DETAILS OF STATE PLAN SCHEMES INDICATING SPILLOVER TO FINANCIAL YEAR  2009-10
WEST DISTRICT ( As on 31/3/2009)
Sl.No NAME OF WORK Name of Contractor Date of Commencement Due Date of Completion Year of Sanction Sanctioned Cost Expenditure Spill over 2009-10 Physical Progress Remarks
Till 31/03/2008 During 2008-09 Total
1 2 3 4 5 6 7 8 9 10 11 12 13
  LINK ROAD                                                                     
1 Construction of Link Road from Kaluk to Sribadam via Samdong road [State Share of RSVY] add  sanction of Diff of Cost of Material 2008 ( Rs 1.23 Lakhs) K.T.Bhutia 2005 2006 Revised 2008 19.10 6.62 12.48 19.10 0.00 100% Work  Closed 
2 Construction of Link Road from Chota Samdong to Majuwa km 3rd. Land Compensation     Sept.2007 17.57 17.57 0.00 17.57 0.00 100% Work  Closed 
3 Construction of Link Road to Kongri- Labdang   Km 2nd to 5th B.P Pradhan & O.P Pradhan       20.59 12.69 0.00 12.69 7.90 100% 9th Plan  Work  Final bill not closed
4 Const of Road from Legship - Geylzing Road to Bhanu Salik  under Geylzing Sub- Div  CRF work                State Plan Rs. 5.61 Lakhs+ CRF 220.11 Lakhs -+ Rs 225.72 Lakhs  N. L. Subedi 9/08 9/10 2008-09 5.61 0.00 5.61 5.61 0.00 ;- Work in progress
5 Const of Road from Chakung Khanerbong Road to Majuwa under Chakung Constituency (Ssno 3/west/Link/Plan dated 3/3/09 Land Compensation     Jan-09 18.98 0.00 0.00 0.00 18.98 LC  
  TOTAL          81.85 36.88 18.09 54.97 26.88    
Division : WEST   
75. ADDITIONAL FACILITIES
Sl.No NAME OF WORK Name of Contractor Date of Commencement Due Date of Completion Year of Sanction Sanctioned Cost Expenditure Spill over 2009-10 Physical Progress Remarks
Till 31/03/2008 During 2008-09 Total
1 2 3 4 5 6 7 8 9 10 11 12 13
                         
                         
                         
          Total 0 0 0 0 0 0