| DETAILS OF STATE PLAN SCHEMES INDICATING SPILLOVER TO FINANCIAL
YEAR 2009-10 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| WEST DISTRICT ( As on 31/3/2009) |
|
| Sl.No |
NAME OF WORK |
Name of Contractor |
Date of Commencement |
Due Date of Completion |
Year of Sanction |
Sanctioned Cost |
Expenditure |
Spill over 2009-10 |
Physical Progress |
Remarks |
|
| Till 31/03/2008 |
During
2008-09 |
Total |
|
| 1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
|
|
| |
CONSTRUCTION OF NEW ROADS |
|
|
|
|
|
|
|
|
|
|
|
|
| 1 |
Construction
of New Road from Rinchenpong Yangsum to Ambetar Km 1st - 4th. |
Land
Compensation |
|
|
Oct-07 |
47.14 |
25.00 |
22.14 |
47.14 |
0.00 |
100% |
Work
closed |
|
|
|
| 2 |
Forest
Compensation for Construction of motorable road from Labdong -Khongri-Pokhari to Karjee |
Forest
Compensation |
- |
- |
2008-09 |
108.79 |
0.00 |
108.79 |
108.79 |
0.00 |
100% |
Work
closed |
|
|
|
| 3 |
Construction
of road from from Recreation Center on Chakung-Chumbong Road Km 2nd in West
Sikkim. |
R.B.Rai |
Apr-05 |
Oct-05 |
Apr-05 |
11.57 |
10.30 |
0.67 |
10.97 |
0.00 |
100% |
Work
closed |
|
|
|
| 4 |
Construction
of Link Road from Upper Rumbuk to Tareybhir Km 3rd |
Phurchuki
Sherpa |
1/4/2005 |
31/04/06 |
2004-05 |
24.73 |
20.13 |
0.00 |
20.13 |
4.60 |
85% |
|
|
|
|
| 5 |
Construction
of Link Road from Upper Rumbuk to Tareybhir Km 4th |
Lakpa
Sherpa |
22.36 |
19.56 |
0.00 |
19.56 |
2.80 |
70% |
|
|
|
|
| 6 |
Construction
of Link Road from Upper Rumbuk to Tareybhir Km 5th |
Lakpa
Sherpa |
24.45 |
7.92 |
12.13 |
20.05 |
4.40 |
70% |
|
|
|
|
| 7 |
Construction
of Link Road from Upper Rumbuk to Tareybhir Km 6th |
Lakpa
Sherpa |
22.75 |
7.63 |
7.37 |
15.00 |
7.75 |
40% |
|
|
|
|
| 8 |
Construction
of Link Road from Upper Rumbuk to Tareybhir Km 7th. |
Samday
Sherpa |
21.55 |
17.85 |
3.70 |
21.55 |
0.00 |
100% |
Work
closed |
|
|
|
| 9 |
Additional
Sanction for LC & FC on construction of Link Road from Upper Rumbuk to
Tareybhir .LC Rs 24.80 & FC 20.18 |
Land
b& Forest Compensation |
|
|
2007/2008 |
44.98 |
24.80 |
20.18 |
44.98 |
0.00 |
FC
Res released |
|
|
|
|
| 10 |
Construction
of link road from Saili Golai to Lower Rumbuk School Km 1st & 2nd. |
B.B.Subba
& S.R.Subba |
2004 |
|
2006 |
31.27 |
31.27 |
0.00 |
31.27 |
0.00 |
100% |
Work closed |
|
|
|
| 11 |
Const
of Motorable Road from Salangdang to Ladhama i/c Bridges ISC. Rs 1647.00 + State 140.51 Lakhs |
D.
P. Deokota |
|
|
2008-09 |
140.51 |
0.00 |
0.00 |
0.00 |
140.51 |
Work
tendered |
|
|
|
|
| 12 |
Carpeting
of approach road from Hee Pool to
yangthang senior secondary school (
NABARD) Total 65.69 lakhs Rs.59.12 Loan+ 6.57 Lakhs State |
|
|
|
2008-09 |
6.57 |
0.00 |
0.00 |
0.00 |
6.57 |
Work
tendered |
|
|
|
|
| 13 |
Const
of Motorable Road from Tathang to Melli Village at Yoksum |
Land
Compensation |
|
|
2008-09 |
13.33 |
0.00 |
13.33 |
13.33 |
0.00 |
compensation |
|
|
|
|
| 14 |
Const.of Motorable
Road from Relley Khola to Phamtam km 1st to 5th |
T.B. Chettri |
03/03 |
02/04 |
2003 & Rev 2008 |
176.46 |
124.63 |
11.80 |
136.43 |
Scheme transferred to New head |
|
|
|
| |
TOTAL |
|
|
|
|
696.46 |
289.09 |
200.11 |
489.20 |
166.63 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|