of premix carpetting /imp. Dentam Uttrey road Km
1st to 10th |
Mr. C.B. Subba |
Tenth Plan |
NLCPR |
- |
399.00 |
399.00 |
0.00 |
3-Mar-05 |
31-Aug-06 |
92% |
205.84 |
0.00 |
205.84 |
5th a/c bill paid to the contractor |
|
|
| 5 |
Surface imp/ carpetting i/c drainage works on Pelling Dentam
road Km 1st to 9th |
Mr. Anjani Kr. Agarwal |
Tenth Plan |
NLCPR |
- |
606.54 |
606.54 |
0.00 |
3-Mar-05 |
31-Aug-06 |
94% |
611.86 |
0.00 |
611.86 |
4th a/c bill paid |
|
|
| 6 |
Surface imp/ carpetting i/c drainage works on Pelling Dentam
road Km 18th to 20th |
CB Subba |
Tenth Plan |
NLCPR |
- |
91.30 |
91.30 |
0.00 |
3-Mar-05 |
31-Aug-06 |
99% |
78.00 |
0.00 |
78.00 |
4th a/c bill paid |
|
|
| 7 |
Surface imp/ carpetting i/c drainage works on Pelling Dentam
road Km 10th to 17th. |
Mr. Mahabir Pd. Agarwal |
Tenth Plan |
NLCPR |
- |
406.79 |
301.97 |
104.82 |
3-Mar-05 |
31-Aug-06 |
93% |
387.98 |
0.00 |
387.98 |
4th a/c bill paid |
|
|
| 8 |
Replacement of B.B. Lal Suspension Bridge on Pelling Dentam road
along Gyalshing Soreng Road. |
Mr. Mahabir Pd. Agarwal |
Tenth Plan |
NLCPR |
- |
200.30 |
200.30 |
0.00 |
3-Mar-05 |
31-Aug-06 |
96% |
75.07 |
0.00 |
75.07 |
In progress |
|
|
| 9 |
Slope stablization of Labling land slide on Yoksum - Tashiding
road |
Mrs Kabita Pradhan |
Tenth Plan |
NLCPR |
Removal |
149.57 |
127.52 |
3.92 |
22-Apr-05 |
21-Apr-06 |
100% |
2.05 |
2.05 |
0.00 |
Work Completed |
|
|
| 10 |
Slope stablization of Chorang land slide on Yoksum - Tashiding
road |
Mr. U. P. Bhutia (Kazi) |
Tenth Plan |
NLCPR |
Removal |
18.13 |
22-Apr-05 |
21-Apr-06 |
100% |
61.23 |
10.00 |
51.23 |
Work Completed |
|
|
| 11 |
Construction of strengthening draianage & carpetting of
Khanisherbong road fKm 1st -11th. |
Mr. B. L. Gurung |
Eleventh Plan |
NEC |
- |
486.36 |
486.36 |
0.00 |
3-Mar-07 |
9-Sep-08 |
45% |
144.11 |
0.00 |
144.11 |
In Progress |
|
|
| 12 |
Replacement of Ringyang
suspension bridge over Ringyang Khola on Soreng-Sombaria road. |
Mr. Sanjay Chandak |
Tenth Plan |
NEC |
- |
332.02 |
332.02 |
0.00 |
8-Aug-05 |
10-Oct-06 |
100% |
328.94 |
0.00 |
328.94 |
completed |
|
|
| 13 |
Strengthening draianage & carpetting of Sombaria Hilley road
Km 1st- 26th |
Mr. Kamal Kr. Rai |
Tenth Plan |
NEC |
- |
845.68 |
845.68 |
0.00 |
1-Nov-06 |
10-Oct-08 |
66% |
208.01 |
0.00 |
208.01 |
In progress |
|
|
| 14 |
Strengthening and carpetting, protection and drainage of
Bermiock Legship road Km. 1st to 9th |
Mr. Atul Dhanotia |
Tenth Plan |
NEC |
- |
449.46 |
449.46 |
0.00 |
16-Feb-06 |
15-Feb-08 |
86% |
194.24 |
0.00 |
194.24 |
In progress |
|
|
| 15 |
Surface improvement and strengthening and premix carpetting of
