STATUS OF ON-GOING NEC WORKS AS ON  SEPTEMBER 2009
Rs in lakhs
Sl no Name of scheme Scope of work Sanctioned No. & date of A/A A.A / EFC Amount  Date and amount of release of fund by NEC Date and amount Released by Finance  Present status Probable date of completion
Physical Expenditure         
  Improvement of Chakung Khaniserbong road  km 1st to 11th. Slip clearance mix soil 1578.75 cum NEC/(T&C)/ APPROVAL/2005-06/22  dated  15.12.05 486.36 29.70 on 30/08/06,100 on 20/07/07,75 on 03/06/08 , 202.80 on 07/08/09           State loan       3.30 on 29/08/06 ,  11.11 on 20/07/07,8.33 on 03/06/08,23 on 07/08/09   1616.55 227.44 Dec'09
  Subgrade preparation 44331.30 cum   15375.44
  Pavement works        
  GSB I 5541.41 cum   1921.93
  GSB II 3324.85 cum   1153.16
  GSB III 3324.90 cum   321.19
  Premix carpeting 44331.29 sqm   150.00
  Edging 21119.60 mtr   7490.40
  Carriage of stock (30-40) 6214.65 qtl   880.66
  Carriage of sand(30-40) 1749.10 cum   117.30
  Carriage of stone(30-40) 13405.80 cum   3396.28
  Excavation foundation 1244.16 cum   600.40
  Stone filling  5387.31 cum   1802.90
  Mixed filling 299.27 cum   273.28
  RRSM wall 3178.2 mtr   1422.93
  Hammer dressed dry wall 243.43 sqm   70.16
  Hand packed stone wall 508.34 qtl   0.00
  Plum wall 127.84 cum   88.50
  G.I wire 1530.97 cum    
  Hill side drain rectangular 332.60 mtr    
  Hill side drain  v shaped 10165.40 mtr    
  Carriage of stock (20-30) 47.44 qtl    
  Carriage of sand(20-30) 1483.23 cum    
  Carriage of stone(20-30) 4424.77 cum    
  Cross drain  16.00 no.    
  Causeway 4.00 no.    
  Total         486.36 459.44   50% 227.44  
Total sanction  486.36 486.36
Total released  459.44 459.44
Total expenditure 227.44 227.44
STATUS OF ON-GOING NEC WORKS AS ON  SEPTEMBER  2009
Rs in lakhs
Sl no Name of scheme Scope of work Sanctioned No. & date of A/A A.A / EFC Amount  Date and amount of release of fund by NEC Date and amount Released by Finance  Present status Probable date of completion
Physical Expenditure        
  Replacement of Ringyang suspension bridge on Soreng Sombaria Road COMPLETED NEC/(T&C)/ APPROVAL/2003-04/15 dated 06.07.2004 332.02 124 on 19/11/.04    90 on  18/06/05          29.70  on  28/08/06  , 55.00 on 12/09/07State loan                   3.3  on  28/08/06  , 6.11 on 12.09.07   COMPLETED 331.84 COMPLETED
  Total         332.02 331.89     331.84  
Total sanction  332.02 332.02
Total released  331.89 331.89
Total expenditure 331.84 331.84
STATUS OF ON-GOING NEC WORKS AS ON  SEPTEMBER 2009
Rs in lakhs
Sl no Name of scheme Scope of work Sanctioned No. & date of A/A A.A / EFC Amount  Date and amount of release of fund by NEC Date and amount Released by Finance  Present status Probable date of completion
Physical Expenditure      
  Surface strengthening ,drainage and carpeting of Sombaria Hilley road in West Sikkim 1)Pavement works     NEC/(T&C)/ APPROVAL/2006-07/5 dated 05.06.06 845.68 85.50 on 28/08/06  100 on 12/07/07 ,75 on 03/06/08 , 25 on 19.01.09,200 on 30/03/09 State loan 9.5 on 28/08/06 , 11.11 on 12/07/07,9.5 on 03/06/08,2.78 on 19/01/09  ,22.22 on 30/03/09     317.22 March'10
  Subgrade preparation 97859.3 sqm   59511.47
  GSB I 491.51 cum   452.71
  GSB II 14878.9 cum   9085.25
  Edging 42755.5 mtr   31304.00
  Premix carpet 97859.3 sqm   30059.80
  Profile correction 2256.43 cum   297.69
  CRSM wall 2620.11 cum   131.71
  Stone filling 2608.44 cum   367.85
  Carriage of stone chips 16494.1 cum   3725.33
  Carriage of stone 5347.34 cum   1649.91
  Carriage of sand  2891.4 cum   280.43
  Carriage of stock 4612.9 qtl   704.09
  Carriage of firewood 1680.19 piles   360.72
  2)Protective works        
  Hill cutting         
  Mixed soil 21225 cum   10981.80
  Hard soil 3762.28 cum   2590.69
  Hard rock with Blasting  1148.57 cum   0.00
  Excavation of foundation  1749.49 cum   1231.07
  CRSM dry  wall  1447.8 cum   271.99
  CRSM wall 2209.71 cum   2325.71
  Standard parapet 1466 mtr   o.oo
  Mixed filling  798.96 cum   240.21
  Stone filling 798.96 cum   240.21
  Carriage of stone 2078.34 cum   1981.04
  Carriage of sand  323.04 cum   274.02
  Carriage of stock 1181.02 qtl   1186.00
  3)Drainage works        
  V shaped drain 23418 mtr    
Sl no Name of scheme Scope of work Sanctioned No. & date of A/A A.A / EFC Amount  Date and amount of release of fund by NEC Date and amount Released by Finance  Present status Probable date of completion
Physical Expenditure        
  Surface strengthening ,drainage and carpeting of Sombaria Hilley road in West Sikkim Rectangular drain  1520 mtr              
  Carriage of stone 6100.4 cum              
  Carriage of sand  908.7 cum              
  Carriage of stock 6544 qtl              
  Cross drain 32 nos.              
