| DETAILS OF STATE PLAN SCHEMES INDICATING SPILLOVER TO FINANCIAL YEAR 2009-10 | |||||||||||
| EAST DISTRICT (STATION, SINGTAM & PAKYONG SUB-DIVISION ) | |||||||||||
| STATE PLAN (AS ON 31.03.2009) | |||||||||||
| (Rupees in lakh) | |||||||||||
| Sl. No | NAME OF WORK | Name of Contractor | Date of Commencement | Due date of Completion | Year of Sanction | Sanctioned Cost | Expenditure | Spillover 2009-10 | Physical Progress | ||
| Upto 31/03/2008 | During 2008-09 | Total | |||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
| CONST. OF NEW ROADS | 0 | ||||||||||
| 1 | Construction of link Road from Basilakha to Middle camp via Radogtar 6th KM (CW15.11+others 2.82) | Jastin Rai | 10.5.05 | 9.2.06 | 2005 | 17.93 | 14.93 | 0.00 | 14.93 | 3.00 | 75% |
| 2 | Construction of link Road from Basilakha to Middle camp via Radogtar 7th KM | Jeewan Subba | 10.5.05 | 9.2.06 | 2005 | 17.23 | 9.93 | 7.30 | 17.23 | 0.00 | 100% |
| 3 | Construction of link Road from Basilakha to Middle camp via Radogtar 8th Km | Paul Rai | 10.5.05 | 9.2.06 | 2005 | 21.36 | 10.01 | 11.33 | 21.34 | 0.00 | 100% |
| 4 | Construction of link Road from Basilakha to Middle camp via Radogtar - 110m span RCC Culvert | Patrush Subba | 10.5.05 | 9.2.06 | 2005 | 12.32 | 0.00 | 12.26 | 12.26 | 0.00 | 100% |
| 5 | Land compenstion for construction of Link road from Basilakha to Middle Camp via Radongtar km 6th to 8th & 10th M Span R.C.C Bridge | Secy LRD | - | - | 2008 | 35.60 | 0.00 | 35.60 | 35.60 | 0.00 | 100% |
| 6 | Const of Approach road to Sivalaya Mandir at pacheykhani Km 1st ( revised for Comp Rs 4.98 | R.N. Baral | 18.7.05 | 15.6.06(Ext.) | Revised 2008 | 28.49 | 12.87 | 15.43 | 28.30 | 0.00 | 100% |
| 7 | Construction of Link Road from Amba to Taja School 1st and 2nd km ( State share of RSVY)&LC Rs 2.91 | Mon Narayan Dhakal | - | - | Revised 2008 | 8.97 | 3.96 | 0.00 | 3.96 | 5.01 | 90% |
| 8 | Construction of road from Assam Pakyong to Kadamtam Village km. 1st | Man Bdr. Manger | 1.07.05 | 30.6.06 | 6/6/2005 | 39.65 | 23.46 | 16.04 | 39.50 | 0.00 | 100% |
| 9 | Construction of road fromAssam Pakyong Road to Kadamthang school 2nd Km | Elies Lepcha | 1.07.05 | 30.06.06 | 6/6/05 | 41.40 | 24.11 | 17.29 | 41.40 | 0.00 | 100% |
| 10 | Construction of road fromAssam Pakyong Road to Kadamthang school 3rd &4th KM | D.P. Mangar | 1.07.05 | 30.06.06 | 6/6/05 | 41.74 | 13.69 | 15.94 | 29.63 | 12.11 | 90% |
| 11 | Construction of road fromAssam Pakyong Road to Kadamthang school 3rd &4th KM Contingency Rs 4.26+ rs Land Comp Rs 25.00 | LC & Cont | completed | 87.70 | 34.15 | 53.36 | 87.51 | 0.00 | 100% | ||
| 12 | Construction of Road from Chandmari Village to Jwarlal Nheru Road ( Revised due to comp . Rs 2.75 lakhs | Karma Wongchuk | 28.09.05 | 27.03.06 | Revised 2008 | 33.38 | 23.76 | 8.34 | 32.10 | 1.28 | 100% |
| 13 | Extension of link road from NH-31 A to Chisopani km 2nd (State share of RSVY Scheme) | Secy LRD | - | - | 2007 | 3.35 | 3.35 | 0.00 | 3.35 | 0.00 | 100% |
| 14 | Extension of Link Road to Dokey Chisopani Pry School including landCompensation ( State Share of RSVY Scheme) | Nabin Rai | 17.10.05 | 20.3.07 | 2005 | 1.72 | 0.00 | 1.68 | 1.68 | 0.00 | 100% |
| 15 | Const of Road from Arubotey to Subaneydara( Damaged Comp) km 1st to 3rd) | Secy LRD | - | - | 2008 | 1.17 | 0.00 | 1.17 | 1.17 | 0.00 | 100% |
| 16 | Land compenstion for construction of Link road fromAmba to Taza (Balance) RSVY | Secy LRD | - | - | 2008 | 2.90 | 0.00 | 2.90 | 2.90 | 0.00 | 100% |
| 17 | Construction of new road from Radong (NH-31A) to Khimsithang via Chuba km 1st to 15th | K.K Agarwal | 2008 | 874.19 | 0.00 | 0.63 | 0.63 | 873.56 | 21% | ||
| TOTAL E-- NEW ROADS | 1269.10 | 174.22 | 199.27 | 373.49 | 894.96 | ||||||