Rimbi Yoksum road Km 1st to 21.70. |
Mr. K. N. Bhutia |
Tenth Plan |
EI |
- |
315.48 |
219.37 |
96.11 |
7-Feb-04 |
6-Aug-05 |
87% |
248.86 |
50.82 |
198.04 |
In Progress |
|
|
| 16 |
Carpetting of Gyalshing Pelling Road, W.Sikkim (EI) |
Mr. K. N. Bhutia |
Tenth Plan |
EI |
- |
87.86 |
87.86 |
0.00 |
7-Feb-04 |
6-Aug-05 |
100% |
87.86 |
0.00 |
87.86 |
Work Completed |
|
|
| 17 |
Widening carpetting & drainage system on Legship - Tashiding road Km 1st-6th. |
Mr. P. K. Agarwal |
Tenth Plan |
NABARD |
- |
73.82 |
73.82 |
0.00 |
2-Jan-01 |
12-May-01 |
95% |
66.86 |
0.00 |
66.86 |
Work Completed |
|
|
| 18 |
Widening carpetting & drainage system on Legship - Tashiding
road Km 7th - 12th. |
Mr. S. D. Bhutia |
Tenth Plan |
NABARD |
- |
66.77 |
66.77 |
0.00 |
2-Jan-01 |
12-May-01 |
98% |
56.41 |
0.00 |
56.41 |
Work Completed |
|
|
| 19 |
Surface imrovement & P/W from Lunchuk to Salangdang road Km
1st-4th. |
Mr. P.K. Chandak |
Tenth Plan |
NABARD |
Expansion |
128.03 |
84.32 |
43.71 |
6-Jun-05 |
6-Jun-06 |
100% |
127.21 |
43.71 |
83.50 |
completed |
|
|
| 20 |
Link Road from Alpine CF to Kaluk Dentam Road |
- |
Tenth Plan |
NABARD |
- |
96.77 |
96.77 |
0.00 |
- |
- |
- |
0.00 |
0.00 |
0.00 |
completed |
|
|
| 21 |
Construction of 65m Span Steel Bridge over Rangit river in
between Mengnem & Phamtam |
Mr. U. P. Bhutia (Kazi) |
Tenth Plan |
RSVY |
- |
272.78 |
148.93 |
123.85 |
23-Nov-05 |
22-May-07 |
60% |
136.56 |
0.00 |
136.56 |
In Progress |
|
|
| 22 |
Construction of link road from Kaluk to Lower Shribadam via
Samdong Km 1st to 5th. |
Mr. K. T. Bhutia |
Tenth Plan |
RSVY |
- |
167.87 |
150.00 |
17.87 |
12-Dec-05 |
6-Jun-07 |
100% |
159.24 |
9.24 |
150.00 |
Final Bill |
|
|
| 23 |
Turning improvement in front of SNT Booking Office &
replacement of drainage syatem at outskirt of Gyalshing Bazar. |
Mrs. Amrita Gurung |
Tenth Plan |
MP LAPS |
- |
9.51 |
0.00 |
9.51 |
5-Dec-06 |
4-Mar-07 |
100% |
4.47 |
0.00 |
4.47 |
Work Completed, final bill submitted |
|
|
| 24 |
App. Road to Rincheypong Gompa / Shreda from Rinchepong Dak
Bunglow Road (Km 1st ch 17th ) |
Mr. D. Lachi Bhutia |
Tenth Plan |
MP LADS |
- |
15.00 |
15.00 |
0.00 |
16-Feb-06 |
15-Feb-08 |
85% |
9.90 |
0.00 |
9.90 |
In progress |
|
|
| 25 |
Restoration of damages, Slip clearence, Drainage &surface
improvement works of Geythang-Karmatar road, Singshore diversion road and
Utterey-Sopakha road in West Sikkim. |
P.K.Subba |
|
BADP |
- |
300.00 |
300.00 |
0.00 |
1-Nov-08 |
31-Oct-09 |
20% |
0.00 |
0.00 |
0.00 |
Agreement preparation |
|
|
| |
STATE PLAN |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 25 |
