| PROGRESS REPORT FOR QUARTER ENDING MARCH 2009 |
|
|
| A. |
Identification
Particulars. |
|
|
|
|
|
| 1 |
Name of
Project/Scheme/Programme |
: |
Surface
Improvement/Widening, Carpetting & Bridge Replacement on Gyalshing -
Soreng Road (upto Dentam). |
|
|
|
a. Pelling - Dentam road (20 Km) & |
|
|
|
b. Replacement of
existing B.B.Lal suspension Bridge over Kalej Khola. |
| 2 |
Location |
|
: |
State |
|
Sikkim |
District |
: |
West |
| 3 |
Date of Approval of
Project/Scheme |
: |
March 2004. |
|
| 4 |
Approved Cost |
|
: |
Rs. 1250.96
lakhs.-NLCPR |
|
| 5 |
Date of completion of
Project/Scheme |
: |
|
|
(i) Stipulated date as
per agreement |
: |
3/9/2007 |
|
|
(ii) Actual date |
|
: |
|
| 6. |
Executing Agency
{State Govt. other agency (specify) |
: |
Roads & Bridges
Department, Government of Sikkim (through government
enlisted contractor). |
|
|
| B. |
Progress of Preliminary
Activities |
|
| Prelimianry Project Activity |
Date |
Remarks |
| Agreement for project execution |
|
|
| (i) |
Preparation of Draft for Bids |
|
|
| (ii) |
Invitation for Bids |
2/08/04 |
|
| (iii) |
Evaluation of Bids |
17/08/04 |
|
| (iv) |
Selection of Agency |
31/01/05 |
|
| (v) |
Awards of works |
16/02/05 |
|
|
|
| C. |
Physical Progress
(Descriptive) |
|
| Sl.No. |
Activities/Major
Items of Work |
Physical
Progress during the Quarter |
Cumulative
Physical Progress |
| A |
Pelling Dentam Road (20Kms) |
| 1 |
Earthwork |
10% |
100% |
| 2 |
Widening/Protection Works |
- |
95% |
| 3 |
Pavement Works |
10% |
90% |
| 4 |
Drainage (hill side) |
10% |
90% |
| 5 |
Sign Board, Kilometer posts etc. |
- |
- |
| TOTAL |
94% |
| B |
Replacement of B.B. Lal Bridge |
| 1 |
Abutment |
|
100% |
| 2 |
Decking |
- |
- |
| 3 |
Steel Girders & accessories |
- |
100% |
| 4 |
Erection bridge girder |
- |
100% |
| 5 |
River training works |
10% |
70% |
| 6 |
Diversion |
- |
100% |
| TOTAL |
96% |
| D. |
Financial Progress |
|
| Sl.No. |
Activities/Major Items of Work |
During Quarter |
Cumulative
Expenditure |
Reason of
Variation |
| A. |
Pelling - Dentam Road (20Kms) |
0.00 |
1045.24 |
|
| B. |
Replacement of B.B.Lal Bridge |
0.00 |
157.55 |
|
| Total Actual Expenditure |
Nil |
1202.79 |
|
|
|
| E. |
Progress of Release of
Fund. |
|
| Sl.No. |
Release of Funds/Payments |
During the Quarter |
Cumulative Amount |
| Grant |
Loan |
Total |
| 1 |
Central
Government to State Government. |
|
0.00 |
|
1099.05 |
103.78 |
|
1202.83 |
| 2 |
State
Government to concerned Department. |
|
0.00 |
|
|
|
|
1202.83 |
| 3 |
Actual disbursement
to contractors/beneficiaries etc |
|
0.00 |
|
|
|
|
1202.79 |
|
|
|
|
|
|
|
|
| F. |
Key Parameters. |
|
|
|
| 1 |
Overall physical
progress (%) |
|
: |
a. Road Work : |
94% |
|
|
|
|
|
b. Bridge Work : |
96% |
|
|
|
|
|
|
| 2 |
Total funds received
from NLCPR |
|
: |
Rs 1099.05 lakhs |
|
| 3 |
Expenditure incurred out
of (2) above |
|
: |
Rs. 1202.79 lakh |
|
| 4 |
Anticipated completion
date of the projects/scheme |
: |
30/06/2009 |
|
|
|
| G. |
Qualitative observations
on the implementation of the project/scheme: |
|
| 1 |
Follow up action on
issues raised in previous quarter |
: |
|
Nil |
|
| 2 |
Major
constraints/problems encountered |
|
: |
|
|
|
| 3 |
Latest inspection notes
on the project containing the following: |
|
|
|
(a) |
Is the copy of DPR
availavle at site? |
|
: |
|
Yes |
|
|
(b) |
What are the
quantitative achievements against the DPR |
: |
|
|
|
|
(c) |
What are the
qualitative assessment of project implementation |
: |
|
|
|
|
(d) |
Suggestive remedial
action to be taken by concerned department/agency may be indicated |
: |
|
Nil |
|
|
(e) |
Is any specific item
pending for clearance with any State Government Authority |
: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Signature by the Certifying Officer |
|
Signature
by the Nodal Officer |
|
| Name |
|
Name |
|
| Designation |
Superintending Engineer |
Designation |
Addl. Chief Engineer |
| Date |
|
Date |
|
| Place |
Gangtok |
Place |
Gangtok |
| Office Seal |
|
Office Seal |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| PROGRESS REPORT
FOR QUARTER ENDING MARCH 2009 |
|
|
| A. |
Identification
Particulars. |
|
|
|
|
|
| 1 |
Name of
Project/Scheme/Programme |
: |
Carpeting/Surface
Improvement of Dentam–Uttarey Road (10 kms) |
|
|
|
|
|
|
|
| 2 |
Location |
|
: |
State |
|
Sikkim |
District |
: |
West |
| 3 |
Date of Approval of
Project/Scheme |
: |
July 2004. |
|
| 4 |
Approved Cost |
|
: |
Rs. 399.00
lakhs.-NLCPR |
|
| 5 |
Date of completion of
Project/Scheme |
: |
|
|
(i) Stipulated date as
per agreement |
: |
10/3/2006 |
|
|
(ii) Actual date |
|
: |
|
|
| 6. |
Executing Agency
{State Govt. other agency (specify) |
: |
Roads &
Bridges Department, Government of Sikkim (through
government enlisted contractor). |
|
|
|
|
|
| B. |