  Culvert 3 nos.              
    Causeway 42 nos.              
  Total         845.68 539.44   72% 317.22  
Total sanction  845.68 845.68
Total released  539.44 539.44
Total expenditure 317.22 317.22
STATUS OF ON-GOING NEC WORKS AS ON  SEPTEMBER  2009
Rs in lakhs
Sl no Name of scheme Scope of work 65 A.A / EFC Amount  Date and amount of release of fund by NEC Date and amount Released by Finance  Present status Probable date of completion
Physical Expenditure        
  Upgradation and extension of Marchak Tumblabong road km 1st to 13th in East Sikkim 1)Earthworks     NEC/(T&C)/ APPROVAL/2006-07/7 dated 05.06.2006 1023.00 99 on 25/08/06,  100 on 12/07/07,175  on 03/06/08, 25 ON 24/12/08,200 on 30/03/09 State loan 11 on 25/08/06 11.11 on 12/07/07,11.11 on 03/06/08,2.78 on 24/12/08, 22.22 on 30/03/09      554.44 March'10
  Hill Cutting works:        
  a. in mixed soil 90475.95 cum   45996.00
  b. in soft rock 4882.50 cum   -
  c. in hard rock with blasting 42469.35 cum   22470.37
  2)Widening andProtective Works        
  Cutting and clearing of mixed slip 2807.66 cum   2807.66
  Excavation of foundation  9288.20 cum   1700.00
  CRSM wall DRY 5631.58 cum   200.00
  CRSM wall in 1:4:8 CC 11038.43 cum   2000.00
  Plum Concrete wall 190.80 cum   190.80
  G.I.wire net mesh 1008.89 sqm   -
  Sausage Dry Stone wall 343.20 sqm   -
  Stone Filling 8475.30 cum   1872.53
  Kutcha Drain 6820.00 m   -
  Carriage of stock materials 5159.68 qtl   -
  Carriage of stock materials 798.37 qtl   1100.00
  Carriage of non stock - stone 815.53 cum   -
  Carriage of non stock - stone 4482.60 cum   2900.00
  Carriage of sand 1635.44 cum   350.00
  Throwing of Spoils 2807.66 cum   2202.80
  Drainage 6700.00 m   -
  3)Pavement Works:        
  Subgrade preparation 52280.11 sqm   16875.00
  Granular Sub Base Grading I 17536.32 cum   3310.78
  WBM Grading II 7842.02 cum   2831.05
  WBM Grading III 3921.01 cum   2831.05
  Edging 24151.20 m   9400.00
  20mm thick Premix carpeting 49642.43 sqm   -
  Standard Parapet 585.00 m     -
Sl no Name of scheme Scope of work Sanctioned No. & date of A/A A.A / EFC Amount  Date and amount of release of fund by NEC Date and amount Released by Finance  Present status Probable date of completion
Physical Expenditure       
    Carriage of stock materials 1882.56 qtl         -    
    Carriage of non stock - sand 5633.60 cum         -    
    Carriage of stones 25712.45 cum         3635.08    
    Carriage of stone chip 938.28 cum         -    
    4)Drainage Works:                  
    Hillside drains V - shaped 7410.00 m         -    
    Hillside drains Rectangular 4800.00 m         -    
    Carriage of stock materials 4361.85 qtl         -    
    Carriage of non stock - stone 3910.20 cum         -    
    Carriage sand 607.14 cum         -    
    Standard Cross Drain 59 Nos no         20.00    
    Culvert 2 m span 5 Nos no         2.00    
    Culvert 1 m span 3 Nos no         6.00    
    Causeway 3 Nos no         -    
  Total         1023.00 776.66   68% 758.31  
Total sanction  1023.00 1023.00
Total released  776.66 776.66
Total expenditure 758.31 758.31
STATUS OF ON-GOING NEC WORKS AS ON September  2009
Rs in lakhs
Sl no Name of scheme Scope of work Sanctioned No. & date of A/A A.A / EFC Amount  Date and amount of release of fund by NEC Date and amount Released by Finance  Present status Probable date of completion
Physical Expenditure        
   Replacement of Takcham Chu suspension bridge on GRBA Road 1)Bridge works     NEC/(T&C)/ APPROVAL/2003-04/14 dated 06.07.2004 476.76 90 on 04/08/04     90 on 18/06/05     29.70  on 29/08/06  60 on 03/07/07    100 on 27/09/08         State loan     10.00 04/08/04   10.00 on 18/06/05   3.3  on 29/08/06    6.67 on 03/07/07  11.11 on 27/09/08       Dec''09
  Hill Cutting works:    
  a. Mixed soil 271.72 cum   53.24
  b. Soft rock 675.48 cum   372.68
  c. Hard rock  225.16 cum   106.48
  d. B. rock (using Explosive) 112.58 cum    
  E/work in foundation Excavation        
  a. Mixed soil 776.28 cum   768.99
  b. Soft rock 208.80 cum   187.80
  c. Hard rock with chiseling only 397.96 cum   490.00
  P/L 1:2:4 CC 30.57 cum   126.89
  P/F and Removing of Form works        
  a. Mass concrete and Foundation 243.06 sqm   113
  b. Square/Rectangular column 432.35 sqm   431.21
  c. Circular column 237.48 sqm   178.54
  d. Floor & Roof 145.71 sqm   -
  e. Beams 260.68 sqm   -
  P/L 1:1:50:3R CC 1099.21 cum   779.59
  P/L 1:1:2 RCC 252.97 cum   -
  Supplying, bending /B of Tor Steel reinforcement   qtl   1169.46
   