Providing Box drain including Check wall below approach road to
Pelling Helipad. |
Suresh Subba |
Tenth Plan |
State Plan |
Removal |
11.25 |
0.00 |
11.25 |
|
|
100% |
9.61 |
9.61 |
0.00 |
|
|
|
| 26 |
Widening carpetting & drainage system on Legship - Tashiding
road Km 1st - 12th. |
Mr. P.K.Agarwal & Mr. S. D. Bhutia |
Ninth Plan |
State Plan |
Removal |
261.02 |
0.00 |
261.02 |
2-Jan-01 |
12-May-01 |
100% |
256.11 |
0.00 |
256.11 |
Work Completed, Balance qty of work to be closed(Revised
66.86+65.98) |
|
|
| 27 |
Carpetting of Legship Gyalshing Road km 1st-3rd |
N.B.Dahal |
Ninth Plan |
State Plan |
Removal |
24.94 |
0.00 |
24.94 |
25-Jun-93 |
20-Mar-96 |
100% |
21.75 |
21.75 |
0.00 |
|
|
|
| 28 |
Consruction of 13m Span RCC Bridges at Ribing, Khola on Chakhung
- Khansirbong road. |
Mr. N.T. Tamang |
Ninth Plan |
State Plan |
Removal |
19.28 |
0.00 |
19.28 |
10-Oct-98 |
5-May-99 |
100% |
8.50 |
8.50 |
0.00 |
Work Completed, final bill to be paid |
|
|
| 29 |
Widening, surface improvement, premix carpetting of Sombaria
Puretar Km 6th to 13th |
Mr. Amrit Subba, Prakash Subba, S.H. Sherpa, P.D. Sherpa |
Tenth Plan |
- |
Removal |
149.37 |
0.00 |
149.37 |
1-Jan-05 |
10-Oct-06 |
100% |
77.99 |
77.99 |
0.00 |
Work Completed, final bill to be paid |
|
|
| 33 |
Technical Surveillance and rehabilitation of Saingshore
Suspensiopn Bridge along Dentam Uttarey Road |
AS Bumper |
|
State Plan |
Replacement |
110.00 |
0.000 |
110.00 |
7-Jun-08 |
7-Nov-06 |
60% |
77.00 |
77.00 |
0.00 |
1st a/c bill paid |
|
|
| 34 |
Construction of 25m span suspension bridge at Reshi Khola on
Shribadam Deyathang road. |
Mr. B.R. Sharma |
Tenth Plan |
State Plan |
Replacement |
45.03 |
0.00 |
45.03 |
3-Mar-05 |
3-Mar-07 |
80% |
27.16 |
27.16 |
0.00 |
In Progress |
|
|
| 35 |
Renovation of 320"0" span suspension bridge over Ramam
river at Jorethang |
Mr. Jagdish Agarwal. |
Tenth Plan |
- |
Replacement |
15.93 |
0.00 |
15.93 |
5-May-06 |
6-Jun-06 |
100% |
14.84 |
14.84 |
0.00 |
Revised Estimate
in Process |
|
|
| 36 |
Renovation of Singsore Bridge along Dentam - Utterey Road |
|
Eleventh Plan |
|
Replacement |
73.41 |
0.00 |
73.41 |
2007 |
- |
- |
0.00 |
0.00 |
0.00 |
|
|
|
| 37 |
Approach road to suspension bridge over Ramam river at Jorethang |
Mrs. Sapana Sunuwar |
Tenth Plan |
- |
Replacement |
1.88 |
0.00 |
1.88 |
12-Dec-05 |
2-Feb-06 |
100% |
1.88 |
1.88 |
0.00 |
completed |
|
|
| 40 |
20mm thick premix crpetting along link road to Manglabaria Km
1st to 3rd. |
Mrs. Karma Uden Bhutia |
Tenth Plan |
State Plan |
Expansion |
27.72 |
0.00 |
27.72 |
23-Dec-02 |
22-Apr-03 |
100% |
25.74 |
25.74 |
0.00 |
Final bill uner procees |
|
|
| 41 |