Progress of Preliminary
Activities |
|
| Prelimianry Project Activity |
Date |
Remarks |
| Agreement for project execution |
|
|
| (i) |
Preparation of Draft for Bids |
|
|
| (ii) |
Invitation for Bids |
|
|
|
| (iii) |
Evaluation of Bids |
|
|
|
| (iv) |
Selection of Agency |
|
17/02/2005 |
|
| (v) |
Awards of works |
|
10/3/2005 |
|
|
|
| C. |
Physical Progress
(Descriptive) |
|
| Sl.No. |
Activities/Major
Items of Work |
Physical
Progress during the Quarter |
Cumulative
Physical Progress |
| A |
|
|
|
| 1 |
Widening/Protective worksEarthwork |
|
0% |
|
|
100% |
| 2 |
Pavement Works |
|
10% |
|
|
100% |
| 3 |
Drainage Works |
|
|
|
|
|
| |
i) Hill
Side Drain |
|
0% |
|
|
100% |
| |
ii) Cross Drain |
|
0% |
|
|
| 4 |
Culvert |
|
0% |
|
|
| 5 |
Signboards, kilometer post etc |
|
|
|
|
|
| |
|
|
|
|
|
|
| TOTAL |
|
Nil |
|
|
100% |
| D. |
Financial Progress |
|
| Sl.No. |
Activities/Major Items
of Work |
|
During Quarter |
Cumulative Expenditure |
Reasons of
Variation |
| A |
|
|
|
|
|
| 1 |
Widening/Protective worksEarthwork |
|
|
57.14 |
|
|
| 2 |
Pavement Works |
|
|
108.11 |
|
|
| 3 |
Drainage Works |
|
|
|
|
|
| |
i) Hill
Side Drain |
|
|
64.38 |
|
|
| |
ii) Cross Drain |
|
|
|
|
|
| 4 |
Culvert |
|
|
3.49 |
|
|
| 5 |
Signboards, kilometer post etc |
|
|
7.41 |
|
|
| 6 |
Escallation |
|
|
20.24 |
|
|
| 7 |
Mobilization advance |
|
|
0.58 |
|
|
| 8 |
Quality Control |
|
|
9.40 |
|
|
| 9 |
Contingency |
|
|
16.05 |
|
|
| 10 |
Miscellaneous works |
|
|
8.61 |
|
|
| TOTAL |
|
|
295.41 |
|
|
| E. |
Progress of Release of
Fund. |
|
| Sl.No. |
Release of Funds/Payments |
During the Quarter |
Cumulative Amount |
| Grant |
Loan |
Total |
| 1 |
Central
Government to State Government. |
|
0.00 |
|
280.00 |
15.56 |
|
295.56 |
| 2 |
State
Government to concerned Department. |
|
0.00 |
|
|
|
|
295.56 |
| 3 |
Actual disbursement
to contractors/beneficiaries etc |
|
0.00 |
|
|
|
|
295.41 |
|
|
| F. |
Key Parameters. |
|
|
|
| 1 |
Overall physical
progress (%) |
|
: |
100% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 2 |
Total funds received
from NLCPR |
|
: |
Rs. 280.00 lakh |
|
| 3 |
Expenditure incurred out
of (2) above |
|
: |
Rs 295.41 lakh |
|
| 4 |
Anticipated completion
date of the projects/scheme |
: |
Completed |
|
|
|
| G. |
Qualitative observations
on the implementation of the project/scheme: |
|
|
|
|
|
|
|
|
|
|
|
| 1 |
Follow up action on
issues raised in previous quarter |
: |
|
Nil |
|
| 2 |
Major
constraints/problems encountered |
|
: |
|
|
| 3 |
Latest inspection notes
on the project containing the following: |
|
|
(a) |
Is the copy of DPR
availavle at site? |
|
: |
|
Yes |
|
|
(b) |
What are the
quantitative achievements against the DPR |
: |
|
|
|
(c) |
What are the
qualitative assessment of project implementation |
: |
|
|
|
(d) |
Suggestive remedial
action to be taken by concerned department/agency may be indicated |
: |
|
Nil |
|
|
(e) |
Is any specific item
pending for clearance with any State Government Authority |
: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Signature by the Certifying Officer |
|
Signature
by the Nodal Officer |
|
| Name |
|
Name |
|
| Designation |
Superintending Engineer |
Designation |
Addl. Chief Engineer |
| Date |
|
Date |
|
| Place |
Gangtok |
Place |
Gangtok |
| Office Seal |
|
Office Seal |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| PROGRESS REPORT
FOR QUARTER ENDING MARCH 2009 |
|
|
| A. |
Identification
Particulars. |
|
|
|
|
|
| 1 |
Name of
Project/Scheme/Programme |
: |
Construction
of Goshkhan Dara Bridge over river Teesta at
Singtam |
|
|
|
|
|
|
|
| 2 |
Location |
|
: |
State |
|
Sikkim |
District |
: |
West |
| 3 |
Date of Approval of
Project/Scheme |
: |
July 2004. |
|
| 4 |
Approved Cost |
|
: |
Rs. 1337.57
lakhs.-NLCPR |
|
| 5 |
Date of completion of
Project/Scheme |
: |
|
|
(i) Stipulated date as
per agreement |
: |
|
|
|
(ii) Actual date |
|
: |
|
|
| 6. |
Executing Agency
{State Govt. other agency (specify) |
: |
Roads &
Bridges Department, Government of Sikkim (through
government enlisted contractor). |
|
|
|
|
|
| B. |
Progress of Preliminary
Activities |
|
| Prelimianry Project Activity |
Date |
Remarks |
| Agreement for project execution |
|
|
| (i) |
Preparation of Draft for Bids |
|
|
| (ii) |
Invitation for Bids |
|
|
|
| (iii) |
Evaluation of Bids |
|
|
|
| (iv) |
Selection of Agency |
|
|
|
| (v) |
Awards of works |
|
|
|
|
|
| C. |
Physical Progress
(Descriptive) |
|
| Sl.No. |
Activities/Major
Items of Work |
Physical
Progress during the Quarter |
Cumulative
Physical Progress |
| A |
|
|
|
| 1 |
Site Clearance |
|
- |
|
|
100% |
| 2 |
Earthwork |
|
- |
|
|
100% |
| 3 |
Pavement, approach & River training |
|
|
|
|
20% |
| 4 |
Drainage & Protective works |
|
- |
|
|
50% |
| 5 |
Bridge work |
|
- |
|
|
35% |