  Carriage of Non stock materials        
  a. Stone chips 1180.55 cum   835.58
  b. Sand 614.33 cum   162.52
  Carriage of Stock materials 8271.00 qtl   5474.68
  Bridge ( Steel component) 90.00 m    
           
Sl no Name of scheme Scope of work Sanctioned No. & date of A/A A.A / EFC Amount  Date and amount of release of fund by NEC Date and amount Released by Finance  Present status Probable date of completion
Physical Expenditure        
    2)Approach road and protective works                
    Hill cutting in mix soil 200.00 cum         -    
    Foundation excavation 172.83 cum         200.84    
    P/L Plum concrete in 1:2:4 CC 143.64 cum         367.36    
    P/L  CRSM in 1:4:8 CC 933.04 cum         -    
    P/L  Stone filling 1541.25 cum         11.33    
    Mixed filling works 551.25 cum         -    
    Carriage of stock materials 625.29 qtl         49150    
    Carriage of Non stock materials 2729.53 cum         288.91    
  Total         476.76 410.78   92% 410.81  
Total sanction  476.76 476.76
Total released  410.78 410.78
Total expenditure 410.81 410.81
STATUS OF ON-GOING NEC WORKS AS ON   SEPTEMBER 2009
Rs in lakhs
Sl no Name of scheme Scope of work Sanctioned No. & date of A/A A.A / EFC Amount  Date and amount of release of fund by NEC Date and amount Released by Finance  Present status Probable date of completion
Physical Expenditure         
  Strengthening Drainage and Carpetting of Sankalang Bey Sakyong to Tingvong High School road Km 1st to 7th in North District, Sikkim COMPLETED     NEC/(T&C)/ APPROVAL/2004-05/04 dated 5th July 2004 401.38 100 on 04/08/04      90 on 18/06/05      29.70 on 25/08/06  70.77 on 20/08/07, 50 on 03/06/08 State loan              3.3 on  25/08/06   7.08 on 20/08/07     COMPLETED 367.19 COMPLETED
  Total         401.38 367.19     367.19  
Total sanction  401.38 401.38
Total released  367.19 367.19
Total expenditure 367.19 367.19
STATUS OF ON-GOING NEC WORKS AS ON  September 2009
Rs in lakhs
Sl no Name of scheme Scope of work Sanctioned No. & date of A/A A.A / EFC Amount  Date and amount of release of fund by NEC Date and amount Released by Finance  Present status Probable date of completion
Physical Expenditure        
  Construction of Bridge over River Teesta on Dikchu Sankalang Mangan Road (SH: Replacement of GOUR suspension Bridge with 100 mtr span steel bridge)       NEC/(T&C)/ APPROVAL/2003-04/54 dated 27.02.2004 ,              Revised estimate No. NEC/T/BR/SKM-IV/03 dt. 9.02.07                  488.57 90 on 04/08/04          90 on 18/06/05       49.50  on 25/08/06    60.00 on 08/06/07  , 75 on 03/06/08         State loan               10.00 on 04/08/04  10.00  on 18/06/05   5.5  on 25/08/06  6.66 on 08/06/07 ,8.33 on 03/06/08       Dec'09
  Clearing of jungles  10000 sqm     10000.00  
  Cutting of trees 30cm-60cm  20 nos     20.00  
  Cutting of trees 60cm-120cm  14 nos     14.00  
  Cutting of trees 120-240 cm  9 nos     9.00  
  E/W in mixed soil  888.02 cum     827.77  
  E/W in  H.R 349.23 cum     323.40  
  E/W in H.R using explosive  349.23 cum     323.40  
  H-P stone solling 29.05 cum     29.06  
  C.C in 1:3:6 14.54 cum     14.54  
  R.C.C in 1:1.5:3 mixed  463.88 cum     480.46  
  R.C.C in 1:1:2 mixed  935.49 cum     501.45  
  S/B/B of tor steel  1804.1 qtl     561.57  
  Wearing course M25  19.68 cum     --------  
  Cement plaster 12mm thk in 1:3  777.11 sqm     --------  
  Form work in foundation  284.34 sqm     284.34  
  Form work in beam etc.  1354.96 sqm     91.75  
  Form work in circular pier  315.59 sqm     315.59  
  Plum cunc. In 1:2:4 284.75 cum     285.36  
  Knitting of G.I.Wire  1105 sqm     1105.00  
  H.P.stone wall   554 cum     255.00  
  Roller cum rocker bearing   4 nos     4.00  
  Dewatering   1 job     1.00  
  Total         488.57 482.75   98.00% 438.94  
Total sanction  443.87 488.57
Total released  404.99 482.75
Total expenditure 438.94 438.94
STATUS OF ON-GOING NEC WORKS AS ON  SEPTEMBER 2009
Rs in lakhs
Sl no Name of scheme Scope of work Sanctioned No. & date of A/A A.A / EFC Amount  Date and amount of release of fund by NEC Date and amount Released by Finance  Present status Probable date of completion
Physical Expenditure        
A Construction of 40 mtr span steel bridge over Rinzi khola at Kholaghari Namchi Vok road COMPLETED     NEC/(T&C)/ APPROVAL/2005-06/05 dated 25th July 2005 157.5 27 on 20/02/06       29.64 on 29/08/06    40.95 on 20/08/07    0.54 on 20.08.08         State loan               3 on 20.02.06, 3.29 on 29/08/06  4.55 on 20/08/07,0.06 on 20.08.08   COMPLETED 216.68 COMPLETED
