| Road Development [E&I Scheme] | ||||||||
| [Road works] | ||||||||
| Progress Report for the Quarter ending " March 2008" State. SIKKIM | ||||||||
| PWD Circle: WEST | ||||||||
| PWD Division: Gyalshing | ||||||||
| Name of Work: Drainage System & Carpetting of Rimbi Yuksom road, West Sikkim. | ||||||||
| Highway No:- - Date of Sanction of estimate: 01/07/2004 | ||||||||
| Job:no: SK E&I 2002-03 03 Amount (Rs): 2,19,37,000 /- | ||||||||
| Section………………… Length: 21.70 Km. Date of Commencement: 22/02/2005 | ||||||||
| Place: Gyalshing From: Rimbi To: Yuksom Target date of Completion: 21/08/2006 | ||||||||
| Mileage/Milometerage……………..From: Rimbi. To: Yuksum Contractor: K.N.Bhutia | ||||||||
| PHYSICAL PROGRESS | ||||||||
| S.no | Item of work | Total quantity as per detailed estimate | Progress at the end of the previous quarter | Cumulative progress upto the end of the quarter under report | Expected date of completi -on | Remarks | ||
| Target% | Actual% | Target% | Actual% | |||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
| 1 | Earthwork (Lac, cum) | 0.91 | 100% | 100% | 100% | 100% | ||
| 2 | Sub-base (Lac,cum) | 0 | ||||||
| 3 | Soling (a) Collection (Lac, cum) | 0.069 | 100% | 100% | 100% | 100% | ||
| (b) Laying (Lac,cum) | 0.069 | 100% | 100% | 100% | 100% | |||
| 4 | Metalling (a) Collection (Lac, cum) | 0.13 | 100% | 85% | 100% | 100% | ||
| (B)Laying (Lac, cum) | 0.13 | 100% | 75% | 100% | 100% | |||
| 5 | Bitumin macadam/DBM (a) Collection | 0.024 | 90% | 70% | 90% | 100% | ||
| (ii) Bitumin (MT) | 305.5 | |||||||
| (b) Laying (Lac,cum) | 0.017 | |||||||
| 6 | Culverts (RM) | 32 | 100% | 80% | 100% | 100% | ||
| 7 | Retaining Walls (RM) | 3600 | 100% | 90% | 100% | 100% | ||
| 8 | Overall Progress % | 100% | ||||||
| 9 | Expenditure (in Rs. lakhs) | 219.37 | ||||||
| 10 | Additional information: | |||||||
| (a) Bottlenecks if any, and action taken towards overcoming them: | ||||||||
| (b) General Brief description and remarks: | ||||||||
| (i) Progress is generally satisfactory/fair/poor: | satisfactory | |||||||
| (ii) Plan & machinery are adequate/inadequate, there being a need for additional: - | adequate | |||||||
| (iii) Labour is adequate/inadequate- the reason being: - | adequate | |||||||
| (IV) Resources (Stores) are adequate/inadequate, there reasons being a shortage of: - | ||||||||
| because of - | ||||||||
| ( c) Liabilities incurred and not otherwise shown in this form (money value to be shown): | ||||||||
| Executive Engineer | ||||||||