| TOTAL |
|
Nil |
|
|
45% |
|
| D. |
Financial Progress |
|
| Sl.No. |
Activities/Major Items
of Work |
|
During Quarter |
Cumulative Expenditure |
Reasons of
Variation |
| A |
|
|
|
|
|
| 1 |
Site Clearance |
|
Nil |
|
|
|
| 2 |
Earthwork |
|
Nil |
|
|
|
| 3 |
Pavement, approach & River training |
|
Nil |
468.00 |
|
|
| 4 |
Drainage & Protective works |
|
Nil |
|
|
|
| 5 |
Bridge work |
|
Nil |
|
|
|
| TOTAL |
|
Nil |
468.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| E. |
Progress of Release of
Fund. |
|
| Sl.No. |
Release of Funds/Payments |
During the Quarter |
Cumulative Amount |
| Grant |
Loan |
Total |
| 1 |
Central
Government to State Government. |
|
|
|
839.70 |
93.30 |
|
933.00 |
| 2 |
State
Government to concerned Department. |
|
|
|
|
|
|
933.00 |
| 3 |
Actual disbursement
to contractors/beneficiaries etc |
|
|
|
|
|
|
468.00 |
|
|
|
|
|
|
|
|
|
| F. |
Key Parameters. |
|
|
|
| 1 |
Overall physical
progress (%) |
|
: |
45% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 2 |
Total funds received
from NLCPR |
|
: |
Rs. 839.70 lakh |
|
| 3 |
Expenditure incurred out
of (2) above |
|
: |
Rs. 468.00 lakh |
|
| 4 |
Anticipated completion
date of the projects/scheme |
: |
30/12/2009 |
|
|
|
| G. |
Qualitative observations
on the implementation of the project/scheme: |
|
|
|
|
|
|
|
|
|
|
|
| 1 |
Follow up action on
issues raised in previous quarter |
: |
|
Nil |
|
| 2 |
Major
constraints/problems encountered |
|
: |
|
|
|
| 3 |
Latest inspection notes
on the project containing the following: |
|
|
|
(a) |
Is the copy of DPR
availavle at site? |
|
: |
|
Yes |
|
|
(b) |
What are the
quantitative achievements against the DPR |
: |
|
45% |
|
|
(c) |
What are the
qualitative assessment of project implementation |
: |
|
|
|
|
(d) |
Suggestive remedial
action to be taken by concerned department/agency may be indicated |
: |
|
Nil |
|
|
(e) |
Is any specific item
pending for clearance with any State Government Authority |
: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Signature by the Certifying Officer |
|
Signature
by the Nodal Officer |
|
| Name |
|
Name |
|
| Designation |
Superintending
Engineer |
Designation |
Addl. Chief Engineer |
| Date |
|
Date |
|
| Place |
Gangtok |
Place |
Gangtok |
| Office Seal |
|
Office Seal |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| PROGRESS REPORT
FOR QUARTER ENDING MARCH 2009 |
|
|
| A. |
Identification
Particulars. |
|
|
|
|
|
| 1 |
Name of
Project/Scheme/Programme |
: |
Carpeting/Surface
Improvement,Protective works & Drainage
on Namchi – Rabongla Road (26kms) in South Sikkim. |
|
|
|
|
|
|
|
| 2 |
Location |
|
: |
State |
|
Sikkim |
District |
: |
West |
| 3 |
Date of Approval of
Project/Scheme |
: |
July 2004. |
|
| 4 |
Approved Cost |
|
: |
Rs. 1207.00 lakhs.-NLCPR |
|
| 5 |
Date of completion of
Project/Scheme |
: |
|
|
(i) Stipulated date as
per agreement |
: |
|
|
|
(ii) Actual date |
|
: |
|
|
| 6. |
Executing Agency
{State Govt. other agency (specify) |
: |
Roads &
Bridges Department, Government of Sikkim (through
government enlisted contractor). |
|
|
|
|
|
| B. |
Progress of Preliminary
Activities |
|
| Prelimianry Project Activity |
Date |
Remarks |
| Agreement for project execution |
|
|
| (i) |
Preparation of Draft for Bids |
|
|
| (ii) |
Invitation for Bids |
|
8/8/2004 |
|
| (iii) |
Evaluation of Bids |
|
|
|
| (iv) |
Selection of Agency |
|
|
|
| (v) |
Awards of works |
|
8/12/2004 |
|
|
|
| C. |
Physical Progress
(Descriptive) |
|
| Sl.No. |
Activities/Major
Items of Work |
Physical
Progress during the Quarter |
Cumulative
Physical Progress |
| A |
|
|
|
| 1 |
Earthwork (widening) |
|
|
|
|
100% |
| 2 |
Protective works |
|
|
|
|
100% |
| 3 |
Pavement works |
|
10% |
|
|
99% |
| 4 |
Drainage & Protective works |
|
|
|
|
|
| 5 |
a. Hillside drain |
|
10% |
|
|
99% |
| |
b. Cross drains |
|
|
|
|
100% |
| 6 |
Signboards etc |
|
|
|
|
100% |
| TOTAL |
|
|
|
|
99% |
|
| D. |
Financial Progress |
|
| Sl.No. |
Activities/Major Items
of Work |
|
During Quarter |
Cumulative Expenditure |
Reasons of
Variation |
| A |
|
|
|
|
|
| 1 |
Earthwork (widening) |
|
Nil |
|
|
|
| 2 |
Protective works |
|
Nil |
|
|
|
| 3 |
Pavement works |
|
Nil |
1164.19 |
|
|
| 4 |
Drainage & Protective works |
|
Nil |
|
|
|
| 5 |
a. Hillside drain |
|
Nil |
|
|
|
| |
b. Cross drains |
|
Nil |
|
|
|
| 6 |
Signboards etc |
|
Nil |
|
|
|
| TOTAL |
|
Nil |
1164.19 |
|
|
|
|
|
|
|
|
|
|
|
|
| E. |
Progress of Release of
Fund. |
|
| Sl.No. |
Release of Funds/Payments |
During the Quarter |
Cumulative Amount |
| Grant |
Loan |
Total |
| 1 |
Central
Government to State Government. |
|
0.00 |
|
1088.08 |
74.01 |
|
1162.09 |
| 2 |
State
Government to concerned Department. |
|
0.00 |
|
|
|
|
1162.09 |
| 3 |
Actual disbursement
to contractors/beneficiaries etc |