295.5 cum
   
597.58 cum
597.58 cum
33.39 cum
565.29 cum
239.4 cum
933.9 cum
466.31 cum
485.42 cum
  Total         157.5    
B Construction of 40 mtr span steel bridge over lower Ben khola at Saino Taar along Pabong-Yangang road. COMPLETED     NEC/(T&C)/ APPROVAL/2005-06/05 dated 25th July 2005 137.34 COMPLETED COMPLETED
  Total         137.34 277.19     263.50  
Total sanction  137.34 294.84
Total released  277.19 277.19
Total expenditure 263.50 263.50
STATUS OF ON-GOING NEC WORKS AS ON  SEPTEMBER  2009
Rs in lakhs
Sl no Name of scheme Scope of work Sanctioned No. & date of A/A A.A / EFC Amount  Date and amount of release of fund by NEC Date and amount Released by Finance  Present status Probable date of completion
Physical Expenditure       
  Replacement of suspension bridge over Rabi khola river at 9th km on Melli-Phong road Hill cutting (Part I)Diversion work NEC/(T&C)/ APPROVAL/2005-06/21 dated 15.12.05 497.3 29.79 on 25/08/06,100 on 13.10.08 ,275 ON 20/03/09 State  3.3 on 25.08.06 , 11.11 on 13.10.08, 30.56 ON 20/03/09     March'10
Mixed  3729.8 cum 3729.8  
soft  941.07 cum 941.07  
Hard 92.44 cum   92.44  
Throwing of spoil 865.83 cum   865.83  
Excavation foundation 673.28 cum   673.28  
CRSM 854.24 cum   854.24  
Hand packed wall 210.13 cum   210.13  
Mixed filling  61.38 cum   61.38  
Stone filling 1395.49 cum   1395.49  
Supply & knitting of G.I wire 1404.54 kg   1404.54  
Kutcha drain 1760.00 m   1760.00  
Culvert 1.00 no.   1.00 343.77
Dewatering 1.00 no.   1.00  
Carriage of stock 686.00 qtl   686.00  
Carriage of sand 207.15 cum   207.15  
Carriage of stone 1468.13 cum   1468.13  
Approaches (Part II)      
Mixed  2918.44 cum   2626.20  
Hard rock  1723.88 cum   1551.50  
Hard rock using blasting 1547.44 cum   1392.70  
Excavation foundation 789.32 cum   236.80  
Stone soiling 270.00 cum      
CRSM 1300.30 cum   325.00  
Stone filling 1008.25 cum      
Stone edging 540.00 m      
Road metal 156.00 cum      
SDBC 1560.00 sqm      
V shape 210.00 m      
Box drain parapet 60.00 m      
  Total         497.3 449.67   50% 343.77  
Total sanction  497.30 497.3
Total released  449.67 449.67
Total expenditure 343.77 343.77
STATUS OF ON-GOING NEC WORKS AS ON  SEPTEMBER   2009
Rs in lakhs
Sl no Name of scheme Scope of work Sanctioned No. & date of A/A A.A / EFC Amount  Date and amount of release of fund by NEC Date and amount Released by Finance  Present status Probable date of completion
Physical Expenditure          
  Replacement of Sumin Wooden Suspension Bridge on Sang Khola Sumin Road COMPLETED     NEC/(T&C)/ APPROVAL/2003-04/13 dated 06.07.2004 285.40 100 on 04/08/04    90 on18/06/05   29.70 on 29/08/06, 37 on 19/01/09   State loan        3.3 on 29/08/06 , 4.11 on 19/01/09   COMPLETED 253.11 COMPLETED
  Total         285.4 274.11     253.11  
Total sanction  285.40 285.40
Total released  274.11 274.11
Total expenditure 253.11 253.11
STATUS OF ON-GOING NEC WORKS AS ON  September 2009
Rs in lakhs
Sl no Name of scheme Scope of work Sanctioned No. & date of A/A A.A / EFC Amount  Date and amount of release of fund by NEC Date and amount Released by Finance  Present status Probable date of completion
Physical Expenditure       
  Const of major retaining structure on app.road to Raj bhawan VIP complex and TNA school COMPLETED     NEC/(T&C)/ APPROVAL/2005-06/07 dated 25th July 2005 110.58 45 on 06/03/06   29.70 on 30/08/06  , 15 on 3.06/07  ,9.82 on 17/03/09State loan        3.3 on 30/08/06,1.67 on 03/06/08,1.09 on 17/03/09   COMPLETED 99.67 COMPLETED
  Total         110.58 110.58     109.27  
Total sanction  110.58 110.58
Total released  110.58 110.58
Total expenditure 109.27 109.27
STATUS OF ON-GOING NEC WORKS AS ON  SEPTEMBER 2009
Rs in lakhs
Sl no Name of scheme Scope of work Sanctioned No. & date of A/A A.A / EFC Amount  Date and amount of release of fund by NEC Date and amount Released by Finance  Present status Probable date of completion
Physical Expenditure        
A. Const of 25 mtr span steel bridge over Upper Ben khola at ben Tarku Rabongla (GLVC) road COMPLETED     NEC/(T&C)/ APPROVAL/2004-05/37 dated 30th March 2005 90.83 45 on 14/02/06   59.40 on 28/08/06     74.48 on 12/07/07  74.48 on 30/03/09   State loan          5.00 on 14.02.06    6.60  on 28/08/06 8.28 on 12/07/07  8.28 on 30/03/09   COMPLETED 258.81 COMPLETED
  Total         90.83    
B. Construction of 50 mtr span steel bridge on approach road to Khedum village       NEC/(T&C)/ APPROVAL/2004-05/37 dated 30th March 2005 190.68   Dec'09