Construction of Motorable Road from Reshi-Khaniserbong, Km 7th-
8th. |
|
Tenth Plan |
State Plan |
Expansion |
20.61 |
0.00 |
20.61 |
- |
- |
70% |
8.09 |
8.09 |
0.00 |
|
|
|
| 42 |
Premix carpetting & Improvement of Pelling - Rimbi road Km
1st-12th .[Additional Sanction] |
K.N.Bhutia, P.T.Bhutia, S.W.Bhutia |
Tenth Plan |
State Plan |
Expansion |
16.12 |
0.00 |
16.12 |
- |
- |
100% |
12.36 |
12.36 |
0.00 |
|
|
|
| 43 |
Premix carpetting works on Gyalshing Pelling road Km 1st &
9th. [State Share of EI] |
Phurden Lama & Palchen Yongda |
Tenth Plan |
State Plan |
Expansion |
146.37 |
0.00 |
146.37 |
15-Oct-03 |
14-Jul-04 |
100% |
134.19 |
134.19 |
0.00 |
|
|
|
| 44 |
Construction &
Protective wall on Kalej Khola Power House to Uttarey Road. |
|
Tenth Plan |
State Plan |
Expansion |
3.99 |
0.00 |
3.99 |
- |
- |
|
0.00 |
0.00 |
0.00 |
|
|
|
| 45 |
Extension of Ribdi Bharang road Km 3rd to 4th.[9th plan] |
N.T.Sherpa |
Ninth Plan |
State Plan |
Expansion |
18.96 |
0.00 |
18.96 |
Feb'99 |
May'2002 |
100% |
17.97 |
17.97 |
0.00 |
|
|
|
| 46 |
Premix carpetting, drainage & Protective Works on
Sombaria-Soreng road Km 1st-8th. |
C.B.Subba |
Tenth Plan |
State Plan |
Expansion |
181.90 |
0.00 |
181.90 |
25-Feb-04 |
24-Mar-05 |
100% |
168.90 |
168.90 |
0.00 |
|
|
|
| 47 |
Land/Damaged Compensation of Link Road to Gitang - Karmatar |
Compensation |
|
State Plan |
Expansion |
2.65 |
0.00 |
2.65 |
- |
- |
100% |
2.65 |
2.65 |
0.00 |
|
|
|
| 48 |
Construction of Link Road from Thongling to Lower Dodak Km 1st |
|
|
State Plan |
Expansion |
35.37 |
0.00 |
35.37 |
- |
- |
100% |
29.87 |
29.87 |
0.00 |
|
|
|
| 49 |
Premix carpetting & improvement of Pelling Rimbi Road Km
1st-12th (Additional Sanction) |
Mr. K.N.Bhutia, Mr. P.T.Bhutia, Mr. S.W.Bhutia |
|
State Plan |
Expansion |
1,155.42 |
1,050.60 |
104.82 |
- |
- |
100% |
839.72 |
12.38 |
827.34 |
Work Completed |
|
|
| 50 |
Construction of Link Road from Angden Gumpa to Upper Rumbuk
School Km 1st. |
Mr. P. T. Sherpa |
Ninth Plan |
State Plan |
Expansion |
7.68 |
0.00 |
7.68 |
3-Mar-95 |
3-Mar-96 |
100% |
5.62 |
5.62 |
0.00 |
Work Completed, Final bill under process |
|
|
| 51 |
Carpetting of Ribdi Bharang
Road km 1st |
Mr.N. T. Sherpa |
Ninth Plan |
State Plan |
Expansion |
8.17 |
0.00 |
8.17 |
2-Feb-99 |
5-May-02 |
100% |
8.17 |
8.17 |
0.00 |
completed |
|
|
| 52 |
Carpetting and P/W on Sombaria
Soreng Road Km 1st - 8th. |
Mr. C. B. Subba |
Tenth Plan |
- |
Expansion |
181.90 |
0.00 |
181.90 |
2-Feb-04 |
3-Mar-05 |
100% |
168.90 |
168.90 |
0.00 |
completed |
|
|
| 53 |
Construction of link road from Kongri -Labdong road Km 1st -
5th. |
Mr. B.P. Pradhan, Mr.