|
0.00 |
|
|
|
|
1164.19 |
|
|
|
|
|
|
|
| F. |
Key Parameters. |
|
|
|
| 1 |
Overall physical
progress (%) |
|
: |
99% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 2 |
Total funds received
from NLCPR |
|
: |
Rs .1088.08 lakh |
|
| 3 |
Expenditure incurred out
of (2) above |
|
: |
Rs .1164.19 lakh |
|
| 4 |
Anticipated completion
date of the projects/scheme |
: |
30/05//2009 |
|
|
|
| G. |
Qualitative observations
on the implementation of the project/scheme: |
|
|
|
|
|
|
|
|
|
|
|
| 1 |
Follow up action on
issues raised in previous quarter |
: |
|
Nil |
|
| 2 |
Major
constraints/problems encountered |
|
: |
|
|
|
| 3 |
Latest inspection notes
on the project containing the following: |
|
|
|
(a) |
Is the copy of DPR
availavle at site? |
|
: |
|
Yes |
|
|
(b) |
What are the
quantitative achievements against the DPR |
: |
|
99% |
|
|
(c) |
What are the
qualitative assessment of project implementation |
: |
|
|
|
|
(d) |
Suggestive remedial
action to be taken by concerned department/agency may be indicated |
: |
|
Nil |
|
|
(e) |
Is any specific item
pending for clearance with any State Government Authority |
: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Signature by the Certifying Officer |
|
Signature
by the Nodal Officer |
|
| Name |
|
Name |
|
| Designation |
Superintending Engineer |
Designation |
Addl. Chief Engineer |
| Date |
|
Date |
|
| Place |
Gangtok |
Place |
Gangtok |
| Office Seal |
|
Office Seal |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| PROGRESS REPORT
FOR QUARTER ENDING MARCH 2009 |
|
|
| A. |
Identification
Particulars. |
|
|
|
|
|
| 1 |
Name of
Project/Scheme/Programme |
: |
Construction
of Diversion Road to Ranipool-Pakyong road (2.83 kms) in East Sikkim. |
|
|
|
|
|
|
|
| 2 |
Location |
|
: |
State |
|
Sikkim |
District |
: |
West |
| 3 |
Date of Approval of
Project/Scheme |
: |
September 2004. |
|
| 4 |
Approved Cost |
|
: |
Rs. 236.87 lakhs.-NLCPR |
|
| 5 |
Date of completion of
Project/Scheme |
: |
|
|
(i) Stipulated date as
per agreement |
: |
21/02/2006 |
|
|
(ii) Actual date |
|
: |
|
|
| 6. |
Executing Agency
{State Govt. other agency (specify) |
: |
Roads &
Bridges Department, Government of Sikkim (through
government enlisted contractor). |
|
|
|
|
|
| B. |
Progress of Preliminary
Activities |
|
| Prelimianry Project Activity |
Date |
Remarks |
| Agreement for project execution |
|
|
| (i) |
Preparation of Draft for Bids |
|
|
| (ii) |
Invitation for Bids |
|
10/12/2004 |
|
| (iii) |
Evaluation of Bids |
|
24/12/2004 |
|
| (iv) |
Selection of Agency |
|
17/02/2005 |
|
| (v) |
Awards of works |
|
21/02/2005 |
|
|
|
| C. |
Physical Progress
(Descriptive) |
|
| Sl.No. |
Activities/Major
Items of Work |
Physical
Progress during the Quarter |
Cumulative
Physical Progress |
| A |
|
|
|
| 1 |
Hill cutting |
|
20% |
|
|
100% |
| 2 |
Protective
works |
|
10% |
|
|
100% |
| 3 |
Pavement
works |
|
20% |
|
|
100% |
| 4 |
Drainage works |
|
20% |
|
|
100% |
| |
|
|
|
|
|
|
| TOTAL |
|
|
|
|
100% |
|
| D. |
Financial Progress |
|
| Sl.No. |
Activities/Major Items
of Work |
|
During Quarter |
Cumulative Expenditure |
Reasons of
Variation |
| A |
|
|
|
|
|
| 1 |
Hill cutting |
|
|
227.76 |
|
| 2 |
Protective
works |
|
|
|
| 3 |
Pavement
works |
|
|
|
| 4 |
Drainage works |
|
|
|
| 5 |
Drainage (Hill side drain) |
|
|
|
| 6 |
Cross Drain & Culvert |
|
|
|
| |
|
|
|
|
| |
|
|
|
|
| TOTAL |
|
Nil |
227.76 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| E. |
Progress of Release of
Fund. |
|
| Sl.No. |
Release of Funds/Payments |
During the Quarter |
Cumulative Amount |
| Grant |
Loan |
Total |
| 1 |
Central
Government to State Government. |
|
|
|
213.27 |
14.49 |
|
227.76 |
| 2 |
State
Government to concerned Department. |
|
|
|
|
|
|
227.76 |
| 3 |
Actual disbursement
to contractors/beneficiaries etc |
|
|
|
|
|
|
227.76 |
|
|
|
|
|
|
|
| F. |
Key Parameters. |
|
|
|
| 1 |
Overall physical
progress (%) |
|
: |
100% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 2 |
Total funds received
from NLCPR |
|
: |
Rs. 213.27 lakh |
|
| 3 |
Expenditure incurred out
of (2) above |
|
: |
Rs. 227.76 lakh |
|
| 4 |
Anticipated completion
date of the projects/scheme |
: |
Completed |
|
|
|
| G. |
Qualitative observations
on the implementation of the project/scheme: |
|
|
|
|
|
|
|
|
|
|
|
| 1 |
Follow up action on
issues raised in previous quarter |
: |
|
Nil |
|
| 2 |
Major
constraints/problems encountered |
|
: |
|
|
|
| 3 |
Latest inspection notes
on the project containing the following: |
|
|
|
(a) |
Is the copy of DPR
availavle at site? |
|
: |
|
Yes |
|
|
(b) |
What are the
quantitative achievements against the DPR |
: |
|
100% |
|
|
(c) |
What are the
qualitative assessment of project implementation |
: |
|
|
|
|
(d) |
Suggestive remedial