  1. F.E. in mixed soil 1938.00 cum 1439.72
  2. P/L stone soling  58.00 cum 66.38
  3. P/L R.C.C. 1:2:4mix 22.43 cum 27.72
  4. P/L R.C.C. 1:1.5:3mix 47.25 cum 0.00
  5. S/B/B steel reinforcement 119.00 qtl 83.71
    6. P/L P.C.C. 1:2:4mix 1579.00 cum 1590.27
    7. P/L CRSM 1:4:8 CCM mix 435.00 cum 347.78
    8. P/L stone filling  660.00 cum 659.87
    9. P/L stone edging = 120 120.00 mtr 120.00
    10. P/Spreading road metal=23 23.00 m2 22.50
    11. P/L std type parapet       
    (45x60x60) 60.34 mtr 60.00
    12. P/L (60x45) cm Box Drain 150.00 mtr 140.00
    13. P/L Hand packed stone wall 415.00 cum 414.30
    14. S/knitting of G.I.wire 1544.00 kg 1543.64
    15. Carriage of sand 455.00 cum 293.40
    16. Carriage of stones 3217.00 cum 1364.27
    17. Carriage of stock 3215.00 qtl 1975.73
    18. Frame work for slab 210.00 sqm  
    19. Carriage of steel bridge 1.00 no  
    20. Painting of bridge  1.00 no.  
    21. Scaffolding & Erection  1.00 no.  
  Total         190.68 281.52   98% 258.81  
Total sanction  190.68 281.51
Total released  281.52 281.52
Total expenditure 258.81 258.81
STATUS OF ON-GOING NEC WORKS AS ON  SEPTEMBER  2009
Rs in lakhs
Sl no Name of scheme Scope of work Sanctioned No. & date of A/A A.A / EFC Amount  Date and amount of release of fund by NEC Date and amount Released by Finance  Present status Probable date of completion
Physical Expenditure       
  Upgradation i/c drainage and carpeting of Ralang Phamtam road in South Sikkim 1)Bridge including abutment     NEC/(T&C)/ APPROVAL/2006-07/4 dated 05.06.06, 1183 99 on 25/08/06,   100 on 03/07/07, 75 on 03/06/08 State loan 11 on 25 /08/06 11.11 on 03/07/07,8.33 on 03/06/08       June'10
  Foundation excavation             
  Soft rock  266.91 cum        
  Stone soiling 13.88 cum        
  RCC 1:2:4 mix 631.77 cum        
  1:3:6 CC 9.27 cum        
  S/B/P  of steel 821.3 qtl        
  Form work 1217.11 sqm        
  Carriage launching of bridges  65 m        
  Cost of  steel truss 50.2 m        
  2)Protection river training            
  Excavation and foundation  3302.54 cum        
  Mixed filling 201.25 cum        
  CRSM wall 1:2:4 mix 1117.93 cum        
  Hand packed wall in sausage 2616.62 cum        
  Kintting of GI wire 4643.97 sqm        
  Carriage of stone 4495.6 cum        
  Carriage of sand 410.8 cum        
  Carriage of stock  3452.6 qtl        
    3)Protective work                
    Foundation excavation  6932.91 cum         2939.291  
    1:4:8 ccm wall 3440.28 cum         1528.143  
    Hammer dressed wall 3297.98 cum         1528.146  
    1:2:4 plum concrete 465.13 cum         184.03  
    Sausage wall 4897.61 cum         1929.249  
    Knitting of G.I wire 13948.82 sqm         5376.636  
    Stone filling 3722.21 cum         1315.229  
    Parapet 1906.5 rm              
    4)Pavement works                  
    Picking of loose material 4644 Nos         3924    
    Stone filling 2291.13 cum         1908.206    
    Excavation and foundation  13403.27 cum         11270.99    
    P/L GSB I 6155.43 cum         5179.21    
    P/L GSB II 3737.48 cum              
    P/L GSB III 3737.48 cum              
    Stone edging 30370 rm         20460.39    
    Premix carpeting 49832.75 sqm              
    Box drain  13 km              
    Cross drain 13 km              
    Culvert RCC 6 nos              
    Carriage of stock  5015.78 qtl         1208.26    
    Carriage of stone 16625.59 cum         7506.957    
    Carriage of sand 2630.7 cum              
  Total         1183 440.44   55% 304.44  
Total sanction  1183.00 1183.00
Total released  440.44 440.44
Total expenditure 304.44 304.44
STATUS OF ON-GOING NEC WORKS AS ON  SEPTEMBER  2009
Rs in lakhs
Sl no Name of scheme Scope of work Sanctioned No. & date of A/A A.A / EFC Amount  Date and amount of release of fund by NEC Date and amount Released by Finance  Present status Probable date of completion
Physical Expenditure        
  Construction of road from 10th mile Legship-Kewzing road to Tingmoo village       NEC/(T&C)/ APPROVAL/2004-05/38 dated 30.03.05 468.29 29.70 on 29/08/06   50 on 12/07/07,  175 on 03/06/08 State loan              3.3 on 29/08/06 5.56 on 12/07/07, 19.44 on 03/06/08       Dec'09
    1)Pavement works                   
    Subgrade preparation 28376.57 sqm         1000    
    GSB 1 4256.49 cum              
    GSB II 4256.49 cum              
    GSB III 2128.23 cum              
    Edging 7359.08 m              
    Premix carpeting  289376.6 sqm              
    Carriage of stone 1167.24 cum              
    Carriage of stock 649.66 qtl              
    Carriage of firewood 39.41 days              
    2)Protective works                  
    Mixed soil 47020.1 cum         21700.00    
    Soft rock 72203.5 cum         13512.20    
    hard rock 155403 cum         20272.10    
    Hard rock with blasting 32201.9 cum         1468.71    
    Excavation of foundation 1032.1 cum              
    CRSM dry wall 1411.25 cum         62.92    
    CRSM 1:4:8 MIX 1192.93 cum         146.81    
    Parapet 322.5 m              
    Stone filling 550.94 cum              
    Carraige of stone 2286.3 cum         160.75    
    Carraige of sand 153.31 cum         367.69    
