DETAILS OF STATE PLAN SCHEMES INDICATING SPILLOVER TO FINANCIAL YEAR  2009-10
                                                WEST DISTRICT                                                                                   (AS ON 31.03.2009)
Sl.No NAME OF WORK Name of Contractor Date of Commencement Due Date of Completion Year of Sanction Sanctioned Cost Expenditure Spill over 2009-10 Physical Progress Remarks
Till 31/03/2008 During 2008-09 Total
1 2 3 4 5 6 7 8 9 10 11 12 13
III  EXPANSION                                                             
1 Premix carpetting along link road to Mangalbari Km 1st-3rd. Karma Uden Bhutia       27.72 26.68 0.00 26.68 1.04 90% 9th Plan work
2 Construction of Motorable Road from Reshi-Khaniserbong, Km 7th- 8th.         20.61 8.09 0.00 8.09 12.52 70% 9th Plan work
3 Surface Improvement, Protective works & drainage of Lungchuk Salangdang road.[State Share of  NABARD] P.K.Chandak 25/06/2005 26/06/2006 Dec.2004 43.71 41.86 0.14 42.00 0.00 100% Work Closed
4 Premix carpetting & Improvement of Pelling - Rimbi road Km 1st-12th .[Additional Sanction] K.N.Bhutia, P.T.Bhutia, S.W.Bhutia - - - 16.12 10.46 4.68 15.14 0.00 100% Work Closed[1]
5 Premix carpetting works on Gyalshing Pelling road Km 1st & 9th. [State Share of EI] 146.57+5.60 Phurden Lama & Palchen Yongda 15/10/03 14/07/2004 2003 151.97 134.19 17.58 151.77 0.00 100% Work Closed
6 Construction &  Protective wall on Kalej Khola Power House to Uttarey Road.   - - 08-09 3.99 0.00 0.00 0.00 3.99 - New Work 08-09
7 Surface Improvement , widening  carpetting & Bridge Replacement on  Pelling Dentam road & BB Lal suspension bridge.[State Share of NLCPR] M.P.Agarwal, A.K.Agarwal 3/3/2005 31/08/2006 Feb.2005 104.81 0.00 0.00 0.00 104.81 73% State share of NLCPR 
8 Extension of Ribdi Bharang road Km 3rd to 4th.[9th plan] N.T.Sherpa Feb'99 May'2002   18.96 17.97 0.00 17.97 0.99 100% 9th Plan work
9 Premix carpetting, drainage & Protective Works on Sombaria-Soreng road Km 1st-8th. C.B.Subba 25/02/2004 24/03/2005 Nov.2003 181.90 168.90 0.17 169.07 12.83 100% Work closed but Stock Adjust Due  
10 Land/Damaged Compensation of Link Road to Gitang - Karmatar Compensation - - 2007 2.65 2.65 0.00 2.65 0.00 100% Work Closed
11 Construction of Link Road from Thongling to Lower Dodak Km 1st Revised LCRs. 28.28 Lakhs Basanti subba & Others - - Revised 2008 63.65 29.87 33.78 63.65 0.00 100% Work Closed
12 Construction of Link Road from Anden Gumpa to Upper Rumbuk Km 1st Revised Addl sanction 1.23 Lakhs 2008-09 P.T.Sherpa Mar-95 Mar-96   8.91 5.62 2.97 8.59 0.00 100% Final bill paid 
13 Land/Damaged Compensation of Link Road to Sribadam - deythang  Raod  Secy LRD - - 2008-09 0.66 0.00 0.66 0.66 0.00 100% Work Closed
14 House Comp of Shri NL Subedi along Legship- Geylzing Road Secy  LRD - - 2008-09 1.93 0.00 1.93 1.93 0.00 100% Work Closed
15 Streg. Widening and carpeting of Road from Pelling to chumbong Km 1st to 4th  (NABARD) Rs.246.00(194.87+51.13 Lakhs State ) P.C. Lama     2008-09 51.13 0.00 0.00 0.00 51.13 Work Tendered  NABARD
16 Payment of compensation for Ribdi - Bhareng Road  km 1&2nd  Secy LRD     2008-09 17.28 0.00 17.28 17.28 0.00 100% Closed 
  TOTAL          716.00 446.29 79.19 525.48 187.31    

[1]