action to be taken by concerned department/agency may be indicated |
: |
|
Nil |
|
|
(e) |
Is any specific item
pending for clearance with any State Government Authority |
: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Signature by the Certifying Officer |
|
Signature
by the Nodal Officer |
|
| Name |
|
Name |
|
| Designation |
Superintending
Engineer |
Designation |
Addl. Chief Engineer |
| Date |
|
Date |
|
| Place |
Gangtok |
Place |
Gangtok |
| Office Seal |
|
Office Seal |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| PROGRESS REPORT
FOR QUARTER ENDING MARCH 2009 |
|
|
| A. |
Identification
Particulars. |
|
| 1 |
Name of
Project/Scheme/Programme |
: |
Upgradation of Ranka-Burtuk-Gangtok road
(8kms). |
|
|
|
|
|
|
|
| 2 |
Location |
|
: |
State |
|
Sikkim |
District |
: |
West |
| 3 |
Date of Approval of
Project/Scheme |
: |
May 2004. |
|
| 4 |
Approved Cost |
|
: |
Rs. 420.00 lakhs.-NLCPR |
|
| 5 |
Date of completion of
Project/Scheme |
: |
|
|
(i) Stipulated date as
per agreement |
: |
11/7/2006 |
|
|
(ii) Actual date |
|
: |
|
|
| 6. |
Executing Agency
{State Govt. other agency (specify) |
: |
Roads &
Bridges Department, Government of Sikkim (through
government enlisted contractor). |
|
|
|
|
|
| B. |
Progress of Preliminary
Activities |
|
| Prelimianry Project Activity |
Date |
Remarks |
| Agreement for project execution |
|
|
| (i) |
Preparation of Draft for Bids |
|
|
| (ii) |
Invitation for Bids |
|
20/06/2004 |
|
| (iii) |
Evaluation of Bids |
|
7/7/2004 |
|
| (iv) |
Selection of Agency |
|
|
|
| (v) |
Awards
of works |
|
4/1/2005 |
|
|
|
| C. |
Physical Progress
(Descriptive) |
|
| Sl.No. |
Activities/Major
Items of Work |
Physical
Progress during the Quarter |
Cumulative
Physical Progress |
| A |
|
|
|
| 1 |
Widening/Protective worksEarthwork |
|
Nil |
|
|
80 |
| 2 |
Pavement Works |
|
Nil |
|
|
65 |
| 3 |
Drainage Works |
|
Nil |
|
|
|
| 4 |
i) Hill
Side Drain |
|
Nil |
|
|
25 |
| 5 |
ii) Cross Drain |
|
Nil |
|
|
50 |
| 6 |
Culvert |
|
Nil |
|
|
- |
| 7 |
Causeway |
|
Nil |
|
|
- |
| 8 |
Signboards, etc. |
|
Nil |
|
|
- |
| TOTAL |
|
|
|
|
75% |
|
| D. |
Financial Progress |
|
| Sl.No. |
Activities/Major Items
of Work |
|
During Quarter |
Cumulative Expenditure |
Reasons of
Variation |
| A |
|
|
|
|
|
| 1 |
Widening/Protective worksEarthwork |
|
Nil |
408.00 |
|
|
| 2 |
Pavement Works |
|
Nil |
|
|
| 3 |
Drainage Works |
|
Nil |
|
|
| 4 |
i) Hill
Side Drain |
|
Nil |
|
|
| 5 |
ii) Cross Drain |
|
Nil |
|
|
| 6 |
Culvert |
|
Nil |
|
|
| 7 |
Causeway |
|
Nil |
|
|
| 8 |
Signboards, etc. |
|
Nil |
|
|
| 9 |
Carriage of Materials |
|
|
|
|
| 10 |
Contingency |
|
|
|
|
| |
|
|
|
|
|
| |
|
|
|
|
|
|
| TOTAL |
|
Nil |
408.00 |
|
|
| E. |
Progress of Release of
Fund. |
|
| Sl.No. |
Release of Funds/Payments |
During the Quarter |
Cumulative Amount |
| Grant |
Loan |
Total |
| 1 |
Central
Government to State Government. |
|
0.00 |
|
387.20 |
20.80 |
|
408.00 |
| 2 |
State
Government to concerned Department. |
|
0.00 |
|
|
|
|
408.00 |
| 3 |
Actual disbursement
to contractors/beneficiaries etc |
|
|
|
|
|
|
408.00 |
|
|
|
|
|
|
|
| F. |
Key Parameters. |
|
|
|
| 1 |
Overall physical
progress (%) |
|
: |
75% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 2 |
Total funds received
from NLCPR |
|
: |
Rs. 387.20 lakh |
|
| 3 |
Expenditure incurred out
of (2) above |
|
: |
Rs. 408.00
lakh |
|
| 4 |
Anticipated completion
date of the projects/scheme |
: |
30/09/2009 |
|
|
|
| G. |
Qualitative observations
on the implementation of the project/scheme: |
|
|
|
|
|
|
|
|
|
|
|
| 1 |
Follow up action on
issues raised in previous quarter |
: |
|
Nil |
|
| 2 |
Major
constraints/problems encountered |
|
: |
|
|
|
| 3 |
Latest inspection notes
on the project containing the following: |
|
|
|
(a) |
Is the copy of DPR
availavle at site? |
|
: |
|
Yes |
|
|
(b) |
What are the
quantitative achievements against the DPR |
: |
|
75% |
|
|
(c) |
What are the
qualitative assessment of project implementation |
: |
|
|
|
|
(d) |
Suggestive remedial
action to be taken by concerned department/agency may be indicated |
: |
|
Nil |
|
|
(e) |
Is any specific item
pending for clearance with any State Government Authority |
: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Signature by the Certifying Officer |
|
Signature
by the Nodal Officer |
|
| Name |
|
Name |
|
| Designation |
Superintending
Engineer |
Designation |
Addl. Chief Engineer |
| Date |
|
Date |
|
| Place |
Gangtok |
Place |
Gangtok |
| Office Seal |
|
Office Seal |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| PROGRESS REPORT
FOR QUARTER ENDING MARCH 2009 |
|
|
| A. |
Identification
Particulars. |
|
| 1 |
Name of
Project/Scheme/Programme |
: |
Replacement
of 2 Nos. of Suspension Bridges on
Pelling-Yuksom road in West Sikkim. |
