DETAILS OF STATE PLAN SCHEMES INDICATING SPILLOVER TO FINANCIAL YEAR  2008-09
EAST  DISTRICT (STATION, SINGTAM & PAKYONG  SUB-DIVISION )
 STATE PLAN (AS ON 31.03.2008)
Sl. No NAME OF WORK Name of Contractor Date of Commencement Due date of Completion Year of Sanction Sanctioned Cost Expenditure  Spillover 2009-10  Physical Progress
as on 31/03/2008 During 2008-09 Total
1 2 3 4 5 6 7 8 9 10 11 12
 EXPANSION                                                            
1 Premix carpetting/Imp. Of Rongli Rorathang road, Km 1st - 11th.( Revised) Kuber Raj Rai 01/01/03 30/4/06(Ext.) 2003 254.00 235.34 18.66 254.00 0.00 100%
2 Upgradation,Premix Carpetting of Pakyong Karthok -road Km 1st to 4th & Pakyong [State Share of EI] P.N.Kazi  28/03/05 27/7/06 2005 143.35 22.31 16.12 38.43 104.92 40%
3 Upgradation,Premix Carpetting of Pakyong Karthok road Km5th to 7th Naya Busty  [State Share of EI] EI 110.34+110.34 Adup Bhutia  1.9.05   2005 110.34 0.00 10.64 10.64 99.70  
4 Upgradation,Premix Carpetting of Pakyong Karthok Road Koltey Tar to Pakyong Rai Goan Km 1st & 2nd.[State Share of EI] 73.14 + 73.14 Devi Dhakal  21/3/05 27/9/05 2005 73.14 30.92 10.60 41.52 31.62 45%
  Other Provisions of the above works (slno 2 to 4) EI 7.74 + &.74 - - - 2005 7.74 6.93 0.00 6.93 0.81  
5 Premix carpetting & Surface Imp. Along Chewribottey-Pandam road, Km 1-6th. ( Forest Comp Paid)  Basu Dev Pradhan 02/12/02 02/12/03 2003 117.78 83.34 12.94 96.28 21.50 90%
6 Construction of bye- pass Road below Mintokgang (Original Rs 74.60 +Addl Rs 5.66)= D.B. Chettri 26/02/04 25/08/04 2004 80.26 71.46 8.58 80.04 0.00 100%
7 Premix carpetting & Surface Imp.of KLT 16th to 26th Km (Revised) P.D. Denzongpa Completed   2003 260.57 252.36 0.41 252.77 7.80 100%
8 Premix carpetting & Surface Imp.of KLT 7th to 15th Km (Revised) L.N. Sarda Completed   2003 232.83 214.16 0.00 214.16 18.67 100%
9 Const. of link road from King Stone to Simana Khola Km 1st to 2nd. Departmental Completed     8.60 0.00 0.00 0.00 8.60 100%
10 Const. of Diversion Road to Ranipool Pakyong Road, 2.83km   [S.Share of NLCPR] Share Rs 23.38+Rs 79.60 Lc + LC 17.72+ Forest Compensation   B. Kr. Agarwal 21/02/05 21/02/06 Revised 2008 120.70 64.60 56.10 120.70 0.00 35%
11 Extension of Pakyong Mamring Tarethang road Km 1st to 10th  Kilometer  1stKM (CW= 21.58 Lakhs+  other  Provisions for all KMs=Rs.7.33 Lakhs) + Addl Sanction of Rs 75.54 Lakhs Comp in 2008 Khus N.Adhikari 10/06/05 10/11/06 Revised 2008 104.45 28.72 75.53 103.79 0.66 90%
12 Extension of Pakyong Mamring Tarethang road Km 1st to 10th  Kilometer 2nd KM Johar Man Rai 10/06/05 10/11/06 2005 16.61 16.37 0.00 16.37 0.24 90%
