| G. NABARD | (Rupees in lakh) | |||||||||||
| Sl.No | NAME OF WORK | Name of Contractor | Date of Commencement | Due date of Completion | Year of Sanction | Sanctioned Cost | Expenditure | Spillover to 2009-10 | Physical Progress | Remarks | ||
| As on 31/03/2008 | During 2008-09 | Total | ||||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 |
| 1 | Construction of Link road from 3rd Mile turning of Tintek Dikchu to Raksay via Kedangthang Km 4th to 6th ( share of NABARD Scheme) | 2008 | 224.66 | 0.00 | 0.00 | 0.00 | 224.66 | 0% | ||||