|
|
|
|
|
|
|
| 2 |
Location |
|
: |
State |
|
Sikkim |
District |
: |
West |
| 3 |
Date of Approval of
Project/Scheme |
: |
July 2004. |
|
| 4 |
Approved Cost |
|
: |
Rs. 327.57 lakhs.-NLCPR |
|
| 5 |
Date of completion of
Project/Scheme |
: |
|
|
(i) Stipulated date as
per agreement |
: |
6/5/2006 |
|
|
(ii) Actual date |
|
: |
|
|
| 6. |
Executing Agency
{State Govt. other agency (specify) |
: |
Roads &
Bridges Department, Government of Sikkim (through
government enlisted contractor). |
|
|
|
|
|
| B. |
Progress of Preliminary
Activities |
|
| Prelimianry Project Activity |
Date |
Remarks |
| Agreement for project execution |
|
|
| (i) |
Preparation of Draft Invitation for Bids |
|
|
| (ii) |
Invitation for Bids |
|
18/11/2004 |
|
| (iii) |
Evaluation of Bids |
|
7/2/2005 |
|
| (iv) |
Selection of Agency |
|
29/03/2005 |
|
| (v) |
Awards
of works |
|
6/5/2005 |
|
|
|
| C. |
Physical Progress
(Descriptive) |
|
| Sl.No. |
Activities/Major
Items of Work |
Physical
Progress during the Quarter |
Cumulative
Physical Progress |
| A |
Rimbi Bridge |
|
|
| 1 |
Sub-Structure |
|
Nil |
|
|
100% |
| 2 |
Super Structure |
|
Nil |
|
|
100% |
| 3 |
Pavement work (Bridge approach) |
|
Nil |
|
|
90% |
| 4 |
Sign board etc |
|
Nil |
|
|
90% |
| |
TOTAL |
|
|
|
|
90% |
| B |
Rathong
Bridge |
|
|
|
|
- |
| 1 |
Sub-Structure |
|
Nil |
|
|
100% |
| 2 |
Super Structure |
|
Nil |
|
|
100% |
| 3 |
Pavement work (Bridge approach) |
|
Nil |
|
|
90% |
| 4 |
Sign board etc |
|
|
|
|
|
| TOTAL |
|
|
|
|
97% |
| D. |
Financial Progress |
|
| Sl.No. |
Activities/Major Items
of Work |
|
During Quarter |
Cumulative Expenditure |
Reasons of
Variation |
| A |
Rimbi Bridge |
|
|
|
|
| 1 |
Sub-Structure |
|
|
305.31 |
|
| 2 |
Super Structure |
|
|
|
| 3 |
Pavement work (Bridge approach) |
|
|
|
| 4 |
Sign board etc |
|
|
|
| B |
Rathong
Bridge |
|
|
|
| 1 |
Sub-Structure |
|
|
|
| 2 |
Super Structure |
|
|
|
| 3 |
Pavement work (Bridge approach) |
|
|
|
| 4 |
Sign board etc |
|
|
|
| |
Contingency |
|
|
|
| |
Miscellaneous |
|
|
|
| TOTAL |
|
Nil |
305.31 |
|
|
| E. |
Progress of Release of
Fund. |
|
| Sl.No. |
Release of Funds/Payments |
During the Quarter |
Cumulative Amount |
| Grant |
Loan |
Total |
| 1 |
Central
Government to State Government. |
|
0.00 |
|
298.88 |
20.43 |
|
319.31 |
| 2 |
State
Government to concerned Department. |
|
0.00 |
|
|
|
|
319.31 |
| 3 |
Actual disbursement
to contractors/beneficiaries etc |
|
|
|
|
|
|
305.31 |
|
|
|
|
|
|
|
|
|
| F. |
Key Parameters. |
|
|
|
| 1 |
Overall physical
progress (%) |
|
: |
Rimbi |
90% |
|
|
|
|
|
Rathong |
97% |
|
|
|
|
|
|
|
| 2 |
Total funds received
from NLCPR |
|
: |
Rs.298.88 lakh |
|
| 3 |
Expenditure incurred out
of (2) above |
|
: |
Rs. 305.31 lakh |
|
| 4 |
Anticipated completion
date of the projects/scheme |
: |
30/06/2009 |
|
|
|
| G. |
Qualitative observations
on the implementation of the project/scheme: |
|
|
|
|
|
|
|
|
|
|
|
| 1 |
Follow up action on
issues raised in previous quarter |
: |
|
Nil |
|
| 2 |
Major
constraints/problems encountered |
|
: |
|
|
|
| 3 |
Latest inspection notes
on the project containing the following: |
|
|
|
(a) |
Is the copy of DPR
availavle at site? |
|
: |
|
Yes |
|
|
(b) |
What are the
quantitative achievements against the DPR |
: |
|
95% |
|
|
(c) |
What are the
qualitative assessment of project implementation |
: |
|
|
|
|
(d) |
Suggestive remedial
action to be taken by concerned department/agency may be indicated |
: |
|
Nil |
|
|
(e) |
Is any specific item
pending for clearance with any State Government Authority |
: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Signature by the Certifying Officer |
|
Signature
by the Nodal Officer |
|
| Name |
|
Name |
|
| Designation |
Superintending Engineer |
Designation |
Addl. Chief Engineer |
| Date |
|
Date |
|
| Place |
Gangtok |
Place |
Gangtok |
| Office Seal |
|
Office Seal |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| PROGRESS REPORT
FOR QUARTER ENDING MARCH 2009 |
|
|
| A. |
Identification
Particulars. |
|
| 1 |
Name of
Project/Scheme/Programme |
: |
Upgradation
of Namchi Assangthang Road km 1st to 5th. |
|
|
|
|
|
|
|
| 2 |
Location |
|
: |
State |
|
Sikkim |
District |
: |
South |
| 3 |
Date of Approval of
Project/Scheme |
: |
Mar-08 |
|
| 4 |
Approved Cost |
|
: |
Rs. 600.00 lakhs.-NLCPR |
|
| 5 |
Date of completion of
Project/Scheme |
: |
|
|
(i) Stipulated date as
per agreement |
: |
|
|
|
(ii) Actual date |
|
: |
2/6/2010 |
|
| 6. |
Executing Agency
{State Govt. other agency (specify) |
: |
Roads &
Bridges Department, Government of Sikkim (through
government enlisted contractor). |
|
|
|
|
|
| B. |
Progress of Preliminary
Activities |
|
| Prelimianry Project Activity |
Date |
Remarks |
| Agreement for project execution |
|
|
| (i) |
