DETAILS OF STATE PLAN SCHEMES INDICATING SPILLOVER TO FINANCIAL YEAR  2008-09
NORTH DISTRICT ( MANGAN SUB-DIVISION & SUB- DIVISION- IV)
B.   MAJOR HEAD :- 5054-04-04.337-60-47-60.47.72 - Replacement (Plan) (Rupees in lakh)
Sl. NAME OF WORK Name of Contractor Date of Commencement Due date of Completion Year of Sanction Sanctioned Cost Expenditure Spillover to 2009-10 Physical Progress Remarks
   Upto                2007-08 During 2008-09 Total  
1 2 3 4 5 6 7 8 9 10 11 12 13
                         
                         
1 Const of 15 M RCC Bridge over Khedum Chu Gyatso Bhutia 12.11.98 11.03.99 1998-99 20.72 19.36 0.00 19.36 0.00 100% A/c closed 
2 Const of 30m RCC Culvert along pangthang - Lingdok road Km 12th Ch 14  - - - 2008 8.29 0.00 8.23 8.23 0.00 100% A/c closed 
3  'Construction of multi span Bridge over Teesta at Gour at Dzongu. (Land compensation ) - - - 2007 6.84 6.62 0.00 6.62 0.00 100% A/c closed 
4 Const. of 55 mtrs Supension Bridge over Khedum Chu at Lachung Needup Lachungpa 12.11.98 11.7.99 98-99 112.31 100.09 1.07 101.16 11.15 100% Forest Compensation remaining
  TOTAL  .  REPLACEMENT  NORTH 148.16 126.07 9.30 135.37 11.15