    Carraige of stock 563.205 qtl         62.58    
    3) Drainage works                  
    V shape drain 3616.4 mtr              
Sl no Name of scheme Scope of work Sanctioned No. & date of A/A A.A / EFC Amount  Date and amount of release of fund by NEC Date and amount Released by Finance  Present status Probable date of completion
Physical Expenditure        
    Rectangular shape 3630 mtr              
    Carraige of stone 2441.59 cum              
    Carraige of sand 285.84 cum              
    Carraige of stock 1562.77 qtl              
    Standard cross drain 24 nos              
    Culvert  11 nos              
  Total         393.00 393.00   92% 207.16  
Total sanction  468.29 393
Total released  393.00 393.00
Total expenditure 207.16 207.16
STATUS OF ON-GOING NEC WORKS AS ON  SEPTEMBER 2009
Rs in lakhs
Sl no Name of scheme Scope of work Sanctioned No. & date of A/A A.A / EFC Amount  Date and amount of release of fund by NEC Date and amount Released by Finance  Present status Probable date of completion
Physical Expenditure         
  Improvement of Bermiok Legship road.       NEC/(T&C)/ APPROVAL/2005-06/6 dated 25.07.05 449.46 75.60 on 28/08/06  75 on 03/07/07,100 on 03/06/08  State loan  8.40 on 28/08/06  8.33 on 03/07/07,11.11 on 03/06/08       Dec'09
  Excavation in mixed soil 2811.26 cum     2811.26    
  CRSM wall 3556 cum     3556    
  Hand packed stone filling 521.1 cum     521.1    
  Carriage of stock materials 1507.74 cum     1507.74    
  Carriage of sand 408.93 cum     408.93    
  Carriage of stone 4009.54 cum     4009.54    
  Sub grade 40834.92 sqm          
  GSB I 4083.56 cum          
  GSB II 3062.61 cum          
  GSB III 3062.61 cum          
  Premix carpeting 41470.51 sqm          
  Stone edging  17661 rm          
  Parapet 1350 rm          
  Carriage of stock  1725.56 qtl          
  Carriage of sand 2017.07 cum          
  Carriage of stone   12179.81 cum          
  V shape drain  7845 rm          
  Box Drain 960 rm          
  Carriage of stock  674.03 qtl          
  Carriage of sand 110.3 cum          
  Carriage of stone   2056.38 cum          
  Cross drain 35 nos     20    
  Causeway 21 nos          
  Culvert 4 nos     1    
  Total       449.46 278.44   89% 278.44  
Total sanction  449.46 449.46
Total released  278.44 278.44
Total expenditure 278.44 278.44
STATUS OF ON-GOING NEC WORKS AS ON SEPTEMBER  2009
Rs in lakhs
Sl no Name of scheme Scope of work Sanctioned No. & date of A/A A.A / EFC Amount  Date and amount of release of fund by NEC Date and amount Released by Finance  Present status Probable date of completion
Physical Expenditure       
  Upgradation and drainage i/c replacement of two bridges on Kimbubotey Sokpey road in south Sikkim.       NEC/(T&C)/ APPROVAL/2006-07/3 dated 05.06.06 1180.89 90 on 28/08/06 , 100 on 12/07/07     ,100 on 30/11/07,75 on 03/06/08  ,25 on 19/01/09      State loan  ,10 on 28/08/06  11.11 on 12/07/07   ,11.11 on 30/11/07,8.33 on 03/06/08, 2.78 on 19/01/09       June'10
  Pavement works        
  Picking up loose material 1290.00 head   460
  Stone filling 1589.74 cum   314.02
  Subgrade preparation 37753.85 sqm   20000
  Subgrade consolidation 37425.06 sqm   20000
  GSB I 6704.09 cum   1652.29
  GSB II 3459.82 cum   826.15
  GSB-III 4108.42 cum   691.96
  P/L Stone Edging: 22643.07 rm   4860
  P/L premix carpetting: 56838.98 sqm   3396.46
  carriage of stock 2036.44 Qtl   1636.36
  Carriage of sand 2824.39 cum   769.64
  Carriage of stone chips 1534.56 cum    
  Carriage of stone 16365.70 cum   6546.28
  Providing Antistripping Compound 2036.52 kg    
  Carriage of firewood 78.85 days    
  Earthwork        
  Hill Cutting: (i):M/Soils: 421.07 cum   21.05
  (ii): S/Rock 536.51 cum    
  (iii): H/Rock: 773.50 cum    
  (iv)B/Rock 1020.11 cum    
  P/W        
  Cutting Mixed Slips. 2888.73 cum   2599.86
  Excavation Foundation: 980.07 cum   1033.87
  P/L 1:4:8 CCM Wall: 801.15 cum   480.69
  P/L 1:2:4 Plum works: 251.60 cum   193.93
  P/L H/P Stone Walls. 571.16 cum   342.7
  Knitting of G.I Wire: 1747.02 sqm   1048.21
  P/L Stone Filling: 454.30 cum   272.58
  P/L Parapet: 3135.00 rm   1881
  Stock Carriages.30-40 1342.92 cum   805.75
Sl no Name of scheme Scope of work Sanctioned No. & date of A/A A.A / EFC Amount  Date and amount of release of fund by NEC Date and amount Released by Finance  Present status Probable date of completion
Physical Expenditure         
    Carriage, Sand.20-30: 347.52 cum         208.51    
    Carriage,Stone.20-30: 2551.83 cum         1531.1    
    Drainage                  
    Cutting & clearing jungle etc 495.00 head         24.75    
    P/L box drain: 6880.00 rm              
    P/L V-Drain: 4740.00 rm              
    Stock Carriages.30-40km 3749.37 rm              
    Carriage, Sand.20-30: 532.35 No.              
    Carriage,Stone.20-30: 4235.00 No.              
    Cutting & clearing jungle etc 640.00 head         64    
    P/L(60x60) C/Drain: 54.00 No.         5.4    
    Stock Carriages.20-30 1195.31 Qtl              
    Carriage, Sand.20-30: 147.42 cum              
    Carriage,Stone.20-30: 645.84 cum              
    Cutting & clearing jungle etc 210.00 head              
    P/L Cause-Way: 15.00 No.              
