DETAILS OF STATE PLAN SCHEMES INDICATING SPILLOVER TO FINANCIAL YEAR  2009-10
NORTH DISTRICT ( MANGAN SUB-DIVISION & SUB- DIVISION- IV)
G. Strengthening Road Infrastructure in Dzongu.            (Rupees in lakh)  
Sl.No NAME OF WORK Name of Contractor Date of Commencement Due date of Completion Year of Sanction Sanctioned Cost Expenditure Spillover to 2009-10 Physical Progress Remarks
As on 31/03/2008 During 2008-09 Total  
1 2 3 4 5 6 7 8 9 10 11 12 13
1 Strengthening, Carpetting and Protective work on DSM Road to Sr. Secondary School km. 1st to 8th.  Sonden Gyamtso Bhutia 1/6/08 1/1/09 2008 391.66 57.78 108.35 166.13 225.53 42%  
2 Strengthening, Carpetting and Protective work on Lingthem to Lingdem Road Km. 1st to 5th.  Samdup Lepcha - - 2008 385.54 42.22 125.38 167.60 217.94 43%  
  TOTAL  :- G.   STRENGTHENING ROAD INFRA. IN DZONGU     777.20 100.00 233.73 333.73 443.47