O.P. Pradhan |
Ninth Plan |
State Plan |
Link Road Plan |
26.38 |
0.00 |
26.38 |
12-Jun-96 |
11-Apr-97 |
100% |
15.69 |
15.69 |
0.00 |
Work Completed |
|
|
| 54 |
Construction of Link Road from Chota Samdong to Majuwa km 3rd. |
Land Compensation |
Eleventh Plan |
State Plan |
Link Road Plan |
17.57 |
0.00 |
17.57 |
Sept.2007 |
- |
100% |
17.57 |
17.57 |
0.00 |
|
|
|
| 55 |
Construction of New road from Rinchenpong Yangsum to Ambetar Km
1st - 4th. |
Land Compensation |
Ninth Plan |
State Plan |
New Road |
47.14 |
0.00 |
47.14 |
Oct-07 |
- |
- |
25.00 |
25.00 |
0.00 |
|
|
|
| 56 |
Construction of motorable road from Pokhari to Karjee Km 1st |
Mr. L.D. Bhutia |
Tenth Plan |
State Plan |
New Road |
36.28 |
0.00 |
36.28 |
27-Feb-03 |
26-Dec-03 |
98% |
22.97 |
22.97 |
0.00 |
In Progress |
|
|
| 57 |
Construction of motorable road from Pokhari to Karjee Km 2nd |
Mr. G.S. Subbba |
Tenth Plan |
State Plan |
New Road |
40.86 |
0.00 |
40.86 |
27-Feb-03 |
26-Dec-03 |
100% |
32.28 |
32.28 |
0.00 |
Work Completed |
|
|
| 58 |
Construction of motorable road from Pokhari to Karjee Km 3rd |
Mr. G.S. Subbba |
Tenth Plan |
State Plan |
New Road |
33.08 |
0.00 |
33.08 |
27-Feb-03 |
26-Dec-03 |
100% |
30.59 |
30.59 |
0.00 |
Work Completed |
|
|
| 59 |
Construction of motorable road from Pokhari to Karjee Km 4th |
Mr. B.P. Pradhan |
Tenth Plan |
State Plan |
New Road |
28.08 |
0.00 |
28.080 |
27-Feb-03 |
26-Dec-03 |
98% |
20.84 |
20.84 |
0.00 |
In Progress |
|
|
| 60 |
Construction of motorable road from U/Labdong to L/Labdong Km
1st. |
Mr. D.K. Pradhan |
Tenth Plan |
State Plan |
New Road |
29.68 |
0.00 |
29.680 |
27-Feb-03 |
26-Dec-03 |
100% |
20.14 |
20.14 |
0.00 |
Work Completed |
|
|
| 61 |
Construction of motorable road from U/Labdong to L/Labdong Km
2nd. |
Mr. G.S. Subbba |
Tenth Plan |
State Plan |
New Road |
31.44 |
0.00 |
31.440 |
27-Feb-03 |
26-Dec-03 |
100% |
20.35 |
20.35 |
0.00 |
Work Completed |
|
|
| 62 |
Construction of motorable road from U/Labdong to L/Labdong Km
3rd. |
Mr. G.S. Subbba |
Tenth Plan |
State Plan |
New Road |
30.95 |
0.00 |
30.950 |
27-Feb-03 |
26-Dec-03 |
98% |
27.33 |
27.33 |
0.00 |
In Progress |
|
|
| 63 |
Construction of motorable road from U/Labdong to L/Labdong Km
4th. |
Mrs. Sabita Subba |
Tenth Plan |
State Plan |
New Road |
|