    Stock Carriages.20-30 652.50 qtl              
    Carriage, Sand.20-30: 115.35 cum              
    Carriage,Stone.20-30: 733.95 cum              
    Bridge works                  
    Cost of steel parts 1 job                
    Launching of bridge 1 job                
    Carriage of steel parts  1 job                
    Painting of steel bridge,bearing plate 1 job                
    Abutment & RCC Decking                  
    Cutting & clearing jungle 10.00 head         5    
    Foundation excavation 158.84 cum         79.42    
    HP stone soling 4.10 cum              
    P/L 1:2:4 cc 6.11 cum              
    P/L 1:2:4 RCC 144.32 cum              
    P/L 1:2:4 plum 184.15 cum              
    P/F/F reinforcement for RCC 18472.96 kg              
    P/F/F formwork for RCC 1 job                
    Carriage of stock materials  960.27 qtl              
    Carriage of sand(30-40km) 106.70 cum              
    carriage of stone (30-40 km) 151.34 cum              
    head load 158.84 cum              
                       
Sl no Name of scheme Scope of work Sanctioned No. & date of A/A A.A / EFC Amount  Date and amount of release of fund by NEC Date and amount Released by Finance  Present status Probable date of completion
Physical Expenditure         
    Approach road & wing wall                  
    Hill cutting (Mixed soil) 3525.43 cum              
    Hard rock 755.45 cum              
    Blasting rock 755.45 cum              
    Excavation foundation(Mixed soil) 469.11 cum              
    Hard rock 201.05 cum              
    1:4:8 CCM wall 315.00 cum              
    1:2:4 plum wall 636.36 cum              
    1:4:8 plum wall 636.36 cum              
    Stone filling 562.50 cum              
    Carriage of stock materials  1660.00 qtl              
    Carriage of sand(30-40km) 352.77 cum              
    carriage of stone (30-40 km) 854.71 cum              
    Carriage of stack stone by head load 1238.30 cum              
    Bridge works                  
    Cost of steel parts 1 job                
    Launching of bridge 1 job                
    Carriage of steel parts  1 job                
    Painting of steel bridge,bearing plate 1 job                
    Abutment & RCC Decking                  
    Cutting & clearing jungle 20.00 head         15    
    Excavation foundation(Mixed soil) 91.42 cum         68.57    
    Hard rock 182.84 cum         137.13    
    Blasting rock 182.84 cum         137.13    
    HP stone soling 8.87 cum              
    P/L 1:2:4 cc 8.87 cum              
    P/L 1:2:4 RCC 637.04 cum              
    P/F/F reinforcement for RCC 81541.12 kg         3261.64    
    P/F/F formwork for RCC 330.24 Sqm         16.51    
    Carriage of stock materials  2881.03 qtl         144.05    
    Carriage of sand(30-40km) 284.20 cum         14.21    
    carriage of stone (30-40 km) 579.85 cum         28.99    
    head load 323.87 cum              
    Approach road & wing wall                  
    Hill cutting (Mixed soil) 3089.81 cum         147.17    
    soft rock 1844.81 cum         16.98    
    Hard rock 3101.06 cum              
    Blasting rock 2164.31 cum              
Sl no Name of scheme Scope of work Sanctioned No. & date of A/A A.A / EFC Amount  Date and amount of release of fund by NEC Date and amount Released by Finance  Present status Probable date of completion
Physical Expenditure        
    Excavation foundation(Mixed soil) 653.34 cum              
    soft rock 653.34 cum              
    Hard rock 326.67 cum         143.73    
    1:2:4 plum wall 2147.39 cum              
    1:2:4 plum wall 724.83 cum         901.9    
    Knitting of GI wire 3000.03 sqm              
    Providing HP stone wall in sausage 1006.03 cum              
    Stone filling 807.10 cum         254.4    
    Carriage of stock materials  4939.76 qtl         1440.5    
    Carriage of sand(30-40km) 673.47 cum         198.19    
    carriage of stone (30-40 km) 579.81 cum              
    Carriage of stack stone by head load 4320.50 cum         1080.13    
    RCC parapet on approach              
    Steel              
    Soling for approaches              
    WBM              
  Total       1180.89 533.33   76% 433.33  
Total sanction  1180.89 1180.89
Total released  533.33 533.33
Total expenditure 433.33 433.33
STATUS OF ON-GOING NEC WORKS AS ON SEPTEMBER 2009
Rs in lakhs
Sl no Name of scheme Scope of work Sanctioned No. & date of A/A A.A / EFC Amount  Date and amount of release of fund by NEC Date and amount Released by Finance  Present status Probable date of completion
Physical Expenditure         
  Surface strengthening ,drainage and carpeting of Assam Pakyong road in East Sikkim 1)Earth works     NEC/(T&C)/ APPROVAL/2006-07/19 dated 25.08.06 750.76 63 on 25/08/06,                100 on 03/07/07  100  on 12/11/07          , 200 on 03/06/08    ,100 on 30/03/09   State loan   7  on 25/08/06  11.11  on 03/07/07   11.11 on 12/11/07, 22.22 on 03/06/08, 11.11 on 30/03/09       Dec '09
  Mixed 11777.78 cum     12512.08    
  Hard 5262.05 cum     5151.98    
  Blasting 1070.83 cum     4091.18    
  2)Protective works              
  Mixed 2712.67 cum      2712.00    
  CRSM wall 1209.84 cum        1200.00    
  HD wall 818.51 cum             
  PCC 1:2:4 3702.88 cum        1327.26    
  Stone filling 1547.57 cum        1547.57    
  Carriage of stock materials 6439.44 qtl       6200    
    Carriage of sand  954.31 cum       900    
    Carriage of stone 6746.44 cum       6500    
    3)Pavement works                
    sub grade 42892.5 sqm       42750    
    Parapet 4530 m            
