PROGRESS REPORT OF WORKS EXECUTED FROM ECONOMIC IMPORTANCE AND INTER STATE CONNECTIVITY
Report for the Quarter ending September 2009
SL.NO NAME OF WORK LENGTH KM/M FOR BRIDGE AMOUNT OF AA AA  NO AND DATE AMOUNT OF TECHNICAL SANCTION DATE OF SANCTION PHYSICAL PROGRESS IN  %
UPTO THE END OF PREVIOUS YEAR DURING THE YEAR TOTAL PROGRESS UPTO THE END OF QUARTER
1 2 3 4 5 6 7 8 9 10
  Economic Importance                
1 Surface Strengthening Protective works & Premix Carpetting of  Gyalshing - Pelling road in West Sikkim. 8.42 87.86 NH 12031/2/2002/SK/EI/NH-10, 27/01/03 87.86 27/01/2003 100 0 100
2 Drainage System & Carpetting of Rimbi Yuksom road, West Sikkim. 21.70 219.37 NH 12031/1/2004/SK/EI/NH-10, 1/07/04 219.37  01/07/2004 100 0 100
3 Improvement of Sang Dipudara road. 12 347.74 NH 12031/3/2007/SK/EI/NH-10, 1/07/07 347.74  01/07/2007 90 0 90
4 Improvement of Pakyong-Karthok-Nayabusty Raigoan road. 10 398.52 NH 12031/4/2007/SK/EI/NH-10, 2/07/07 398.52  01/07/2007 50 5 55
5 Construction of Gurassey road from Bio-Diversity park (Temi) 8 1010.92 NH 12031/54/2005/SK/EI/NH-10, 20/11/06 1010.92 20/11/2006 0 12 12
6 Construction of road from Radong (NH 31 A ) to Kimchithang via Chuba km 1st to 15th 15 701.88 NH 12031/55/2005/SK/EI/NH-10, 25/09/06 701.88 25/11/2006 30 0 30
SL.NO NAME OF WORK LENGTH KM/M FOR BRIDGE AMOUNT OF AA AA  NO AND DATE AMOUNT OF TECHNICAL SANCTION DATE OF SANCTION PHYSICAL PROGRESS IN  %
UPTO THE END OF PREVIOUS YEAR DURING THE YEAR TOTAL PROGRESS UPTO THE END OF QUARTER
1 2 3 4 5 6 7 8 9 10
  Inter State Connectivity                
7 Carpeting and strengthening works on Melli Nayabazar Road km 1st to 27th 27 298.56  NH 12031/1/2000/SK/ISC/NH-10 ,25/07/2000 298.56 25/07/2000 100 0 100
8 Surface Strengthening Protective works & Premix Carpetting of  Duga-Pachekhani road km 1st to 14th East Sikkim                14 433.77  NH 12031/17/2004/SK/ISC/NH-10 ,29/11/2004 433.77 29/11/2004 100 0 100
9 Widening, Surface Imp, P. Works & Drainage along Phongla-Sirwani road, Km 1st to 28th. 28 999.08 NH 12031/18/2004/SK/ISC/NH-10 18/03/05 999.08 18/03/2005 100 0 100
10 Widening, Improvement, P. works  Drainage and Carpetting of  Melli Phongla Road KM 1st -23rd in South Sikkim 23 1298.60 NH 12031/56/2005/SK/ISC/NH-10 , 31/01/06 1298.60 31/01/2006 40 35 75
11 Surface improvement ,protective works and drainage along Rangpo-Duga-Pendam road. 15 950.00 NH 12031/17/2006/SK/EI/NH-10 , 30/03/07 950.00 30/03/2007 70 0 70
12 Improvement of Rhenock-Simana khola km 1st to 3rd 3 250.00 NH 12031/18/2006/SK/ISC/NH-10 , 31/03/07 250.00 31/03/2007 30 5 35
13 Construction of road from Salangdang to Lohdhama including 5 nos. of bridges. 5 1647.00 NH 12031/18/2008/SK/ISC/NH-10 , 23/10/08 1647.00 23/10/2009 0 10 10
  Total   8643.30