Preparation of Draft Invitation for Bids |
|
|
| (ii) |
Invitation for Bids |
|
|
|
| (iii) |
Evaluation of Bids |
|
|
|
| (iv) |
Selection of Agency |
|
|
|
| (v) |
Awards
of works |
|
2/3/2009 |
|
|
|
| C. |
Physical Progress
(Descriptive) |
|
| Sl.No. |
Activities/Major
Items of Work |
Physical
Progress during the Quarter |
Cumulative
Physical Progress |
| A |
Hill cutting |
|
10% |
| 1 |
Protective
works |
|
|
|
|
0% |
| 2 |
Pavement
works |
|
|
|
|
0% |
| 3 |
Drainage works |
|
|
|
|
0% |
| TOTAL |
|
Nil |
|
|
10% |
| D. |
Financial Progress |
|
| Sl.No. |
Activities/Major Items
of Work |
|
During Quarter |
Cumulative Expenditure |
Reasons of
Variation |
| A |
|
|
|
|
|
| 1 |
Hill cutting |
|
|
139.38 |
|
| 2 |
Protective
works |
|
|
|
| 3 |
Pavement
works |
|
|
|
| 4 |
Drainage works |
|
|
|
| TOTAL |
|
Nil |
139.38 |
|
|
| E. |
Progress of Release of
Fund. |
|
| Sl.No. |
Release of Funds/Payments |
During the Quarter |
Cumulative Amount |
| Grant |
Loan |
Total |
| 1 |
Central
Government to State Government. |
|
0.00 |
|
188.52 |
20.95 |
|
209.47 |
| 2 |
State
Government to concerned Department. |
|
0.00 |
|
|
|
|
209.47 |
| 3 |
Actual disbursement
to contractors/beneficiaries etc |
|
|
|
|
|
|
139.38 |
|
|
|
|
|
|
|
| F. |
Key Parameters. |
|
|
|
| 1 |
Overall physical
progress (%) |
|
: |
10% |
|
|
|
|
|
|
|
|
| 2 |
Total funds received
from NLCPR |
|
: |
Rs.209.47 lakh |
|
| 3 |
Expenditure incurred out
of (2) above |
|
: |
Rs. 139.38 lakh |
|
| 4 |
Anticipated completion
date of the projects/scheme |
: |
2/6/2010 |
|
|
|
| G. |
Qualitative observations
on the implementation of the project/scheme: |
|
|
|
|
|
|
|
|
|
|
|
| 1 |
Follow up action on
issues raised in previous quarter |
: |
|
Nil |
|
| 2 |
Major
constraints/problems encountered |
|
: |
|
|
|
| 3 |
Latest inspection notes
on the project containing the following: |
|
|
|
(a) |
Is the copy of DPR
availavle at site? |
|
: |
|
Yes |
|
|
(b) |
What are the
quantitative achievements against the DPR |
: |
|
10% |
|
|
(c) |
What are the
qualitative assessment of project implementation |
: |
|
|
|
|
(d) |
Suggestive remedial
action to be taken by concerned department/agency may be indicated |
: |
|
Nil |
|
|
(e) |
Is any specific item
pending for clearance with any State Government Authority |
: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Signature by the Certifying Officer |
|
Signature
by the Nodal Officer |
|
| Name |
|
Name |
|
| Designation |
Superintending Engineer |
Designation |
Addl. Chief Engineer |
| Date |
|
Date |
|
| Place |
Gangtok |
Place |
Gangtok |
| Office Seal |
|
Office Seal |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| PROGRESS REPORT
FOR QUARTER ENDING MARCH 2009 |
|
|
| A. |
Identification
Particulars. |
|
| 1 |
Name of
Project/Scheme/Programme |
: |
Construction
of pre-stressed bridge over river Rangit on legship-Tashiding Road. |
|
|
|
|
|
|
|
| 2 |
Location |
|
: |
State |
|
Sikkim |
District |
: |
West |
| 3 |
Date of Approval of
Project/Scheme |
: |
Sep-08 |
|
| 4 |
Approved Cost |
|
: |
Rs. 1253.20 lakhs.-NLCPR |
|
| 5 |
Date of completion of
Project/Scheme |
: |
|
|
(i) Stipulated date as
per agreement |
: |
|
|
|
(ii) Actual date |
|
: |
30/12/2010 |
|
| 6. |
Executing Agency
{State Govt. other agency (specify) |
: |
Roads &
Bridges Department, Government of Sikkim (through
government enlisted contractor). |
|
|
|
|
|
| B. |
Progress of Preliminary
Activities |
|
| Prelimianry Project Activity |
Date |
Remarks |
| Agreement for project execution |
|
|
| (i) |
Preparation of Draft Invitation for Bids |
|
|
| (ii) |
Invitation for Bids |
|
|
|
| (iii) |
Evaluation of Bids |
|
|
|
| (iv) |
Selection of Agency |
|
|
|
| (v) |
Awards
of works |
|
2/3/2009 |
|
|
|
| C. |
Physical Progress
(Descriptive) |
|
| Sl.No. |
Activities/Major
Items of Work |
Physical
Progress during the Quarter |
Cumulative
Physical Progress |
| A |
|
|
|
| 1 |
Sub-Structure |
|
|
|
|
10% |
| 2 |
Super Structure |
|
|
|
|
|
| TOTAL |
|
Nil |
|
|
10% |
| D. |
Financial Progress |
|
| Sl.No. |
Activities/Major Items
of Work |
|
During Quarter |
Cumulative Expenditure |
Reasons of
Variation |
| A |
|
|
|
|
|
| 1 |
Sub-Structure |
|
|
273.03 |
|
| 2 |
Super Structure |
|
|
|
| TOTAL |
|
Nil |
273.03 |
|
|
| E. |
Progress of Release of
Fund. |
|
| Sl.No. |
Release of Funds/Payments |
During the Quarter |
Cumulative Amount |
| Grant |
Loan |
Total |
| 1 |
Central
Government to State Government. |
|
0.00 |
|
430.40 |
47.82 |
|
478.22 |
| 2 |
State
Government to concerned Department. |
|
0.00 |
|
|
|
|
478.22 |
| 3 |
Actual disbursement
to contractors/beneficiaries etc |
|
|
|
|
|
|
273.03 |
|
|
|
|
|
|
|
| F. |
Key Parameters. |
|
|
|
| 1 |
Overall physical
progress (%) |
|
: |
10% |
|
|
|
|
|
|
|
|
| 2 |
Total funds received
from NLCPR |