    GSB I 6527.94 cum       5219.19    
    GSB II 2586.47 cum            
    GBS III 2586.47 cum            
    Stone edging 9030 m            
    Premix carpeting 34419.7 sqm            
    Carriage of stock materials 2128.72 qtl            
    Carriage of sand  2574.17 cum            
    Carriage of stone 13449.05 cum       5219.19    
    Drainage works                
    Cross drain 31 no.       25    
    Culvert 5         4    
    Steel bridge 1         1    
  Total         750.76 625.55   80% 578.40  
Total sanction  750.76 750.76
Total released  625.55 625.55
Total expenditure 578.40 578.40
STATUS OF ON-GOING NEC WORKS AS ON  SEPTEMBER  2009
Rs in lakhs
Sl no Name of scheme Scope of work Sanctioned No. & date of A/A A.A / EFC Amount  Date and amount of release of fund by NEC Date and amount Released by Finance  Present status Probable date of completion
Physical Expenditure        
  Construction and improvement of road from Turung school to Suminkhor primary school km 1st to 5th.       NEC/(T&C)/ APPROVAL/2007-08/1 dated 1st May 2007 358.66 50 on 14/06/07,100 on  13.10.08 , 150.00 17/03/09 State loan       5.56  on 14/06/07,11.11 on 13.10.08, 16.67  on        Dec'09
  1)Earth work              
Mixed 46254.32 cum     46254.32    
soft 21390.49 cum     21390.49    
Hard 12369.00 cum     12369.00    
Blasting 3785.83 cum     3785.83    
2)Protective works              
Mixed 3893.62 cum     1946.81    
HD wall 3133.74 cum          
CRSM wall 5445.14 cum     2722.57    
Stone filling 2942.01 cum     1618.1    
Mixed filling  2942.01 cum     1471    
Carriage of stock materials 2489.5 qtl     1618.17    
Carriage of sand  626.19 cum     438.33    
Carriage of stone 5989.25 cum     4072    
3)Pavement work              
Sub grade  28497.6 cum          
Consolidation 28497.6 cum          
Stone edging 9499.2 m          
GSB I 1769.16 cum          
GSB II 2756.18 cum          
GSB III 1444.97 cum          
Premix carpeting 19592.12 sqm          
Prime coat 19592.12 sqm          
Carriage of stock materials 903.6 qtl          
Carriage of sand  642.12 cum          
Carriage of stone 10219.29 cum          
Sl no Name of scheme Scope of work Sanctioned No. & date of A/A A.A / EFC Amount  Date and amount of release of fund by NEC Date and amount Released by Finance  Present status Probable date of completion
Physical Expenditure        
    Carriage of firewood 13.06 pile              
    4)Drainage works              
Box drain 1020 m              
V shape drain 3622 m              
Cross drain 35 no.              
Carriage of stock materials 931 qtl              
Carriage of sand  294.23 cum              
Carriage of stone 1463.41 cum              
  Total         358.66 333.34   83% 204.62  
Total sanction  358.66 358.66
Total released  333.34 333.34
Total expenditure 204.62 204.62
STATUS OF ON-GOING NEC WORKS AS ON SEPTEMBER  2009
Rs in lakhs
Sl no Name of scheme Scope of work Sanctioned No. & date of A/A A.A / EFC Amount  Date and amount of release of fund by NEC Date and amount Released by Finance  Present status Probable date of completion
Physical Expenditure        
  Construction of Makha bridge over river Tista khola at Tanak on Makha Lingi Yangang Ravangla road. Approach and wing wall NEC/APPROVAL/2005-06/17 dated 24/10/05 495.25 44.55 on 25/08/06, State               4.95 on 25 /08/06     30.23 June'10
  Cutting clearing jungle 100 heads          
  Mixed 102.15 cum     100    
  soft 153.23 cum     50    
  Hard 255.38 cum     10.00    
  CCM wall 1161.09 cum     100.00    
  Plum wall 604 cum          
  Stone filling 2662.5 cum            
  Box drain 70 rm            
  Parapet 96 rm            
  Stone edging 4.14 rm            
  Stone soiling 46.8 cum            
  Stone metaling 31.2 cum            
  Premix carpeting 364 sqm            
    Carriage of stock materials 1525.31 qtl              
    Carriage of sand  279.7 cum              
    Carriage of stone 2255.34 cum              
    Abutment              
    Mixed 69.51 cum              
    Hard  173.78 cum              
    Blasting 104.27 cum              
    Hand packed stone soiling 25.73 cum              
    1:1/2:3 cc 25.73 cum              
    Rcc 1:2:4 2278.5 cum              
    1:1.5:3 RCC 49.06 cum              
    Tor steel  227850 kg              
    Form work for RCC 422.1 sqm              
    Carriage of stock materials 9869 Qtl              
    Carriage of sand  1033.95 cum              
    Carriage of stone 1046.81 cum              
    Protective work              
                   
    Mixed 60 cum              
    Hard  150 cum              
    Soft 90 cum              
    Knitting of G.I wire 1386 sqm              
    Hand packed stone wall 720 cum              
    Hand packed stone filling 180 cum              
    Carriage of stock materials 17.03 qtl              
    Carriage of sand  360 cum              
    Carriage of stone 360 cum              
        495.25 250.50   14% 32.28  
Total sanction  495.25 495.25
Total released  250.50 250.50
Total expenditure 32.28 32.28
STATUS OF ON-GOING NEC WORKS AS ON SEPTEMBER  2009
Rs in lakhs
  Name of scheme Scope of work Sanctioned No. & date of A/A A.A / EFC Amount  Date and amount of release of fund by NEC Date and amount Released by Finance  Present status Probable date of completion
Physical Expenditure        
   Survey Investigation and preparation of DPR for the 11th Plan road schemes.       NEC/(T&C)/ APPROVAL/2007-08/06 dated 8th February  2008 32.00 08/02/08   State loan3.20 on 08/02/08   80% 25.50 Dec'09
              32.00   80% 25.50  
Total sanction  32.00
Total released  32.00
Total expenditure 25.50