13 Extension of Pakyong Mamring Tarethang road Km 1st to 10th  Kilometer  3rdKM  Ganesh Kr Pradhan 10/06/05 10/11/06 2005 22.70 12.94 9.22 22.16 0.54 98%
14 Extension of Pakyong Mamring Tarethang road Km 1st to 10th  Kilometer  4th KM Udai Mishra 10/06/05 10/11/06 2005 17.92 12.02 5.58 17.60 0.32 99%
15 Extension of Pakyong Mamring Tarethang road Km 1st to 10th  Kilometer  5th KM K.S.Rai 10/06/05 31/5/2007(Ext.) 2005 27.01 16.05 0.00 16.05 10.96 70%
16 Extension of Pakyong Mamring Tarethang road Km 1st to 10th  Kilometer  6th KM Iswar Kr Dangal 10/06/05 10/11/06 2005 21.15 10.44 7.95 18.39 2.76 70%
17 Extension of Pakyong Mamring Tarethang road Km 1st to 10th  Kilometer  7th  K.S.Rai 10/06/05 31/5/07(Ext.) 2005 22.10 8.68 0.00 8.68 13.42 70%
18 Extension of Pakyong Mamring Tarethang road Km 1st to 10th  Kilometer 8 th KM Mahesh Kr Pradhan 10/06/05 10/11/06 2005 21.66 0.00 11.01 11.01 10.65 85%
19 Extension of Pakyong Mamring Tarethang road Km 1st to 10th  Kilometer 9th KM Kamal Adhikari 10/06/05 10/11/06 2005 19.24 8.00 11.21 19.21 0.03 65%
20 Extension of Pakyong Mamring Tarethang road Km 1st to 10th  Kilometer 10th KM Milan Dahal 10/06/05 10/11/06 2005 10.70 0.00 10.43 10.43 0.27 65%
22 Construction of Road from Zingla to Martam 2.36 Km. (Add sanction of Rs 10.96 Lakhs + Rs. 7.03 Forest +0.55 Lakh for LC in 2008) Land Compensation - - Revised 2008 25.67 14.16 17.99 32.15 0.00 100%
23 Feeder Raod to development Area( Addl sanction on 9th Paln scheme)  Ssno 1/East/Exp/06-07 T. wangchok - - 2006 5.04 5.04 0.00 5.04 0.00 100%
24 Const of 40 Mts span Bridge over Rongli Khola along  arubotey subaney dara Raod Ssno 2/E/exp/06-07 Ashok Ts. Bhutia - - 2006 16.50 14.24 0.00 14.24 2.26 100%
25 Stregenth of drainage from Lal Turing to basilakha Km 1 to 3 Ssno 5/E/exp/06-07 ( State share of NABARD) G. M Gurung - - 2006 33.19 0.00 32.79 32.79 0.00 100%
26 Immediate Restoration of Mamring Amba Road km 3rd Departmental 6.11.06 05.05.08 2006 6.77 6.68 0.00 6.68 0.00 100%
27     Relocation     and extension of HT &LT line and shifting of 25 KVA outdoor   pipe    distribution sub-station at Barchangey Village East. Power Department     2006 3.37 3.37 0.00 3.37 0.00 100%
28 Const of Truckable Road from Rongli to talkharka (State share of BADP) LC Km 1st to 5th Secy LRD - - 2008 1.03 0.00 0.00 0.00 1.03 100%
29 Const. of link road from King Stone to Simana Khola Km 1st to 2nd. Secy LRD LC   2008-09 42.18 0.00 42.18 42.18 0.00 0%
30 Const of 3KM Link raod from Nop Goan to Barpipal Dara in east sikkim under CRF. Est costRs.  120.33 Lakhs (CRF Rss.107.92 Lakhs+Rs. 12.40 Lakhs State) Hemendra Adhikari     2008-09 12.40 0.00 0.00 0.00 12.40 0%
  Sang Khola - Zingla Road  Km 18th  LC           0.54      
  TOTAL C -  EXPANSION         1839.00 1138.13 358.48 1495.61 349.16