|
: |
Rs.478.22 lakh |
|
| 3 |
Expenditure incurred out
of (2) above |
|
: |
Rs. 273.03 lakh |
|
| 4 |
Anticipated completion
date of the projects/scheme |
: |
30/12/2010 |
|
|
|
|
|
|
|
|
|
|
| G. |
Qualitative observations
on the implementation of the project/scheme: |
|
|
|
|
|
|
| 1 |
Follow up action on
issues raised in previous quarter |
: |
|
Nil |
|
| 2 |
Major
constraints/problems encountered |
|
: |
|
|
|
| 3 |
Latest inspection notes
on the project containing the following: |
|
|
|
(a) |
Is the copy of DPR
availavle at site? |
|
: |
|
Yes |
|
|
(b) |
What are the
quantitative achievements against the DPR |
: |
|
10% |
|
|
(c) |
What are the
qualitative assessment of project implementation |
: |
|
|
|
|
(d) |
Suggestive remedial
action to be taken by concerned department/agency may be indicated |
: |
|
Nil |
|
|
(e) |
Is any specific item
pending for clearance with any State Government Authority |
: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Signature by the Certifying Officer |
|
Signature
by the Nodal Officer |
|
| Name |
|
Name |
|
| Designation |
Superintending Engineer |
Designation |
Addl. Chief Engineer |
| Date |
|
Date |
|
| Place |
Gangtok |
Place |
Gangtok |
| Office Seal |
|
Office Seal |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| PROGRESS REPORT
FOR QUARTER ENDING MARCH 2009 |
|
|
| A. |
Identification
Particulars. |
|
| 1 |
Name of
Project/Scheme/Programme |
: |
Upgradation
of Pakyong Machong Rolep Road km 1st to 35th. |
|
|
|
|
|
|
|
| 2 |
Location |
|
: |
State |
|
Sikkim |
District |
: |
East |
| 3 |
Date of Approval of
Project/Scheme |
: |
Nov-08 |
|
| 4 |
Approved Cost |
|
: |
Rs. 3335.58 lakhs.-NLCPR |
|
| 5 |
Date of completion of
Project/Scheme |
: |
|
|
(i) Stipulated date as
per agreement |
: |
|
|
|
(ii) Actual date |
|
: |
15/02/2012 |
|
| 6. |
Executing Agency
{State Govt. other agency (specify) |
: |
Roads &
Bridges Department, Government of Sikkim (through
government enlisted contractor). |
|
|
| B. |
Progress of Preliminary
Activities |
|
| Prelimianry Project Activity |
Date |
Remarks |
| Agreement for project execution |
|
|
| (i) |
Preparation of Draft Invitation for Bids |
|
|
| (ii) |
Invitation for Bids |
|
|
|
| (iii) |
Evaluation of Bids |
|
|
|
| (iv) |
Selection of Agency |
|
|
|
| (v) |
Awards
of works |
|
10/2/2009 |
|
|
|
| C. |
Physical Progress
(Descriptive) |
|
| Sl.No. |
Activities/Major
Items of Work |
Physical
Progress during the Quarter |
Cumulative
Physical Progress |
| A |
|
|
|
| 1 |
Hill cutting |
|
|
|
|
10% |
| 2 |
Protective
works |
|
|
|
|
|
| 3 |
Pavement
works |
|
|
|
|
|
| 4 |
Drainage works |
|
|
|
|
|
| TOTAL |
|
Nil |
|
|
10% |
| D. |
Financial Progress |
|
| Sl.No. |
Activities/Major Items
of Work |
|
During Quarter |
Cumulative Expenditure |
Reasons of
Variation |
| A |
|
|
|
|
|
| 1 |
Hill cutting |
|
|
652.44 |
|
| 2 |
Protective
works |
|
|
|
| 3 |
Pavement
works |
|
|
|
| 4 |
Drainage works |
|
|
|
| TOTAL |
|
Nil |
652.44 |
|
| E. |
Progress of Release of
Fund. |
|
| Sl.No. |
Release of Funds/Payments |
During the Quarter |
Cumulative Amount |
| Grant |
Loan |
Total |
| 1 |
Central
Government to State Government. |
|
0.00 |
|
1028.60 |
114.28 |
|
1142.88 |
| 2 |
State
Government to concerned Department. |
|
0.00 |
|
|
|
|
1142.88 |
| 3 |
Actual disbursement
to contractors/beneficiaries etc |
|
|
|
|
|
|
652.44 |
|
|
|
|
|
|
|
| F. |
Key Parameters. |
|
|
|
| 1 |
Overall physical
progress (%) |
|
: |
10% |
|
|
|
|
|
|
|
|
| 2 |
Total funds received
from NLCPR |
|
: |
Rs.1142.88 lakh |
|
| 3 |
Expenditure incurred out
of (2) above |
|
: |
Rs. 652.44lakh |
|
| 4 |
Anticipated completion
date of the projects/scheme |
: |
15/02/2012 |
|
| G. |
Qualitative observations
on the implementation of the project/scheme: |
|
|
|
|
|
|
|
|
|
|
|
| 1 |
Follow up action on
issues raised in previous quarter |
: |
|
Nil |
|
| 2 |
Major
constraints/problems encountered |
|
: |
|
|
|
| 3 |
Latest inspection notes
on the project containing the following: |
|
|
|
(a) |
Is the copy of DPR
availavle at site? |
|
: |
|
Yes |
|
|
(b) |
What are the
quantitative achievements against the DPR |
: |
|
10% |
|
|
(c) |
What are the
qualitative assessment of project implementation |
: |
|
|
|
|
(d) |
Suggestive remedial
action to be taken by concerned department/agency may be indicated |
: |
|
Nil |
|
|
(e) |
Is any specific item
pending for clearance with any State Government Authority |
: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Signature by the Certifying Officer |
|
Signature
by the Nodal Officer |
|
| Name |
|
Name |
|
| Designation |
Superintending Engineer |
Designation |
Addl. Chief Engineer |
| Date |
|
Date |
|
| Place |
Gangtok |
Place |
Gangtok |
| Office Seal |
|
Office Seal |
|
|
|
|
|
|
|
|
|
|
|
|