| DETAILS OF STATE PLAN SCHEMES INDICATING SPILLOVER TO FINANCIAL YEAR 2009-10 | ||||||||||||
| EAST DISTRICT (STATION, SINGTAM & PAKYONG SUB-DIVISION ) | ||||||||||||
| STATE PLAN (AS ON 31.03.2009) | ||||||||||||
| (Rupees in lakh) | ||||||||||||
| Sl. No | NAME OF WORK | Name of Contractor | Date of Commencement | Due date of Completion | Year of Sanction | Sanctioned Cost | Expenditure | Spillover 2009-10 | Physical Progress | Remarks | ||
| up to 31/03/2008 | During 2008-09 | Total | ||||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 |
| LINK ROAD | ||||||||||||
| 1 | Construction of Link Road from Sakyong to Beying km 1st to 2nd (State Share of NABARD) | Tej Bdr. Pradhan | 2008 | 19.47 | 0.00 | 0.00 | 0.00 | 19.47 | 75% | |||
| 2 | Const. of 20 chain road from Bio Control Lab to Phewk Busty i/c LC Rs 35.87 Lakhs | G. K. Chettri | 31.05.04 | 30.6.06 (Ext) | Revised 2008 | 72.02 | 32.99 | 39.03 | 72.02 | 0.00 | 100% | |
| 3 | Const of Link Road from Rongli to Talkharka (PH II)KM 2nd &3rd Land Compensation | Secy LRD | - | - | 2008 | 22.73 | 0.00 | 22.73 | 22.73 | 0.00 | 100% | |
| 4 | Payment of Compesation for link Road from ICAR Complex to Gairi Goan | Secy LRD | 2009 | 11.22 | 0.00 | 11.22 | 11.22 | 0.00 | 100% | |||
| 5 | Immediate Rest of Raley Kambal Road Km 1st to 7th | Deptt | 2009 | 10.00 | 0.00 | 10.00 | 10.00 | 0.00 | 100% | |||
| 6 | Immediate Rest of Duga- Pachak & Duga Chewribotey Raod Road Km | Deptt | 2009 | 10.00 | 0.00 | 9.98 | 9.98 | 0.00 | 100% | |||
| Immediate Rest of Lower Samdong Road km 1st to 3rd | Deptt | 2009 | 10.00 | 0.00 | 9.98 | 9.98 | 0.00 | 100% | ||||
| TOTAL D- LINK ROAD | 155.44 | 32.99 | 102.94 | 94.75 | 19.47 | - | ||||||